HomeMy WebLinkAbout9977RESOLUTION NO. 9,977
A RESOLUTION AUTHORIZING THE EXTENSION OF THE ENGINEERING
SERVICES CONTRACT WITH THE MEHLBURGER FIRM ASSOCIATED
WITH PHASE 11 OF THE LANDFILL DEVELOPMENT.
211
WHEREAS, the original contract of $639,353.97 with the Mehlburger Firm was for
engineering services related to the design and construction of Phase It of the landfill; and
WHEREAS, during the course of the construction and study of alternatives decisions were
made which changed the course of some activities, $146,952.66 was deleted from the contract and
$198,458.43 was added; and
WHEREAS, the most significant items that would not be completed are a cell design,
leachate heavy metal design, leachate sludge disposal design and completion of the bailer facility
design; and
WHEREAS, major items that were expanded or added include the heavy equipment wash,
fueling station, old landfill gas study, in -place density study and to evaluate compliance with a new
requirement by ADPC &E for an air permit.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF DIRECTORS OF
THE CITY OF LITTLE ROCK, ARKANSAS:
SECTION 1. The City Manager is authorized to extend the engineering services contract
with the Mehlburger Firm associated with Phase 11 of the Landfill development.
SECTION 2. Funding in the amount of $51,505.77 is available from the Solid Waste
Revenue Bond Fund.
ADOPTED: May 6, 1997
TEST: d�,,� APP VED:
-A1t4. �{L �7�1A
ROBBTE HANCOCK JIM ILEY
CITY CLERK M AVCO R
APP VED AS TO FORM-
#A.
THOMAS M. CARPENTUR
CITY ATTORNEY