RESOLUTION NO. 9,418
A RESOLUTION AUTHORIZING THE CITY
MANAGER TO ACCEPT BIDS AND AWARD A
CONTRACT FOR CONSTRUCTION OF WEST
6TH STREET, APPIANWAY TO THAYER, A
CDBG PROJECT FOR THE DEPARTMENT OF
NEIGHBORHOODS AND PLANNING.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF DIRECTORS OF
THE CITY OF LITTLE ROCK, ARKANSAS:
SECTION 1. The City Manager is authorized to accept bids
and award a contract to Gene Summers Construction Company of
Little Rock, Arkansas, in the amount of $153,800 ($160,000
allowance for change orders pending City Manager approval) for
street construction, West 6th Street - Appianway to Thayer.
SECTION 2. Funds are available for this purpose in account
number 19100 - 2/21100 -5.
ADOPTED: June 20, 1995
A'
"PROVED AS TO FORM:
THOPM5 M. C-AF.Fk;NTka4 (j
CITY ATTORNEY
•
• PURCHASING FACT SHEET 0 332
BID NO: 95279 DATE ADVERTISED: 4/21/95 & 4/28/95
DATE OPENED: 5/23/95 BID LIST: 78317
NUMBER SOLICITED: 90
DEPARTMENT: Neighborhoods & Planning (CDBG)
DESCRIPTION: Street Construction, W. 6th Street - Appianway to Thayer
FUNDING: CDBG
ACCOUNT NUMBER: 19100 - 2/21100 -5
APPROPRIATION OR TRANSFER REQUIRED: None
ACCOUNT AVAILABILITY: $160,000
AMOUNT OF PURCHASE: $153,800
SUGGESTED AWARDEE: Gene Summers Construction
Little Rock, AR
RECOMMENDATION AND DISCUSSION: It is recommended that the low bid be
accepted. It is also recommended that $160,000 be allowed for this contract
for City Manager approved change orders.
n
BID #: 95279
DEPARTMENT: NeighborhA Planning (CDBG) •
DESCRIPTION: Street Construction, W. 6th Street - Appianway to Thayer
TABULATION
Gene Summers Construction ($153,800) Award
Township Builders 163,090
Harris Construction Management 166,708.25
Harold Davis Construction 183,743.96
Heller Co. 229,676