HomeMy WebLinkAboutZ-10316 Staff Report Approval 071626
File No.: Z-10316
Owners: Sanscript Enterprises LLC/Doris Smith
Applicant: Vernon Huiett (Agent)
Address: 14 Otter Creek Court
Legal Description: Lot 4, Otter Creek Business Park, Otter Creek Community,
Little Rock, Arkansas
Zoned: C-1
Present Use: Vacant
Proposed Use: Parking Lot
Variance(s) Requested: A variance from the regulations of Section 36-299(e)(1) to allow a reduction in the front yard setback in a C-1 district.
A variance from the regulations of Section 36-510 to allow the construction of a new parking area without interior landscaping or portion of the perimeter screening in a C-1 district
A variance from the regulations of Section 30-45 to allow construction of the new parking area without interior curb, gutter and wheel stops in a C-1 district
Justification: The applicant’s justification letter was submitted with the application.
STAFF REPORT
Planning and Development Civil Engineering Comments:
No Comment
B. Buffering and Landscape Comments:
No Comments
C. Building Codes Comments:
No Comments.
D. Staff Analysis:
The property located at 14 Otter Creek Court is within a predominately C-1 zoned neighborhood, within the Otter Creek Business park subdivision. The survey indicates the lot has a width
of 319 feet and a depth of 110 feet and is currently vacant.
The applicant is proposing to construct a new 4,098 square foot laundormat on the west side of the property with an adjoining twenty-six (26) space parking lot.
The site plan indicates that the lot is bordered along the north perimeter by Callagahan Creek and floodway. The Callagahan Creek flooding is shown to extend into the property rendering
greater than 40% of the lot unusable for placement of a structure. This floodway designation also requires that an unhindered fire access way be provided along its perimeter.
Section 36-299(e)(1) states: There shall be a front yard having a depth of not less than twenty-five (25) feet to the front line of the building”. Therefore, the applicant is requesting
to allow a reduction in the front setback from twenty-five (25) feet to ten (10) feet.
Section 36-510 states: The landscaping and screening requirements set forth in chapter 15, article IV, shall be in full force and effect when erecting, constructing, enlarging or otherwise
altering any vehicular use area”. Therefore, the applicant is requesting to allow the omission of the landscaping and screening on the north property line, which abuts the floodway.
Section 15-97(a) states: Interior landscape areas shall comprise at least eight (8) percent of any vehicular use area containing twelve (12) or more parking spaces. Therefore, the applicant
is requesting to allow the omission of the required interior parking area landscape.
Section 36-45 states: When an off-street parking area adjoins public right-of-way, inner curbing shall be provided as follows:
(1) When no sidewalk exists or is proposed in the right-of-way the inner curb may be located on the property line.
(2) if the proposed parking is to be parallel to the right-of-way the inner curbing may be located on the property line.
(3) If there is an existing or proposed sidewalk and the proposed parking stalls are to be oriented into the sidewalk, the inner curbing shall be located two and one-half (2 ½ ) feet
inside the property line.
(4) The inner curb shall be at least four (4) inches in width and extend a minimum of four (4) inches above the driving surface and a minimum of six (6) inches below the driving surface.
(5) a reinforced precast curb or fence equivalent to this curb may be used upon approved by planning and development.
Therefore, the applicant is requesting a variance to allow construction of the new parking area without interior curb gutter and wheel stops along the north property line
to allow fire and rescue access.
Staff is supportive of the requested variances. Staff views the requests as reasonable. Staff believes that due to the extremely limited useable area of the lot that a genuine hardship
exists so as to allow the property to have a viable use. Staff agrees with the proposed location of the structure and dumpster along with the parking layout which maximizes the limited
area of the lot.
E. Staff Recommendation:
Staff recommends approval of the requested front yard setback reduction from
twenty-five (25) feet to no less than ten (10) feet.
Staff recommends approval of the request to allow the omission of the required interior parking area landscape.
Staff recommends approval of the request to allow the omission of the required landscaping and screen on the north perimeter of the lot which abuts the floodway.
Staff recommends approval of the request to allow construction of the new parking area without interior curb gutter and wheel stops adjacent to the floodway perimeter.
Subject to the following conditions:
A building permit must be obtained prior to construction.
A SFHA Development permit must be obtained prior to receipt of construction permit.