HomeMy WebLinkAboutResponse to Comments 1 042226City of Little Rock Planning and Development
Planning Commission Hearing/May 14, 2026
Applicant Comments for Proposed Development
Applicant responses are due no later than Friday, April 24, 2026. Please submit
revised site plans, if applicable, along with written responses from Development
Staff and “Other Departments” to: tthrower@littlerock.gov
RE: Z-9407-E
Village at Whispering Valley/The Beverly – Revised PRD
W. of Village Run Pkwy., S. of Alexander Road
Development Staff Comments:
1. Provide detailed cover letter describing aspects of the proposed use including number
of additional buildings, type of units, required parking spaces, common areas,
amenities, etc.
Revised detailed cover letter provided.
2. Provide bill of assurance.
Bill of Assurance provided.
3. Provide building elevations for each building type for proposed use.
New building elevations provided.
4. Provide completed Street ROW Agreement form (circle agree/disagree).
Signed Street ROW Agreement included on page 11.
5. Sight lighting must be low-level and directed away from adjacent properties.
All sight lighting will be low-level and directed away from adjacent properties. All sight
lighting will comply with applicable City Ordinances.
6. Signs must comply with Section 36-552 of the City’s Zoning Ordinance (signs
permitted in multifamily zones).
All signs will comply with all applicable City Ordinances.
7. Any fence or wall erected must comply with Section 36-516 of the City’s Zoning
Ordinance.
All fences and walls will comply with all applicable City Ordinances.
8. Landscaping must comply with Chapter 15 of the Landscape Code.
All Landscaping will comply with all applicable City Ordinances.
Z-9407-E
Village at Whispering Valley/The Beverly – Revised PRD W. of Village Run Pkwy.,
S. of Alexander Road
1. All documents are to be submitted to Planning and Development for complete plan
check.
All documents will be submitted as required.
2. All documents shall be prepared by an Arkansas Licensed Professional Engineer.
All documents will be prepared by Arkansas Licensed Professional Engineer
3. The Land Survey to be no older than five (5) years prepared, stamped, and signed
by an Arkansas Licensed Professional Land Surveyor.
Land Survey will be no more than 5 years old prepared, stamped, and signed by an
Arkansas Licensed Professional Land Surveyor.
4. Provide complete parking spaces layout including accessible parking spaces
based on Arkansas Fire Prevention Code and City of Little Rock Municipal Code
section 36-511
Parking layout including accessible parking spaces based on Arkansas Fire
Prevention Code and City of Little Rock Municipal Code section 36-511
5. All documents shall be prepared based on the current Arkansas Fire Prevention
Codes, City of Little Rock Municipal codes and ordinances, and current
Stormwater Management and Drainage Manual.
All documents will be prepared based on the current Arkansas Fire Prevention Codes,
City of Little Rock Municipal codes and ordinances, and current Stormwater Management
and Drainage Manual.
6. Along with the Grading application (GLA), The applicant to submit traffic impact
study (TIA) showing the additional, projected traffic expected to be generated by
the proposed development.
GLA & TIA will be submitted as requested.
7. All streets to meet the current City of Little Rock Master Street Plan.
All streets will meet the current City of Little Rock Master Street Plan
8. Any work involving one (1) or more acres of disturbed area requires a State of
Arkansas NPDES permit. Contact the Arkansas Department of Environmental
Quality, NPDES branch at 501-682-0744 for applications and information about
General Stormwater Discharge Construction Permit #ARR150000.
All required permits will be obtained.
9. Driveways shall meet all City Standard Details and City Code Sec. 30-43.
Driveways will meet all City Standard Details and City Code Sec. 30-43.
10. Any new development shall be reviewed to ensure all codes, specifications, and
ordinances are met before issuing any related permits.
Understood.
11. Prior to issuance of Certificate of Occupancy; the applicant shall provide as-built
plans and data entry template of newly installed or modified public and private
stormwater drainage system to Planning and Development Dept., Civil
Engineering Private Development by email to CEPermits@littlerock.gov
Ok