Loading...
HomeMy WebLinkAboutResponse to Comments 022026Water regarding procedures for installation of water facilities and/or fire service. Approval of plans by the Arkansas Department of Health Engineering Division and Little Rock Fire Department is required. ➢ Approval has been provided by CAW, LRFD, and ADH. 5. A Capital Investment Charge base on the size of meter connection(s) will apply to this project in addition to normal charges. This fee will apply to all connections including metered connections off the private fire system. ➢ Acknowledged. 6. If there are facilities that need to be adjusted and/or relocated, contact Central Arkansas Water. That work would be done at the expense of the developer. ➢ Acknowledged. 7. The facilities on-site will be private. When meters are planned off private lines, private facilities shall be installed to Central Arkansas Water’s material and construction specifications and installation will be inspected by and engineer, licensed to practice in the State of Arkansas Execution of Customer Owned Line Agreement is required. ➢ Acknowledged. 8. Due to the nature of this facility, installation of an approved reduces pressure zone backflow preventer assembly (RPZ) is required on the domestic water service. This assembly must be installed prior to the first point of use. Central Arkansas Water (CAW) requires that upon installation of the RPZ, successful test of the assembly must be completed by a certified Assembly Tester licenses by the State of Arkansas and approved by CW. The test results must be sent to CAW’s Cross Connection Section within ten days of installation and annually thereafter. Contact the Cross Connection Section at 377-1226 if you would like to discuss backflow prevention requirements for this project. ➢ Acknowledged. 9. Fire sprinkler systems which do not contain additives such as antifreeze shall be isolated with a double detector check valve assembly. If additives are used, a reduces pressure zone backflow preventer shall be required. ➢ Acknowledged. Fire Marshall Comments 1. Must comply with Arkansas Fire Prevention Code 2021 edition. All projects submitted for zoning approval must comply with the Arkansas Fire Prevention Code, 2021 Edition, including any comments or requirements provided by the Little Rock Fire Marshal’s Office, prior to acceptance. ➢ Acknowledged Development Statt Comments 1. Will the proposed mini-storage facility contain a 24-hour, on site manager? ➢ The manager will be on site 6 am to 10 pm 7 days a week. 2. Provide separation for buildings 2-6 depicted on the site plan. ➢ The space between each building is 20 feet. The dimensions of that space can be found on Sheet C1.3 Enlarged Site Plan B. 3. Provide operating hours including days and times of the week for the proposed use. ➢ Hours of operation will be 6am to 10pm 7 days a week. However, the office will only be open Monday – Saturday 8am – 6pm. 4. Screening will be required along the East property line. ➢ Acknowledged. 5. The dumpster area depicted on the site plan must be screened and comply with section 36-523 of the City’s Zoning Ordinance ➢ Acknowledged. 6. All sight lighting must be low-level and directed away from adjacent properties. ➢ Acknowledged. 7. All signage must comply with section 36-555 of the City’s Zoning Ordinance (signs permitted in commercial zones). ➢ Acknowledged. 8. Any fence or wall erected must comply with section 36-516 of the City’s Zoning Ordinance. ➢ Acknowledged. 9. Any required landscaping must comply with Chapter 15 of the City’s Landscape Ordinance. ➢ Acknowledged If you have any questions, please give me a call. Dylan Summerville Phillip Lewis Engineering (501)-326-0662 February 19, 2026 Little Rock Engineering Engineering Section – City of Little Rock RE: Civil Engineering Review BenBran Storage 4301 S University Little Rock AR 72204 City of Little Rock Planning Review Z-7838-A To whom it may concern, please find below our responses to each Engineering comment. Design plans are revised and re-submitted along with this letter. Civil Review Comments 1. Provide complete Site Plan for staffs review comments below are based on survey provided. ➢ Acknowledged. 2. Grading permit will be required. ➢ Acknowledged. 3. ADA Access shall be shown to the Right-of-Way ➢ Engineering Staff approved no ADA route due to lack of pedestrian pathway along S University. 4. Handicap Parking shall include one van stall 11ft wide with a 5ft minimum aisle ➢ Acknowledged. 5. Contact Planning and Development Dept., Engineering Division at 501-371-4817 or at 501- 918-5348 for inspections of any work in the public right-of-way prior to placement of concrete or asphalt or for on-site clarification of requirements prior to commencing work. Failure to do so can result in removal of any improperly placed concrete or asphalt at the expense of the owner or contractor. ➢ Acknowledged. 6. Hauling of cut and/ or fill material on or off project sites over municipal streets require approval prior to a grading permit being issued. Contact Public Works Traffic Engineering at 621 S. Broadway 501-379-1800 with any questions or for more information. ➢ Acknowledged. 7. Damage to public and private property due to hauling operations or operations of construction related equipment from a construction site shall be repaired by the responsible party prior to the issuance of a certificate of occupancy. ➢ Acknowledged. 8. Any new development shall be permitted and receive all reviews to ensure all codes, specifications, and ordinance of occupancy. ➢ Acknowledged. Landscape Review Comments 1. Developments with fewer than one hundred fifty (150) parking spaces have: (1)Single-trunk trees with a minimum caliper of two (2) inches measured twelve (12) inches above grade at planting; or 0(2) Multitrunk trees with a minimum of three (3) canes with a minimum caliper of one (1) inch each measured twelve (12) inches above grade at planting. ➢ Acknowledged. 2. 15.96 states that: A perimeter planting strip is required along any side of a vehicular use area that abuts adjoining property or the right-of-way of any street, highway, or freeway. This strip shall be at least nine (9) feet wide. ➢ Acknowledged. 3. 15-95 states: Where development which requires screening abuts land use of a more restrictive nature at least eighty (80) percent of the view of the vehicular use area and parked vehicles shall be screened so as to not be visible when viewed from the adjacent property. A wooden fence may satisfy sixty-five (65) percent of the requirement and evergreen trees may be used to satisfy the balance. ➢ Acknowledged. 4. 15.97 (a) Interior landscape areas shall comprise at least eight (8) percent of any vehicular use area containing twelve (12) or more parking spaces. (b) In order to apply toward the required eight (8) percent landscape areas, the minimum size of an interior landscape area shall be one hundred fifty (150) square feet for developments with one hundred fifty (150) or fewer parking spaces. ➢ Acknowledged. 5. 15.98 (b) one (1) tree and four (4) shrubs shall be planted in the building landscape areas for each forty (40) linear feet of vehicular use area abutting the building. (c) Fore buildings greater than forty (40) feet in height at least one-third (1/3) of the trees to be places in the building landscape area shall be of a species with a mature height greater than thirty (30) feet. ➢ Acknowledged. 6. Sec. 15-100. (a) Raised concrete curbing or other approved devices shall be placed around the base of each landscaped area to protect plantings from automobile and pedestrian traffic. Such curbing should be offset two (2) feet from planting areas abutting parked vehicles in order to protect plantings from vehicle front end overhand and vehicle doors opening into planter areas. (b) The soil within the landscape areas shall be properly prepared prior to plant installation in accordance with acceptable horticultural practices. (c) Massin of shrubs is permitted only in mulch beds and not in grass or turf areas. ➢ Acknowledged. LR City Comments 1. Provide a 10’ utility easement on the West side of the property adjoining University Avenue ➢ 10’ utility easement has been added. 2. All Central Arkansas Water requirements in effect at the time of request for water service must be met. ➢ Acknowledged. 3. The Little Rock Fire Department needs to evaluate this site to determine whether additional public and/or private fire hydrant(s) will be required. If additional fire hydrant(s) are required, they will be installed at the Developer’s expense. ➢ Plans have been submitted to LRFD for evaluation. 4. Please submit plans for water facilities and/or fire protection system to Central Arkansas Water for review. Plan revisions may be required after additional review. Contact Central Arkansas