HomeMy WebLinkAboutStaff Report with MinutesApril 3, 2025
Historic District Commission
IV
Roll Call
DEPARTMENT OF PLANNING AND
DEVELOPMENT
723 West Markham Street
Little Rock, Arkansas 72201-1 334
Phone: (501) 371-4790 Fax:(501) 399-3435
www.Iittlerock.gov
LITTLE ROCK HISTORIC DISTRICT COMMISSION
MINUTE RECORD
Thursday, April 3, 2025, 4:00 p.m.
Board Room, Little Rock City Hall, 500 W. Markham
Members Present: Christina Aleman, Chair
Amber Jones, Vice Chair
Tom Fennell
Dr. Thomas DeGraff III
Chase Waters
Members Absent: Scott Green
Diane Thomas -Holliday
Staff Present: Hannah Ratzlaff
Raeanne Gardner
Cameron Bowden
Finding a Quorum
A quorum was present being five (5) in number.
Citizen Communication
Ms. Donna Colon addressed the commission. Ms. Colon expressed concern
regarding HDC2025-005 and enforcement action regarding the property at 1420
Commerce Street. The item was deferred to the May 1st meeting due to the applicant
providing the incorrect hearing date in the public notice letter.
Minutes
None
1
April 3, 2025
Historic District Commission
V
M
IM
National Register Nominations
None
Deferred Certificates of Appropriateness
None
New Certificates of Appropriateness
1. HDC2025-004
Joe Tollett
515 Rock Street
Rehabilitation, Site Improvements, Front
Porch Alterations and Reconstruction
2. HDC2025-005 CPA OZ Investments LLC
1420 S. Commerce Street
Skylights, Front Porch Alterations, Fencing
Deferred to May 1st, 2025 meeting due to
failure to meet public notice
requirements
3. HDC2025-006 First Lutheran Church
700 S. Rock Street
Rehabilitation, Site Improvements, Rear
Two -Story Enclosed Porch Alteration
0)
'I
�11f Iv
A04 PFr"c—
��� & ION a �-
« �
lion
a-1:3 �k
1 � ���
, ,
April 3, 2025
Historic District Commission
residence in 1867. The structure is Contributing to the MacArthur Park Historic District
and the most recent Arkansas Architectural Resource Form (PU2977, 2007) is provided
as Attachment C.
Development History
The Narkinsky House is supported by a brick masonry pier foundation and features a
rectangular plan covered by composite shingle, low-pitched hipped roof with gable
dormers on the front and side elevations. The home features elaborate Italianate
architectural detailing for a one-story dwelling, such as decorative eave brackets, tall,
narrow six -over -six wood windows with segmental arches, and a central wood frame
porch with Doric columns. The home's historic architectural detail are well documented
through photographs of the Narkinsky family, c. 1917-1942 (Attachment D). The
Narkinsky's were a Jewish family who lived in the structure during the early 20' century.
The structure is first depicted in the 1897 Sanborn map as a single -story frame dwelling
with a central, three-quarter front porch covered by non-combustible roofing, likely
metal, and a rear Ell wing, and rear porch covered by wood shake roofing (Figure 3). By
1913, the structure's rear wing and porch were removed, an addition was constructed,
and the front porch roof was covered with composite shingles (Figure 4). A rear room and
stoop were constructed at the rear of the addition and was covered by a wood shake
roof. By 1939, the rear stoop was enclosed and all roofing material was composite
shingle (Figure 5). Sometime between 1978 and 1987, the structure's front porch floor
and foundation was modified sometime between 1978 and 1987 with the original brick
masonry pierfoundation and wood floor being replaced with a solid brickfoundation and
brick floor (Figure 6).
Previous Action
On February 12, 2025, a COC (HDC2025-002) was issued to Joe Tollet for window repairs
and HVAC unit replacement.
On July 18, 2024, a COC (HDC2024-023) was issued to Joe Toilet for gutter installation
along the rear enclosed porch.
On May 3, 2024, a COC (HDC2024-012) was issued to Joe Tollett for the installation of a
ridge vent.
On May 29, 2025, a COC (HDC2024-007) was issued to Joe Tollett for the removal of non -
historic signage, removal of a handicap ramp on the front facade, and siding repair.
9
April 3, 2025
Historic District Commission
On June 15, 2023, a COC (HDC2023-015) was issued to Jean Madden and Camellia
Walker for porch repair, wood siding and trim board repair, wood soffit, fascia, and
bracket repair, painting, and roofing repair.
On April 4, 1991, a COA (HDC1991-001) was issued to Jean Madden for the renovation
and repair to front porch and an addition of a handicap ramp.
On September 3, 1987, a COA (HDC1987-003) was issued to Jean Madden for restoration
of a front porch.
! y
J
nl n
x
x A
!1
i
f
Figure 3. 515 Rock Street, 1987, Sanborn Map, Little RocFigure 4. 515 Rock Street, 1913, Sanborn Map, Little Rock.
k.
Figure 5. 515 Rock Street, 1939, Sanborn Map, Little Rock.
site.
Sanborn Maps:
C. EXISTING CONDITIONS:
No previous actions were found on this
Figure 6. 515 Rock Street, 1950, Sanborn Map, Little Rock.
See site photos (Attachment A) and application packet (Attachment B). The application
packet includes cover letter, application, site plan, architectural illustration, and
product sheets and specifications. Historical photographs of the site are found in
Attachment D.
April 3, 2025
Historic District Commission
D. NEIGHBORHOOD COMMENTS:
The time of distribution, there were no comments regarding this application.
All owners of properties located within 200 feet of the site and all neighborhood
associations registered with the City of Little Rock that surround the site were notified of
the public hearing.
E. ANALYSIS:
Pier Foundation Enclosure, Crawl Space Vents and Doors
The application proposes removing the existing painted plywood boards and enclosing
the brick masonry pierfoundation with salvaged brick, set back by 2 inches. Additionally,
the proposal includes installing cast iron crawl space vents and three smooth steel crawl
space doors.
Staff finds the proposal is consistent with the Design Guidelines, specifically Guideline
4.3 (4). The proposal uses appropriate infill material and sets the new material back a
few inches to differentiate between the historic pier system and the new infill material.
The crawl space vents and doors will be installed into the infill brick and the products are
compatible and subordinate to the historic feature.
Staff finds the proposal is consistent with the SOI Standards, specifically standard 9:
"New additions, exterior alterations, or related new construction shall not destroy
historic materials that characterize the property. The new work shall be differentiated
from the old and shall be compatible with the massing, size, scale, and architectural
features to protect the historic integrity of the property and its environment."
Front Porch Reconstruction
The application proposes several improvements and repairs to the front porch.
These include installing new flashing and metal roofing, removing the non -historic,
existing foundation (Figure 7), and reconstructing the pier and beam foundation
displayed in the Narkinsky family photographs (Attachment D). The porch
foundation will have a tongue -and -groove floor and foundation openings will be
covered in lattice. The front steps will be rebuilt using brick, wood, or concrete, and
black handrails will be added to meet code requirements.
The existing columns will be repositioned to align with the original foundation
location and roof elements. Missing eave brackets will be reconstructed, and the
fascia will be repaired and rebuilt as needed, based on physical evidence of the
original fascia found in the structure's attic (Figure 17, 18). The existing porch light
will be replaced (Figure 16), and the porch ceilingwill undergo plaster repair (Figure
7
April 3, 2025
Historic District Commission
13, 14). Lastly, the non -original horizontal support beams attaching the columns to
the front fagade wall will be removed (Figure 15).
Staff finds the reconstruction of missing or altered architectural elements based on
physical and pictorial evidence (Attachment D) to be consistent with Guideline
4.13(4). The proposed reconstruction ofthe missing architectural elements —porch
foundation, metal roofing, flooring, column realignment, eave brackets, fascia —
are supported bythe Narkinskyfamily photos, the Sanborn maps, and the physical
evidence assessed on site. Additionally, the proposed porch handrail is consistent
with Guideline 4.13(7) and is simple and subordinate in design and compatible with
the historic attributes of the property. Staff finds wood to be the most compatible
material for the reconstruction of the front steps, based on pictorial evidence.
Staff finds the proposal is consistent with the SOI Standards, specifically standard
6: "Deteriorated historic features shall be repaired rather than replaced. Where the
severity of deterioration requires replacement of a distinctive feature, the new
feature shall match the old in design, color, texture, and other visual qualities and,
where possible, materials. Replacement of missing features shall be substantiated
by documentary, physical, or pictorial evidence."
Porch Column Base Substitute Material
The application proposed to replace the existing front porch wood column bases
with fiber -reinforced polymer to reduce the risk of rot. Fiberglass and the related
Fiber Reinforced Polymers (collectively FRP) are synthetic materials that can be
molded into decorative shapes and details. They are lightweight and are often used
as a substitute for decorative wood or masonry elements. More information
regarding FRP can be found on page 56 of the Design Guidelines.
Staff finds the proposal to be inconsistent with the Design Guidelines. Guideline
3.6(3) discourages the removal of architectural features that are in good condition
and Guideline 4.13(1) encourages the replacement of historic materials too
deteriorated to repair with in kind materials. Staff finds that the requested
substitute material is not inappropriate for this use if replacement was necessary,
however the condition of the column bases has not deteriorated to the extent that
they cannot be repaired through ordinary maintenance.
Staff finds the proposal is inconsistent with the SOI Standards, specifically
standard 6: "Deteriorated historic features shall be repaired rather than replaced.
Where the severity of deterioration requires replacement of a distinctive feature,
the new feature shall match the old in design, color, texture, and other visual
N
April 3, 2025
Historic District Commission
qualities and, where possible, materials. Replacement of miss ingfeatures shall be
substantiated by documentary, physical, or pictorial evidence."
Realignment of Side Elevation Baseboards
The application proposes realigning the exterior, horizontal trim boards on the
historic rear addition with the trim boards of the original structure (Figure 9,12). The
addition was constructed sometime between 1897 and 1913 and is considered to
be historic. The misaligned trim boards showcase the expansion of the dwelling to
accommodate the occupants and is historic in its own right (Attachment D).
Staff finds the realignment of the side elevation baseboards to be inconsistent with
Guideline 4.8. The proposal alters an existing historic feature and is not
substantiated by documentation.
Staff finds the proposal is inconsistent with SOI Standards, specifically standard 4:
"Most properties change over time; those changes that have acquired historic
significance in their own right shall be retained and preserved."
Reconstruction of Chimneys
The application proposes to reconstruct two original chimneys that were once
prominent to the exterior: one near the front of the structure along the north
elevation and one near the rear of the structure along the south elevation, see front
fagade illustration in Attachment B. The two chimneys are visible in historic
photographs (Figure x and x), were removed by 1978, and the interior elements
remain beneath the roofline.
Staff finds the reconstruction of the two prominent chimneys consistent with
Guideline 4.26. The proposed reconstruction of the chimneys are supported by the
Narkinsky family photos and the physical evidence assessed on site.
Staff finds the proposal is consistent with the SOI Standards, specifically standard
6: "Deteriorated historic features shall be repaired rather than replaced. Where the
severity of deterioration requires replacement of a distinctive feature, the new
feature shall match the old in design, color, texture, and other visual qualities and,
where possible, materials. Replacement of missing features shall be substantiated
by documentary, physical, or pictorial evidence."
I]
April 3, 2025
Historic District Commission
Rear Porch Step Replacement
The application proposes replacing the rear porch steps with brick and the installation
of a handrail (Figure 10). The existing wood steps are deteriorated and require
replacement. As currently constructed, the steps and risers do not meet code. The rear
of the structure, inclusive of the steps, is visible from the public alley.
Staff finds the replacement of the rear steps to be necessary and finds the proposed
material to be inconsistent with Guideline 4.13 (1). Staff finds that brick steps may
appear as conjecture and that concrete steps would be more appropriate. The rear
steps are not protected by a covering, were humbly constructed, and are located on
the rear fagade. Concrete is a more compatible replacement as it is simple in design
and affords durability. Additionally, the proposed porch handrail is consistent with
Guideline 4.13(7) and is simple and subordinate in design and compatible with the
historic attributes of the property.
Staff finds the proposal is mostly consistent with the SOI Standards, specifically
standard 6: "Deteriorated historic features shall be repaired rather than replaced.
Where the severity of deterioration requires replacement of a distinctive feature, the
newfeature shall match the old in design, color, texture, and othervisual qualities and,
where possible, materials. Replacement of missingfeatures shall be substantiated by
documentary, physical, or pictorial evidence."
Sidewalk Replacement
The application proposes replacingthe concrete segment of the public sidewalkforthe
length of the propertywith brick masonry based on evidence from historic photographs
(Attachment D). The bricks will be laid in a herringbone pattern to reconstruct the
pattern visible in the historic photographs. Staff finds the sidewalk replacement
consistent with Guideline 9.8(5). The proposal is substantiated by pictorial evidence.
Staff finds the proposal is consistent with the SOI Standards, specifically standard 6:
"Deteriorated historic features shall be repaired rather than replaced. Where the
severity of deterioration requires replacement of a distinctive feature, the new feature
shall match the old in design, color, texture, and other visual qualities and, where
possible, materials. Replacement of missing features shall be substantiated by
documentary, physical, or pictorial evidence."
10
April 3, 2025
Historic District Commission
F. STAFF RECOMMENDATION:
Staff recommends the approval of the application, as submitted, excluding approval
for the realignment of the exterior trim boards and the replacement of the column
base with substitute materials, with the following conditions:
1. Chimneys: The location and design of the reconstructed chimneys will be
based directly on physical and documented evidence. Chimney flashing
to be installed in step pattern in the mortar joints of the masonry. Brick
masonry and mortar will match existing in dimension, scale, color,
texture and other physical attributes.
2. Sidewalk: Reconstruction of the brick masonry sidewalk will be based
directly on documented evidence. Additional engineering review and
inspection is required by the Planning & Development Department to
assure that the resulting sidewalk meets relevant accessibility and
environmental codes.
3. Exterior Porch Light: New lighting will conform to Guideline 9.22 and
require final review and approval by the staff.
4. Rear porch steps will be constructed of wood or concrete.
5. Front porch steps will be constructed of wood.
G. STAFF RECOMMENDATION (APRIL 3, 2025)
Staff member Ratzlaff presented the application to the commission. Commissioner
Fennell asked whether any historic documentation existed regarding the railing along
the rear steps. Ratzlaff identified a historic photograph included in the staff report that
depicted the railing.
Mr. Joe Tollett, the property owner and applicant, addressed the Commission. He
noted that the current railing is made of galvanized pipe and is not original, as shown in
the historic photographs.
Commissioner Aleman asked Mr. Tollett whether he was amenable to staff's
recommendations. Mr. Tollett responded that most of staff's comments had been
anticipated and were addressed during the Design Review Committee meeting. He
expressed agreement with all staff recommendations except for one: his request to use
a substitute material for the front porch column bases. Mr. Tollett explained that he
believed the current bases were not original and had been previously repaired with
profiles inconsistent with those shown in the historic photographs. He expressed a
desire to recreate the original profile using a substitute material.
11
April 3, 2025
Historic District Commission
Commissioner Jones commended the application for its alignment with the Design
Guidelines and the applicant's attention to detail in the restoration effort. She
acknowledged that the current column bases were not original and stated that, while
restoring the original profiles was appropriate, using wood rather than a substitute
material would be more consistent with the Design Guidelines and the Secretary of the
Interior's Standards. Commissioner Aleman concurred.
Mr. Tollett also requested an extension of the standard one-year expiration term for the
Certificate of Appropriateness (COA) to three years, explaining that he would be
completing the work himself. Staff member Ratzlaff confirmed that the request was
reasonable given the scope of work and noted that the ordinance permits the
commission to extend the COA expiration term at the applicant's request based on
project scope.
Commissioner Fennell made a motion to approve the application with staff's
recommendations, specifying that wood steps be used for the rear porch, and granting
a three-year extension of the COA expiration term. Commissioner Jones seconded the
motion. The motion passed with 5 ayes, 0 noes, and 2 absent.
12