HomeMy WebLinkAboutS-1721 Staff AnalysisITEM NO.: 2
NAME: Alexander Distribution Warehouse Subdivision Site Plan Review
LOCATION: located on South Loop Road just North of Alexander Road
S-1721
Planninq Staff Comments:
1. Provide notification of the abutting property owners including the certified abstract
list, notice form with affidavit executed and proof of mailing. The notice must be
mailed no later than February 5, 2014. The Office of Planning and Development
must receive the proof of notice no later than February 14, 2014.
2. Provide the building coverage, both the principal and accessory, in square feet.
3. Provide the floor area, principal and accessory of the proposed structures.
4. Provide the proposed number of parking spaces, employee and visitor.
5. Provide a note on the site plan indicating the maximum building height. The
maximum height allowed in the 1-2 zoning district is 45-feet.
6. Provide the number of spaces proposed for the future employee parking area.
7. The design standards for the South Loop Bypass — divided roadway — 4 through
lanes with a divided median; median openings at collector and arterial road
crossings; partially controlled property access with ingress and egress at a minimum
spacing of 300-feet; joint access driveways with right turn channelization and
deceleration lanes are encouraged.
Variance/Waivers: Land Alteration Variance (?)
Public Works Conditions:
1. Due to Master Street Plan requirements and restriction of the right-of-way purchase
deeds, the only full access to South Loop Road is from arterial and collector streets.
The proposed commercial street to the north must be removed.
2. Per the Master Street Plan, half of a minor arterial street should be constructed
along the south property line to the west property line with a temporary gravel
turnaround of 100 feet in diameter. Additional street width is needed at the South
Loop Road intersection.
3. With site development, provide the design of street conforming to the Master Street
Plan. Construct one-half street improvement to the new minor arterial street along
the south property line including 5-foot sidewalks with the planned development.
One half of a minor arterial street consists of 27.5 feet of pavement with a 2 foot curb
and gutter section. The full street width must be constructed at the South Loop
Road intersection. A median cut can be constructed of sufficient size and width for a
future minor arterial street intersection from the east.
4. Provide a letter prepared by a registered engineer certifying the sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards.
Item # 2.
5. A grading permit in accordance with Section 29-186 (c) and (d) will be required prior
to any land clearing or grading activities at the site. Other than residential
subdivisions, site grading and drainage plans must be submitted and approved prior
to the start of construction. A variance must be requested to grade off the proposed
site.
6. Stormwater detention ordinance applies to this property.
7. If disturbed area is one (1) or more acres, obtain a NPDES stormwater permit from
the Arkansas Department of Environmental Quality prior to the start of construction.
8. Street Improvement plans shall include signage and striping. Public Works must
approve completed plans prior to construction.
9. Streetlights are required by Section 31-403 of the Little Rock code. Provide plans
for approval to Traffic Engineering. Streetlights must be installed prior to
platting/certificate of occupancy. Contact Traffic Engineering 379-1813 (Greg
Simmons) for more information.
10. Damage to public and private property due to hauling operations or operation of
construction related equipment from a nearby construction site shall be repaired by
the responsible party prior to issuance of a certificate of occupancy.
11.The proposed location of the new driveway to the subject property on the new minor
arterial street must be located at least 600 feet from the South Loop Road right-of-
way and at least 150 feet from the property line of the subject property.
Utilities and Fire Department/County Planning:
Wastewater: Sewer main extension required with easements if sewer service is
required for this project. Contact Little Rock Wastewater Utility for additional
information.
Entergy: Entergy Distribution does not object, but Entergy Transmission will need to
review and respond.
Center -Point EneLgy: No comment received.
AT & T: No comment received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for water
service must be met.
2. A water main extension will be needed to provide water service to Lots 3 and 4 on
this property.
3. This development will have minor impact on the existing water distribution system.
Proposed water facilities will be sized to provide adequate pressure and fire
protection.
Item # 2.
4. The Little Rock Fire Department needs to evaluate this site to determine whether
additional public and/or private fire hydrant(s) will be required. If additional fire
hydrant(s) are required, they will be installed at the Developer's expense.
5. Please submit plans for water facilities and/or fire protection system to Central
Arkansas Water for review. Plan revisions may be required after additional review.
Contact Central Arkansas Water regarding procedures for installation of water
facilities and/or fire service. Approval of plans by the Arkansas Department of
Health Engineering Division and the Little Rock Fire Department is required.
6. Contact Central Arkansas Water regarding the size and location of the water meter.
7. A Capital Investment Charge based on the size of meter connection(s) will apply to
this project in addition to normal charges. This fee will apply to all connections
including metered connections off the private fire system.
8. If there are facilities that need to be adjusted and/or relocated, contact Central
Arkansas Water. That work would be done at the expense of the developer.
9. Due to the nature of this facility, installation of an approved reduced pressure zone
backflow preventer assembly (RPZA) is required on the domestic water service.
This assembly must be installed prior to the first point of use. Central Arkansas
Water requires that upon installation of the RPZA, successful tests of the assembly
must be completed by a Certified Assembly Tester licensed by the State of Arkansas
and approved by Central Arkansas Water. The test results must be sent to Central
Arkansas Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 377-1226 if you would
like to discuss backflow prevention requirements for this project.
10. The facilities on -site will be private. When meters are planned off private lines.
Private facilities shall be installed to Central Arkansas Water's material and
construction specifications and installation will be inspected by an engineer, licensed
to practice in the State of Arkansas. Execution of Customer Owned Line agreement
is required.
Fire Department: Place fire hydrant(s) per code. Maintain access. Contact the Little
Rock Fire Department for additional information.
County Planning: No comment.
CATA: Out of service area.
Parks and Recreation: No comment received.
Planning Division: No comment.
Item # 2,
Landscape-
1. Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
2. Interior landscape areas shall comprise a minimum of eight (8) percent of any
vehicular use area containing twelve (12) or more parking spaces.
3. An automatic irrigation system to water landscaped areas will be required.
4. Prior to the issuance of a building permit, it will be necessary to provide an approved
landscape plan stamped with the seal of a registered landscape architect.
5. The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can
be given when preserving trees of six (6) inch caliper or larger.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, February 5, 2014.
Item # 2.
February 20, 2014
ITEM NO.: 2
FILE NO.: S-1721
NAME: Alexander Distribution Warehouse Subdivision Site Plan Review
LOCATION: Located on South Loop Road just North of Alexander Road
DEVELOPER:
Saad Development Corporation
3601 Spring Hill Business Park Suite 200
Mobile, AL 36608
FNGINEER:
White-Daters and Associates
Mr. Joe White
24 Rahling Circle
Little Rock, AR 72223
CURRENT ZONING: 1-2, Light Industrial
PLANNING DISTRICT: 16 — Otter Creek
CENSUS TRACT- 41.04
VARIANCEMAIVERS: A variance from Section 29-186 to allow advanced grading
on an adjacent property.
A. PROPOSAUREQUESTIAPPLICANT'S STATEMENT:
The property contains 42+ acres and is located on South Loop Road just north of
Alexander Road. The property is currently zoned 1-2, Light Industrial District.
The request is for approval of a site plan per Section 31-13 of the Little Rock
Code to allow the construction of multiple buildings on a single site. The
development is proposed as a build to suit project for a large national tenant.
The building will cover just over 300,000 square feet of warehouse space to allow
package distribution for the Central Arkansas area. Access for the trucks will be
taken from a new arterial along the southern boundary of the development which
connects to South Loop Road just north of Alexander Road.
The developer is requesting a variance from the City's Land Alteration Ordinance
to allow advanced grading on an adjacent site just to the east. The property is
owned by the seller. The applicant states grading in this area will allow the
properties to match grade and eliminate the need to haul fill into this site.
February 20, 2014
SUBDIVISION
ITEM NO.: 2(Cont.)FILE NO.: S-1721
B. EXISTING CONDITIONS:
The site is a pasture bounded by a railroad main line on the northwest and an
electrical transmission line on the south. The site is relatively flat with few trees.
There is a stock pond located within the property near the western edge. The
east bound lanes of South Loop Road have been constructed. The right of way
is in place for the west bound lanes. The bridge crossing the railroad main line is
an elevated bridge and was constructed as a two-lane bridge. Alexander Road is
located to the south of this site and Mabelvale West Road to the north.
Alexander Road is a two lane road with open ditches for drainage. Some
improvements have been made to the intersection of Mabelvale West Road
South Loop Road however the north side of the intersection is an open ditch.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has received a few informational phone calls from area
residents. All property owners located within 200-feet of the site along with
Southwest Little Rock United for Progress, the Alexander Road Neighborhood
Association and the Meyer Lane Neighborhood Association were notified of the
public hearing. (The Meyer Road Neighborhood Notice was returned to staff and
marked unforwardable. In addition staff called the phone number listed for the
contact person. The phone number has been disconnected.)
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Due to Master Street Plan requirements and restriction of the right-of-way
purchase deeds, the only full access to South Loop Road is from arterial
and collector streets. The proposed commercial street to the north must be
removed.
2. Per the Master Street Plan, half of a minor arterial street should be
constructed along the south property line to the west property line with a
temporary gravel turnaround of 100 feet in diameter. Additional street width
is needed at the South Loop Road intersection.
3. With site development, provide the design of street conforming to the
Master Street Plan. Construct one-half street improvement to the new
minor arterial street along the south property line including 5-foot sidewalks
with the planned development. One half of a minor arterial street consists of
27.5 feet of pavement with a 2 foot curb and gutter section. The full street
width must be constructed at the South Loop Road intersection. A median
cut can be constructed of sufficient size and width for a future minor arterial
street intersection from the east.
2
February 20, 2014
SUBDIVISION
NO.: 2 (Cont.
FILE NO.: S-1721
4. Provide a letter prepared by a registered engineer certifying the sight
distance at the intersection(s) comply with 2004 AASHTO Green Book
standards.
5. A grading permit in accordance with Section 29-186 (c) and (d) will be
required prior to any land clearing or grading activities at the site. Other
than residential subdivisions, site grading and drainage plans must be
submitted and approved prior to the start of construction. A variance must
be requested to grade off the proposed site.
6. Stormwater detention ordinance applies to this property.
7. If disturbed area is one (1) or more acres, obtain a NPDES stormwater
permit from the Arkansas Department of Environmental Quality prior to the
start of construction.
8. Street Improvement plans shall include signage and striping. Public Works
must approve completed plans prior to construction.
9. Streetlights are required by Section 31-403 of the Little Rock code. Provide
plans for approval to Traffic Engineering. Streetlights must be installed prior
to platting/certificate of occupancy. Contact Traffic Engineering 379-1813
(Greg Simmons) for more information.
10. Damage to public and private property due to hauling operations or
operation of construction related equipment from a nearby construction site
shall be repaired by the responsible party prior to issuance of a certificate of
occupancy.
11. The proposed location of the new driveway to the subject property on the
new minor arterial street must be located at least 600 feet from the South
Loop Road right-of-way and at least 150 feet from the property line of the
subject property.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer main extension required with easements if sewer service is
required for this project. Contact Little Rock Wastewater Utility for additional
information.
Entergy: Entergy Distribution does not object, but Entergy Transmission will
need to review and respond.
Center -Point Energy: No comment received.
AT & T: No comment received.
3
February 20, 2014
SUBDIVISIO
ITEM NO.: 2 (Cont.) FILE NO.: S-1721
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for
water service must be met.
2. This development will have minor impact on the existing water distribution
system. Proposed water facilities will be sized to provide adequate pressure
and fire protection.
3. The Little Rock Fire Department needs to evaluate this site to determine
whether additional public and/or private fire hydrant(s) will be required. If
additional fire hydrant(s) are required, they will be installed at the Developer's
expense.
4. Please submit plans for water facilities and/or fire protection system to Central
Arkansas Water for review. Plan revisions may be required after additional
review. Contact Central Arkansas Water regarding procedures for installation
of water facilities and/or fire service. Approval of plans by the Arkansas
Department of Health Engineering Division and the Little Rock Fire
Department is required.
5. Contact Central Arkansas Water regarding the size and location of the water
meter.
6. A Capital Investment Charge based on the size of meter connection(s) will
apply to this project in addition to normal charges. This fee will apply to all
connections including metered connections off the private fire system.
7. If there are facilities that need to be adjusted and/or relocated, contact Central
Arkansas Water. That work would be done at the expense of the developer.
8. Due to the nature of this facility, installation of an approved reduced pressure
zone backflow preventer assembly (RPZA) is required on the domestic water
service. This assembly must be installed prior to the first point of use.
Central Arkansas Water requires that upon installation of the RPZA,
successful tests of the assembly must be completed by a Certified Assembly
Tester licensed by the State of Arkansas and approved by Central Arkansas
Water. The test results must be sent to Central Arkansas Water's Cross
Connection Section within ten days of installation and annually thereafter.
Contact the Cross Connection Section at 377-1226 if you would like to
discuss backflow prevention requirements for this project.
El
February 20, 2014
SUBDIVISION
ITEM NO.: 2 (Cont_
F
G
FILE NO.: S-1721
9. The facilities on -site will be private. When meters are planned off private
lines. Private facilities shall be installed to Central Arkansas Water's material
and construction specifications and installation will be inspected by an
engineer, licensed to practice in the State of Arkansas. Execution of
Customer Owned Line agreement is required.
Fire Department: Place fire hydrant(s) per code. Maintain access. Contact the
Little Rock Fire Department for additional information.
County Planning: No comment.
CATA: Out of service area.
Parks and Recreation: No comment received.
ISSUES/TECHNICAUDESIGN:
Planning Division: No comment.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance
requirements.
2. Interior landscape areas shall comprise a minimum of eight (8) percent of any
vehicular use area containing twelve (12) or more parking spaces.
3. An automatic irrigation system to water landscaped areas will be required.
4. Prior to the issuance of a building permit, it will be necessary to provide an
approved landscape plan stamped with the seal of a registered landscape
architect.
5. The City Beautiful Commission recommends preserving as many existing
trees as feasible on this site. Credit toward fulfilling Landscape Ordinance
requirements can be given when preserving trees of six (6) inch caliper or
larger.
SUBDIVISION COMMITTEE COMMENT:
(January 29, 2014)
Mr. Joe White of White-Daters and Associates was present representing the
request. Staff presented an overview of the item stating the request was for a
multiple building site plan review to allow the placement of a warehouse
distribution center on 40+ acres. Staff stated there were few outstanding
technical issues associated with the request. Staff requested Mr. White provide
5
February 20, 2014
SUBDIVISION
ITEM NO.: 2 (Cont.) _ FILE NO.: S-1721
the maximum building height for the structures, the percentage of building
coverage and the number of parking spaces indicated for employee parking.
Public Works comments were addressed. Staff stated access to South Loop
Road was not permitted due to conditions placed on the Federal Grant received
to construct the street. Staff stated the stormwater detention ordinance would
apply to the development of the property. Staff questioned if grading would take
place off -site. Staff stated half street improvements were required to the
proposed arterial street.
Landscaping comments were addressed. Staff stated interior landscape areas
were to comprise a minimum of eight percent of the vehicular use area
containing twelve or more parking spaces. Staff stated prior to the issuance of a
building permit a landscape plan prepared by a registered landscape architect
would be required.
Staff noted comments from the other reporting departments and agencies
suggesting the applicant contact them individually for additional clarification.
There was no further discussion of the item. The Committee then forwarded the
item to the full Commission for final action.
H. ANALYSIS:
The applicant submitted a revised site plan to staff addressing a number of the
issues raised at the January 29, 2014, Subdivision Committee meeting. The
applicant has provided the maximum building height for the building, the
percentage of building coverage and the number of parking spaces to serve the
employees.
The property is currently zoned 1-2, Light Industrial District. The request is for
approval of a site plan per Section 31-13 of the Little Rock Code to allow the
construction of multiple buildings on a single site. The principal structure is
proposed containing 305,000 square feet of warehouse space. The site has
been moved to the west and no longer has frontage on South Loop Road. The
reason for the relocation was to avoid wetlands located near the southeastern
portion of the site. The improvements to South Loop Road will be completed at
the time the property with frontage is developed. Access to the development will
be taken from a new arterial, future Mabelvale Cut-off Road, along the southern
boundary of the development.
The developer is requesting to construct the full 59 foot width of the east
1,280 feet of the Mabelvale Cut-off Extension as shown on the Master Street
Plan with sidewalk on the north side only and construct a temporary cul de sac at
11
February 20, 2014
SUBDIVISION
ITEM NO.: 2 Cont.) FILE NO.: S-1721
the end of the paving. In addition the applicant is proposing to place a full traffic
signal at the intersection of Mabelvale West and South Loop Road along with
restriping of the intersection and one lane of additional paving on the north side
of the intersection as outlined by the Public Works staff. This construction will be
completed in lieu of the half street improvements for the entire length of the
Mabelvale Cut-off Extension adjacent to the applicant's property. At the time the
street design of Mabelvale Cut-off is submitted to Public Works for review and
approval a traffic study will be required to determine the design of the intersection
and the need for a traffic signal at the intersection of Mabelvale Cut-off and South
Loop Road.
The building coverage proposed for the principal structure is 15.4 percent. The
entrance building is proposed containing 3,140 square feet with a building
coverage of 0.16 percent and the vehicle maintenance building is proposed
containing 5,180 square feet of floor area with a building coverage of
0.26 percent.
The site plan indicates a total of 630 employee parking spaces will be
constructed with the initial development. An additional 120 spaces are indicated
on the site plan as future expansion of the employee parking area.
The applicant has indicated the maximum building height proposed is 45-feet.
The 1-2, Light Industrial Zoning District allows a maximum building height of
45-feet. All signage is proposed to comply with the typical standards of the
zoning ordinance for industrially zoned property.
The developer is requesting a variance from the City's Land Alteration Ordinance
to allow advanced grading on an adjacent site just to the east. The property is
owned by the seller. The applicant states grading in this area will allow the
properties to match grade and eliminate the need to haul fill into this site.
Staff is supportive of the proposed development and the street improvements as
indicated by the applicant. The request is for a multiple building site plan review
to allow the placement of a warehouse distribution facility on this 1-2, Light
Industrial zoned property containing 40+ acres. The site plan appears to fully
comply with the minimum standards of the zoning district. There is a variance
associated with the City's Land Alteration Ordinance to allow grading of a portion
of an adjacent site with the grading of this site. Staff is supportive of allowing the
grading as proposed. To staffs knowledge there are no remaining outstanding
technical issues associated with the request.
7
February 20, 2014
SUBDIVISION
ITEM NO.: 2 (Cont.) FILE NO.: S-172
STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
Staff recommends approval of the variance request from the City's Land
Alteration Ordinance to allow grading of a portion of an adjacent site with the
grading of this site.
Staff recommends in -lieu of construction of one-half street improvements to
Mabelvale Cut-off Road the applicant construct the full 59 foot width of the east
1,280 feet of the Mabelvale Cut-off Extension as shown on the Master Street
Plan with sidewalk on the north side only and construct a temporary cul de sac at
the end of the paving.
Staff recommends at the time the street design is submitted to Public Works for
review and approval a traffic study will be required to determine the design of
the intersection and the need for a traffic signal at the intersection of Mabelvale
Cut-off and South Loop Road.
PLANNING COMMISSION ACTION: (FEBRUARY 20, 2014)
The applicant was present. There were registered objectors present. Staff presented
the item with a recommendation of approval of the request subject to compliance with
the comments and conditions as outlined in paragraphs D, E and F of the agenda staff
report. Staff presented a recommendation of approval of the variance request from the
City's Land Alteration Ordinance to allow grading of a portion of an adjacent site with
the grading of this site. Staff presented a recommendation in -lieu of construction of
one-half street improvements to Mabelvale Cut-off Road the applicant construct the full
59 foot width of the east 1,280 feet of the Mabelvale Cut-off Extension as shown on the
Master Street Plan with sidewalk on the north side only and construct a temporary
cul de sac at the end of the paving. Staff presented a recommendation at the time the
street design was submitted to Public Works for review and approval a traffic study was
required to determine the design of the intersection and the need for a traffic signal at
the intersection of Mabelvale Cut-off and South Loop Road.
Mr. Joe White of White-Daters and Associates addressed the Commission on the merits
of the request. He stated the property was zoned 1-2, Light Industrial which allowed the
construction of the facility as proposed. Mr. White stated the only reason the
development was before the Commission was to allow multiple buildings as per the
Subdivision Ordinance. He stated he had suggested to the developers to place the
E:3
February 20, 2014
SUBDIVISION
ITEM NO.: 2 (Cont.) FILE NO.: S-1721
loading dock doors on the south side of the building due to grade issues. Mr. White
stated the developers refused this suggestion because of their sensitivity to the
neighborhood. He stated the developers were requesting to construct the entire width
of Mabelvale Cut-off Extension along their frontage instead of constructing '/2 street
improvements along their entire frontage. Mr. White stated the street construction for
full width verses 1/2 width construction had been done before the most recent case was
LaMarche Drive next to the Gardens at Valley Falls. He stated the developers were
providing a traffic signal at the intersection of Mabelvale West and South Loop Road to
allow safe access to the site.
Ms. BJ Wyrick, City Director Ward 7, addressed the Commission with concerns. She
stated she was a property owner in the area and lived across Alexander Road from the
proposed development. She stated she understood property rights, zoning and the site
plan review process. Director Wyrick stated she was concerned with the impact the
proposed development would have on the new South Loop Road. She stated before
South Loop Road was constructed the neighborhood had two (2) entrances but both
were impacted by at -grade railroad crossings. Director Wyrick stated the limited access
impacted public health and safety for area residents. She stated the volume of traffic
and the truck traffic from the facility would impact South Loop Road: Director Wyrick
stated she was aware a traffic study had been completed and the volume of traffic did
not meet warrants to place a traffic signal at the intersection of South Loop Road and
the Mabelvale Cut-off Extension. Director Wyrick stated even if warrants were not met
there would be a need for a traffic signal at the intersection.
Ms. Pam Adcock, President of Southwest Little Rock United for Progress, addressed
the Commission with concerns. She stated the developer should be required to
construct full street improvements connecting to Alexander Road with the new
construction and to place a traffic signal at the intersection of South Loop Road and
Mabelvale Cut-off Extension.
Mr. Ronnie Dedman addressed the Commission with concerns. He stated he lived in
the area and was concerns with traffic flow. He stated South Loop Road had improved
access to the area.
Mr. White stated the developers were not prepared to construct the full street
improvements from the site to Alexander Road. The Commission questioned the traffic
study which had been completed. Mr. White stated there were two (2) questions being
generated about traffic signals. He stated one was if a traffic signal was warranted at
Mabelvale West and South Loop Roads located to the north of the site and if a traffic
signal was warranted at South Loop Road and Mabelvale Cut-off Extension. Mr. White
stated according to the traffic study the warrants would be met at the intersection of
Mabelvale West and South Loop Roads but not on the Mabelvale Cut-off Extension and
South Loop Road.
9
February 20, 2014
SUBDIVISION
ITEM NO.: 2 (Cont.
FILE NO.:
Mr. Ernie Peters addressed the Commission stating it would be a number of years
before a light was warranted at South Loop Road and Mabelvale Cut-off Extension. He
stated without the new development warrants were not met for a traffic signal at
Mabelvale West and South Loop Roads. Mr. Peters stated only when the projections
for the new development were factored into the overall traffic counts did the intersection
of South Loop and Mabelvale West Roads meet warrants for the traffic signal.
There was no further discussion of the item. The Chair entertained a motion of approval
of the item as presented by staff. The motion carried by a vote of 10 ayes 0 noes and
1 absent.
10
James, Donna
From: Joe White, Jr. <jwhite@whitedaters.com>
Sent: Monday, February 10, 2014 7:44 AM
To: James, Donna
Subject: In lieu wording
Attachments: 20140206124831.pdf, 20140206130207.pdf
The developer is not asking the City of Little Rock to pay for any improvements
associated with this project.
The developer is requesting to construct the full 59 ft width of the east 1280 ft of the
Alexander Extension as shown on the MSP (see the first attachment) with sidewalk on the
north side only, a temporary culdesac at the end of the paving, a full traffic signal at
the intersection of Mabelvale West & South Loop Road along with restriping of the
intersection and one lane of additional paving on the north side of the intersection as
outlined by the Public Works staff (see second attachment) in lieu of the half street
improvements for the entire length of the Alexander Extension.
Joe White, P.E.
White-Daters & Associates, Inc.
24 Rahling Circle
Little Rock, AR 72223
P: (501) 821-1667
F: (501) 821-1668