ITEM NO.: 5 FILE NO.: S-1516
NAME: Taylor Glenn Addition Preliminary Plat
LOCATION: West end of Beckenham Drive, near the intersection with Huntleigh Court
DEVELOPER:
Beverly A. Taylor
2102 Old Forge Drive
Little Rock, AR 72227
ENGINEER -
Robert Holloway
200 Casey Drive
Maumelle, AR 72113
AREA: 5.47 acres
CURRENT ZONING
PLANNING DISTRICT
CENSUS TRACT:
NUMBER OF LOTS: 10
R-2, Single-family
19 - Chenal
42.06
VARIANCES/WAIVERS REQUESTED: None requested.
FT. NEW STREET: 495 LF
The Little Rock Planning Commission at their February 21, 1995, Public Hearing, was
scheduled to review a proposed preliminary plat for the area. Prior to the public hearing
the applicant submitted a request withdrawing the proposed plat. The proposed plat
included the subdivision of the site with ten (10) single-family lots.
A. PROPOSAUREQUEST:
The applicant is now proposing the subdivision of this 5.47-acre tract into ten (10)
single-family lots. The lots range in size from 0.238 acres to 0.575 acres with an
average lot size of 0.309 acres. The site plan includes two (2) areas set aside as
tracts. Tract A has been indicated for future development and Tract B has been
indicated as open space.
March 30, 2006
SUBDIVISION
ITEM NO.: 5 Cont. FILE NO.: S-1516
Beckenham Drive has been indicated to extend from the current terminus to the
northwest to the property's boundary. The terminus of the street has been
indicated with a hammerhead turn -around per the Master Street Plan.
B. EXISTING CONDITIONS:
The site is undeveloped and heavily wooded along the northern portion of the
property. The property located along the southern portion of the site was
previously cleared. There are parts of two lots, which are fairly level; however,
the majority of the area is extremely hilly, with grades ranging from 12 to
26 percent.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has received several informational phone calls from
residents. The abutting property owners along with the Chenal Ridge Property
Owners Association were notified of the public hearing.
D. ENGINEERING COMMENTS:
Public Works. Conditions:
1. Beckenham Drive is classified on the Master Street Plan as a collector
street. A dedication of right-of-way to 60 feet will be required.
2. With the site development, provide the design of the street conforming to
the Master Street Plan. Construct street improvements to the street
including 5-foot sidewalk on one side with the planned development.
3. Construct full width of street at hammerhead and extend construction
improvements to the property line.
4. If disturbed area is one (1) or more acres, obtain a NPDES storm water
permit from the Arkansas Department of Environmental Quality prior to the
start of construction.
5. A grading permit in accordance with Section 29-186 (c) and (d) will be
required prior to any land clearing or grading activities at the site. Site
grading, and drainage plans will need to be submitted and approved prior
to the start of construction.
6. Storm water detention ordinance applies to this property. Show the
proposed location for storm water detention facilities on the plan.
7. On site striping and signage plans should be forwarded to Public Works,
Traffic Engineering for approval with the site development package.
8. Prepare a letter of pending development addressing streetlights as
required by Section 31-403 of the Little Rock code. Contact Traffic
Engineering at (501) 379-1813 (Steve Philpott) for more information
regarding streetlight requirements.
9. Obtain permits prior to doing any street cuts or curb cuts. Obtain barricade
2
March 30, 2006
SUBDIVISION
ITEM NO.: 5 (Cont.
E.
F
G.
FILE NO.: S-1516
permit prior to doing any work in the right-of-way. Contact Traffic
Engineering at (501) 379-1817 (Derrick Bergfield) for more information.
10. Hauling of fill material on or off site over municipal streets and roads
requires approval prior to a grading permit being issued. Contact Public
Works Traffic Engineering at 621 S. Broadway, (501) 379-1817 (Derrick
Bergfield) for more information.
UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer main extension required, with easements, if service is
required for the project. Contact Little Rock Wastewater Utility at 688-1414 for
additional information.
Entergy: No comment received.
Center -Point Ener : No comment received.
SBC: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at
the time of request for water service must be met. A Capital Investment Charge
based on the size of connection(s) will apply to this project in addition to normal
charges if additional and/or larger meter is installed. A water main extension will
be required in order to provide service to this property. This development will
have minor impact on the existing water distribution system. Proposed water
facilities will be sized to provide adequate pressure and fire protection. Contact
Central -Arkansas Water at 377-1225 for additional information.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department at 918-3700 for additional information.
County Planning: No comment.
CATA: The site is not located on a dedicated CATA Bus Route.
ISS U ES/TEC H N I CALIDES IG N:
Planning Division: No comment.
Landscape: No comment.
SUBDIVISION COMMITTEE COMMENT:
(March 8, 2006)
Mr. Bob Holloway was present representing the request. Staff presented the
item stating there were few outstanding issues associated with the proposed
3
March 30, 2006
SUBDIVISION
ITEM NO.: 5
LE NO.: S-1516
request. Staff requested the applicant provide the zoning classification .within the
plat boundary and of abutting properties. Staff also stated the street name was
spelled incorrectly and requested the applicant correct the spelling.
Public Works comments were addressed. Staff stated Beckenham Drive was
indicated on the Master Street Plan as a collector street and the.:.indicated
right-of-way and street width was adequate to meet the Master Street Plan
standard. Staff stated Beckenham Drive needed to be extended to the property
line and the turn -around should provide a proper turning radius. Staff stated the
storm water detention ordinance applied to the proposed development and
requested the proposed detention facilities be indicated on the proposed
preliminary plat.
Staff noted comments from the other reporting departments and agencies
suggesting the applicant contact them individually for additional clarification.
There was no further discussion of the item. The Committee then forwarded the
item to the full Commission for final action.
H. ANALYSIS:
The applicant submitted a revised preliminary plat to staff addressing most of the
issues raised at the March 8, 2006, Subdivision Committee meeting. The
applicant has indicated the zoning classification within the plat boundary and -of
abutting properties and provided the correct spelling of Beckenham Drive.
Beckenham Drive has been extended to the property line and the turn -around
now :,:provides a proper turning radius. The proposal indicates storm water
detention facilities on the proposed preliminary plat and the applicant has
indicated detention facilities will be sized to handle post development flows.
Tract A has been indicated for future development and Tract B has been
indicated as detention and open space.
The :applicant is proposing the subdivision of this 5.47 acre tract into ten (10)
single-family lots at a density of 5.4 units per acre. The lots range in:size from
0.238 acres to 0.575 acres with an average lot size of 0.309 acres. The lots
have been indicated with a minimum lot width of 85.5 and a minimum lot depth of
114.18. The indicated lot area, widths and depths are more than adequate to
meet the minimum requirements of the Subdivision Ordinance.
Staff is supportive of the proposed request. The indicated subdivision appears to
fully comply with the minimum standards set forth in the ordinance. To staffs
knowledge there are no outstanding issues associated with the request:
4
March 30, 2006
UBDIVISION
ITEM NO.: 5 (Cont.) FILE NO.: S-1516
STAFF RECOMMENDATION:
Staff recommends approval of the requested preliminary plat subject to
compliance with the comments and conditions as outlined in paragraphs D, E
and F of the above agenda staff report.
PLANNING COMMISSION ACTION: (MARCH 30, 2006)
The applicant was present representing the request. There were no registered
objectors present. Staff presented the item with a recommendation of approval of the
requested preliminary plat subject to compliance with the comments and conditions as
outlined in paragraphs D, E and F of the agenda staff report.
There was no further discussion of the item. The chair entertained a motion for
placement of the item on the Consent Agenda for Approval. The motion carried by a
vote of 10 ayes, 0 noes and 1 absent.
5
ITEM NO.: 5
S-1516
NAME: Taylor Glenn Addition Preliminary Plat
LOCATION: West end of Beckenham Drive, near the intersection with Huntleigh Court
Planning_ Staff Comments:,
1. Provide notification of abutting property owners of the site, complete with the
certified abstract list, notice form with affidavit executed and proof of mailing. The
notice must be mailed no later than March 15, 2006. The Office of Planning and
Development must receive the proof of notice no later than March 24, 2006.
2. Provide the source of title in the General Notes Section of the proposed preliminary
plat.
3. Provide the limits of the floodway and/or floodplain or provide a statement indicating
the site is not located within a floodway or floodplain.
4. Provide a storm drainage analysis for all water courses entering and leaving the plat
boundary.
5. Provide a preliminary storm drainage plan with typical ditch section shown.
6. Provide the zoning classification within the plat area along with the zoning
classification of abutting properties.
7. Provide a phasing plan if applicable.
Variance/Waivers: None requested.
Public Works Conditions:
1. Beckenham Drive is classified on the Master Street Plan as a collector street. A
dedication of right-of-way to 60 feet will be required.
2. With the site development, provide the design of the street conforming to the
Master Street Plan. Construct street improvements to the street including 5-foot
sidewalk on one side with the planned development.
3. Construct full width of street at hammerhead and extend construction
improvements to the property line.
4. If disturbed area is one (1) or more acres, obtain a NPDES storm water permit
from the Arkansas Department of Environmental Quality prior to the start of
construction.
5. A grading permit in accordance with Section 29-186 (c) and (d) will be required
prior to any land clearing or grading activities at the site. Site grading, and
drainage plans will need to be submitted and approved prior to the start of
construction.
6. Storm water detention ordinance applies to this property. Show the proposed
location for storm water detention facilities on the plan.
7. On site striping and signage plans should be forwarded to Public Works, Traffic
Engineering for approval with the site development package.
Item # 5
8. Prepare a letter of pending development addressing streetlights as required by
Section 31-403 of the Little Rock code. Contact Traffic Engineering at (501) 379-
1813 (Steve Philpott) for more information regarding streetlight requirements.
9. Obtain permits prior to doing any street cuts or curb cuts. Obtain barricade permit
prior to doing any work in the right-of-way. Contact Traffic Engineering at (501)
379-1817 (Derrick Bergfield) for more information.
10. Hauling of fill material on or off site over municipal streets and roads requires
approval prior to a grading permit being issued. Contact Public Works Traffic
Engineering at 621 S. Broadway, (501) 379-1817 (Derrick Bergfield) for more
information.
Utilities and Fire Department/County Planning:
Wastewater: Sewer main extension required, with easements, if service is required
for the project. Contact Little Rock Wastewater Utility at 688-1414 for additional
information.
Entergy:
Center -Point Energy:
SBC:
Central Arkansas Water: All Central Arkansas Water requirements in effect at the time
of request for water service must be met. A Capital Investment Charge based on the
size of connection(s) will apply to this project in addition to normal charges if additional
and/or larger meter is installed. A water main extension will be required in order to
provide service to this property. This development will have minor impact on the existing
water distribution system. Proposed water facilities will be sized to provide adequate
pressure and fire protection. Contact Central Arkansas Water at 377-1225 for additional
information.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department at 918-3700 for additional information.
County_Planning: No comment.
CATA: The site is not located on a dedicated CATA Bus Route.
Planning Division: No comment.
Landscape: No comment.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat (to include the
additional information as noted above) to staff on Wednesday, March 15, 2006.