HomeMy WebLinkAboutS-1397-B Staff AnalysisFILE NO.: S-1397-B
NAME: Stone Creek Phase I Replat
LOCATION: Located on the West end of Glen Valley Drive on Clancy Court
DEVELOPER:
AS Rosen & Associates, Inc.
Bill Bosley, Agent
9107 Rodney Parham Road
Little Rock, AR 72203
ENGINEER:
Civil Design, Inc.
15104 Cantrell Road
Little Rock, AR 72223
AREA: 6.582 acres
CURRENT ZONING:
PLANNING DISTRICT:
CENSUS TRACT:
Variance/Waivers:
NUMBER OF LOTS: 23
R-2, Single-family
19 — Chenal Planning District
42.11
FT. NEW STREET: 0 LF
1. A variance to allow a 15-foot front building line along Lots 1 R — 17R.
2. A variance to allow a 15-foot rear yard setback of 15-feet for Lots 15R and 16R.
BACKGROUND:
On October 16, .2004, the Little Rock Planning Commission reviewed a request to
subdivide 15.4 acres into 55 single-family lots. The proposal included the development
of the lots with garden style patio homes. The lots would be developed in three phases
with 23 lots in the first phase (a final plat was executed for this phase on May 25, 2005),
7 lots in the second phase and 25 lots in the third phase. The applicant has indicated
the lots would be served by a series of residential streets (cul-de-sacs) with no outlet
being planned to Gooch Lane.
The development included a portion of Heatherbrae Phase 3, which was previously
reviewed and approved for a preliminary plat. The applicant proposed to revise the
previously approved plat. The revision included a reduction of the on -site detention
FILE NO.: S-1397-B
area. The applicant worked with the Corp of Engineers, to reduce the previously
required detention area.
A. PROPOSAL/REQUEST:
The applicant is now proposing a replat of Lots 1 — 17 of the Stonecreek
Addition. The area is within the previously approved and final platted Phase I.
The purpose of the replat is to extend the side lot lines of Lots 5 —14 across the
permanent drainage easement, reduce the front building line on Lots 1 — 17 from
25-feet to 15-feet and reduce the rear yard setback of Lots 15 and 16 from
25-feet to 15-feet.
The applicant has indicated the reduced setbacks are necessary for the
developer to maintain the average home size currently being developed in the
area. The applicant has indicated Lots 5 — 14 contain a 20-foot permanent
drainage and a 15-foot permanent landscape easement across the rear, while
Lots 16 and 17 are subject to a 25-foot sewer easement that cuts across a
portion of each lot's rear yard.
B. EXISTING CONDITIONS:
The site is a vacant tree covered site with a large drainage ditch extending
through the center of the site. There is a FEMA mapped floodway located along
the northern boundary of the site. The existing Glen Valley Drive dead -ends at
the proposed entrance into the subdivision.
There are single-family homes located in the area with the Heatherbrae
Subdivision located to the east and new homes being constructed on tracts on
Gooch Lane to the west. Gooch Lane does not extend into the proposed
development.
C. NEIGHBORHOOD COMMENTS:
All abutting property owners and Westchester/Heatherbrae Neighborhood
Association were notified of the public hearing. As of this writing staff has not
received any comment from area residents.
D. ENGINEERING COMMENTS:
Public Works Conditions:
1. Verify that the minimum Finish Floor elevations as shown on the plat are one
foot above the base flood elevation.
2. Plat should indicate no fencing or landscaping within the platted drainage
easement areas.
3. Ditch banks need to be stabilized with a permanent vegetation cover per
original plan approval.
4. Street light installation needs to be completed.
2
FILE NO.: S-1397-B (Cont.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING.
Wastewater: Existing sewer main located on site with service lines installed for
original lots. If any lot lines have changed where service is not available to new
lots without crossing another lot the owner of the property will be responsible to
construct any new service lines required to serve that lot. Contact Little Rock
Wastewater Utility at 688-1414 for additional details.
Entergy: Approved as submitted.
Center -Point Energy: Approved as submitted.
SBC: No comment received.
Central Arkansas Water: No objection.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department for additional information.
County Planning: No comment.
CATA: The site is not located on a dedicated CATA bus route.
F. ISSUES/TECHNICAL/DESIGN:
G.
Planning Division: No comment.
Landscape: No comment.
SUBDIVISION COMMITTEE COMMENT:
(July 28, 2005)
The applicant was present. Staff presented an overview of the proposed replat
to the Committee members present. Staff stated the developer had previously
platted the lots with an open space tract adjacent to the eastern property line.
Staff stated the developer was now requesting to replat the lots to incorporate the
tract into the individual lots. Staff stated with the replat the developer would be
able to reduce the rear yard setback to the 15-foot landscape easement indicated
on the plat. Staff questioned fencing. The applicant stated fencing would be
allowed at the top of the levee or along the eastern side of the landscape
easement. He stated the Corp of Engineers had agreed to the placement of
fencing in this location.
Public Works comments were addressed. Staff stated the minimum Finish Floor
elevations should be shown on the proposed plat. Staff stated the ditch banks
would need to be stabilized with a permanent vegetation cover per the original
plat approval.
3
FILE NO.: S-1397-B (Cont.) _
Staff noted comments from the other reporting departments and agencies
suggesting the applicant contact them individually for additional clarification.
There was no further discussion of the item. The Committee then forwarded the
item to the full Commission for final action.
H. ANALYSIS:
The applicant submitted a revised plat to staff addressing most of the issues
raised at the July 28, 2005, Subdivision Committee meeting. The applicant has
indicated the location of the proposed fencing along the eastern boundary of the
15-foot landscape easement. The applicant has also indicated the finished floor
elevation on the proposed plat.
The applicant has indicated a front building line of 15-feet along Lots 1 R — 17R
and Lot 23R. The applicant is requesting a 15-foot rear building setback of along
Lots 15R and 16R. The applicant has indicated an average lot size of 80-feet by
132-feet or 10,560 square feet and a minimum lot size of 80-feet by 110-feet or
8,800 square feet. `
Staff is supportive of the applicant's proposed replat of the indicated lots and the
requested variances. The purpose of the replat is to extend the side lot lines of
Lots 5 —14 across the permanent drainage easement, reduce the front building
line on Lots 1 — 17 from 25-feet to 15-feet and reduce the rear yard setback of
Lots 15 and 16 from 25-feet to 15-feet. The applicant has indicated the reduced
setbacks are necessary for the developer to maintain the average home size
currently being developed in the area. The applicant has indicated Lots 5 — 14
contain a 20-foot permanent drainage and a 15-foot permanent landscape
easement across the rear, while Lots 16 and 17 are subject to a 25-foot sewer
easement that cuts across each lot's rear yard. To staffs knowledge there are
no outstanding issues associated with the proposed request. Staff feels the
proposed reduced building line and setbacks will not have any adverse impact on
the adjoining properties.
I. STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
conditions outlined in paragraphs D, E and F of the above agenda staff report.
Staff recommends approval of the requested variance to allow a reduced front
building line for proposed Lots 1 R —17R and Lot 25R.
Staff recommends approval of the applicant's request for a reduced rear yard
setback of 15-feet for proposed Lots 15R and 16R.
4
FILE NO.: S-1397-B (Cont.
PLANNING COMMISSION ACTION: (AUGUST 18, 2005)
The applicant was present representing the request. There were no registered
objectors present. Staff presented the item with a recommendation of approval of the
request subject to compliance with the conditions outlined in paragraphs D, E and F of
the agenda staff report. Staff also presented a recommendation of approval of the
requested variance to allow a reduced front building line for proposed Lots 1 R — 17R
and Lot 25R and the applicant's request for a reduced rear yard setback of 15-feet for
proposed Lots 15R and 16R.
There was no further discussion of the item. The chair entertained a motion for
placement of the item for inclusion on the consent agenda for approval. The motion
carried by a vote of 9 ayes, 0 noes and 2 absent.
5
August 18, 2005
ITEM NO.: 2 FILE NO.:
NAME: Stone Creek Phase I Replat
LOCATION: Located on the West end of Glen Valley Drive on Clancy Court
DEVELOPER:
AS Rosen & Associates, Inc.
Bill Bosley, Agent
9107 Rodney Parham Road
Little Rock, AR 72203
ENGINEER:
Civil Design, Inc.
15104 Cantrell Road
Little Rock, AR 72223
AREA: 6.582 acres
CURRENT ZONING
PLANNING DISTRICT:
CENSUS TRACT
Variance/Waivers:
NUMBER OF LOTS: 23
R-2, Single-family
19 — Chenal Planning District
42.11
FT. NEW STREET: 0 LF
1. A variance to allow a 15-foot front building line along Lots 1 R —17R.
2. A variance to allow a 15-foot rear yard setback of 15-feet for Lots 15R and 16R.
BACKGROUND:
On October 16, 2004, the Little Rock Planning Commission reviewed a request to
subdivide 15.4 acres into 55 single-family lots. The proposal included the development
of the lots with garden style patio homes. The lots would be developed in three phases
with 23 lots in the first phase (a final plat was executed for this phase on May 25, 2005),
7 lots in the second phase and 25 lots in the third phase. The applicant has indicated
the lots would be served by a series of residential streets (cul-de-sac's) with no outlet
being planned to Gooch Lane.
The development included a portion of Heatherbrae Phase 3, which was previously
reviewed and approved for a preliminary plat. The applicant proposed to revise the
August 18, 2005
UBDIVISION
ITEM NO.: 2 (Cont.)FILE NO.: S-1397-B
previously approved plat. The revision included a reduction of the on -site detention
area. The applicant worked with the Corp of Engineers, to reduce the previously
required detention area.
A. PROPOSAL/REQUEST:
1
C
The applicant is now proposing a replat of Lots 1 — 17 of the Stonecreek
Addition. The area is within the previously approved and final platted Phase I.
The purpose of the replat is to extend the side lot lines of Lots 5 —14 across the
permanent drainage easement, reduce the front building line on Lots 1 — 17 from
25-feet to 15-feet and reduce the rear yard setback of Lots 15 and 16 from
25-feet to 15-feet.
The applicant has indicated the
developer to maintain the average
area. The applicant has indicate
drainage and a 15-foot permanent
Lots 16 and 17 are subject to a
portion of each lot's rear yard.
EXISTING CONDITIONS:
reduced setbacks are necessary for the
home size currently being developed in the
d Lots 5 — 14 contain a 20-foot permanent
landscape easement across the rear, while
25-foot sewer easement that cuts across a
The site is a vacant tree covered site with a large drainage ditch extending
through the center of the site. There is a FEMA mapped floodway located along
the northern boundary of the site. The existing Glen Valley Drive dead -ends at
the proposed entrance into the subdivision.
There are single-family homes located in the area with the Heatherbrae
Subdivision located to the east and new homes being constructed on tracts on
Gooch Lane to the west. Gooch Lane does not extend into the proposed
development.
NEIGHBORHOOD COMME
All abutting property owners and Westchester/Heatherbrae Neighborhood
Association were notified of the public hearing. As of this writing staff has not
received any comment from area residents.
D. ENGINEERING COMMENTS:
Public Works Conditions:
1. Verify that the minimum Finish Floor elevations as shown on the plat are one
foot above the base flood elevation.
2. Plat should indicate no fencing or landscaping within the platted drainage
easement areas.
3. Ditch banks need to be stabilized with a permanent vegetation cover per
2
August 18, 2005
SUBDIVISION
ITEM NO.: 2 Cont.) FILE NO.: S-1397-B
original plan approval.
4. Street light installation needs to be completed.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Existing sewer main located on site with service lines installed for
original lots. If any lot lines have changed where service is not available to new
lots without crossing another lot the owner of the property will be responsible to
construct any new service lines required to serve that lot. Contact Little Rock
Wastewater Utility at 688-1414 for additional details.
Entergy: Approved as submitted.
Center -Point Energy: Approved as submitted.
SBC: No comment received.
Central Arkansas Water: No objection.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department for additional information.
County Planning: No comment.
CATA: The site is not located on a dedicated CATA bus route.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division: No comment.
Landscape: No comment.
G. SUBDIVISION COMMITTEE COMMENT: (July 28, 2005)
The applicant was present. Staff presented an overview of the proposed replat
to the Committee members present. Staff stated the developer had previously
platted the lots with an open space tract adjacent to the eastern property line.
Staff stated the developer was now requesting to replat the lots to incorporate the
tract into the individual lots. Staff stated with the replat the developer would be
able to reduce the rear yard setback to the 15-foot landscape easement indicated
on the plat. Staff questioned fencing. The applicant stated fencing would be
3
August 18, 2005
SUBDIVISION
ITEM NO_: 2 [Cont.] FILE NO.: S-1397-B
allowed at the top of the levee or along the eastern side of the landscape
easement. He stated the Corp of Engineers had agreed to the placement of
fencing in this location.
Public Works comments were addressed. Staff stated the minimum Finish Floor
elevations should be shown on the proposed plat. Staff stated the ditch banks
would need to be stabilized with a permanent vegetation cover per the original
plat approval.
Staff noted comments from the other reporting departments and agencies
suggesting the applicant contact them individually for additional clarification.
There was no further discussion of the item. The Committee then forwarded the
item to the full Commission for final action.
H. ANALYSIS:
The applicant submitted a revised plat to staff addressing most of the issues
raised at the July 28, 2005, Subdivision Committee meeting. The applicant has
indicated the location of the proposed fencing along the eastern boundary of the
15-foot landscape easement. The applicant has also indicated the finished floor
elevation on the proposed plat.
The applicant has indicated a front building line of 15-feet along Lots 1 R — 17R
and Lot 23R. The applicant is requesting a 15-foot rear building setback of along
Lots 15R and 16R. The applicant has indicated an average lot size of 80-feet by
132-feet or 10,560 square feet and a minimum lot size of 80-feet by 110-feet or
8,800 square feet.
Staff is supportive of the applicant's proposed replat of the indicated lots and the
requested variances. The purpose of the replat is to extend the side lot lines of
Lots 5 —14 across the permanent drainage easement, reduce the front building
line on Lots 1 — 17 from 25-feet to 15-feet and reduce the rear yard setback of
Lots 15 and 16 from 25-feet to 15-feet. The applicant has indicated the reduced
setbacks are necessary for the developer to maintain the average home size
currently being developed in the area. The applicant has indicated Lots 5 — 14
contain a 20-foot permanent drainage and a 15-foot permanent landscape
easement across the rear, while Lots 16 and 17 are subject to a 25-foot sewer
easement that cuts across each lot's rear yard. To staffs knowledge there are
no outstanding issues associated with the proposed request. Staff feels the
proposed reduced building line and setbacks will not have any adverse impact on
the adjoining properties.
4
August 18, 2005
SUBDIVISION
ITEM NO.: 2 (Cont.) FILE NO.: S-1397-B
STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
conditions outlined in paragraphs D, E and F of the above agenda staff report.
Staff recommends approval of the requested variance to allow a reduced front
building line for proposed Lots 1 R —17R and Lot 25R.
Staff recommends approval of the applicant's request for a reduced rear yard
setback of 15-feet for proposed Lots 15R and 16R.
PLANNING COMMISSION ACTION: (AUGUST 18, 2005)
The applicant was present representing the request. There were no registered
objectors present. Staff presented the item with a recommendation of approval of the
request subject to compliance with the conditions outlined in paragraphs D, E and F of
the agenda staff report. Staff also presented a recommendation of approval of the
requested variance to allow a reduced front building line for proposed Lots 1 R — 17R
and Lot 25R and the applicant's request for a reduced rear yard setback of 15-feet for
proposed Lots 15R and 16R.
There was no further discussion of the item. The chair entertained a motion for
placement of the item for inclusion on the consent agenda for approval. The motion
carried by a vote of 9 ayes, 0 noes and 2 absent.
5