HomeMy WebLinkAboutS-1240-O Application►4rea Zoning
City of Little Rock Planning & Development
Case: S-1240-0
Location: Colonel Glenn Plaza Loop
Ward:7 N
PD: 12
CT:24.05 0 250 500
TRS: T1 N R13W 21 Feet
City of Little Rock Planning & Development
Case No: S-1240-0
Name: KIA Dealership
Location: Colonel Glenn Plaza Loop
Issue: Site Plan Review
N
A
City of Little Rock
Department of Planning and Development Planning
723 West Markham Street Zoning and
Little Rock, Arkansas 72201-1334 Subdivision
Phone: (501) 371-4790 Fax: (501) 399-3435 or 371-6863
May 1, 2017
The Holloway Firm
Mr. Mark Redder
200 Casey Drive
Maumelle, AR 72113
Re: S-1240-0 - Steve Landers KIA Dealership Subdivision Site Plan Review, located
on the Northwestern corner of Colonel Glenn Plaza Loop
Dear Sirs:
This is to advise you that in connection with your request concerning the above referenced
file number the following action was taken by the Planning Commission at its meeting on April
27, 2017:
X Approved with conditions.
Recommended approval with conditions.
Recommended approval as submitted.
Denied your request as submitted.
Deferred to the Meeting.
Other:
If you have any questions please do not hesitate to contact me at 371-6821.
Respectfully,
Donna James, AICP
Subdivision Administrator
sitpin.doc
03/01/10
INFORMATION SHEET FOR
SUBDIVISION PUD's PD's, ZONING
OR SUBDIVISION SITE PLAN REVIEWS
ITEM NO. DA`I'
FILE NO- J r L ' -o
NAME: Steve Landers KIA
LOCATION: Glenn Ridge Crossings Subdivision
March 27, 2017
DEVELOPER: ITR Construction
STREET ADDRESS 5104 Sarna Drive
CITY/STATE/ZIP North Little Rock, AR 72118
TELEPHONE NO. 501-650-0562
ENGINEER: Holloway Engineering, Surveying & Civil Design, PLLc
STREET ADDRESS 200 Casey Drive
CITY/STATE/ZIP Maurnelle, AR 72113
TELEPHONE NO. 501-851-3366
AREA 16.162 Acres (704,004.77SF) NUMBER OF LOTS 2
FT. NEW STREET 0
ZONING C-4 PROPOSED USES Auto Dealership
PLANNING DISTRICT 18 CENSUS TRACT 2405
VARIANCES REQUESTED
1.) Removal of 50' Buffer on the West Side
2.)
3.)
4.)
sitpin.doc
03/01/10
AFFIDAVIT
I, C �! certify by my signature below that I hereby
authorize &4(6i� t�'�t ^l %� s ��'`� COS"� act as my agent regarding the
Site Plan Review Application of the below described property.
Property described as:
SE 1/4, NW 1/4 & NE 1/4, SW 1/4 of Section 21, Township 1 North, Range 13 West,
Little Rock, Pulaski County, Arkansas
Signature of
2(j-I
Date
Subscribed and sworn to me a Notary Public on this 0), Qday of
_7ffikelL , '�0i
Notary Public
My Commission Expires:
uvic ! G � oa- l
, 1 %4'
BRAND K. ARPS
?.nr w.sp.4
MY COMMISSION # 12382606
'n;
EXPIRES: June 16, 2021
Pulaski Cou,E
.0 HOLLOWAY ENGINEERING
Surveying, & Civil Design, PLLC
March 20, 2017
Donna James
Subdivision Administrator
City of Little Rock Planning and Development
723 West Markham Street
Little Rock, Arkansas 72201-1334
RE: Site Plan Review Application for Steve Landers KIA Dealership on Colonel Glenn
Plaza Loop (SE 1/4, NW 1/4 & NE 1/4, SW 1/4 of Section 21, Township 1 North, Range
13 West, City of Little Rock, Pulaski County, AR)
Ms. James,
Please find attached 18 copies of the Site Plan for the above referenced project. Also
find a check in the amount of $355.00 for the review fee. As you know, a portion of this
property is on the Agenda to be considered for a rezoning to C-4 Commercial to allow
an auto dealership to locate on this property. This project would be the first of two
developments proposed on this property.
We are also asking that the 50-foot buffer along the West side of the property be
removed. This development is approximately 30 feet higher that the adjacent properties
to the West.
If you have any questions please call me at 501-851-3366.
Sincerely,
i P
Mark Redder
Office: 200 Casey Drive, MaumeUe, AR 72113
Phone: 501-851-3366 Fax: 501-851-3368 Email: admin@holloway-eng.com
.p .6-xa..TT.QO T.v. ETTZL aR.u. Uvipn49WD �!uf J04 vaaou :ocoae
B9EE-TW (i09 OOZ M Ti1■ 98A1�E.il�l'�-unoJ f�lsglnd `�°Q�i ai >� 3.7 ll[i0.'/50/IO:v3oV 00 LV
011,4'0192a JJAJO 8'OWPAJng a $uf990.1�) 76pN U1401t] Hatl :OaHaaua
ONNONION3 AVMO-nOH df�{ga�fead SI`A v�uc� p ueLj nG .avT
ea
• �f
a
sM M
lit
5Y
cr
DgFF
by
��
51
5,
Pa P
�H
S
sY
4••8•
!1•'%(e
$S
5
a
a
0, 009xo $�
p35
jj I; I I III; 800X*
i l l I�
�a9o7rx
I-11:1
o,tl t00-9102 tivwasetl\slapuvl - a6pltl uua{9 Te a�N uta10 IBO-9102\9t02\ :l
HOLLOWAY ENGINEERING
(0
Surveying, & Civil Design, PLLC
April 7, 2017
Donna James
Subdivision Administrator
City of Little Rock Planning and Development
723 West Markham Street
Little Rock, Arkansas 72201-1334
Re: Site Plan Review Application for Steve Landers KIA Dealership on Colonel Glenn
Plaza Loop (SE 1/4, NW 1/4 & NE 114, SW 1/4 of Section 21, Township 1 North, Range
13 West, City of Little Rock, Pulaski County, AR
Dear Ms. James,
Please find attached the following for the above -referenced project:
1. Notice of Public Hearing to property owners lying within 200 feet of boundary
of property.
2. The Certified Receipts from the Post Office dated April 7, 2017.
3. The Certified list of property owners from Lenders Title Company.
If you need further information regarding this project, please don't hesitate to call.
Respectfully,
Brandi Arps
Officc: 200 Casa- Drive, Nfaumcllc, AR 72113
Phone: 501-851-3366 Fax: 501-851-3368 Email: admin(ct,)hollowIN--cng.com
1pin au, 0•In11110
NOTICE, OF PUBLIC HEARING BETOR1?
'I'IIU: LITTLE' ROCK PI,ANNINC COMMISSION
ON AN APPLICATION FOR SITE, PLAN REVIEW
I'o AI.I, oatners of Iand Ivinp oiihin 2110 Im IIf IIle houndloy of properly :it:
Atldt'css: Colonel Glenn Road, LAW flock, AR
(iL'llt: fill I .111':Illllll: SI: I1,1. NW 114 & Nr 114. SW 1f4 of Smlior1 21 romislup I Nonl,, Ikaoge 13 West. I alto Ruck, 110iMi Ca.mly An
O►►'Well by: Glenn Ritlgo Crossings II, LLC
%oninp: G4
I'ruposed l'st : Atllomolivo Dealership
NOTICI? IS 11HREBY (71V1?N THAT aW application Im Site Plan Review has been filed with the
Deparuncnl of Planning and Development. A public hearing on said appfic:lliun ►sill he held by the
Little Ruck Planning Commission in the Board of Directors C'hanibcr, Second I'lonr, City Hall. on .
Llpril 27. 2017 at 4 00 -...._ p.nl.
ALL PARTIES IN INTERIiST MAY APPL•AR and he heart) al said lime and plate, ill' May nalify the
Manning Commission of their views on Ihis matter by letter. All persons interested ill this request are
invited to call or visit the Deparinlent of Planning and Development. 723 West Markham. 171-•1790, and
to review the application and discuss same with the Planning slalT.
AFFIDAVIT
1Ic1'e11, ccllik tlMl I ha%c aolitied :ill the propell.% onncr, (11'rrinitl ltilllin .1,1)I1 feel t,l'the allo\e
pmpc111 Ih:u Nul,jccl prtlpcll) is bcin� cumitlrltd I'm tine Ilan Rea iciN itild Thal a Ihlbllc I IL-061W 1, ill he
held h\ the [.title Rock Planning Colmili'oitul :it the lilac ,Ind lift t• tic"Vi Bled :Ilxl\ e.
Applicant lowlier oraulhoriied agcolt
(N:nnc) 071
(D:uc1
f�
U
m
M
r-i
M
I'll
nj
0
C1
rr"
rn
.-i-
a'
IT
m
LITTLE'ROCKY
AR 72204
m
]
r-I
Possngrs
C1113
F-1
12
!Y!
IA4
rij
solussi U1
Posirpialk
$CI. (I CI Here
Mj
M
(EndorGe-imM
it'.6160mi Wiviopy Fee
-;OCI-
a-rkwWAmit ric(Itik")
(14/07/2017
m
n,iFofqi
MOO. July 2,Dl.. Sco far F)-MruCli;'ivn
U.S.
postal service",
CERTIFIED
MAILO RECEIPT
Domestfo
Afall Q01Y
1--l"OrPrifor6eflon, VIMIt our wa�Aa-at mymuupsx=,�
k1j11M'.W11111 , I - 111111-M imml
m
In 12
ru Curtiliod Foe $0. 1) C11
Holum Rocelpt Fee Here
(Endorsement Roquiroll)
Restricted QCAFVOTY Fee
En (Lrvior."mm I Ftimuired)
13-
IT Irl rotal FIC 04/07/2017
In 0 M
r 300
1 01 12 19 F
M *jjwg;4
Z,
17�- or PO Be, Liftis. Rou-k, 722pity fil.�lr
= �S F0TMM%4 i A ki Y. MOM
Lr7
r—,
I Ti
FO MI MNEAROL�S.
PAO
m
M Certified Fee
_1 Return Receipt Foe
F. (Fndorsemont Pirt(uirod)
I
I
1105(ftled Delivery Fee
(Endor,orrient Required)
$0 .
W.M.Y.91" Mm ma,1461091IMMITIV
KANSAS CITY, MO,641,06
12
Cuitlfimd Fee
$0. OCI
Rokrn fluvoipt Foo
(BiLrommont Rsquirod)
$0
Postmark
Hero
HoSbr1ck,dDo1!veryFcv
(EndmsomrMt RoqulrA
TOM 11
04/07/2017
44
of PO VC t
Gory Star
"
LITM�RKK, OW7 2M
(1113
12
Certified Foe
Postmark
Roltan Irlevelpt Fee Hem
(Endommioril Requlfod) 1.1 Cl CI
linclrirrod DOR Fee
(EMM 11MIJAI =111rud)
1101al PC. 04/07/2017
1..w40,,,35q ov* E'N"Itdc"i
S�iVVes't
. Or -
or PO 6o.
Mon,
'PH 5,5416
PoAwt.114
12
Total Pos 04/07/201 ?
"!J
or PO Box•f A? 't ij
L
City Swe.
11111111111M. W.- nomafnd�
Date: March 29, 2017
File Number: 17-015041-050
Prepared For: Holloway Engineering
Lenders Title Company has searched the records of the Real Estate Records of Pulaski County, Arkansas
to determine the apparent ownership of property within 200 feet of the perimeter of the following described
property as of March 16, 2017 at 8:00 a.m.
Lands lying in SE1/4, NWl/4 and the NEI/4, SWIM, Section 21, Township I North, Range 13
West, more particularly described as follows:
Commencing at a found I" pipe at the Southeast corner of the NE 1/4, SW 1/4 of said Section 21;
thence North 87 degrees 48 minutes 01 seconds West 1045.41 feet to the point of beginning;
thence continue North 87 degrees 48 minutes 01 seconds West 266.52 feet; thence North 02
degrees 59 minutes 21 seconds East 1113.83 feet; thence North 03 degrees 00 minutes 44 seconds
East 209,69 feet; thence South 61 degrees 33 minutes 44 seconds East 129.17 feet; thence North
27 degrees 08 minutes 26 seconds East 487.28 feet to a point on the south right of way of Colonel
Glenn Plaza Loop; thence continue along said right of way South 53 degrees 01 minutes 41
seconds East 249.09 feet; thence along a curve to the left having a radius of 599,95 feet and a
chord bearing and distance of South 59 degrees 21 minutes 16 seconds East 132.16 feet; thence
South 65 degrees 52 minutes 57 seconds East 63.27 feet; thence along a curve to the right having a
radius of 50.00 feet and a chord bearing and distance of South 19 degrees 21 minutes 33 seconds
East 72.54 feet; thence South 27 degrees 08 minutes 25 seconds West 625.42 feet; thence along a
curve to the left having a radius of 230.00 feet and a chord bearing and distance of South 15
degrees 15 minutes 19 seconds West 94.74 feet; thence South 03 degrees 22 minutes 12 seconds
West 73.88 feet; thence along a curve to the left having a radius of 230.00 feet and a chord bearing
and distance of South 09 degrees 58 minutes 11 seconds East 106.13 feet; thence South 47 degrees
54 minutes 30 seconds West 297.51 feet; thence South 02 degrees 27 minutes 53 seconds West
367.29 feet containing 16.162 acres more or less.
Following is a list of apparent owners of property within 200 feet of the perimeter of the above
described property as reflected by the records of the Real Estate Records of Pulaski County, Arkansas:
Colonel Glenn Development Co., 11219 Financial Parkway, Suite 300, Little Rock, AR,
72211.
2. LL Ark Properties, LLC, 3701 Alabama Ave South, St. Louis Park, MN, 55416.
Little Rock School District, 810 West Markham Street, Little Rock, AR, 72201.
4. Helen M. Andrews, 8101 Westwood Ave, Little Rock, AR, 72204,
EPT Tittle Rock Inc,, 909 Walnut Street, Suite 200, Kansas City, MO, 64106.
This Ownership/Zone Search is intended for the exclusive use of the addressee for informational
purposes only, Lenders Title Company is not expressing or attempting to express an opinion as to the validity
of the title to the above described property or property noted as being within 200 feet thereof (collectively
referred to as "the property"), the accuracy of the addresses, nor as to the validity of any interests or
I;fC • Ownenhlp'Zone Scnrchalf I of 2
encumbrances, both recorded and unrecorded, that pertain to the property. While Lenders Title Company
believes that the information stated above is accurate, no assurances are made nor is any liability assumed by
Lenders Title Company for any incorrect information stated herein or omitted herefrom, For assurances as to
the title to the property, addressee should obtain a title insurance commitment/policy.
Sincerely,
Lenders Title Company
Arkansas License No. [A-82
BY:
Title gent License Number: 1617
City of Little Rock
Department of Planning and Development Planning
723 West Markham Street Zoning and
Little Rock, Arkansas 72201-1334 Subdivision
Phone: (501) 371-4790 Fax: (501) 399-3435 or 371-6663
NOTICE OF PUBLIC HEARING BEFORE THE LITTLE ROCK PLANNING
COMMISSION ON A REQUEST FOR A USE CHANGE OR DEVELOPMENT OF
LAND
March 23, 2017
Waters Edge Neighborhood Association
Mr. Kenneth Jones
2 Buffalo Cove
Little Rock, AR 72204
REQUEST: Steve Landers KIA Dealership Subdivision Site Plan Review S-1240-0
a request for multiple building site plan review to allow the placement of a new
automobile dealership and allow a separate detached carwash and service facility.
GENERAL LOCATION OR ADDRESS: located on the Southeastern corner of Colonel
Glenn Plaza Looa and David O Dodd Road
OWNED BY/APPLICANT: Steve Landers — Holloway Engineering, Mark Redder
(501.851.3366) Agent
NOTICE IS HEREBY GIVEN THAT an application for a Subdivision Site Plan Review of
the above property has been filed with the Department of Planning and Development. A
public hearing will be held by the L.R. Planning Commission in the Little Rock Board of
Directors Chambers, second floor, City Hall, 500 West Markham Street, on June 8,
2017 at 4:00 P.M. This notice is provided in order to assure that neighborhood
associations are aware of issues that may affect their neighborhood. Information
requests should be directed to the Planning staff at 371-4790.
Tony Bozynski
Director of Planning and Development
City of Little Rock
Department of Planning and Development Planning
723 West Markham Street Zoning and
Little Rock, Arkansas 72201-1334 Subdivision
Phone: (501) 371-4790 Fax: (501) 399-3435 or 371-6863
NOTICE OF PUBLIC HEARING BEFORE THE LITTLE ROCK PLANNING
COMMISSION ON A REQUEST FOR A USE CHANGE OR DEVELOPMENT OF
LAND
March 23, 2017
John Barrow Neighborhood Association
Carolyn Heitman
8123 West 40th
Little Rock, AR 72204
REQUEST: Steve Landers KIA Dealership Subdivision Site Plan Review S-1240-0
a request for multiple building site plan review to allow the placement of a new
automobile dealership and allow a separate detached carwash and service facility.
GENERAL LOCATION OR ADDRESS: located on the Southeastern corner of Colonel
Glenn Plaza Loop and David O Dodd Road
OWNED BY/APPLICANT: Steve Landers -- Holloway Engineering, Mark Redder
501.851.3366 Agent
NOTICE IS HEREBY GIVEN THAT an application for a Subdivision Site Plan Review of
the above property has been filed with the Department of Planning and Development. A
public hearing will be held by the L.R. Planning Commission in the Little Rock Board of
Directors Chambers, second floor, City Hall, 500 West Markham Street, on June 8,
2017 at 4:00 P.M. This notice is provided in order to assure that neighborhood
associations are aware of issues that may affect their neighborhood. Information
requests should be directed to the Planning staff at 371-4790.
Tony Bozynski
Director of Planning and Development
City of Little Rock
Department of Planning and Development Planning
723 West Markham Street Zoning and
Little Rock, Arkansas 72201-1334 Subdivision
Phone: (501) 371-4790 Fax: (501) 399-3435 or 371-6863
NOTICE OF PUBLIC HEARING BEFORE THE LITTLE ROCK PLANNING
COMMISSION ON A REQUEST FOR A USE CHANGE OR DEVELOPMENT OF
LAND
March 23, 2017
Crystal Valley Property Owners Association
Larry Welch
16001 Crystal Valley Rd.
Little Rock, AR 72210
REQUEST: Steve Landers KIA Dealership Subdivision Site Plan Review S-1240-0 .
a request for multiple building site plan review to allow the placement of a new
automobile dealership and allow a separate detached carwash and service facility.
GENERAL LOCATION OR ADDRESS: located on the Southeastern corner of Colonel
Glenn Plaza Loop and David O Dodd Road
OWNED BY/APPLICANT: Steve Landers — Hollowav Enaineerina, Mark Redder
(501.851.3366) Aaent
NOTICE IS HEREBY GIVEN THAT an application for a Subdivision Site Plan Review of
the above property has been filed with the Department of Planning and Development. A
public hearing will be held by the L.R. Planning Commission in the Little Rock Board of
Directors Chambers, second floor, City Hall, 500 West Markham Street, on June 8,
2017 at 4:00 P.M. This notice is provided in order to assure that neighborhood
associations are aware of issues that may affect their neighborhood. Information
requests should be directed to the Planning staff at 371-4790.
Tony Bozynski
Director of Planning and Development
NAME
PLANNING COMMISSION REVIEW
CENTRAL ARKANSAS WATER
05 April 2017
TYPEISSUE
COMMENTS
CHENALMARKET REVISED Z-6318-E NO OBJECTIONS; All Central Arkansas
Water requirements in effect at the time of
request for water service must be met.
NAME
DAVIS STORAGE
DEVELOPMENT LONG -FORM
PCD
TYPE ISSUE COMMENTS
Z-89737-C All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
A water main extension will be needed to
provide water service to this property.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow, preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
FA
NAME TYPE ISSUE COMMENTS
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
3
NAME TYPE ISSUE COMMENTS
FIRE AUTO EXPANSION Z-6054-C All Central Arkansas Water requirements in
REVISED LONG -FORM PCD effect at the time of request for water service
must be met.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
NAME TYPE ISSUE COMMENTS
discuss backflow, prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
QUICK'S ;ALE PLACE S-1787 All Central Arkansas Water requirements in
PRELIMINARY PLAT effect at the time of request for water service
must be met.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
NO OBJECTIONS; All Central Arkansas
Water requirements in effect at the time of
request for water service must be met.
5
NAME
LAWSON WEST SHORT -FORM
PD-C
TYPE ISSUE
Z-9207
COMMENTS
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
A water main extension will be needed to
provide water service to this property.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
1.1
NAME TYPE ISSUE COMMENTS
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
GRAHAM PROPERTY Z-9208
If there are facilities that need to be adjusted
MANAGEMENT SHORT -FORM
and/or relocated, contact Central Arkansas
PD-R
Water. That work would be done at the
expense of the developer.
NO OBJECTIONS; All Central Arkansas
Water requirements in effect at the time of
request for water service must be met.
LAWSON SHORT -FORM PD-R Z-9210
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Contact Central Arkansas Water regarding
the size and location of the water meter.
HAWKINS SHORT -FORM PCD Z-2306 NO OBJECTIONS; All Central Arkansas
Water requirements in effect at the time of
request for water service must be met.
NAME
TYPEISSUE
ARKANSAS INDOOR SOCCER Z-9209
SHORT -FORM PID
COMMENTS
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
U_
NAME TYPE ISSUE COMMENTS
pressure zone backflow preventer shall be
required.
NAME TYPEISSUE
PRESBYTERIAN VILLAGE Z-7091-A
REVISED SHORT -FORM PD-R
COMMENTS
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
If there are facilities that need to be adjusted
and/or relocated, contact Central Arkansas
Water. That work would be done at the
expense of the developer.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
10
NAME TYPE ISSUE COMMENTS
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
11
NAME TYPE ISSUE COMMENTS
6608 BASELINE ROAD SHORT -
FORM PD-O
Z-9023
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
12
NAME
WELLINGTON CREEK
SUBDIVISION PRELIMINARY
PLAT
S-1788
pressure zone backflow preventer shall be
required.
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
A water main extension will be needed to
provide water service to this property.
Please submit plans for water facilities to
Central Arkansas Water for review. Plan
revisions may be required after additional
review. Contact Central Arkansas Water
regarding procedures for installation of water
facilities. Approval of plans by Central
Arkansas Water, the Arkansas Department
of Health Engineering Division and Little
Rock Fire Department is required.
Additional fire hydrant(s) will be required.
Contact the Little Rock Fire Department to
obtain information regarding the required
placement of the hydrant(s) and contact
Central Arkansas Water regarding
procedures for installation of the hydrant(s).
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges.
13
NAME TYPEISSUE
KUM AND GO CONVENIENCE S-1788-A
STORE SUBDIVISION SITE PLAN
REVIEW
COMMENTS
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
14
NAME TYPE ISSUE COMMENTS
pressure zone backflow preventer shall be
required.
WE
NAME TYPE ISSUE COMMENTS
THE CRESTAT CHENAL LONG- Z-9211
FORM PD-R
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
16
NAME
TYPEISSUE
MARKHAM HARRISON Z-6860-E
PROPERTIES SHORT -FORM PD-
O
LOT Z-2A-R LITTLE ROCK S-1026-B
INDUSTRIAL DISTRICT REPLAT
J & R PROPERTIES REVISES Z-7895-D
SHORT -FORM PCD
COMMENTS
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
NO OBJECTIONS; All Central Arkansas
Water requirements in effect at the time of
request for water service must be met.
The existing 10' Central Arkansas Water
easement needs to be added to the plat.
NO OBJECTIONS; All Central Arkansas
Water requirements in effect at the time of
request for water service must be met.
17
NAME TYPE ISSUE COMMENTS
STEVE LANDERS KIA S-1240-0
DEALERSHIP SUBDIVISION SITE
PLAN REVIEW
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
18
NAME TYPE ISSUE COMMENTS
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
19
NAME TYPE ISSUE COMMENTS
JAMES MITCHELL SCHOOL
REVISED SHORT -FORM PCD
Z-5442-F
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
20
NAME
LITTLE ROCK RACKET CLUB
LONG -FORM PD-O
TYPE ISSUE COMMENTS
pressure zone backflow preventer shall be
required.
Z-1840-D All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
If there are facilities that need to be adjusted
and/or relocated, contact Central Arkansas
Water. That work would be done at the
expense of the developer.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
21
NAME
B & G PROPERTIES SHORT -
FORM PID
TYPE ISSUE COMMENTS
Z-1620-A Central Arkanasas Water retains the utility
easement in what was W 35TH ST. The 8"
water main and the easement needs to be
shown on the plat.
22
NAME
THE UNITED METHODIST
CHILDREN'S HOME CAMPUS
LONG -FORM POD
TYPE ISSUE COMMENTS
Z-5574-D All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
A water main extension will be needed to
provide water service to this property.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
This development will have minor impact on
the existing water distribution system.
Proposed water facilities will be sized to
provide adequate pressure and fire
protection.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
23
NAME TYPE ISSUE COMMENTS
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
24
NAME TYPE ISSUE COMMENTS
SMALL EMERGENCY HOSPITAL Z-9103-A
SHORT -FORM POD
All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
The Little Rock Fire Department needs to
evaluate this site to determine whether
additional public and/or private fire hydrant(s)
will be required. If additional fire hydrant(s)
are required, they will be installed at the
Developer's expense.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
25
NAME TYPE ISSUE COMMENTS
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
pressure zone backflow preventer shall be
required.
26
NAME
DASH HEATING AND COOLING
REVISED SHORT -FORM PD-O
TYPE ISSUE COMMENTS
Z-6060-A All Central Arkansas Water requirements in
effect at the time of request for water service
must be met.
Please submit plans for water facilities
and/or fire protection system to Central
Arkansas Water for review. Plan revisions
may be required after additional review.
Contact Central Arkansas Water regarding
procedures for installation of water facilities
and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering
Division and Little Rock Fire Department is
required.
A Capital Investment Charge based on the
size of meter connection(s) will apply to this
project in addition to normal charges. This
fee will apply to all connections including
metered connections off the private fire
system.
Contact Central Arkansas Water regarding
the size and location of the water meter.
The facilities on -site will be private. When
meters are planned off private lines, private
facilities shall be installed to Central
Arkansas Water's material and construction
specifications and installation will be
inspected by an engineer, licensed to
practice in the State of Arkansas. Execution
of Customer Owned Line Agreement is
required.
Due to the nature of this facility, installation
of an approved reduced pressure zone
backflow preventer assembly (RPZ) is
required on the domestic water service. This
assembly must be installed prior to the first
point of use. Central Arkansas Water (CAW)
requires that upon installation of the RPZA,
successful tests of the assembly must be
completed by a Certified Assembly Tester
licensed by the State of Arkansas and
approved by CAW. The test results must be
sent to CAW's Cross Connection Section
within ten days of installation and annually
thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to
discuss backflow prevention requirements
for this project.
Fire sprinkler systems which do not contain
additives such as antifreeze shall be isolated
with a double detector check valve
assembly. If additives are used, a reduced
27
NAME TYPE ISSUE COMMENTS
pressure zone backflow preventer shall be
required.
28
MEMORANDUM
TO: DONNA JAMES, SUBDIVISION ADMINISTRATOR
FROM: TRACY SPILLMAN, PLANS DEVELOPMENT ADMINISTRATOR
SUBJECT: REVIEW OF THE BUFFER AND LANDSCAPE REQUIREMENTS OF
THE APRIL 05, 2017, SUBDIVISION COMMITTEE MEETING
CC: DANA CARNEY, ZONING & SUBDIVISION MANAGER
DATE: MARCH 31, 2017
1. 2400 West 651h Street(S-1026-B)
No Comment
2. Colonel Glenn Plaza Loop (S-1240-A)
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
A land use buffer six (6) percent of the average width / depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The
properties to the west and south are zoned OS. The maximum dimension shall be fifty
(50) feet. As a component of all land use buffer requirements, opaque screening, whether
a fence or other device, a minimum of six (6) feet in height shall be required upon the
property line side of the buffer. A minimum of seventy (70) percent of the land use buffer
shall be undisturbed. Easements cannot count toward fulfilling this requirement. The
plantings, existing and purposed, shall be provided within the landscape ordinance of the
city, section 15-81.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). For
developments with more than one hundred fifty (150) parking spaces the minimum size
of an interior landscape area shall be three hundred (300) square feet. Interior islands
must be a minimum of seven and one half (7 1/2) feet in width. Trees shall be included in
the interior landscape areas at the rate of one (1) tree for every twelve (12) parking
spaces.
Landscape areas shall be provided between the vehicular use area used for public parking
and the general vicinity of the building, excluding truck loading or service areas not open
to public parking. These shall be provided at the rate equivalent to planter strip three (3)
feet wide along the vehicular use area. One (1) tree and four (4) shrubs shall be planted in
the building landscape areas for each forty (40) linear feet of vehicular use area abutting
the building.
An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger.
The development of two (2) acres or more requires the landscape plan to be stamped with
the seal of a Registered Landscape Architect.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
3. Stewart Road and Simpson Lane (5-1787
No Comment
4. SEC Chenal Parkwa and Welling on Hills Road S-1788
No Comment
5. 15617 Chenal Parkway (5-1788-A
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements, the Chenal Overlay District.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
A land use buffer six (6) percent of the average width / depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The minimum
dimension shall be nine (9) feet. The property to the east is zoned OS. As a component of
all land use buffer requirements, opaque screening, whether a fence or other device, a
minimum of six (6) feet in height shall be required upon the property line side of the
buffer. A minimum of seventy (70) percent of the land use buffer shall be undisturbed.
Easements cannot count toward fulfilling this requirement. The plantings, existing and
purposed, shall be provided within the landscape ordinance of the city, section 15-81. A
portion of the southeast buffer is deficient.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). The minimum
size of an interior landscape area shall be one hundred fifty (150) square feet for
developments with one hundred fifty (150) or fewer parking spaces. Interior islands must
be a minimum of seven and one half (7 1/2) feet in width. Trees shall be included in the
interior landscape areas at the rate of one (1) tree for every twelve (12) parking spaces.
Landscape areas shall be provided between the vehicular use area used for public parking
and the general vicinity of the building, excluding truck loading or service areas not open
to public parking. These areas shall be equal to an equivalent planter strip three (3) feet
wide along the vehicular use area.
A landscape irrigation system shall be required for developments of one (1) acre or
larger.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
6. 3401 — 3423 Mabelvale Pike (Z-1620-A)
No Comment
7. 41 Hunting Road (Z-1840-D)
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
A land use buffer six (6) percent of the average width / depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The property
to the east is zoned R-2. As a component of all land use buffer requirements, opaque
screening, whether a fence or other device, a minimum of six (6) feet in height shall be
required upon the property line side of the buffer. A minimum of seventy (70) percent of
the land use buffer shall be undisturbed. Easements cannot count toward fulfilling this
requirement. The plantings, existing and purposed, shall be provided within the landscape
ordinance of the city, section 15-81.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). The minimum
size of an interior landscape area shall be one hundred fifty (150) square feet for
developments with one hundred fifty (150) or fewer parking spaces. Interior islands must
be a minimum of seven and one half (7 1/2) feet in width. Trees shall be included in the
interior landscape areas at the rate of one (1) tree for every twelve (12) parking spaces.
Any exiting landscape or irrigation disturbed by construction shall be repaired or replaced
before completion and final acceptance of the project.
Note on plan any existing trees or groups of trees that are to remain. Trees selected for
preservation shall have the area within the dripline fenced with protective fencing and
protected from development activities. Graphically indicate the area to be protected on
the plan and provide detail of the protective fencing.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
8. 600 East 21" Street (Z-2306-B)
Any new site development must comply with the City's minimal landscape and buffer
ordinance requirements.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
9. 241 Q 5 Battery Street (Z-5442-F)
Any new site development must comply with the City's minimal landscape and buffer
ordinance requirements.
Existing vehicular use areas may continue as nonconforming until such time as a
building permit is granted to enlarge or reconstruct a structure on the property
exceeding ten (10) percent of the existing gross floor area. At such time ten (10) percent
of the existing vehicular use area shall be brought into compliance with the landscape
ordinance and shall continue to full compliance on a graduated scale.
If building rehabilitation exceeds fifty percent (50%) of the replacement cost then the
landscaping and buffer must also come into compliancy accordingly.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
10. 2202 S. Filmore Z-5574-D
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). The minimum
size of an interior landscape area shall be one hundred fifty (150) square feet for
developments with one hundred fifty (150) or fewer parking spaces.
Landscape areas shall be provided between the vehicular use area used for public parking
and the general vicinity of the building, excluding truck loading or service areas not open
to public parking. These areas shall be equal to an equivalent planter strip three (3) feet
wide along the vehicular use area.
A landscape irrigation system shall be required for developments of one (1) acre or
larger.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
11. 842.1 Stagecoach Road Z-6054-C
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
A land use buffer will be required when an adjacent property has a dissimilar use of a
more restrictive nature. As a component of all land use buffer requirements, opaque
screening, whether a fence or other device, a minimum of six (6) feet in height shall be
required upon the property line side of the buffer. A minimum of seventy (70) percent of
the land use buffer shall be undisturbed. Easements cannot count toward fulfilling this
requirement. The plantings, existing and purposed, shall be provided within the landscape
ordinance of the city, section 15-81. The property to the north and east is zoned R-2, a
minimum buffer will be required at six (6) percent of the average depth / width of the lot.
Street buffers will be required at six (6) percent of the average depth of the lot. The
minimum dimension shall be one-half (1/2) the full width requirement but in no case less
than nine (9) feet. The maximum dimension required shall be fifty (50) feet.
Street buffer is deficient.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). The minimum
size of an interior landscape area shall be one hundred fifty (150) square feet for
developments with one hundred fifty (150) or fewer parking spaces. Trees shall be
included in the interior landscape areas at the rate of one (1) tree for every twelve (12)
parking spaces.
Building landscape areas shall be provided between the vehicular use area used for public
parking and the general vicinity of the building. These shall be provided at the rate
equivalent to planter strip three (3) feet wide along the vehicular use area. One (1) tree
and four (4) shrubs shall be planted in the building landscape areas for each forty (40)
linear feet of vehicular use area abutting the building
An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger.
The development of two (2) acres or more requires the landscape plan to be stamped with
the seal of a Registered Landscape Architect.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
12. 12417 Cantrell Road Z-6060-A
No Comment
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
13. 16105 Chenal Parkway (Z-6318-E)
No Comment
14. 5307 A Street (Z-6860-E)
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
Street buffers will be required at six (6) percent of the average depth of the lot. The
minimum dimension shall be one-half ('/2) the full width requirement but in no case less
than nine (9) feet. The property is located in the City's designated mature area. A twenty-
five (25%) percent reduction of the buffer requirements is acceptable. The minimum
dimension of the buffer shall be six (6) feet nine (9) inches. After the five foot ROW
dedication the street buffer is deficient.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property. This strip shall be at least nine (9) feet wide. The property is located
in the City's designated mature area. A twenty-five (25%) percent reduction of the buffer
requirements is acceptable. The minimum dimension of the perimeter planting strip shall
be six (6) feet nine (9) inches. The east and west perimeters are deficient.
An irrigation system shall be required for developments of one (1) acre or larger.
For developments of less than one (1) acre a there shall be a water source within seventy-
five (75) feet of the plants to be irrigated.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
15.510 Brookside Drive (Z-709_1-A)
Any new site development must comply with the City's minimal landscape and buffer
ordinance requirements.
A small amount of landscape will need to be provided between the new structure, parking
areas, and the public right-of-way. Provide plant material at the rate of one (1) tree and
four (4) shrubs for every forty (40) linear feet between the building and parking areas.
Provide plant material at the rate one (1) tree and three (3) shrubs between the building
and the public right-of-way.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
16. 716 AppianwayZ-7895-D)
No Comment
17. Southwest comer of I-630 and Fair Park 4-8472-D
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements and the Presidential Park Overlay District.
Street buffers will be required at six (6) percent of the average depth of the lot. The
minimum dimension shall be one-half (1/2) the full width requirement but in no case less
than nine (9) feet. The maximum dimension required shall be fifty (50) feet. The property
is located in the City's designated mature area. A twenty-five (25%) percent reduction of
the perimeter width requirements is acceptable. A minimum twenty-eight (28) foot buffer
is required adjacent to the Fair Park Boulevard right-of-way.
Street buffers shall be a minimum of thirty (30) feet in width when abutting an
expressway except within mature areas. A twenty-five (25%) percent reduction of
the perimeter width requirements is acceptable. A minimum twenty-three (23) foot buffer
is required adjacent to the I-630 right-of-way
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
Building landscape areas shall be provided at the rate equivalent to planter strip three (3)
feet wide along the vehicular use area. One (1) tree and four (4) shrubs shall be planted in
the building landscape areas for each forty (40) linear feet of vehicular use area abutting
the building.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip. The property is located in the City's designated
mature area. A twenty-five (25%) percent reduction of the perimeter width requirements
is acceptable.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). For
developments with more than one hundred fifty (150) parking spaces the minimum size
of an interior landscape area shall be three hundred (300) square feet. Interior islands
must be a minimum of seven and one half (7 1/2) feet in width. Trees shall be included in
the interior landscape areas at the rate of one (1) tree for every twelve (12) parking
spaces. The property is located in the City's designated mature area. A 25%
reduction of the interior parking requirements is acceptable.
Dumpsters, loading docks, heating and air conditioning units, external storage of
materials, communications equipment and similar outside activities and appurtenances
shall be screened from abutting properties and streets.
An irrigation system shall be required for developments of one (1) acre or larger.
The development of two (2) acres or more requires the landscape plan to be stamped with
the seal of a Registered Landscape Architect.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
18. 8222 Stagecoach (Z-8737-C
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
A land use buffer will be required when an adjacent property has a dissimilar use of a
more restrictive nature. As a component of all land use buffer requirements, opaque
screening, whether a fence or other device, a minimum of six (6) feet in height shall be
required upon the property line side of the buffer. A minimum of seventy (70) percent of
the land use buffer shall be undisturbed. Easements cannot count toward fulfilling this
requirement. The plantings, existing and purposed, shall be provided within the landscape
ordinance of the city, section 15-81. The properties to the north and west are zoned R-2, a
minimum buffer will be required at six (6) percent of the average depth / width of the lot.
The minimum dimension adjacent to the north property line shall be forty-five (45) feet,
thirty-two (32) feet of this buffer is to remain undisturbed.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
Landscape areas shall be provided between the vehicular use area used for public parking
and the general vicinity of the building
A landscape irrigation system shall be required for developments of one (1) acre or
larger.
The development of two (2) acres or more requires an approved landscape plan stamped
with the seal of a registered landscape architect prior to the issuance of a building permit.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
19.6608 Baseline Road (Z-902)-B
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
A land use buffer six (6) percent of the average width / depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The property
to the north and a portion of the properties to the east and west are zoned R-2. As a
component of all land use buffer requirements, opaque screening, whether a fence or
other device, a minimum of six (6) feet in height shall be required upon the property
line side of the buffer. A minimum of seventy (70) percent of the land use buffer shall be
undisturbed. Easements cannot count toward fulfilling this requirement. The plantings,
existing and purposed, shall be provided within the landscape ordinance of the city,
section 15-81.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). The minimum
size of an interior landscape area shall be one hundred fifty (150) square feet for
developments with one hundred fifty (150) or fewer parking spaces. Interior islands must
be a minimum of seven and one half (7 1/2) feet in width. Trees shall be included in the
interior landscape areas at the rate of one (1) tree for every twelve (12) parking spaces.
An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
20. 10115 Rodney Parham Road Z-9103-A
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements.
A land use buffer six (6) percent of the average width / depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The property
to the south is zoned R2. As a component of all land use buffer requirements, opaque
screening, whether a fence or other device, a minimum of six (6) feet in height shall be
required upon the property line side of the buffer. A minimum of seventy (70) percent of
the land use buffer shall be undisturbed. Easements cannot count toward fulfilling this
requirement. The plantings, existing and purposed, shall be provided within the landscape
ordinance of the city, section 15-81.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
Trees shall be included in the interior landscape areas at the rate of one (1) tree for every
twelve (12) parking spaces
One (1) tree and four (4) shrubs shall be planted in the building landscape areas for each
forty (40) linear feet of vehicular use area abutting the building
An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger.
The development of two (2) acres or more requires the landscape plan to be stamped with
the seal of a Registered Landscape Architect.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
21.5000 Hope Lane (Z-9207)
Any new site development must comply with the City's minimal landscape and buffer
ordinance requirements.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
22. 1417 Kavanaugh Boulevard Z-9208
No Comment
23. SWC C and Walnut Streets _ 324 Walnut Street Z-9210
No Comment
24. 6611 Young Road (Z-9290)
Any new site development must comply with the City's minimal landscape and buffer
ordinance requirements.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
25. West side of Chenal Parkway '/a mile south of Northfield Drive Z-9211
Site plan must comply with the City's minimal landscape and buffer ordinance
requirements, the Chenal Overlay District.
Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9)
feet wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30)
linear feet of perimeter planting strip.
A land use buffer six (6) percent of the average width / depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The minimum
dimension shall be nine (9) feet. The surrounding properties are zoned R-2. As a
component of all land use buffer requirements, opaque screening, whether a fence or
other device, a minimum of six (6) feet in height shall be required upon the
property line side of the buffer. A minimum of seventy (70) percent of the land use
buffer shall be undisturbed. Easements cannot count toward fulfilling this requirement.
The plantings, existing and purposed, shall be provided within the landscape ordinance
of the city, section 15-81. A portion of the southeast buffer is deficient.
Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). For
developments with more than one hundred fifty (150) parking spaces the minimum size
of an interior landscape area shall be three hundred (300) square feet. Interior islands
must be a minimum of seven and one half (7 1/2) feet in width. Trees shall be included in
the interior landscape areas at the rate of one (1) tree for every twelve (12) parking
spaces.
Landscape areas shall be provided between the vehicular use area used for public parking
and the general vicinity of the building, excluding truck loading or service areas not open
to public parking. These areas shall be equal to an equivalent planter strip three (3) feet
wide along the vehicular use area.
The development of two (2) acres or more requires the landscape plan to be stamped with
the seal of a Registered Landscape Architect.
A landscape irrigation system shall be required for developments of one (1) acre or
larger.
The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
Public Works Review Comments
Planning Commission Board of Adjustment
Agenda Date: 4-27-17
Z File Number S-1026-B
Lot Z-2A-R Little Rock Industrial District Replat 2400 W. 65th St.
1 Engineering comments may apply at time of building permit or with future development.
Z File Number S-1240-0
Steve Landers KIA Dealership Subdivision Site Colonel Glenn Plaza Loop
1 Sidewalks with appropriate handicap ramps are required to be installed adjacent to Colonel Glenn
Plaza Loop in accordance with Sec. 31-175 of the Little Rock Code and the Master Street Plan.
2 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
3 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. Is a variance being
requested to advance grade beyond the north lot where development is proposed?
4 Storm water detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the plan. Maintenance of the detention pond and all private drainage
improvements is the responsibility of the developer and/or property owner.
5 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
6 Provide a letter prepared by a registered engineer certifying the intersection sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards.
7 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
8 Retaining walls designed to exceed 15 ft in height are required to seek a variance for construction.
Provide proposed wall elevations.
9 Prior to construction of retaining walls, a engineer's certification of design and plans must be
submitted to Public Works for approval. After construction, an as -built certification is required for
construction of the retaining wall.
10 Unloading of vehicles is not allowed within the right-of-way. Show proposed delivery truck route
within the site.
Z File Number S-1787
Quick's Lake Place Pre Plat
NWC Stewart Rd & Simpson Lane
1 Stewart Rd is classified on the Master Street Plan as a minor arterial. A dedication of right-of-way 45
feet from centerline will be required.
Friday, March 31, 2017 Page 1 of 14
2 What is the status of Simpson Lane (public right-of-way/private easement)? If a public right-of-way,
Simpson Lane is classified on the Master Street Plan as a residential street. A dedication of right-of-
way 25 feet from centerline will be required.
3 A 20 feet radial dedication of right-of-way is required at the intersection of Stewart Rd and Simpson
Lane depending on the status of Simpson Lane.
4 With site development, provide design of street conforming to the Master Street Plan. Construct
one-half street improvement to Stewart Road including 5-foot sidewalks with planned development.
A 6 ft wide paved shoulder should be provided on Stewart Rd adjacent to the subject property.
5 With site development, provide design of street conforming to the Master Street Plan. Construct
one-half street improvement to Simpson Lane including 5-foot sidewalks with planned development.
This conditions depends on the status of Simpson Lane.
6 All driveways shall be concrete aprons per City Ordinance.
7 Storm water detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the plan. Maintenance of the detention pond and all private drainage
improvements is the responsibility of the developer and/or 1
8 In accordance with Section 32-8, no obstruction to visibility shall be located within a triangular area
50' back from the intersecting right-of-way line (or intersecting tangent lines for radial dedications) at
the intersection of driveway with Stewart Road.
9 Provide a letter prepared by a registered engineer certifying the intersection sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards. A sight distance of at least 445 ft
as shown in Exhibit 9-55 should be provided.
Z File Number 5-1788
Wellington Creek Subdivision Pre Plat SEC Chenal Parkway & Wellington Hills Road
1 Chenal Parkway is classified on the Master Street Plan as a principal arterial. Dedication of right-of-
way should be a sufficient width to construct 1 additional - 11 ft lane, 2 ft of curb and gutter, a 6 ft
green space, and a 5 ft sidewalk.
2 With site development, provide design of street conforming to the Master Street Plan. Construction
one-half street improvements to Chenal Parkway, Chenal Parkway bridge, and the 5 ft sidewalk with
planned development. One (1) additional lane should be constructed of an 11 ft lane width and 2 ft of
curb and gutter. A payment should be made in -lieu of construction of the first 15 linear feet of the
bridge. The payment should be for the estimated cost to widen the Chenal Parkway bridge to
provide 3 - 11 ft vehicle travel lanes, a 2 ft parapet wall, a 10 ft pedestrian lane, and the outer bridge
deck wall. The unit cost of the bridge widening was provided to the design professionals on the
project. The payment should be made prior to approval of the final plat.
With site development, provide design of street conforming to the Master Street Plan. Construct
one-half street improvement to Kanis Rd including the Kanis Road bridge and a 5-foot sidewalk with
planned development. The new back of curb should be located 29.5 ft from the existing centerline
with a 5 ft sidewalk placed at the property line. A payment in -lieu of construction should be provided
for Kanis Road improvements prior to the approval of the final plat of a lot adjacent to Kanis Road.
The payment should include the first 15 linear ft of the Kanis Road bridge. Payment should be for
the estimated cost to widening the Rock Creek bridge to provide 2.5 - 11 ft vehicle travel lanes, a 2 ft
parapet wall, a 10 ft pedestrian lane, and the outer bridge deck wall from the striped centerline of the
bridge. The unit cost of the bridge widening was provided to the civil engineer. The payment
should be made prior to approval of the final plat.
Friday, March 31, 2017 Page 2 of 14
4 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
5 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. Is an advanced
grading variance being requested to advance grade future phases with construction on lot 1?
6 Storm water detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the plan. Maintenance of the detention pond and all private drainage
improvements is the responsibility of the developer and/or land owner.
7 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
8 A special Grading Permit for Flood Hazard Areas will be required per Sec. 8-283 prior to
construction.
9 The minimum Finish Floor elevation of at least 1 foot above the base flood elevation is required to
be shown on plat and grading plans.
10 In accordance with Section 31-176, floodway areas must be shown as floodway easements or be
dedicated to the public. In addition, a 25 foot wide drainage and access easement is required adjacent
to the floodway boundary. The area within the proposed floodway should be rezoned Open Space.
11 Alteration of the water course will require approval from the Little Rock District of the US Army
Corps of Engineers prior to start of work.
12 The proposed alteration of the floodway will require flood map revisions. Obtain a conditional letter
of map revision (CLOMR) and no rise certification approval from Public Works and the Federal
Emergency Management Agency prior to issuance of a grading permit and/or building permit. An
approved letter of map revision (LOMR) must be obtained prior to issuance of a certificate of
occupancy.
13 Driveway locations and widths do not meet the traffic access and circulation requirements of Sections
30-43 and 31-210. The lots share driveway access centered on the property line. The width of
driveway must not exceed 36 feet. The driveway spacing on arterial streets is 150 ft from the side
property line and 300 ft from street intersections and other driveways. Separate driveway variances are
required for the driveway width and spacing.
14 Kanis Road is classified on the Master Street Plan as a minor arterial. A dedication of right-of-way
45 feet from centerline will be required. At arterial -arterial intersection an additional 10 ft of right-of-
way measured from the centerline of the right-of-way should be dedicated for a right turn lane. The
additional right-of-way shall normally be 250 ft in length measured from the intersecting right-of-way.
The total dedication is 55 ft from centerline.
15 A 75 to 100 feet radial dedication of right-of-way is required at the intersection of Kanis Rd and
Wellington Hills Road (arterial -arterial).
16 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e).
17 Erosion controls must be installed to reduce discharge of polluted stormwater.
18 Provide a letter prepared by a registered engineer certifying the intersection sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards.
19 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
Friday, March 31, 2017 Page 3 of 14
20 Prior to construction of retaining walls, a engineer's certification of design and plans must be
submitted to Public Works for approval. After construction, an as -built certification is required for
construction of the retaining wall.
21 Performance bond and payment for boundary street improvements are required to be provided prior to
the approval of the final plat of a lot.
Z File Number S-1788-A
Kum and Go Convenience Store Site Plan Review 15617 Chenal Parkway
width
bridge
Open
An
1 Chenal Parkway is classified on the Master Street Plan as a principal arterial. Dedication of right-of-
way should be a sufficient width to construct 1 additional - 11 ft lane, 2 ft of curb and gutter, a 6 ft
green space, and a 5 ft sidewalk.
2 With site development, provide design of street conforming to the Master Street Plan. Construction
one-half street improvements to Chenal Parkway, Chenal Parkway bridge, and the 5 ft sidewalk
with planned development. One (1) additional lane should be constructed of an 11 ft lane
and 2 ft of curb and gutter. A payment should be made in -lieu of construction of the first 15 linear
feet of the bridge. The payment should be for the estimated cost to widen the Chenal Parkway
bridge to
provide 3 - 11 ft vehicle travel lanes, a 2 ft parapet wall; a 10 ft pedestrian lane, and the outer
deck wall. The unit cost of the bridge widening was provided to the design professionals on the
3 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
4 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. Is an advanced
grading variance being requested to advance grade future phases with construction on lot 1?
5 Storm water detention ordinance applies to this property. Show the proposed location for
stormwater detention facilities on the plan. Maintenance of the detention pond and all private
drainage improvements is the responsibility of the developer and/or land owner.
6 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
7 A special Grading Permit for Flood Hazard Areas will be required per Sec. 8-283 prior to
construction.
8 The minimum Finish Floor elevation of at least 1 foot above the base flood elevation is required to
be shown on plat and grading plans.
9 In accordance with Section 31-176, floodway areas must be shown as floodway easements or be
dedicated to the public. In addition, a 25 foot wide drainage and access easement is required
adjacent to the floodway boundary. The area within the proposed floodway should be rezoned
10 Alteration of the water course will require approval from the Little Rock District of the US Army
Corps of Engineers prior to start of work.
11 The proposed alteration of the floodway will require flood map revisions. Obtain a conditional letter
of map revision (CLOMR) and no rise certification approval from Public Works and the Federal
Emergency Management Agency prior to issuance of a grading permit and/or building permit.
approved letter of map revision (LOMR) or the adoption of the preliminary FIRMs must be
obtained prior to issuance of a certificate of occupancy.
Friday, March 31, 2017 Page 4 of 14
variances
for
12 Driveway locations and widths do not meet the traffic access and circulation requirements of Sections
30-43 and 31-210. The lots share driveway access centered on the property line. The width of
driveway must not exceed 36 feet. The driveway spacing on arterial streets is 150 ft from the side
property line and 300 ft from street intersections and other driveways. Separate driveway
are required for the driveway width and spacing.
13 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e).
14 Erosion controls must be installed to reduce discharge of polluted stormwater.
15 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to
issuance of a certificate of occupancy.
16 Prior to construction of retaining walls, a engineer's certification of design and plans must be
submitted to Public Works for approval. After construction, an as -built certification is required
construction of the retaining wall.
17 All driveways shall be concrete aprons per City Ordinance.
18 The access ramp on the NW corner of the property should be reconstructed per PW-51 to align the
ramp with the Wellington Road pedestrian crossing.
Z File Number Z-1620-A
B & G Properties PID 3401 - 3423 Mabelvale Pike
1 Mabelvale Pike is classified on the Master Street Plan as a minor arterial. A dedication of right-of-
way 45 feet from centerline will be required.
2 Due to the proposed use of the property, the Master Street Plan specifies that W. 34th Street for the
frontage of this property must meet commercial street standards. Dedicate right-of-way to 30 feet from
centerline.
3 A 20 feet radial dedication of right-of-way is required at the intersection of Mabelvale Pike and W.
34th St.
Z File Number Z-1840-D
Little Rock Raquet Club PD-O 1 Huntington Road
1 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction.
2 A handicap ramp is required to be installed on Huntington Road at in accordance with Sec. 31-175
of the Little Rock Code and the Master Street Plan. The access ramp has been constructed.
3 Provide a Sketch Grading and Drainage Plan for the additional parking areas per Sec. 29-186.
4 On site striping and signage plans must be desinged per MUTCD standards.
5 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
6 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to
issuance of a certificate of occupancy.
Friday, March 31, 2017 Page 5 of 14
for
7 Prior to construction of retaining walls, a engineer's certification of design and plans must be
submitted to Public Works for approval. After construction, an as -built certification is required
construction of the retaining wall.
8 Show the proposed parking wheel stops on the plan to confirm parking aisle widths and traffic flow.
Z File Number Z-2306-B
Hawkins PCD
600 E. 21 st St.
1 A 20 feet radial dedication of right-of-way is required at the intersection of E. 21 st St. and Park Lane.
2 At the time of future builiding expansion or expansion of the use of the property, the driveways on E.
21st St. and Park Lane closest to the street intersection may be required to be closed.
Z File Number Z-5442-F
James Mitchell School Rev PCD
2410 S. Battery School
1 Due to the proposed use of the property, the Master Street Plan specifies that Battery Street for the
frontage of this property must meet commercial street standards. Dedicate right-of-way to 30 feet from
centerline.
2 Due to the proposed use of the property, the Master Street Plan specifies that 24th Street for the
frontage of this property must meet commercial street standards. Dedicate right-of-way to 30 feet from
centerline.
3 Due to the proposed use of the property, the Master Street Plan specifies that Summit Ave.for the
frontage of this property must meet commercial street standards. Dedicate right-of-way to 30 feet from
centerline.
4 Roosevelt Rd is classified on the Master Street Plan as a principal arterial with special design
standards. Dedication of right-of-way to 35 feet from centerline will be required.
5 A 20 feet radial dedication of right-of-way is required at the four (4) street intersection adjacent to the
site.
6 Repair or replace any curb and gutter or sidewalk that is missing, damaged, or obstructed by
vegetation in the public right-of-way prior to occupancy.
7 Property frontage needs to have the sidewalks and ramps brought up to the current ADA standards.
8 Vehicle stacking or stopping within the public right-of-way for student pick up and drop off is not
permitted.
9 Submit a Traffic Impact Study and/or Traffic Control Plan for the proposed project. Study should
address trip generation and trip distribution for the development, vehicle stacking, student drop-off
and pick-up and also should take into account existing and projected traffic growth.
10 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
Z File Number Z-5574-D
United Methodist Children's Home Campus POD 2022 S. Fillmore St.
1 Charles Bussey Ave. is classified on the Master Street Plan as a residential street. A dedication of
right-of-way 25 feet from centerline will be required.
Friday, March 31, 2017 Page 6 of 14
2 Fillmore St. is classified on the Master Street Plan as a residential Street. A dedication of right-of-
way 25 feet from centerline will be required.
3 A 20 feet radial dedication of right-of-way is required at the intersection of Fillmore St. and Charles
Bussey Ave.
4 In accordance with Section 31-176, floodway areas must be shown as floodway easements or be
dedicated to the public. In addition, a 25 foot wide drainage and access easement is required adjacent
to the floodway boundary.
5 The area within the floodway should be rezoned Open Space.
6 With site development, provide design of street conforming to the Master Street Plan. Construct
one-half street improvement to Charles Bussey Ave. including 5-foot sidewalks with planned
development. The new back of curb should be located 13 ft from centerline.
7 Sidewalks with appropriate handicap ramps are required to be constructed along Fillmore St. in
accordance with Sec. 31-175 of the Little Rock Code and the Master Street Plan.
8 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
9 Remove existing driveways on Fillmore St. that are fenced and not proposed to be used.
10 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. A variance must be
requested for an advanced grading permit for the "Lay Down" area.
11 Storm water detention ordinance applies to this property. Maintenance of the detention pond and all
private drainage improvements is the responsibility of the developer and/or property owner to
maintain.
12 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
13 The proposed driveway on Fillmore St. shall be constructed with concrete aprons per City Ordinance
and not exceed 26 ft in width and not exceed a 15 ft radius. The call box for the gate shall be located
no closer than 40 ft from Fillmore St. If the gate will be open all day during daylight hours, the gate
can be located at least 20 ft from Fillmore St.
14 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
15 Obtain a franchise agreement from Public Works (Bennie Nicolo, 371-4818) for the private
improvements located in the right-of-way such as parking, plantings, signage, fencing, etc..
Z File Number Z-6054-C
Fitts Auto Expansion Rev PCD 8421 Stagecoach Rd
1 Stagecoach Rd is classified on the Master Street Plan as a principal arterial. Dedication of right-of-
way to 55 feet from centerline will be required.
Friday, March 31, 2017 Page 7 of 14
2 Sidewalks with appropriate handicap ramps are required to be installed along Stagecoach Rd and
extend to the side property line in accordance with Sec. 31-175 of the Little Rock Code and the
Master Street Plan. Addiitional sidewalk should be constructed along the frontage of the new
property to the east. Sidewalk should also be constructed to the southwest property line west of the
existing west driveway.
3 Obtain permits for improvements within State Highway right-of-way from AHTD, District VI.
4 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. Is an advanced
grading variance being requested to grade future phases with construction of Phase 1?
5 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e). Provide finished floor elevations,
floodplain and floodway, and fill embankments or retaining walls.
6 Storm water detention ordinance applies to this property. Show the proposed location for
stormwater detention facilities on the plan. Maintenance of the detention pond and all private
drainage improvements is the responsibility of the developer and/or owner.
7 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
8 A special Grading Permit for Flood Hazard Areas will be required per Sec. 8-283 prior to
construction.
9 The minimum Finish Floor elevation of at least 1 ft above the base flood elevation is required to be
shown on plat and grading plans.
10 In accordance with Section 31-176, floodway areas must be shown as floodway easements or be
dedicated to the public. In addition, a 25 foot wide drainage and access easement is required
adjacent to the floodway boundary. If property within the floodway should be zoned as Open
11 Vehicle offloading within the public right-of-way is not allowed. Provide the truck manuevering
route on the site plan.
12 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to
issuance of a certificate of occupancy.
13 Driveway locations and widths do not meet the traffic access and circulation requirements of Sections
30-43 and 31-210. Driveway spacing on an arterial street is 300 ft from intersections and other
driveways and 150 ft from the property line. The width of driveway must not exceed 36 feet. A
variance must be requested for the proposed driveway location.
Z File Number Z-6060-A
Dash Heating & Cooling Rev PD-O 12417 Cantrell Road
1 Cantrell Rd is classified on the Master Street Plan as a principal arterial. Dedication of right-of-way to
55 feet from centerline will be required.
2 Due to Piedmont Pond located downstream of the subject property, adequate erosion controls are
required to be installed and maintained during construction.
3 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction.
Friday, March 31, 2017 Page 8 of 14
4 Storm water detention ordinance applies to this property. The project would qualify for a
contribution in -lieu of construction at the time of the building permit.
4 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e).
Z File Number Z-6318-E
Chenal Market Rev PCD
16105 Chenal Parkway
1 Stormwater detention is provided for proposed Lot 2 on proposed Lot 1. Maintenance of detention
ponds is the responsbility of the property owner or property owner's association. How will detention
be provided for proposed lot 2?
2 Access easements or shared access and parking should be provided.
3 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
4 In accordance with Section 31-176, floodway areas must be shown as floodway easements or be
dedicated to the public. In addition, a 25 foot wide drainage and access easement is required adjacent
to the floodway boundary. The floodway should be rezoned Open Space.
Z File Number Z-6488-B
KLR Properties POD
12400 Cantrell Road
1 All previous engineering comments and conditions made on the approved application apply
Z File Number Z-6860-E
Markham Harrison Properties PD-O
5307 A St.
1 Due to the proposed use of the property, the Master Street Plan specifies that A Street for the frontage
of this property must meet commercial street standards. Dedicate right-of-way to 30 feet from
centerline.
2 With site development, provide design of street conforming to the Master Street Plan. Construct
one-half street improvement to A St. including 5-foot sidewalks with planned development. The new
curb should connect with the newly installed curb to the west at the same width.
3 Driveway locations and widths do not meet the traffic access and circulation requirements of Sections
30-43 and 31-210. A variance is required to be obtained for the driveway location. Driveway spacing
on commercial streets is 250 ft from street intersections and other driveways and 125 ft from side
property lines.
Z File Number Z-7091-A
Presbyterian Village PD-R
510 Brookside Drive
1 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
2 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
Z File Number Z-7895-D
J & R Properties Rev PCD 716 Appianway St.
Friday, March 31, 2017 Page 9 of 14
I The proposed gates should be installed as shown on plan.
Z File Number Z-8472-D
Mid -Town & Fair Park PCD SWC I-630 & Fair Park Blvd.
(501)
for
1 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
2 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
3 Plans of all work in right-of-way shall be submitted for approval prior to start of work. Obtain
barricade permit prior to doing any work in the right-of-way from Traffic Engineering at
379- 1805 (Travis Herbner).
4 Storm water detention ordinance applies to this property.
5 Prior to construction of retaining walls, a engineer's certification of design and plans must be
submitted to Public Works for approval. After construction, an as -built certification is required
construction of the retaining wall.
6 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction.
7 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to
issuance of a certificate of occupancy.
8 Provide additional right-of-way for "T" turnaround.
Z File Number Z-8737-C
Davis Storage Development PCD 8222 Stagecoach Road
1 Stagecoach Rd is classified on the Master Street Plan as a principal arterial. Dedication of right-of-
way to 55 feet from centerline will be required.
2 The proposed driveway apron(s) should be constructed in accordance with AHTD driveway details to
provide future pedestrian crossing in conformance with ADA guidelines.
3 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
4 Obtain permits for improvements within State Highway right-of-way from AHTD, District VI.
5 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. Will
construction
of the development be phased? Will an advance grading variance be requested to advance grade
future phases with the construction of phase 1?
6 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e).
7 Storm water detention ordinance applies to this property. Maintenance of the detention pond and all
private drainage improvements is the responsibility of the developer and/or property owner.
8 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
Friday, March 31, 2017 Page 10 of 14
9 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to
issuance of a certificate of occupancy.
10 If a drive thru fast food restaurant is proposed, show the amount of vehicle stack and the order board
location.
11 Sidewalks with appropriate handicap ramps are required to be constructed adjacent to Stagecoach
Road in accordance with Sec. 31-175 of the Little Rock Code and the Master Street Plan. The back
of the new sidewalk should be located at the property line and connected with existing adjacent
sidewalk.
12 A special Grading Permit for Flood Hazard Areas will be required per Sec. 8-283 prior to
construction.
13 The minimum Finish Floor elevation of of at least 1 ft above the base flood elevation is required to
be shown on plat and grading plans.
14 Driveway locations and widths do not meet the traffic access and circulation requirements of Sections
30-43 and 31-210. A variance is required for the proposed driveways. Driveway spacing on arterial
streets is 300 ft between driveways and intersections and 150 ft from side property lines. The width
of driveway must not exceed 36 feet.
Z File Number Z-9023-B
6608 Baseline Road PD-O 6608 Baseline Rd
1 Repair or replace any curb and gutter or sidewalk that is damaged in the prior to the issuance of the
certificate of occupancy.
2 Obtain permits for improvements within State Highway right-of-way from AHTD, District VI.
Z File Number Z-9103-A
Small Emergency Hospital POD 10115 Rodney Parham Rd
1 Rodney Parham Rd is classified on the Master Street Plan as a minor arterial. A dedication of right-
of-way 45 feet from centerline will be required.
2 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy. The existing curb cuts not planned to be used should be removed and replaced with curb
and gutter and new sidewalk if needed.
3 In accordance with Section 31-176, floodway areas must be shown as floodway easements or be
dedicated to the public. In addition, a 25 foot wide drainage and access easement is required adjacent
to the floodway boundary. The floodway should be rezoned Open Space.
4 Pedestrian access should be provided to the front door of the facility from the right-of-way.
5 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction.
6 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e). Show the proposed finished floor
elevation.
7 The minimum Finish Floor elevation of at least 1 ft above the base flood elevation is required to be
shown on plat and grading plans.
Friday, March 31, 2017 Page I 1 of 14
8 Storm water detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the plan. Maintenance of the detention pond and all private drainage
improvements is the responsibility of the developer and/or property owner.
9 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
10 A special Grading Permit for Flood Hazard Areas will be required per Sec. 8-283 prior to
construction.
11 Hauling of fill material on or off site over municipal streets and roads requires approval prior to a
grading permit being issued. Contact Public Works Traffic Engineering at 621 S. Broadway, (501)
379-1805 (Travis Herbner) for more information.
12 Driveway locations and widths do not meet the traffic access and circulation requirements of Sections
30-43 and 31-210. The width of driveway must not exceed 36 feet. The proposed driveway location
creates left turn conflicts. A variance is required for the proposed driveway location. The driveway
spacing on arterial streets is at least 150 ft from the property line and at least 300 ft from intersections
and other driveways.
13 In accordance with Section 32-8, no obstruction to visibility shall be located within a triangular area
50' back from the intersecting right-of-way line (or intersecting tangent lines for radial dedications) at
the proposed driveway.
14 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
15 Provide a letter prepared by a registered engineer certifying the intersection sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards.
Z File Number Z-9207
Lawson West PD-C 5000 Hope Lane
1 The private street should connect into Lawson Road with a concrete apron per City Ordinance.
2 Provide a letter prepared by a registered engineer certifying the intersection sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards. Sight distance of at least 445 ft
must be provided.
3 Lawson Road is classified on the Master Street Plan as a minor arterial. A dedication of right-of-way
45 feet from centerline will be required.
4 Storm water detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the plan. Maintenance of the detention pond and all private drainage
improvements is the responsibility of the developer and/or land owner.
5 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
6 In accordance with Section 32-8, no obstruction to visibility shall be located within a triangular area
50' back from the intersecting right-of-way line (or intersecting tangent lines for radial dedications) at
the intersection of private street with Lawson Rd.
Z File Number Z-9208
Graham Property Management PD-R 1417 Kavanaugh Blvd
0 No comments
Friday, March 31, 2017 Page 12 of 14
Z File Number Z-9209
Arkansas Indoor Soccer PID
6611 Young Road
1 Young Road is classified on the Master Street Plan as a collector street. A dedication of right-of-way
30 feet from centerline will be required.
2 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
3 Storm water detention will not apply to the proposed development being less than 1 acre in size.
Z File Number Z-9210
Lawson PD-R
324 Walnut St.
1 A 20 feet radial dedication of right-of-way is required at the intersection of C St. and Walnut St.
2 The fence must be moved out of the public right-of-way.
3 Where is vehicle parking proposed outside of the right-of-way? The face of the garage must be
located at least 20 ft from the property line. A parking pad must be constructed of sufficient length
and width for 1 car to park outside of the right-of-way.
Z File Number Z-9211
The Crest at Chenal PD-R
South of Chenal Pkwy & Northfield Dr
1 With site development, provide design of street conforming to the Master Street Plan. Construct
one-half street improvement to Chenal Parkway including 5-foot sidewalks with planned
development. Chenal Parkway should be widened to conform with the Master Street Plan. A left
turn lane with tapers should be provided which may result in widening apast the property line.
2 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. Is the construction
of the project planned to be phased?
3 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e).
4 Storm water detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the plan. Maintenance of the detention pond and all private drainage
improvements is the responsibility of the developer and/or property owner.
5 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
6 Show proposed gate and call box locations.
7 In accordance with Section 32-8, no obstruction to visibility shall be located within a triangular area
50' back from the intersecting right-of-way line (or intersecting tangent lines for radial dedications) at
the driveway intersection.
8 Provide a letter prepared by a registered engineer certifying the intersection sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards and provides at least 500 ft of
unobstructed sight distance for 45 mph.
9 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
Friday, March 31, 2017 Page 13 of 14
10 The owner and/or manager of each multi -family residence of 100 or more dwelling units shall provide
recycling and encourage participation by the tenants, renters, or owners of each unit. Contact
Melinda Glasgow at 371-4646 for more information.
11 The proposed median in the driveway is too wide and should be narrowed to 12 to 15 ft in width.
The nose of the median should be placed no closer than 12 ft from the future back of curb on Chenal
Parkway.
Friday, March 31, 2017 Page 14 of 14
Public Works Review Comments
Board of Adjustment
Agenda Date: 4/27/2017
Z File Number 5-1788
Wellington Creek Subdivision Pre Plat
Planning
SEC Chenal Parkway & Wellington Hills Road
1 Chenal Parkway is classified on the Master Street Plan as a principal arterial. Dedication of right-of-
way should be a sufficient width to construct 1 additional - 11 ft lane, 2 ft of curb and gutter, a 6 ft
green space, and a 5 ft sidewalk.
2 With site development, provide design of street conforming to the Master Street Plan. Construction
one-half street improvements to Chenal Parkway, Chenal Parkway bridge, and the 5 ft sidewalk with
planned development. One (1) additional lane should be constructed of an 11 ft lane width and 2 ft of
curb and gutter. A payment should be made in -lieu of construction of the first 15 linear feet of the
bridge. The payment should be for the estimated cost to widen the Chenal Parkway bridge to
provide 3 - 11 ft vehicle travel lanes, a 2 ft parapet wall, a 10 ft pedestrian lane, and the outer bridge
deck wall. The unit cost of the bridge widening was provided to the design professionals on the
project. The payment should be made prior to approval of the final plat.
With site development, provide design of street conforming to the Master Street Plan. Construct
one-half street improvement to Kanis Rd including the Kanis Road bridge and a 5-foot sidewalk with
planned development. The new back of curb should be located 29.5 ft from the existing centerline
with a 5 ft sidewalk placed at the property line. A payment in -lieu of construction should be provided
for Kanis Road improvements prior to the approval of the final plat of a lot adjacent to Kanis Road.
The payment should include the first 15 linear ft of the Kanis Road bridge. Payment should be for
the estimated cost to widening the Rock Creek bridge to provide 2.5 - 11 ft vehicle travel lanes, a 2 ft
parapet wall, a 10 ft pedestrian lane, and the outer bridge deck wall from the striped centerline of the
bridge. The unit cost of the bridge widening was provided to the civil engineer. The payment
should be made prior to approval of the final plat.
4 Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-way prior to
occupancy.
5 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and
drainage plans must be submitted and approved prior to the start of construction. Is an advanced
grading variance being requested to advance grade future phases with construction on lot 1?
6 Storm water detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the plan. Maintenance of the detention pond and all private drainage
improvements is the responsibility of the developer and/or land owner.
7 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
8 A special Grading Permit for Flood Hazard Areas will be required per Sec. 8-283 prior to
construction.
9 The minimum Finish Floor elevation of at least 1 foot above the base flood elevation is required to
be shown on plat and grading plans.
Monday, April 03, 2017 Page 1 of 2
10 In accordance with Section 31-176, floodway areas must be shown as floodway easements or be
dedicated to the public. In addition, a 25 foot wide drainage and access easement is required adjacent
to the floodway boundary. The area within the proposed floodway should be rezoned Open Space.
1 I Alteration of the water course will require approval from the Little Rock District of the US Army
Corps of Engineers prior to start of work.
12 The proposed alteration of the floodway will require flood map revisions. Obtain a conditional letter
of map revision (CLOMR) and no rise certification approval from Public Works and the Federal
Emergency Management Agency prior to issuance of a grading permit and/or building permit. An
approved letter of map revision (LOMR) must be obtained prior to issuance of a certificate of
occupancy.
13 Driveway locations and widths do not meet the traffic access and circulation requirements of Sections
30-43 and 31-210. The lots share driveway access centered on the property line. The width of
driveway must not exceed 36 feet. The driveway spacing on arterial streets is 150 ft from the side
property line and 300 ft from street intersections and other driveways. Separate driveway variances are
required for the driveway width and spacing.
14 Kanis Road is classified on the Master Street Plan as a minor arterial. A dedication of right-of-way
45 feet from centerline will be required. At arterial -arterial intersection an additional 10 ft of right-of-
way measured from the centerline of the right-of-way should be dedicated for a right turn lane. The
additional right-of-way shall normally be 250 ft in length measured from the intersecting right-of-way.
The total dedication is 55 ft from centerline.
15 A 75 to 100 feet radial dedication of right-of-way is required at the intersection of Kanis Rd and
Wellington Hills Road (arterial -arterial).
16 Provide a Sketch Grading and Drainage Plan per Sec. 29-186 (e).
17 Erosion controls must be installed to reduce discharge of polluted stormwater.
18 Provide a letter prepared by a registered engineer certifying the intersection sight distance at the
intersection(s) comply with 2004 AASHTO Green Book standards.
19 Damage to public and private property due to hauling operations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance
of a certificate of occupancy.
20 Prior to construction of retaining walls, a engineer's certification of design and plans must be
submitted to Public Works for approval. After construction, an as -built certification is required for
construction of the retaining wall.
21 Performance bond and payment for boundary street improvements are required to be provided prior to
the approval of the final plat of a lot.
22 Per Section 29-190, a minimum undisturbed strip 25 ft wide except for reasonable access shall be
provided along each side of streams having a 10 yr storm >150 cfs. The undisturbed strip should be
measured from the top of the bank.
23 In accordance with 31-210 (h)(12), access driveways running parallel to the street shall not create a
four-way intersection within 75' of the future curb line of the street.
Monday, April 03, 2017 Page 2 of 2
To: Dana Carney, Zoning & Subdivision Manager Date: 3-30-17
Donna James, Zoning
Monte Moore, Subdivision
From: Curtis Richey / Mark Alderfer: Building Codes
Building Code Comments:
Z-1840-D 1 Huntington Road
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey@littlerock.,gov or
Mark Alderfer at 501.371.4875; malderfer@littlerock.gov .
Z-1620-A 3401- 3423 Mabelvale Pike
NC -
Z-5574-D 2022 S. Fillmore
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; cricheyPlittlerock.gov or
Mark Alderfer at 501.371.4875; rnalderfer@littlerock.gov .
Z-9103-A 10115 RodneV Parham
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey@littlerock.gov or
Mark Alderfer at 501.371.4875; malderfer@littlerock.gov .
Z-6060-A 12417 Cantrell
NC
Z-9211 West side of Chenal !_.mile south of Northfield Drive
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey littlerock.gov or
Mark Alderfer at 501.371.4875; malderfer@littlerock.gov .
Z-6860-E 5307 A Street
NC
S-1026-B 2400 West 654" Street
NC
Z-7895-0 716 Appian Wad[
NC
S-1240-0 Colonel Glenn Plaza Loop
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey P littlerock.gov or
Mark Alderfer at 501.371.4875; malderfer@iittlerock.goy .
Z-5442-F 2410 South Batte Street
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; criich-.v [ittlerock.gav_ or
Mark Alderfer at 501.371.4875; malderfegVittlerock.gov .
Z-9209 6611 Young Road
NC
Z-7091-A 510 Brookside
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey @littlerock. ov or
Mark Alderfer at 501.371.4875; malderfer littlerock. ov .
Z-9023-B 6608 Baseline Road
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichev@littlerock.gay or
Mark Alderfer at 501.371.4875; malderfer@littlerock.gov .
S-1788 SEC Chenal and Wellington Hills Road
NC
S-1788-A 1561 Chenal Parkwa
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey@littlerock.go or
Mark Alderfer at 501.371.4875; ma Id e rferP little rock. ov .
Z-6318-E 16105 Chenal Parkway
NC
Z-89737-C 8222 Stagecoach Road
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; cricheyPlittleropk.gov or
Mark Alderfer at 501.371.4875; malderfer littlerock.gov .
Z-60654-C 8421 Stagecoach Road
NC
S-1787 Stewart Road and Sampson Lane
NC
Z-9207 5000 Hope Lane
NC
Z-9208 1417 Kavanaugh
Project is subject to full commercial plan review and approval prior to issuance of a building permit. For
information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey2littlerock.gov or
Mark Alderfer at 501.371.4875; malderfer@iittlerock.gov .
Z-2306-B 600 East 215t Street
Project is a change in occupancy and is therefore subject to current building code requirements. Review
and approval is required by Building Codes Division before occupancy takes place. For information on
submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichev@littlerock.org or
Mark Alderfer at 501.371.4875; malderfer@littierock.org.
Z-9210 SWC C and Walnut Street— 324 Walnut Street
NC
Regards, Curtis Richey
Commercial Plans Examiner
Quick's Lake — PCRB Comments — 3/31/17
1. Provide letter and engineering certification for the new driveway stating that
intersection will have a safe sight distance and meet AASHTO sight distance
requirements.
rev 5-26-16
Pulaski County Final Plat Checklist
PLANNING AND DEVELOPMENT
3200 BROWN STREET
LITTLE ROCK, AR 72204
501-340-8260
DATE: 3/27/17
DEVELOPMENT: Quick Lake's Place Lots 1-3 Final Plat
LOCATION: East side of Hwy 300 South of Pinnacle Road
ENGINEER/SURVEYOR: Mike Marlar
PLANNING JURISDICTION: Pulaski County/LR ETJ
Van McClendon Planning & Development Director
The final plat shall indicate the following information:
1)
no
3.7 A.L-3.
LETTER OF APPLICATION, BILL OF ASSURANCE
2)
yes
3.7 C.1.-4.
15 COPIES OF THE PROPOSED FINAL PLAT
3)
yes
3.7 C.5.a.
NAME OF SUBDIVISION (NO DUPLICATION)
4)
yes
3.7 C.5.b.
NAME AND ADDRESS OF OWNER OF RECORD
5)
yes
3.7 C.5.c.
SOURCE OF TITLE
6)
yes
3.7 C.5.d.
NAME AND ADDRESS OF SUBDIVIDER
7)
no
3.7 C.5.e.
DATE OF DRAWING, NORTH POINT, GRAPHIC SCALE AND TWO LAND
CORNERS AND STATE PLANE COORDINATES FOR AT LEAST TWO PQINTS
8)
yes
3.7 C.5.f
LOCATION OF PLAT/TRACT BY LEGAL DESCRIPTION GIVING ACREAGE
9)
yes
3.7 C.5.g.-h.
VICINITY MAP AND MAP KEY
10)
no
3.7 C.5.i.
TRUE COURSES AND DISTANCES TO TWO NEAREST ESTABLISHED SECTION
CORNERS OR BENCHMARKS AND STATE PLANE COORDINATES FOR BOTH
POINTS
11)
yes
3.7 C.5 j.
BOUNDARY LINES OF TRACT WITH EXACT DIMENSIONS
12)
yes
3.7 C.51.
MUNICIPAL, COUNTY OR SECTION LINES
13)
yes
3.7 C.5.1.
STREET AND ALLEY AND OTHER R.O.W. LINES
14)
yes
3.7 C.5.m.
STREET CENTERLINES WITH ANGLES AND DISTANCES
15)
yes
3.7 C.5.n.
LOT AND BLOCK NUMBERS
rev 5-26-16
16)
yes
3.7. C.S.o.
EASEMENTS, PUBLIC SERVICE, UTILITY, RIGHT OF WAY, ETC.
17)
n/a
3.7 C.S.p.
ACCURATE OUTLINES AND DESCRIPTIONS OF PUBLIC USE AREAS
18)
no
3.7 C.S.q.
ACCURATE MONUMENT LOCATION AND DESCRIPTION
19)
yes
3.7 C.S.r.
DIMENSIONS, ANGLES, ETC.
20)
n/a
3.7 C.S.s.
CERTIFICATE OF ENGINEERING IF DESIGNED IMPROVEMENTS INCLUDED
21)
yes
3.7 C.S.t.
CERTIFICATE OF SURVEYING ACCURACY
22)
yes
3.7 C.S.u.
CERTIFICATE OF OWNER
23)
no
3.7 C.S.w.
CERTIFICATE OF FINAL APPROVAL
24)
no
3.7 C.6.a.
CERTIFICATION OF WATER SUPPLY AND SANITARY SEWER DISPOSAL
25)
n/a
3.7 C.6.b.
CALCULATION AND FIELD NOTES
26)
n/a
3.7 C.6.c.
REQUIRED BONDS, LETTERS OF CREDIT, CASH DEPOSITS, ETC.
27)
no
3.7 C.6.d.
ELECTRONIC COPY OF THE FINAL PLAT IN AUTOCAD 2000 OR HIGHER
28)
yes
3.7 C.6.e.
FEMA PANEL NUMBER AND FLOODWAY/PLAIN DESIGNATED
29)
n/a
3.7C.6.f.
ELEVATION CERTIFICATES
30)
n/a
3.13 C.A
PHASING
31)
no
4.1 A.
ACCESS
32)
no
4.113.1.-3.
CONFORMANCE TO MUNICIPAL AND COUNTY PLANS
33)
yes
4.1D.
STREET(S) NAME
34)
n/a
4.1E.
LANDLOCKED PARCELS
35)
n/a
4.1F.1.-4.
NEW PRIVATE STREETS
36)
n/a
4.2 A.1.-12.
DESIGN SPECIFICATIONS (STREETS)
37)
n/a
4.2 B.L-2.
BLOCKS
38)
yes
4.2 C.1.-6.
LOT DESIGN
39)
yes
4.2 D.
EASEMENTS
40)
n/a
4.2. E.
PARKING
41)
n/a
8.1
DEVELOPMENT IN WATERSHED OF PUBLIC WATER SUPPLY
42)
n/a
8.2 A-C
WASTEWATER DISCHARGE PLAN
43)
n/a
8.3
STORMWATER DISCHARGE PLAN
44)
n/a
8.4 A-G
PERFORMANCE STANDARDSBMP'S USED
rev 5-26-16
45)
n/a
8.7 A-B
ADDITIONAL PLAT AND SITE PLAN APPLICATION REQUIREMENTS
46)
n/a
8.8
NPDES REQUIREMENTS
47)
n/a
8.9A-D
UNDISTURBED AREAS
48)
n/a
8.10A-B
CONSTRUCTION ON VERY HIGH SLOPES
49)
no
FEES PAID
Staff Comments:
1.) Provide Bill of Assurance for review.
7.) Provide state plane coordinates for two lot corners.
10.) Show distance to second section or quarter section corner and provide state plane
coordinates for both corners.
18.) Label all property corner pins.
23.) Provide Pulaski County Certificate of Final Approval.
24.) Provide Health Department approval all undeveloped lots.
27.) Provide copy of plat in autocad format.
31.) Adjust easement once right of way is dedicated for Stewart Road.
32.) Dedicate right of way as required to equal 45' (one half of a minor arterial) west from
the Stewart Road centerline. Label the Stewart Road Centerline.
49.) Pay $10.00 review fee.
Additional Staff Comments:
Adjust building line once the right of way for Stewart Road is dedicated.
Add note to plat and bill of assurance stating that rear setback for both lots is 25' minimum
and side yard setbacks to be 8' minimum.
Obtain driveway permits from Pulaski County Road and Bridge for all new driveways off
Stewart Road.
The 4.88 acre tract to the north of Lot 1 needs to be included as a Lot in this plat as it
differs from its original configuration and is less than 10 acres. The 4.88 acre tract may
also be combined with the 14.33 acre tract Mr. Barnes owns to the west and shown as a
separate tract on this plat and therefore would not need to be platted as a lot.
Pulaski County Road and Bridge requires a site distance certification for the driveway
location prior to approval of the plat. Contact Daniel Phillips at 501-340-6800 for further
information.
Staff Recommendation: Approval subject to compliance with staff requirements.
Z-1620-A Address: 3401 — 3423
Mabelvale Pike
Planning Division: This request is located in 1630 Planning District. The Land Use
Plan shows Light Industrial (LI) for these properties. The Light Industrial category
provides for light warehouse, distribution or storage uses, and/or other industrial
uses that are developed in a well -designed "park like" setting. The applicant has
applied for a rezoning from 1-2 (Light Industrial District) to Short -form PID (Planned
Industrial Development) to recognize existing multi -family.
Master Street Plan: North of the properties is W 34t" Street and it is shown as a
Local Street on the Master Street Plan. West of the properties is Mabelvale Pike
and it is shown as a Minor Arterial on the Master Street Plan. The primary function
of a Local Street is to provide access to adjacent properties. Local Streets that are
abutted by non-residential zoning/use or more intensive zoning than duplexes are
considered as "Commercial Streets". A Collector design standard is used for
Commercial Streets. A Minor Arterial provides connections to and through an
urban area and their primary function is to provide short distance travel within the
urbanized area. Entrances and exits should be limited to minimize negative effects
of traffic and pedestrians on Mabelvale Pike since it is a Minor Arterial. These
streets may require dedication of right-of-way and may require street
improvements for entrances and exits to the site.
Bicvcle Plan: A Class II Bike Lane is shown along Mabelvale Pike. Bike Lanes
provide a portion of the pavement for the sole use of bicycles.
Z-1840-D Address: 1 Huntington
Road
Planning Division: This request is located in West Little Rock Planning District.
The Land Use Plan shows Public Institution (PI) for this property. This category
includes public and quasi -public facilities that provide a variety of services to the
community such as schools, libraries, fire stations, churches, utility substations,
and hospitals. The applicant has applied for a rezoning from R4 (Two -Family
District) to Long -form PD-O (Planned Development Office) to allow for additional
parking and a parking deck to the existing site (Little Rock Athletic Club).
Master Street Plan: East of the property is Huntington Road and it is shown as a
Local Street on the Master Street Plan. The primary function of a Local Street is
to provide access to adjacent properties. Local Streets that are abutted by non-
residential zoning/use or more intensive zoning than duplexes are considered as
"Commercial Streets". A Collector design standard is used for Commercial
Streets. This street may require dedication of right-of-way and may require street
improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-2306-B Address: 600 East 21th
Street
Planning Division: This request is located in Central City Planning District. The
Land Use Plan shows Residential Low Density (RL) for this property. The
Residential Low Density (RL) category provides for single family homes at
densities not to exceed 6 units per acre. Such residential development is typically
characterized by conventional single family homes, but may include patio or
garden homes and cluster homes, provided that the density remain less than 6
units per acre. The applicant has applied for a rezoning from R-4 (Two -Family
District) to Short -form PCD (Planned Commercial Development) to allow
commercial uses in existing vacant commercial building.
Master Street Plan: Park Lane and East 21 st Street are both shown as Local
Streets on the Master Street Plan. The primary function of a Local Street is to
provide access to adjacent properties. Local Streets that are abutted by non-
residential zoning/use or more intensive zoning than duplexes are considered as
"Commercial Streets". A Collector design standard is used for Commercial
Streets. These streets may require dedication of right-of-way and may require
street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-5442-F Address: 2410 South
Battery Street
Planning Division_ This request is located in Central City Planning District. The
Land Use Plan shows Mixed Use (MX) for this property The Mixed Use category
provides for a mixture of residential, office, and commercial uses to occur. A
Planned Zoning District is required if the use is entirely office or commercial or if
the use is a mixture of the three. The applicant has applied for a Rezoning from a
PCD (Planned Commercial Development) to a Revised Short -form PCD (Planned
Commercial Development) to review the placement of a school within the existing
building.
Master Street Plan: S Summit St, W 24st and S Battery St are shown as a Local
Streets on the Master Street Plan. South of the property is W Roosevelt RD and
is shown as a Principal Arterial on the Master Street Plan. The primary function
of a Local Street is to provide access to adjacent properties. Local Streets that
are abutted by non-residential zoning/use or more intensive zoning than
duplexes are considered as "Commercial Streets". A Collector design standard is
used for Commercial Streets. The primary function of a Principal Arterial Street
is to serve through traffic and to connect major traffic generator or activity centers
within an urbanized area. Entrances and exits should be limited to minimize
negative effects of traffic and pedestrians on W Roosevelt Road since it is a
Principal Arterial. These streets may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-5574-D
Address: 2022 S Fillmore
Planning Division: This request is located in 1630 Planning District. The Land Use
Plan shows Public Institution (PI) for this property. This category includes public
and quasi -public facilities that provide a variety of services to the community such
as schools, libraries, fire stations, churches, utility substations, and hospitals. The
applicant has applied for a rezoning from R-2 (Single -Family District) to Long -form
POD (Planned Office Development) to allow a Methodist Children's Home to add
a new building with parking to this campus.
Master Street Plan: S Fillmore St and W Charles Bussey Ave are both shown as
a Local Streets on the Master Street Plan. The primary function of a Local Street
is to provide access to adjacent properties. Local Streets that are abutted by non-
residential zoning/use or more intensive zoning than duplexes are considered as
"Commercial Streets". A Collector design standard is used for Commercial
Streets. These streets may require dedication of right-of-way and may require
street improvements for entrances and exits to the site.
Bicvcle Plan: There are no bike routes shown in the immediate vicinity.
Z-6054-F
Address: 8421 Stagecoach
Road
Planning Division: This request is located in Otter Creek Planning District. The
Land Use Plan shows C (Commercial) and MOC (Mixed Office and Commercial)
for this property. The Commercial category includes a broad range of retail and
wholesale sales of products, personal and professional services, and general
business activities. Commercial activities vary in type and scale, depending on the
trade area that they serve. The Mixed Office and Commercial category provides
for a mixture of office and commercial uses to occur. Acceptable uses are office or
mixed office and commercial. A Planned Zoning District is required if the use is
mixed office and commercial. The applicant has applied for a rezoning from C-4
(Open Display District), PCD (Planned Commercial Development) and R-2 (Single -
Family Development) to PCD (Planned Commercial Development) to allow for
expansion of the existing commercial use.
Master Street Plan: North of the property is Stagecoach Road and it shown as a
Principal Arterial on the Master Street Plan. The primary function of a Principal
Arterial Street is to serve through traffic and to connect major traffic generator or
activity centers within an urbanized area. Entrances and exits should be limited
to minimize negative effects of traffic and pedestrians on Stagecoach Road since
it is a Principal Arterial. This street may require dedication of right-of-way and
may require street improvements for entrances and exits to the site.
Bicycle Plans A Class II Bike Lane is shown along Stagecoach Road. Bike Lanes
provide a portion of the pavement for the sole use of bicycles.
Z-6060-A Address: 12417 Cantrell
Road
Planning Division: This request is located in River Mountain Planning District. The
Land Use Plan shows Office (0) for this property. The office category represents
services provided directly to consumers (e.g., legal, financial, medical) as well as
general offices which support more basic economic activities. The applicant has
applied for a Rezoning from PD-O (Planned Development Office) and R-2 (Single-
family district) to Revised Short -form PD-O (Planned Development Office) to add
additional land area. The request is within the Highway 10 Design Overlay District.
Master Street Plan: North of the Property is Cantrell Road and it shown as a
Principal Arterial on the Master Street Plan. The primary function of a Principal
Arterial Street is to serve through traffic and to connect major traffic generator or
activity centers within an urbanized area. Entrances and exits should be limited
to minimize negative effects of traffic and pedestrians on Cantrell Road since it is
a Principal Arterial. This street may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: A Class I Bike Path is shown along Cantrell Road. A Bike Path is to
be a paved path physically separate for the use of bicycles. Additional right-of-way
or an easement is recommended. Nine -foot paths are recommended to allow for
pedestrian use as well (replacing the sidewalk).
Z-6318-E Address: 16105 Chenal
Parkway
Planning Division: This request is located in Ellis Mountain Planning District. The
Land Use Plan shows Commercial (C) for this property. The Commercial category
includes a broad range of retail and wholesale sales of products, personal and
professional services, and general business activities. Commercial activities vary
in type and scale, depending on the trade area that they serve. The applicant has
applied for a rezoning from PCD (Planned Commercial Development) to a revised
Long -form PCD (Planned Commercial Development) to allow the creation of an
additional lot. The request is within the Highway 10 Design Overlay District.
Master Street Plan: North of the property is Chenal Parkway and it shown as a
Principal Arterial on the Master Street Plan. West of the property is Kirk Road
and it is shown as a Collector on the Master Street Plan The primary function of a
Principal Arterial Street is to serve through traffic and to connect major traffic
generator or activity centers within an urbanized area. Entrances and exits
should be limited to minimize negative effects of traffic and pedestrians on
Chenal Parkway since it is a Principal Arterial. The primary function of a Collector
Road is to provide a connection from Local Streets to Arterials. These Streets
may require dedication of right-of-way and may require street improvements for
entrances and exits to the site. The request is within the Chenal Design Overlay
District.
Bicycle Plan: A Class I Bike Path is shown along Chenal Parkway. A Bike Path
is to be a paved path physically separate for the use of bicycles. Additional right-
of-way or an easement is recommended. Nine -foot paths are recommended to
allow for pedestrian use as well (replacing the sidewalk).
Z-6860-E Address: 5307 A Street
Planning Division: This request is located in Heights Hillcrest Planning District.
The Land Use Plan shows Office (0) for this property. The office category
represents services provided directly to consumers (e.g., legal, financial, medical)
as well as general offices which support more basic economic activities. The
applicant has applied for a rezoning from 0-3 (General Office District) to Short -
form POD (Planned Office Development) to allow a parking lot. The request is
within the Midtown Design Overlay District.
Master Street Plan: North of the property is A Street and it shown as a Local
Street on the Master Street Plan. The primary function of a Local Street is to
provide access to adjacent properties. A Collector design standard is used for
Commercial Streets. This Streets may require dedication of right-of-way and
may require street improvements for entrances and exits to the site.
Bicvcle Plan: There are no bike routes shown in the immediate vicinity.
Z-7091-A
Address: 501 Brookside
Drive
Planning Division: This request is located in West Little Rock Planning District.
The Land Use Plan shows Residential High (RH) for this property. The Residential
High category accommodates residential development of more than twelve (12)
dwelling units per acre. The applicant has applied for a rezoning from PRD
(Planned Residential Development) to Revised Short -form PD-R (Planned
Development Residential) to allow the construction of a chapel adjacent to the
existing nursing home.
Master Street Plan: North of the property is Brookside Drive and it shown as a
Local Street on the Master Street Plan. The primary function of a Local Street is
to provide access to adjacent properties. A Collector design standard is used for
Commercial Streets. This Street may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-7895-D
Address: 716 Appianway
St
Planning Division: This request is located in the 1-630 Planning District. The Land
Use Plan shows Mixed Office and Commercial (MOC). The Mixed Office and
Commercial category provides for a mixture of office and commercial uses to
occur. Acceptable uses are office or mixed office and commercial. A Planned
Zoning District is required if the use is mixed office and commercial. The applicant
has applied for a Rezoning from PCD (Planned Commercial Development) to a
Revised Short -form PCD (Planned Commercial Development) to allow outdoor
storage of materials.
Master Street Plan: East of the property is Appian Street and it shown as a Local
Street on the Master Street Plan. The primary function of a Local Street is to
provide access to adjacent properties. A Collector design standard is used for
Commercial Streets. This Street may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-8737-C
Address: 8222 Stagecoach
Road
Planning Division: This request is located in the Crystal Valley Planning District.
The Land Use Plan shows Commercial (C). The Commercial category includes a
broad range of retail and wholesale sales of products, personal and professional
services, and general business activities. Commercial activities vary in type and
scale, depending on the trade area that they serve. The applicant has applied for
a rezoning from C-3 (General Commercial Development) to Long -form PCD
(Planned Commercial Development) to allow a mini -warehouse on site.
Master Street Plan: South of the property is Stagecoach Road and it shown as a
Principal Arterial on the Master Street Plan. The primary function of a Principal
Arterial Street is to serve through traffic and to connect major traffic generator or
activity centers within an urbanized area. Entrances and exits should be limited
to minimize negative effects of traffic and pedestrians on Stagecoach Road since
it is a Principal Arterial. This street may require dedication of right-of-way and
may require street improvements for entrances and exits to the site.
Bicycle Plan: A Class II Bike Lane is shown along Stagecoach Road. Bike Lanes
provide a portion of the pavement for the sole use of bicycles.
Z-9023-B Address: 6608 Baseline
Road
Planning Division: This request is located in the Geyer Springs West Planning
District. The Land Use Plan shows Office (0). The office category represents
services provided directly to consumers (e.g., legal, financial, medical) as well as
general offices which support more basic economic activities. The applicant has
applied for a rezoning from R-2 (Single -Family District) to Short -form PD-O
(Planned Development Office) with 0-3 uses.
Master Street Plan: South of the property is Baseline Road and it shown as a
Principal Arterial on the Master Street Plan. The primary function of a Principal
Arterial Street is to serve through traffic and to connect major traffic generator or
activity centers within an urbanized area. Entrances and exits should be limited
to minimize negative effects of traffic and pedestrians Baseline Road since it is a
Principal Arterial. This Street may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: A Class II Bike Lane is shown along Baseline Road. Bike Lanes
provide a portion of the pavement for the sole use of bicycles.
Z-9103-A Address: 10115 Rodney
Parham Road
Planninq Division: This request is located in the Rodney Parham Planning District.
The Land Use Plan shows Office (0). The office category represents services
provided directly to consumers (e.g., legal, financial, medical) as well as general
offices which support more basic economic activities. The applicant has applied
for a rezoning from 0-3 (General Office District) to Short -form POD (Planned Office
Development) to add hospital as an allowable use.
Master Street Plan: South of the property is Rodney Parham Road and it shown
as a Minor Arterial on the Master Street Plan. Arterial provides connections to and
through an urban area and their primary function is to provide short distance travel
within the urbanized area. Entrances and exits should be limited to minimize
negative effects of traffic and pedestrians on Rodney Parham Road. This street
may require dedication of right-of-way and may require street improvements for
entrances and exits to the site.
Bicycle Plan: A Class II Bike Lane is shown along Rodney Parham Road. Bike
Lanes provide a portion of the pavement for the sole use of bicycles.
Z-9207 Address: 5000 Hope Lane
Planning Division: This request is located in the Ellis Mountain Planning District,
The Land Use Plan shows Residential Low Density (RL). The Residential Low
Density (RL) category provides for single family homes at densities not to exceed
6 units per acre. Such residential development is typically characterized by
conventional single family homes, but may include patio or garden homes and
cluster homes, provided that the density remain less than 6 units per acre. The
applicant has applied for a rezoning from R-2 (Single -Family District) to Short -form
PD-C (Planned Development Commercial) to allow contractor office and
equipment storage
Master Street Plan: East of the property is Hope Lane and it shown as a Local
Street on the Master Street Plan. The primary function of a Local Street is to
provide access to adjacent properties. A Collector design standard is used for
Commercial Streets. This Street may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-9208
Address:1417 Kavanaugh
Boulevard
Planning Division: This request is located in the Heights Hillcrest Planning District.
The Land Use Plan shows Residential High Density (RH). The Residential High
category accommodates residential development of more than twelve (12)
dwelling units per acre. The applicant has applied for a rezoning from R5 (Urban
Residence District) to Short -form PD-R (Planned Development Residential) to
allow rebuilding of a 4-plex. The request is within Hillcrest Overlay District.
Master Street Plan: North of the property is Kavanaugh Blvd and it shown as a
Collector on the Master Street Plan. The primary function of a Collector Road is to
provide a connection from Local Streets to Arterials. This Street may require
dedication of right-of-way and may require street improvements for entrances and
exits to the site.
Bicycle Plan: There is a Class III Bike Route shown on Kavanaugh Blvd. These
bike routes require no additional right-of-way, but either a sign or pavement
marking to identify and direct the route.
Z-9209 Address: 6011 Young
Road
Planning Division: This request is located in the 65t" East Planning District. The
Land Use Plan shows Industrial (1). The industrial category encompasses a wide
variety of manufacturing, warehousing research and development, processing,
and industry related office and service activities. Industrial development typically
occurs on an individual tract basis rather than according to an overall development
plan. The applicant has applied for a rezoning from 1-2 (light Industrial District.) to
Short -form PID (Planned Industrial Development) to add an outdoor soccer field
as an allowable use.
Master Street Plan: North of the property is Young Road and it shown as a
Collector on the Master Street Plan. South of the property is Frontage Road to
Interstate 30 and it is a Freeway on the Master Street Plan. The primary function
of a Collector Road is to provide a connection from Local Streets to Arterials. The
primary function of a Freeway is to serve through long distance trips. Freeways
are always designed as full access control roads (no direct access) Entrances and
exits should be limited to minimize negative effects of traffic and pedestrians on I-
30 since it is a Freeway This Street may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-9210 Address: SWC C and
Walnut Streets — 324
Walnut Street
Planning Division: This request is located in the Heights Hillcrest Planning District.
The Land Use Plan shows Residential Low Density (RL) for this property. The
Residential Low Density is for single-family homes at densities no greater than six
dwelling units per acre. The applicant has applied for a rezoning from R-3 (Single
Family District) to Short -form PD-R (Planned Development Residential) to allow
the creation of a second lot for a new single-family home.
Master Street Plan: Walnut Street and C Street are both shown as Local Streets
on the Master Street Plan. The primary function of a Local Street is to provide
access to adjacent properties. A Collector design standard is used for Commercial
Streets. These Streets may require dedication of right-of-way and may require
street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Z-9211
Address: West side of
Chenal Parkway
approximately % mile south
of Northfield Drive
Planning Division: This request is located in the Chenal Planning District. The
Land Use Plan shows Residential Low Density (RL) for this property. The
Residential Low Density is for single-family homes at densities no greater than six
dwelling units per acre. The applicant has applied for a rezoning from R-2 (Single -
Family District) to long form PD-R (Planned Development Residential) to allow age
restricted multi -family residential. The request is in within the Chenal Overlay
district.
Master Street Plan: West of the property is Chenal Parkway and it shown as a
Collector on the Master Street Plan. The primary function of a Principal Arterial
Street is to serve through traffic and to connect major traffic generator or activity
centers within an urbanized area. Entrances and exits should be limited to
minimize negative effects of traffic and pedestrians Chenal Parkway since it is a
Principal Arterial. This Street may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: A Class I Bike Path is shown along Chenal Parkway. A Bike Path
is to be a paved path physically separate for the use of bicycles. Additional right-
of-way or an easement is recommended. Nine -foot paths are recommended to
allow for pedestrian use as well (replacing the sidewalk).
Entergy Arkansas Inc.
#9 Entergy Court
Little Rock. AR 72211
March 30, 2017
City of Little Rock
Department of Planning and Development
ATTN: Ms. Donna James, AICP
723 West Markham Street
Little Rock, AR 72201-1334
RE: Entergy comments related to Planning and Zoning items for the April 271 Meeting
Ms. James,
Please find below Entergy's comments related to the items received from the Department of Planning and
Development last week. The request letter said to have the comments back to you by April 5", 2017.
■ Chenal Market —16105 Chenal Parkway: Z-6318-E
Entergy does not object to this proposal. Service is already being provided to this structure. Contact
Entergy in advance to discuss any changes to electrical service requirements, or adjustments to existing
facilities (if any) as this proposal proceeds.
+ David Storage Development — 8222 Stagecoach Rd: Z-89737-C
Entergy does not object to this proposal. An overhead power line exists on the east side of this property.
The main power line runs along Stagecoach Road. Caution should be used in the siting and construction
of the easternmost building as it may be very near to an overhead power line. Please ensure that proper
NESC and OSHA required clearances are maintained. Contact Entergy in advance to discuss future
service requirements, new facilities locations and adjustments to existing facilities (if any) as this project
proceeds.
■ Fits Auto Expansion — 8421 Stagecoach Rd: Z-6054-C
Entergy does not object to this proposal. There do not appear to be any conflicts with existing electrical
utilities based on the information provided. Contact Entergy in advance to discuss electrical service
requirements, or adjustments to existing facilities (if any) as this proposal proceeds.
■ Quick's Lake Place Prelim Plat — Stewart Rd and Simpson Ln: 5-1787
Entergy does not object to this proposal. An overhead three-phase power line exists along the south side
of Stewart Road at this location. There do not appear to be any conflicts with existing Entergy facilities.
Contact Entergy in advance to discuss future service requirements, new facilities locations and
adjustments to existing facilities (if any) as this project proceeds.
0 Lawson West Short -form — 5000 Hope Lane: Z-9207
Entergy does not object to this proposal. An overhead power line exists on the east side of this property.
The main power line runs along Lawson Road. Contact Entergy in advance to discuss any changes in
future service requirements, new facilities locations and adjustments to existing facilities (if any) as this
project proceeds.
■ Graham Property Management —1417 Kavanaugh Blvd: Z-9208
Entergy does not object to this proposal. Service is already being provided to this property from the alley
in the rear. Contact Entergy in advance to discuss any changes to electrical service requirements, or
adjustments to existing facilities (if any) as this proposal proceeds.
o Hawkins Short -form — 600 East 21" St: Z-2306-B
Entergy does not object to this proposal. Service is already being provided to this property from the west
side of Park Street. Contact Entergy in advance to discuss any changes to electrical service requirements,
or adjustments to existing facilities (if any) as this proposal proceeds..
Lawson Short -form — SWC C and Walnut Sts.: Z-9210
Entergy does not object to this proposal. However, an overhead power line runs in the alley on the west
side of the property, and an overhead service line runs from a pole at the entrance to the alley on C Street
to the existing home on the corner of Walnut and C Streets. Both of these existing lines may present a
conflict with the construction of the new residence. Caution should be exercised so that all OSHA and
NESC clearances to power lines are maintained during and after construction. Relocation costs may be
incurred for any adjustments to the existing power lines. Contact Entergy in advance to discuss any
changes to electrical service requirements, or adjustments to existing facilities (if any) for this proposal.
■ Arkansas Indoor Soccer — 6611 Young Rd: Z-9209
Entergy does not object to this proposal. An existing three phase, power line exists along east side of this
property, but does not appear to be in conflict with the proposed plans. Contact Entergy in advance to
discuss future service requirements, new facilities locations and adjustments to existing facilities (if any)
as this project proceeds.
■ Presbyterian Village — 510 Brookside Dr.: Z-7091-A
Entergy does not object to this proposal. Service is already being provided to this property from the rear
of the property on the west side of the existing development. Contact Entergy in advance to discuss any
changes to electrical service requirements, or adjustments to existing facilities (if any) as this proposal
proceeds.
6608 Baseline Rd. Short -form — 6608 Baseline Rd: Z-9023-B
Entergy does not object to this proposal. An existing three phase, power line exists on the north side of
Baseline Road at this location, but does not appear to be in conflict with the proposed plans. Caution
should be used when construction a drive underneath the existing power line to ensure that all proper
clearances are maintained. Contact Entergy in advance to discuss future service requirements, new
facilities locations and adjustments to existing facilities (if any) as this project proceeds.
• Wellington Creek Subdiv Prelim Plat — SEC Chenal Pkwy & Wellington Hills Rd: S-1788
Entergy does not object to this proposal. An existing single phase, power line exists on the east side of
Wellington Hills at the south end of this location, and a 3 phase power line exists along the north property
line on Chenal Parkway. Neither appears to be in conflict with the proposed plans. Caution should be
used when constructing a drive underneath the existing power line to ensure that all proper clearances are
maintained. Contact Entergy in advance to discuss future service requirements, new facilities locations
and adjustments to existing facilities (if any) as this project proceeds.
Kum & Go Convenience Store Subdiv Site Plan —15617 Chenal Pkwy.: S-1788-A
Entergy does not object to this proposal. A three phase power line exists along the north property line on
Chenal Parkway. It does not appear to be in conflict with the proposed plans. Caution should be used
when constructing a drive underneath the existing power line to ensure that all proper clearances are
maintained. Contact Entergy in advance to discuss future service requirements, new facilities locations
and adjustments to existing facilities (if any) as this project proceeds.
The Crest at Chenal — W side of Chenal Pkwy approx. 1/4 mile S of Northfield Dr: Z-9211
Entergy does not object to this proposal. An existing single phase, underground power line exists on the
northwest of this development, and a 3 phase overhead power line exists across Chenal Parkway and east
of the development. Neither appears to be in conflict with the proposed plans. Contact Entergy well in
advance to discuss future service requirements, new facilities locations and adjustments to existing
facilities (if any) as this project proceeds.
• Markham Harrison Properties — 5307 A St.: Z-6860-E
Entergy does not object to this proposal. An existing Overhead power line exists in the alley to the south
of this property. It does not appear to be in conflict with the proposed development. Contact Entergy in
advance to discuss future service requirements, new facilities locations and adjustments to existing
facilities (if any) as this project proceeds.
• Lot Z-2A-R Little Rock Industrial District — 2400 W 65" St: S-1026-B
Entergy Distribution does not object to this re -plat proposal. A three phase power line exists along the
northern edge of the 100 foot AP&L easement depicted on the submitted drawing. This power line can be
utilized to provide power to any future development on this proprty. However, the re -plat also involves
an existing Entergy Transmission power line and easement. Should the property develop, then contact
Entergy Transmission well in advance to discuss the future use of its easements and contact Entergy
Distribution in advance to discuss future service requirements, new Distribution facilities locations and
adjustments to existing Distribution facilities (if any) as this project proceeds..
s J&R Properties Revised Short -form — 716 Appianway: Z-7895-D
Entergy does not object to this proposal. Service is already being provided to the structure at this address
and the proposed use of the land does not appear to conflict with any existing electrical facilities
(Distribution or Transmission). Contact Entergy in advance to discuss any changes to these plans,
electrical service requirements, or adjustments to existing facilities (if any) as this proposal proceeds.
Steve Landers Kia Dealership Subdiv Site Plan — Col Glenn Plaza Loop: S-1240-0
Entergy does not object to this proposal. An underground three phase power line exists to the east of this
property serving existing customers. This line can likely be used for this proposed project. There do not
appear to be any conflicts with existing Entergy facilities. Contact Entergy in advance to discuss future
service requirements, new facilities locations and adjustments to existing facilities (if any) as this project
proceeds.
James Mitchell School Revised Short -form — 2410 S Battery St: Z-5442-F
Entergy does not object to this proposal. Three phase electrical service is already being provided to the
structure. Power lines (overhead) currently exist on the north and west sides of this property. They do
not appear to be in conflict with the proposed use of the existing building. Contact Entergy in advance to
discuss any changes to electrical service requirements, or adjustments to existing facilities (if any) as this
project proceeds.
Little Rock Racket Club Long -form —1 Huntington Rd: Z-1840-D
Entergy does not object to this proposal. There do not appear to be any overhead, primary voltage
electrical facilities in conflict with the proposal to add parking at this location. However, there appear to
be some secondary voltage wires and poles supplying private area lighting which are in conflict. These
are usually fairly easy to adjust. Contact Entergy in advance to discuss future service requirements, new
facilities locations and adjustments to existing facilities (if any) as this property is developed.
■ B&G Properties Short -form — 3401-3423 Mabelvale Pike: Z-1620-A
Entergy does not object to this proposal. Electrical service is already being provided to structures on this
property. Contact Entergy in advance to discuss any changes to electrical service requirements, or
adjustments to existing facilities (if any) for this proposal.
• The United Methodist Children's Home Campus — 2022 S Fillmore: Z-5574-D
Entergy does not object to this proposal. There do not appear to be any conflicts with existing power
lines in the area. Single phase power lines exist on the east and west sides of the property. Contact
Entergy in advance to discuss future service requirements, new facilities locations and adjustments to
existing facilities (if any) as this property is developed.
• Small Emergency Hospital Short -form —10115 Rodney Parham: Z-9103-A
Entergy does not object to this proposal. An existing three phase, power line exists along west side of this
property and along the north side of Rodney Parham Road at this location. Neither of these appear to be
in conflict with the proposed development. Contact Entergy in advance to discuss future service
requirements, new facilities locations and adjustments to existing facilities (if any) as this project
proceeds.
• Dash Heating and Cooling Revised Short -form —12417 Cantrell Rd.: Z-6060-A
Entergy does not object to this proposal. A three phase, overhead power line exists along the west side of
this property but does not appear to be in conflicts with the addition of the land area. Contact Entergy in
advance to discuss future service requirements, new facilities locations and adjustments to existing
facilities (if any) as this project proceeds.
If you need further assistance you may call me at 501-954-5158 or e-mail me at bneumei@entergy.com.
Sincerely,
Bernard Neumeier
Region Engineering Supervisor
Entergy Arkansas, Inc.
To: Donna James
From: Captain Tony Rhodes / Captain John Hogue: Fire Marshal
Comment for the following Locations:
Z-6318-E 16105 Chenal Parkwa
Fire Hydrants.
Date: March 29, 2017
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Commercial and Industrial Developments —2 means of access. -Maintain fire apparatus access roads
as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1
Section D104.1 Buildings exceeding three stories or 30 feet in height. Building or facilities exceeding 30
feet or three stories in height shall have at least two means of fire apparatus access for each structure.
Section D104.2 Building exceeding 62,000 square feet in area. Buildings or facilities having a gross
building area of more than 62,000 square feet shall be provide with two separate and approved fire
apparatus access roads.
Exception: Projects having a gross building area of up to 124,000 square feet that have a single
approved fire apparatus access road when all building are equipped throughout with approved
automatic sprinkler systems.
D104.3 Remoteness. Where two fire apparatus access roads are required, they shall be placed a
distance apart equal to not less than one half of the length of the maximum overall diagonal dimension
of the lot or area to be served, measured in a straight line between accesses.
30' Tall Buildings - Maintain aerial fire apparatus access roads as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D105.1— D105.4
D105.1 Where Required. Where the vertical distance between the grade plane and the highest
roof surface exceed 30', approved aerial fire apparatus access roads shall be provided. For the purposes
of this section the highest roof surfaces shall be determined by measurement to the eave of a pitched
roof, the intersection of a roof to the exterior wall, or the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed with of
26', exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes meeting this condition
shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and shall be
positioned parallel to one entire side of the building. The side of the building on which the aerial fire
apparatus access road is positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over the aerial fire
apparatus access road or between the aerial fire apparatus road and the building. Other obstructions
shall be permitted to be places with the approval of the fire code official.
Dead Ends.
Maintain fire apparatus access roads at dead end locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.4 Dead Ends. Dead-end fire apparatus access roads in excess
of 150 feet shall be provided with width and turnaround provisions in accordance with Table D103.4.
Requirements for Dead-end fire apparatus access roads.
Gates
Maintain fire apparatus access road gates as per Appendix D of the 2012 Arkansas Fire Prevention
Code Vol. 1 Section D103.5 Fire apparatus access road gates. Gates securing the fire apparatus access
roads shall comply with all of the following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by one person.
4. Gate components shall be maintained in an operable condition at all times and replaces or
repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire department personnel
for emergency access. Emergency opening devices shall be approved by the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and padlock unless they are
capable of being opened by means of forcible entry tools or when a key box containing the keys
to the lock is installed at the gate location.
7. Locking device specifications shall be submitted for approval \by the fire code official
8. Electric gate operators, where provided, shall be listed in accordance with UL 325.
9. Gates, intended for automatic operation shall be designed, constructed and installed to comply
with requirements of ASTM F 2200.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
Z-89737-C 8222 5taizecoach Road
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loadin
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Commercial and industrial Developments — 2 means of access. - Maintain fire apparatus access roads
as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1
Section D104.1 Buildings exceeding three stories or 30 feet in height. Building or facilities exceeding 30
feet or three stories in height shall have at least two means of fire apparatus access for each structure.
Section D104.2 Building exceeding 62,000 square feet in area. Buildings or facilities having a gross
building area of more than 62,000 square feet shall be provide with two separate and approved fire
apparatus access roads.
Exception: Projects having a gross building area of up to 124,000 square feet that have a single
approved fire apparatus access road when all building are equipped throughout with approved
automatic sprinkler systems.
D104.3 Remoteness. Where two fire apparatus access roads are required, they shall be placed a
distance apart equal to not less than one half of the length of the maximum overall diagonal dimension
of the lot or area to be served, measured in a straight line between accesses.
30' Tall Buildings - Maintain aerial fire apparatus access roads as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D105.1— D105.4
D105.1 Where Required. Where the vertical distance between the grade plane and the highest
roof surface exceed 30', approved aerial fire apparatus access roads shall be provided. For the purposes
of this section the highest roof surfaces shall be determined by measurement to the eave of a pitched
roof, the intersection of a roof to the exterior wall, or the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed with of
26', exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes meeting this condition
shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and shall be
positioned parallel to one entire side of the building. The side of the building on which the aerial fire
apparatus access road is positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over the aerial fire
apparatus access road or between the aerial fire apparatus road and the building. Other obstructions
shall be permitted to be places with the approval of the fire code official.
Gates
Maintain fire apparatus access road gates as per Appendix D of the 2012 Arkansas Fire Prevention
Code Vol. 1 Section D103.5 Fire apparatus access road gates. Gates securing the fire apparatus access
roads shall comply with all of the following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by one person.
4. Gate components shall be maintained in an operable condition at all times and replaces or
repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire department personnel
for emergency access. Emergency opening devices shall be approved by the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and padlock unless they are
capable of being opened by means of forcible entry tools or when a key box containing the keys
to the lock is installed at the gate location.
7. Locking device specifications shall be submitted for approval \by the fire code official
8. Electric gate operators, where provided, shall be listed in accordance with UL 325.
9. Gates, intended for automatic operation shall be designed, constructed and installed to comply
with requirements of ASTM F 2200.
Dead Ends.
Maintain fire apparatus access roads at dead end locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.4 Dead Ends. Dead-end fire apparatus access roads in excess
of 150 feet shall be provided with width and turnaround provisions in accordance with Table D103.4.
Requirements for Dead-end fire apparatus access roads.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
Z-6054-C 8421 Stagecoach Road
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Commercial and Industrial Developments — 2 means of access. - Maintain fire apparatus access roads
as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1
Section D104.1 Buildings exceeding three stories or 30 feet in height. Building or facilities exceeding 30
feet or three stories in height shall have at least two means of fire apparatus access for each structure.
Section D104.2 Building exceeding 62,000 square feet in area. Buildings or facilities having a gross
building area of more than 62,000 square feet shall be provide with two separate and approved fire
apparatus access roads.
Exception: Projects having a gross building area of up to 124,000 square feet that have a single
approved fire apparatus access road when all building are equipped throughout with approved
automatic sprinkler systems.
D104.3 Remoteness. Where two fire apparatus access roads are required, they shall be placed a
distance apart equal to not less than one half of the length of the maximum overall diagonal dimension
of the lot or area to be served, measured in a straight line between accesses.
30' Tall Buildings -Maintain aerial fire apparatus access roads as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D105.1— D105.4
D105.1 Where Required. Where the vertical distance between the grade plane and the highest
roof surface exceed 30', approved aerial fire apparatus access roads shall be provided. For the purposes
of this section the highest roof surfaces shall be determined by measurement to the eave of a pitched
roof, the intersection of a roof to the exterior wall, or the top of the parapet wails, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed with of
26', exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes meeting this condition
shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and shall be
positioned parallel to one entire side of the building. The side of the building on which the aerial fire
apparatus access road is positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over the aerial fire
apparatus access road or between the aerial fire apparatus road and the building. Other obstructions
shall be permitted to be places with the approval of the fire code official.
Dead Ends.
Maintain fire apparatus access roads at dead end locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.4 Dead Ends. Dead-end fire apparatus access roads in excess
of 150 feet shall be provided with width and turnaround provisions in accordance with Table D103.4.
Requirements for Dead-end fire apparatus access roads.
Gates
Maintain fire apparatus access road gates as per Appendix D of the 2012 Arkansas Fire Prevention
Code Vol. 1 Section D103.5 Fire apparatus access road gates. Gates securing the fire apparatus access
roads shall comply with all of the following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by one person.
4. Gate components shall be maintained in an operable condition at all times and replaces or
repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire department personnel
for emergency access. Emergency opening devices shall be approved by the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and padlock unless they are
capable of being opened by means of forcible entry tools or when a key box containing the keys
to the lock is installed at the gate location.
7. Locking device specifications shall be submitted for approval \by the fire code official
8. Electric gate operators, where provided, shall be listed in accordance with UL 325.
9. Gates, intended for automatic operation shall be designed, constructed and installed to comply
with requirements of ASTM F 2200.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
5-1787 Stewart Road and Simpson Lane
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
Z-9207 5000 Hope Lane
No Comment
Z-9208
Full Plans review
Z-2306-B 600 East 215t Street
No Comment
Z-9198 5801 Baseline
No Comment
Z-9210 324 Walnut Street
No Comment
Z-9209 6611 Young Road
No Comment
Z-7091-A 510 Brookside Drive
Full plan review
Z-9023-B 6608 Baseline Road
Full plans review
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Lam
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Fire HWdrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
S-1788 SEC Chenal Parkway and Wellington Hills Road
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Commercial and Industrial Develo ments— 2 means of access. - Maintain fire apparatus access roads
as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1
Section D104.1 Buildings exceeding three stories or 30 feet in height. Building or facilities exceeding 30
feet or three stories in height shall have at least two means of fire apparatus access for each structure.
Section D104.2 Building exceeding 62,000 square feet in area. Buildings or facilities having a gross
building area of more than 62,000 square feet shall be provide with two separate and approved fire
apparatus access roads.
Exception: Projects having a gross building area of up to 124,000 square feet that have a single
approved fire apparatus access road when all building are equipped throughout with approved
automatic sprinkler systems.
D104.3 Remoteness. Where two fire apparatus access roads are required, they shall be placed a
distance apart equal to not less than one half of the length of the maximum overall diagonal dimension
of the lot or area to be served, measured in a straight line between accesses.
30' Tali Buildings - Maintain aerial fire apparatus access roads as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D105.1— D105.4
D105.1 Where Required. Where the vertical distance between the grade plane and the highest
roof surface exceed 30', approved aerial fire apparatus access roads shall be provided. For the purposes
of this section the highest roof surfaces shall be determined by measurement to the eave of a pitched
roof, the intersection of a roof to the exterior wall, or the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed with of
26', exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes meeting this condition
shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and shall be
positioned parallel to one entire side of the building. The side of the building on which the aerial fire
apparatus access road is positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over the aerial fire
apparatus access road or between the aerial fire apparatus road and the building. Other obstructions
shall be permitted to be places with the approval of the fire code official.
Dead Ends.
Maintain fire apparatus access roads at dead end locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.4 Dead Ends. Dead-end fire apparatus access roads in excess
of 150 feet shall be provided with width and turnaround provisions in accordance with Table D103.4.
Requirements for Dead-end fire apparatus access roads.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
5-1788-A 15617 Chenal Parkwa
Full plans review
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
Z-9211 West side of Chenal Parkwa
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
30' Tall Buildings - Maintain aerial fire apparatus access roads as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D105.1— D105.4
D105.1 Where Required. Where the vertical distance between the grade plane and the highest
roof surface exceed 30', approved aerial fire apparatus access roads shall be provided. For the purposes
of this section the highest roof surfaces shall be determined by measurement to the eave of a pitched
roof, the intersection of a roof to the exterior wall, or the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed with of
26', exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes meeting this condition
shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and shall be
positioned parallel to one entire side of the building. The side of the building on which the aerial fire
apparatus access road is positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over the aerial fire
apparatus access road or between the aerial fire apparatus road and the building. Other obstructions
shall be permitted to be places with the approval of the fire code official.
Dead Ends.
Maintain fire apparatus access roads at dead end locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.4 Dead Ends. Dead-end fire apparatus access roads in excess
of 150 feet shall be provided with width and turnaround provisions in accordance with Table D103.4.
Requirements for Dead-end fire apparatus access roads.
Gates
Maintain fire apparatus access road gates as per Appendix D of the 2012 Arkansas Fire Prevention
Code Vol. 1 Section D103.5 Fire apparatus access road gates. Gates securing the fire apparatus access
roads shall comply with all of the following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by one person.
4. Gate components shall be maintained in an operable condition at all times and replaces or
repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire department personnel
for emergency access. Emergency opening devices shall be approved by the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and padlock unless they are
capable of being opened by means of forcible entry tools or when a key box containing the keys
to the lock is installed at the gate location.
7. Locking device specifications shall be submitted for approval \by the fire code official
8. Electric gate operators, where provided, shall be listed in accordance with UL 325.
Gates, intended for automatic operation shall be designed, constructed and installed to comply
with requirements of ASTM F 2200.
Multi-Familv Residential Developments
As per Appendix D, Section D106.1 of the 2012 Arkansas Fire Prevention Code Vol. 1. Projects having
more than 100 dwelling units. Multiple -family residential projects having more than 100 dwelling units
shall be equipped throughout with two separate and approved fire apparatus access roads.
Exception: Projects having up to 200 dwelling units may have a single approved fire apparatus
access road when all building, including nonresidential occupancies are equipped throughout with
approved automatic sprinkler systems installed in accordance with Section 903.3.1.1 or 903.3.1.2
As per Appendix D, Section D106.2 of the 2012 Arkansas Fire prevention Code Vol. 1. Projects having
more than 200 dwelling units. Multiple -family residential projects having more than 200 dwelling units
shall be provided with two separate and approved fire apparatus access roads regardless of whether
they are equipped with an approved automatic sprinkler system.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
Z-6860-E 5307 A Street
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
S-1026-B 2400 West 65t" Street
No Comment
Z-7895-D 716 Appianway
No Comment
S-1240-0 Colonel Glenn Plaza Loo
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D,of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Commercial and Industrial Developments — 2 means of access. - Maintain fire apparatus access roads
as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1
Section D104.1 Buildings exceeding three stories or 30 feet in height. Building or facilities exceeding 30
feet or three stories in height shall have at least two means of fire apparatus access for each structure.
Section D104.2 Building exceeding 62,000 square feet in area. Buildings or facilities having a gross
building area of more than 62,000 square feet shall be provide with two separate and approved fire
apparatus access roads.
Exception: Projects having a gross building area of up to 124,000 square feet that have a single
approved fire apparatus access road when all building are equipped throughout with approved
automatic sprinkler systems.
D104.3 Remoteness. Where two fire apparatus access roads are required, they shall be placed a
distance apart equal to not less than one half of the length of the maximum overall diagonal dimension
of the lot or area to be served, measured in a straight line between accesses.
30' Tall Buildings - Maintain aerial fire apparatus access roads as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D105.1— D105.4
D105.1 Where Required. Where the vertical distance between the grade plane and the highest
roof surface exceed 30', approved aerial fire apparatus access roads shall be provided. For the purposes
of this section the highest roof surfaces shall be determined by measurement to the eave of a pitched
roof, the intersection of a roof to the exterior wall, or the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed with of
26', exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes meeting this condition
shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and shall be
positioned parallel to one entire side of the building. The side of the building on which the aerial fire
apparatus access road is positioned shall be approved by the fire code official.
13105.4 Obstructions. Overhead utility and power lines shall not be located over the aerial fire
apparatus access road or between the aerial fire apparatus road and the building. Other obstructions
shall be permitted to be places with the approval of the fire code official.
Dead Ends.
Maintain fire apparatus access roads at dead end locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.4 Dead Ends. Dead-end fire apparatus access roads in excess
of 150 feet shall be provided with width and turnaround provisions in accordance with Table D103.4.
Requirements for Dead-end fire apparatus access roads.
Maintain fire apparatus access road gates as per Appendix D of the 2012 Arkansas Fire Prevention
Code Vol. 1 Section D103.5 Fire apparatus access road gates. Gates securing the fire apparatus access
roads shall comply with all of the following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by one person.
4. Gate components shall be maintained in an operable condition at all times and replaces or
repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire department personnel
for emergency access. Emergency opening devices shall be approved by the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and padlock unless they are
capable of being opened by means of forcible entry tools or when a key box containing the keys
to the lock is installed at the gate location.
7. Locking device specifications shall be submitted for approval \by the fire code official
8. Electric gate operators, where provided, shall be listed in accordance with UL 325.
Gates, intended for automatic operation shall be designed, constructed and installed to comply
with requirements of ASTM F 2200.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
Z-5442-F 2410 South Battery Street
Full Plans Review
Z-1840-D 1 Huntington Road
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.1 Access road width with a hydrant. Where a fire hydrant is
located on a fire apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention Code Vol.
1 Section D103.2 Grade. Fire apparatus access roads shall not exceed 10 percent in grade except as
approved by the fire chief.
Loa_ dingy
Maintain fire apparatus access road design as per Appendix D of the 2012 Arkansas Fire Prevention Code
Vol. 1 Section D102.1 Access and loading. Facilities, buildings or portions of buildings hereafter
constructed shall be accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable of supporting the
imposed load of fire apparatus weighing at least 75,000 pounds.
Dead Ends.
Maintain fire apparatus access roads at dead end locations as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.4 Dead Ends. Dead-end fire apparatus access roads in excess
of 150 feet shall be provided with width and turnaround provisions in accordance with Table D103.4.
Requirements for Dead-end fire apparatus access roads.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire Prevention Code. Section C101—
C105, in conjunction with Central Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire
Marshals Office (Capt. Tony Rhodes 501-918-3757 or Capt. John Hogue 501-918-3754). Number and
Distribution of Fire Hydrants as per Table C105.1.
Z-1620-A 3401-3423 Mabelvale Pike
Full Plans Review
Z-5574-D 2022 South Fillmore
Full Plans Review
Z-9103-A 10115 Rednev Parham Road
Full Plans Review
Z-6060-A 12417 Cantrell Road
No Comment
Regards, Captain Rhodes and Captain Hogue
Office: 918-3710
Little Rock Wastewater Comments
Project Number 5-1026-B
Project Name Project Type
Lot Z-2 A-R LR Industrial Replat Revise Bldg lines
District Replat
Project Number 5-1240-0
Project Name Project Type
Steve Landers Kia Subdivision Site Plan Review
Project Number S-1787
Project Name
Project Type
Quick's Lake Place
Preliminary Plat
Project Number 5-1788
Project name
Project Type
Wellington Creek
Preliminary Plat - Comm'I Subdiv.
Subdivision
Project Number 5-1788-A
Project Name
Project Type
Kum and Go Convenience
Subdivision Multiple Bldg Site Plan
Store
Project Number Z-1620-A
Project Name
Project Type
B&G Properties
Planned Development: Industrial
Project Number Z-1840-D
Project Name
Project Type
Little Rock Racquet Club
Planned Development: Office
Project Number Z-2306-B
Project Name
Hawkins PCD
Comment Made
Sewer Available to this site.
Comment Made
Sewer Available to this site. Existing easements must
be retained. EAD Approval Required for oil separator
Comment Made
Outside Service Boundary- No Comment.
Comment Made
Sewer main extension required with easements if new
sewer service is required for this project (for Lot 1).
Comment Made
Sewer main extension required with easements if new
sewer service is required for this project (for Lot
1).rbmoreland@sbcglobal.net
Comment Made
Sewer Available to this site.
Comment Made
Sewer Available to this site.
Project Type Comment Made
Planned Development: Commercial Sewer Available to this site.
Thursday, March 30, 2017 Page 1 of 3
Project Number Z-5442-F
Project Name
Project Type
Comment Made
James Mitchell School
Planned Development: Commercial
Sewer Available to this site.
EAD approval required if
food prep on site.
Project Number Z-5574-D
Project Name
Project Type
Comment Made
United Methodist Church
Planned Development: Office
Sewer Available to this site.
Existing easements must
Childrens Home
be retained.
Project Number Z-6054-C
Project Name
Project Type
Comment Made
Fitts Auto Expansion
Planned Development: Commercial
Sewer Available to this site.
Existing easements must
be retained.
Project Number Z-6060-A
Project Name
Project Type
Comment Made
Dash Heating and Cooling
Planned Development: Office
Sewer Available to this site.
Existing easements must
be retained.
Project Number Z-6318-E
Project Name
Project Type
Comment Made
Chenal Market Revised
Planned Development: Commercial
Sewer Available to this site.
Existing easements must
be retained.
Project Number Z-6860-E
Project Name
Project Type
Comment Made
Markham Harrison
Planned Development: Office
Sewer Available to this site.
Properties parking lot
Project [Number Z-7091-A
Project Name
Project Type
Comment Made
Presbyterian Village Chapel
Planned Development: Residential
Sewer Available to this site.
Project Number Z-7895-D
Project Name
Project Type
Comment Made
J&R Properties PCD
Planned Development: Commercial
Sewer Available to this site.
Project Number Z-89737-C
Project Name
Project Type
Comment Made
Davis Storage Development
Planned Development: Commercial
Sewer Available to this site.
Thursday, March 30, 2017
Page 2 of 3
Project Number Z-9023-A
Project Name Project Type
6608 Baseline Road PD-0 Planned Development: Office
Project Number Z-9103 A
Project Name Project Type
Small Emergency Hospital Planned Development: Office
Project Number Z-9207
Project Dame
Lawson West
Project Number Z-9208
Project Name
Grahams Property
Management
Project Number Z-9209
Project Name
Arkansas Indoor Soccer
Project Number Z-9210
Project dame
Lawson PD-R
Project Number Z-9211.
Project Name
The Crest at Chenai
Comment Made
Sewer main extension required with easements if new
sewer service is required for this project.
Comment Made
Sewer Available to this site. Existing easements must
be retained. EAD Analysis required
Project Type Comment bade
Planned Development: Commercial Outside Service Boundary - No Comment.
Project Type Comment Made
Planned Development: Residential Sewer Available to this site. Existing easements must
be retained.
Project Type Comment Made
Planned Development: Industrial Sewer Available to this site.
Project Type Comment Made
Planned Development: Residential Sewer main extension required with easements if new
sewer service is required for this project.
Project Type Comment Made
Planned Development: Residential Sewer main extension required with easements if new
sewer service is required for this project. Capacity Fee
Analysis required. EAD Approval required if food prep
on site.
Thursday, March 30, 2017 Page 3 of 3
City of Little Rock
Planning and Development
Filing Fees
Date 12j,-,) , 20_L]
Annexation
Board of Adjustment
Cond Use Permit/T UP
Final Plat
Planned Unit Dev
Preliminaiy Plat
Special Use Permit
Rezoning
Site Plans
Street Name Change
Street Name Signs
Number at ea
Public Hearing Signs
Number .-at 6 2 ea
Total
File No