HomeMy WebLinkAboutS-0157-D Staff AnalysisJanuary 22, 1985
SUBDIVISIONS
Item No. 4
NAME:
Hooper Bond Addition
Revised Preliminary Plat
LOCATION: Northwest Corner of Markham
at Shackleford Road
DEVELOPER: ENGINEER:
Hooper Bond Fund 3 Mehlburger, Tanner & Associates
University Tower Bldg. 201 South Izard
Penthouse Little Rock, AR 72204
12th and University
Little Rock, AR 72204
AREA: 11.6 acres NO. OF LOTS: 7 FT. NEW STREET: 950
ZONING: "C-3"
PROPOSED USES: Commercial Offices
STAFF REPORT:
This is a proposal by the applicant to revise an approved
preliminary by changing the location of Shackleford Drive to
make it a through street. The reason submitted is to
facilitate the sale of the property.
The City Engineer has requested that an in -lieu
contribution for street improvements on West Markham be
required upon the final plat of the first of Lots 3-7; and
that an internal drainage plan to include detention
considerations be submitted. Engineering reports that plans
for this extension have been approved.
STAFF RECOMMENDATION:
Approval, subject to comments made.
SUBDIVISION COMMITEE REVIEW:
The applicant was present. The Committee reviewed the
application and passed it to the Commission.
Water Works - Require a 10' easement north of and parallel
to the existing 20" water main, a drainage ditch north of
the easement to handle the north -south runoff and a
reinforced concrete slab to protect the existing 39" water
main.
January 22, 1985
SUBDIVISIONS
Item No. 4 - Continued
PLANNING COMMISSION ACTION:
The applicant was present. There were no objectors. A
motion for approval was made and passed by a vote of:
11 ayes, 0 noes and 0 absent.
January 22, 1985
SUBDIVISIONS
Item No. 4
NAME:
LOCATION:
DEVELOPER:
Hooper Bond Addition
Revised Preliminary Plat
Northwest Corner of Markham
at Shackleford Road
ENGINEER:
Hooper Bond Fund 3 Mehlburger, Tanner & Associates
University Tower Bldg. 201 South Izard
Penthouse Little Rock, AR 72204
12th and University
Little Rock, AR 72204
AREA: 11.6 acres NO. OF LOTS: 7 FT. NEW STREET: 950
ZONING: "C-3"
PROPOSED USES: Commercial Offices
STAFF REPORT:
This is a proposal by the applicant to revise an approved
preliminary by changing the location of Shackleford Drive to
make it a through street. The reason submitted is to
facilitate the sale ❑f the property.
The City Engineer has requested that an in -lieu
contribution for street improvements on West Markham be
required upon the final plat ❑f the first of Lots 3-7; and
that an internal drainage plan to include detention
considerations be submitted. Engineering reports that plans
for this extension have been approved.
STAFF RECOMMENDATION:
Approval, subject to comments made.
SUBDIVISION COMMITEE REVIEW:
The applicant was present. The Committee reviewed the
application and passed it to the Commission.
Water Works - Require a 10' easement north of and parallel
to the existing 20" water main, a drainage ditch north of
the easement to handle the north -south runoff and a
reinforced concrete slab to protect the existing 39" water
main.
auuic .,L w&'Lua wLLL ue waives or aiieviaLeu as a
January 22, 1985
SUBDIVISIONS
Item No. 4 - Continued
PLANNING COMMISSION ACTION:
The applicant was present. There were no objectors. A
motion for approval was made and passed by a vote of:
11 ayes, 0 noes and 0 absent.