HomeMy WebLinkAboutS-0089-A ApplicationCIVIL ENGINEERING DIVISION
FINAL PLAT FILING APPROVALS
FINAL PLAT NAME: Kimball's South Park Lots 1 OR & I 1 R Block 32
I have made a final inspection of the improvements and find that:
All improvements shown on construction drawings for the development are constructed and in conformance
with City requirements/standards.
Certain Improvements remain uncompleted and a punch list has been prepared and sent.
Engineering Specialist Date:
ADDRESSING SPECI LIST REPORT
I have reviewed the plat and find that the street names and street configuration are acceptable.
Addressing Specialist Date;
TRAFFIC ENGINEER REPORT
I have reviewed the plat and find that:
All streetlight installation, striping, signage and other traffic improvements have been constructed and are in
conformance with City requirements/standards.
street signs should be ordered and billed to developer. Work orders have been prepared for signage.
Certain improvements remain uncompleted and a punch list has been prepared and sent.
Approved engineering drawings for streetlight system Have been received and approved. Applicant is
responsible to furnish as -built drawings once streetlights have been installed.
Traffic Engineer Date:
CIVIL ENGINEER REPORT
I have reviewed the file for this matter and find that:
The maintenance bond has been submitted and it is the proper type and amount.
Financial assurance for the uncompleted improvements listed above has been received.
As -built drainage plans in electronic form have been submitted.
All other requirements for final plat approval have been satisfied.
Civil Engineer I/H Date:
SURVEYOR REPORT
I have reviewed the plat and find that:
All requirements for final plat approval have been satisfied.
MANAGER APPROVAL
Surveyor Date:
All Civil Engineering requirements for filing this final plat have been satisfied.
!/ IaZC.� �L'B2l.Cr�ZG
Design Review Engineer/Civil Engineering Manager
Date: 9-16-2020
Effective: September 11, 2020
City of Little Rock
Planning and Development
Filing Fees
Date , 20
Annexation
$
Board of Adjustment
$
Cond Use Permit/ T UP
$
Final Plat
$
Planned Unit Dev
$
Preliminary Plat
$
Special Use Permit
$
Rezoning
$
Site Plans
Street Name Change''�
$y
Street Name Signs:
Number at ea
Public Hearing Signs
y " L�►U
Number at ea
$
Total
File No
Location
Awlican# . r S �
CIVIL ENGINEERING DIVISION
FINAL PLAT FILING APPROVALS
' & 11 R B1 k 32
J
t 11'A
S �Il
FINAL PLAT NAME: Kunba u s South Park Lots 1 OR oc
I have made a final inspection of the improvements and find that:
All improvements shown on construction drawings for the development are constructed and in conformance 0�
with City requirements/standards.
Certain Improvements remain uncompleted and a punch list has been prepared and sent.
Engineering Specialist Bate:
ADDRESSING SPECIALIST REPORT
I have reviewed the plat and find that the street names and street configuration are acceptable.
Addressing Specialist Date:
TRAFFIC ENGINEER REPORT
I have reviewed the plat and find that:
All streetlight installation, striping, signage and other traffic improvements have been constructed and are in
conformance with City requirements/standards.
street signs should be ordered and billed to developer. Work orders have been prepared for signage.
Certain improvements remain uncompleted and a punch list has been prepared and sent.
Approved engineering drawings for streetlight system have been received and approved. Applicant is
responsible to furnish as -built drawings once streetlights have been installed.
Traffic Engineer Date:
CIVIL ENGINEER REPORT
I have reviewed the file for this matter and find that:
The maintenance bond has been submitted and it is the proper type and amount.
Financial assurance for the uncompleted improvements listed above has been received.
As -built drainage plans in electronic farm have been submitted.
All other requirements for final plat approval have been satisfied_
Civil Engineer I/II Date:
SURVEYOR REPORT
I have reviewed the plat and find that:
4 All requirements for final plat approval have been satisfied.
Surveyor Date:
MANAGER APPROVAL
All Civil Engineering requirements for filing this final plat have been satisfied.
Date: 9-16-2020
Design Review Enginneer/Civil Engineering Manager
Effective: September 11, 2020
Gmail
Jonathan Hope <jonathanlhope@gmail.com>
Replat: 2510 & 2504 South lzard
Floriani, Vince <VFloriani@littlerock.gov>
To: Jonathan Hope <jonathanlhope@gmail.com>
Cc: "Moore, Monte" <MMoore@littlerock.gov>, "Harper, Vance" <VHarper@littlerock.gov>
Engineering is OK with the final plat.
Vince Florian!, P.E.
Design Review Engineer
Little Rock Public Works -Civil Engineering
723 W. Markham St.
Little Rock, AR 72201
501-371-4817
vfloriani@littlerock.gov
From: Jonathan Hope <jonathanihope@gmail. com>
Sent: Tuesday, September 15, 2020 8:37 AM
To: Floriani, Vince <VFloriani@littlerock.gov>
Cc: Moore, Monte <MMoore@littlerock.gov>; Harper, Vance <VHarper@littlerock.gov>
Subject: Re: Replat: 2510 & 2504 South Izard
Wed, Sep 16, 2020 at 1:32 PM
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you
recognize the sender and know the content is safe.
Vince,
[Quoted text hidden]
[Quoted text hidden]
Kimball's Southpark Sign-off-a_C10518297.pdf
64K
Gmai[
Replat: 2510 & 2504 South Izard
Jason Lowder <Jason.Lowder@carkw.com>
To: Jonathan Hope <jonathanlhope@gmail.com>
Central Arkansas Water approves with no comments.
Respectfully,
Jason Lowder, Engineering Technician
jason.lowder@carkw.com
501-377-1245
Jonathan Hope <jonathanlhope@gmail.com>
Tue, Sep 29, 2020 at 12:34 PM
From: Jonathan Hope <jonathanlhope@gmail.com>
Sent: Friday, September 25, 2020 9:44 AM
To: Vincent Hotho <Steven.Hotho@Irwu.com>; Mark <malderfer@littlerock.org>; Curtis <crichey@littlerock.org>; Jason
Lowder <Jason.Lowder@carkw.com>; Gatlin, Allen <allen.gatlin@lrwu.com>
Subject: [External] Fwd: Replat: 2510 & 2504 South Izard
[CAUTION:] This email originated from outside of the CAW. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
[Quoted text hidden]
E Gmail
Replat: 2510 & 2504 South Izard
Jonathan Hope <jonathanihope@gmail.com>
Vincent Hotho <Steven.Hotho@lrwra.com> Tue, Sep 29, 2020 at 3:31 PM
To: Jonathan Hope <jonathanlhope@gmail.com>
Cc: Jason Lowder <jason.lowder@carkw.com>, Allen Gatlin <Allen. Gatli n@lrwra. com>, "Moore, Monte"
<mmoore@littlerock.gov>
LRWRA has no objection.
[Quoted text hidden]
Gmail
Replat: 2510 & 2504 South Izard
KEATHLEY, CHRIS <ck0826@att.com>
To: Jonathan Hope <jonathanlhope@gmail.com>
Jonathan Hope <jonathanihope@gmail.com>
Mon, Nov 30, 2020 at 4:39 PM
AT&T approves the request to replat 2504/2510 S Izard St in the City of Little Rock. Thanx Chris
Chris Keathley
Lead O5P Ping & Eng Dsgn
501.615.5823 Cell
ck0826@att.com
[Quoted text hidden]
2504-2510- S Izard St-AT&T-20-0823_Split-11X17_09-29-2020 (1).pdf
662K
11 . Cmail
Jonathan Hope <jonathanlhope@gmail.com>
Replat: 2510 & 2504 South Izard
Reynolds, Megan M <megan.reynolds@centerpointenergy.com> Tue, Dec 1, 2020 at 1:37 PM
To: "jonathanlhope@gmail.com" <jonathanlhope@gmail.com>
Good afternoon Mr. Hope,
I have reviewed the attached request and found that CenterPoint Energy does not have any objections to the replat for
Lot 11 R and Lot 1 OR, Block 32 of Kimball's South Park Addition, Little Rock.
Please let me know if you have any questions.
Thank you,
Megan Reynolds
Associate Engineer I AR/OK Region
501.377.4629 work 1501.553.4787 cell
CenterPointEnergy.com
From: Gober, Adam P<adam.gober@centerpointenergy.com>
Sent: Tuesday, December 1, 2020 1:02 PM
To: Reynolds, Megan M<megan.reynolds@centerpointenergy.com>
Subject: FW: [External Email] Fwd: Replat: 2510 & 2504 South Izard
Good afternoon Megan,
Could you please take a look at this replat?
Thank you!
Cefltef ain[. Adam P. Gober
Enenp Engineer I AR/OK Region
F Gmail
Replat: 2510 & 2504 South Izard
Vance, Brad <BVANCE1@entergy.com>
To: Jonathan Hope <jonathanlhope@gmail. com>
Entergy has no problems with this replat.
Thanks,
Brad
Jonathan Hope <jonathanihope@gmail.com>
Tue, Dec 1, 2020 at 5:05 PM
From: Jonathan Hope <jonathanlhope@gmail.com>
Sent: Tuesday, December 01, 2020 12:58 PM
To: Gober, Adam P<adam.gober@centerpointenergy.com>; Vance, Brad <BVANCE1 @entergy.com>
Subject: Fwd: Replat: 2510 & 2504 South Izard
EXTERNAL SENDER. DO NOT click links, or open attachments, if sender is
unknown, or the message seems suspicious in any way. DO NOT provide your user
ID or password.
[Quoted text hidden]
This message is intended for the exclusive use of the intended addressee. If you have received this message in error or
are not the intended addressee or his or her authorized agent, please notify me immediately by e-mail, discard any paper
copies and delete all electronic files of this message.
Gmail
Replat: 2510 & 2504 South Izard
Jonathan Hope <jonathanlhope@gmail.com>
Vincent Hotho <Steven.Hotho@lrwra.com>
To: Jonathan Hope <jonathanihope@gmail.com>
Cc: Jason Lowder <jason.lowder@carkw.com>, Allen Gatlin <Allen. Gati i n@l rwra. com>
No further comments, if those have been addressed.
[Quoted text hidden]
Tue, Sep 29, 2020 at 10:59 AM
Gmail
Replat: 2510 & 2504 South Izard
Jonathan Hope <jonathanihope@gmail.com>
Vincent Hotho <Steven. Hotho@lrwra. com>
To: Jonathan Hope <jonathanihope@gmail.com>
Cc: Jason Lowder <jason.lowder@carkw.com>, Allen Gatlin <AIIen.Gatlin@lrwra.com>,
<mmoore@littierock.gov>
LRWRA has no objection.
[Quoted text hidden]
Tue, Sep 29, 2020 at 3:31 PM
"Moore, Monte"
I_ Gmail
Replat: 2510 & 2504 South Izard
Jason Lowder <Jason.Lowder@carkw.com>
To: Jonathan Hope <jonathanlhope@gmail.com>
Central Arkansas Water approves with no comments.
Respectfully,
Jason Lowder, Engineering Technician
jason.lowder@carkw.com
501-377-1245
Jonathan Hope <jonathanlhope@gmail.com>
Tue, Sep 29, 2020 at 12:34 PM
From: Jonathan Hope <jonathanIhope @gmail. com>
Sent: Friday, September 25, 2020 9:44 AM
To: Vincent Hotho <Steven.Hotho@lrwu.com>; Mark <malderfer@littlerock.org>; Curtis <crichey@littlerock. org>; Jason
Lowder <Jason.Lowder@carkw.com>; Gatlin, Allen <allen.gatlin@lrwu.com>
Subject: [External] Fwd: Replat: 2510 & 2504 South Izard
[CAUTION:] This email originated from outside of the CAW. Do not click links or open attachments unless you recognize
the sender and know the content is safe.
[Quoted text hidden]
CIVIL ENGINEERING DIVISION
FINAL PLAT FILING APPROVALS
FINAL PLAT NAME: Kimball's South Park Lots 1 OR & 11 R Block 32
I have made a final inspection of the improvements and find that:
All improvements shown on construction drawings for the development are constructed and in conformance
with City requirements/standards.
Certain Improvements remain uncompleted and a punch list has been prepared and sent.
Engineering Specialist Date:
ADDRESSING SPECIALIST REPORT
I have reviewed the plat and find that the street names and street configuration are acceptable.
Addressing Specialist Date:
TRAFFIC ENCINEER REPORT
I have reviewed the plat and find that:
All streetlight installation, striping, signage and other traffic improvements have been constructed and are in
conformance with City requirements/standards.
street signs should be ordered and billed to developer. Work orders have been prepared for signage.
Certain improvements remain uncompleted and a punch list has been prepared and sent.
Approved engineering drawings for streetlight system have been received and approved. Applicant is
responsible to furnish as -built drawings once streetlights have been installed.
Traffic Engineer Date:
CIVIL ENGINEER REPORT
I have reviewed the file for this matter and find that:
The maintenance bond has been submitted and it is the proper type and amount.
Financial assurance for the uncompleted improvements listed above has been received.
As -built drainage plants in electronic form have been submitted.
All other requirements for fmal plat approval have been satisfied.
Civil Engineer IM Date:
SURI FYQR REPORT
I have reviewed the plat and find that:
All requirements for final plat approval have been satisfied.
Surveyor Date:
MANAGER APPROVAL
All Civil Engineering requirements for filing this final plat have been satisfied.
Date: 9-16-2020
Design Review Engineer/Civil Engineering Manager
Effective: September 11, 2020
Gmail
Replat: 2510 & 2504 South Izard
Jonathan Hope <jonathanlhope@gmail.com>
Floriani, Vince <VFloriani@littlerock.gov>
To: Jonathan Hope <jonathanihope@gmail.com>
Cc: "Moore, Monte" <MMoore@littlerock.gov>, "Harper, Vance" <VHarper@littlerock.gov>
Engineering is OK with the final plat.
Vince Floriani, P.E.
Design Review Engineer
Little Rock Public Works -Civil Engineering
723 W. Markham St.
Little Rock, AR 72201
501-371-4817
vfloriani@littlerock.gov
From: Jonathan Hope <jonathanlhope@gmail.com>
Sent: Tuesday, September 15, 2020 8:37 AM
To: Floriani, Vince <VFloriani@littlerock.gov>
Cc: Moore, Monte <MMoore @I ittlerock.gov>; Harper, Vance <VHarper@littlerock.gov>
Subject: Re: Replat: 2510 & 2504 South Izard
Wed, Sep 16, 2020 at 1:32 PM
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you
recognize the sender and know the content is safe.
Vince,
[Quoted text hidden]
[Quoted text hidden]
- Kimball's Southpark Sign-off-a_C10518297.pdf
64K