HomeMy WebLinkAboutS-1706 Staff Analysis2. Contact Central Arkansas Water regarding the size and location of the water meter.
3. A Capital Investment Charge based on the size of meter connection(s) will apply to
this project in addition to normal charges. This fee will apply to all connections
including metered connections off the private fire system.
4. If there are facilities that need to be adjusted and/or relocated, contact Central
Arkansas Water. That work would be done at the expense of the developer.
5. Contact Central Arkansas Water if additional fire protection or metered water service
is required.
6. The Little Rock Fire Department needs to evaluate this site to determine whether
additional public or private fire hydrant(s) will be required. If additional fire hydrant(s)
are required, they will be installed at the Developer's expense.
7. Due to the nature of this facility, installation of an approved reduced pressure zone
backflow preventer assembly (RPZA) is required on the domestic water service.
This assembly must be installed prior to the first point of use. Central Arkansas
Water requires that upon installation of the RPZA, successful tests of the assembly
must be completed by a Certified Assembly Tester licensed by the State of Arkansas
and approved by Central Arkansas Water. The test results must be sent to Central
Arkansas Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 377-1226 if you would
like to discuss backflow prevention requirements for this project.
Fire Department: Provide a letter of acknowledgement from the area volunteer fire
department. Place fire hydrant(s) per code. Maintain access. Contact the Little Rock
Fire Department for additional information.
County Planning:
1. Tie survey to two section corners.
2. Show state plane coordinates for two property corners.
3. Obtain septic approval from AHD.
4. Show 40' building setback not 25'.
5. Dedicate Right of Way on east side of Pinnacle Valley Road to equal one-half of 90
feet (45').
6. Obtain variance from Little Rock Planning Commission for construction to Master
Road Plan standards for Pinnacle Valley Road.
7. Obtain Flood Development Permit from Pulaski County Public Works (340-6800).
8. Show vicinity map.
9. Obtain driveway permit from Pulaski County Public Works (340-6800).
10. Show source of title.
CATA: Approved as submitted. The site is not located on a dedicated CATA Bus
Route.
Parks and Recreation: No comment received -
Planning Division: No comment.
Landscape: No comment.
Item # 1.
ITEM NO.: 1,
NAME: West Pulaski Volunteer Fire Station District 23 Preliminary Plat — Lot 1
Pinnacle Valley Station
LOCATION: located immediately North of 8501 Pinnacle Valley Road (Northeast corner
of Pinnacle Valley Road)
Plannin Staff Comments:
1. Provide notification of the abutting property owners including the certified abstract
list, notice form with affidavit executed and proof of mailing. The notice must be
mailed no later than August 7, 2013. The Office of Planning and Development must
receive the proof of notice no later than August 16, 2013.
2. Provide a deed or a survey for the larger acreage this site is being "cut" from.
3. Correct the signature of the Certificate of Owner.
4. Provide the source of title of the landowner for the proposed parcel.
5. Provide Final Plat Approval Certification for the County on the proposed plat.
6. Not sure of the street address provided on the proposed plat.
Variance/Waivers: None requested
Public Works Conditions:
1. Pinnacle Valley Road is classified on the Master Street Plan as a minor arterial. A
dedication of right-of-way 45 feet from centerline will be required.
2. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan.
3. A 20 foot radial dedication of right-of-way is required at the intersection of Pinnacle
Valley Road and Beck Road.
Utilities and Fire Department/County Planning:
Wastewater: Located outside the City limits, City sewer is not available. Provide
Septic Certification and/or Approval from the Arkansas Department of Health.
Entergy: Entergy has a 3 (P power line across the street from the platted area and will
work with the property owner to provide service when requested.
Center -Point Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for water
service must be met.
Item # 1.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, August 7, 2013.
Item # 1.
August 22, 2013
ITEM NO.: 1 FILE NO.: S-1706
NAME: West Pulaski Volunteer Fire Station District 23 Preliminary Plat — Lot 1
Pinnacle Valley Station
LOCATION: Located immediately North of 8501 Pinnacle Valley Road (Northeast
corner of Pinnacle Valley Road and Beck Road)
DEVELOPER:
West Pulaski County Volunteer Fire Department
Hatcher Enterprises, Inc.
P.O. Box 3505
Little Rock, AR 72203
SURVEYOR:
Arrow Surveying
Blake Butler
P.O. Box 1308
Maumelle, AR 72113
AREA: 0.898 acres
CURRENT ZONING:
PLANNING DISTRICT
CENSUS TRACT:
NUMBER OF LOTS: 1
R-2, Single-family
1 — River Mountain
42.05
VARIANCEANAIVERS: None requested.
FT. NEW STREET: 0 LF
A. PROPOSAUREQUEST/APPLICANT'S STATEMENT:
The request is to allow the creation of a single parcel containing 0.898 acres from
a 10+ acre tract. The lot will be final platted with the remainder of the area
remaining in a metes and bounds legal description. The purpose of the lot is to
allow the construction of a fire station to serve this area of West Pulaski County.
The lot is 180.67-feet by 218.85-feet containing 0.898 acres with access on
Pinnacle Valley Road.
August 22, 2013
SUBDIVISION
ITEM NO.: 1 (Cont.) FILE NO.: S-17
B. EXISTING CONDITIONS:
The property is located on Pinnacle Valley Road just north of the intersection with
Beck Road. The area is developed with single-family homes located on large
lots and/or acreage. The corner of Beck Road and Pinnacle Valley Road
contains a non-residential building located on C-1, Neighborhood Commercial
zoned property which is under renovation. Across Pinnacle Valley Road are
single-family homes, a barn and riding arena. An illegal private air strip has been
constructed on property located to the southwest.
Along Pinnacle Valley Road the County has installed a separate bicycle lane.
Pinnacle Valley Road is a two lane road. Within the general area are several
parks including Two Rivers Park, Pinnacle Mountain State Park and Maumelle
Corps of Engineers Park. There are no curb, gutter or sidewalk located along
this section of the road.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has received several informational phone calls from area
residents concerning the proposed request. All abutting property owners along
with the River Valley Property Owners Association were notified of the public
hearing.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS-
1 . Pinnacle Valley Road is classified on the Master Street Plan as a minor
arterial. A dedication of right-of-way 45 feet from centerline will be required.
2. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan.
3. A 20 foot radial dedication of right-of-way is required at the intersection of
Pinnacle Valley Road and Beck Road.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Located outside the City limits, City sewer is not available. Provide
Septic Certification and/or Approval from the Arkansas Department of Health.
Entergy: Entergy has a 3 4) power line across the street from the platted area and
will work with the property owner to provide service when requested.
Center -Point Enercv: No comment received.
2
August 22, 2013
SUBDIVISION
ITEM NO.: 1 (Cont.) FILE NO.: S-1706
AT & T: No comment received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for
water service must be met.
2. Contact Central Arkansas Water regarding the size and location of the water
meter.
3. A Capital Investment Charge based on the size of meter connection(s) will
apply to this project in addition to normal charges. This fee will apply to all
connections including metered connections off the private fire system.
4. If there are facilities that need to be adjusted and/or relocated, contact Central
Arkansas Water. That work would be done at the expense of the developer.
5. Contact Central Arkansas Water if additional fire protection or metered water
service is required.
6. The Little Rock Fire Department needs to evaluate this site to determine
whether additional public or private fire hydrant(s) will be required. If
additional fire hydrant(s) are required, they will be installed at the Developer's
expense.
7. Due to the nature of this facility, installation of an approved reduced pressure
zone backflow preventer assembly (RP7A) is required on the domestic water
service. This assembly must be installed prior to the first point of use.
Central Arkansas Water requires that upon installation of the RP7A,
successful tests of the assembly must be completed by a Certified Assembly
Tester licensed by the State of Arkansas and approved by Central Arkansas
Water. The test results must be sent to Central Arkansas Water's Cross
Connection Section within ten days of installation and annually thereafter.
Contact the Cross Connection Section at 377-1226 if you would like to
discuss backflow prevention requirements for this project.
Fire Department: Provide a letter of acknowledgement from the area volunteer
fire department. Place fire hydrant(s) per code. Maintain access. Contact the
Little Rock Fire Department for additional information.
County Planning.
1. Tie survey to two section corners.
2. Show state plane coordinates for two property corners.
3. Obtain septic approval from AHD prior to construction.
3
August 22, 2013
SUBDIVISION
EM NO.: 1 (Cont.) FILE NO.: S-1706
4. Show 40' building setback not 25'.
5. Dedicate Right of Way on east side of Pinnacle Valley Road to equal
one-half of 90 feet (45').
6. Obtain variance from Little Rock Planning Commission for construction to
Master Road Plan standards for Pinnacle Valley Road if required as part of
the Conditional Use Permit Application (Z-8877).
7. Obtain Flood Development Permit from Pulaski County Public Works
(340-6800).
8. Show vicinity map.
9. Obtain driveway permit from Pulaski County Public Works (340-6800).
10. Show source of title.
CATA: Approved as submitted. The site is not located on a dedicated CATA
Bus Route.
Parks and Recreation: No comment received.
F. ISSUES/TECHNICAUDESIGN:
G.
Planning Division: No comment.
Landscape: No comment.
SUBDIVISION COMMITTEE COMMENT:
(August 1, 2013)
The applicant was present. Staff presented an overview of the request stating
the Commission would review a Conditional Use Permit for this site at their
August 8, 2013, public hearing to allow the construction of a fire station on this
property. Staff stated the plat was being requested to create a tract less than
one acre in size to allow the local fire district ownership of the property proposed
for the new station. Staff requested the engineer provide the certificate of owner
and correct the address of the owner on the proposed plat.
Public Works comments were addressed. Staff started Pinnacle Valley Road
was classified on the Master Street Plan as a minor arterial which would require
a dedication of right of way to 45-feet from centerline.
Staff noted comments from the other reporting departments and agencies
suggesting the applicant contact them individually for additional clarification.
There was no further discussion of the item. The Committee then forwarded the
item to the full Commission for final action.
4
August 22, 2013
SUBDIVISION
ITEM NO.: 1 Cont.) FILE NO.: S-1706
H. ANALYSIS:
The applicant submitted a revised preliminary plat to staff addressing the issues
raised at the August 1, 2013, Subdivision Committee meeting. The revised plat
indicates the certificate of owner and corrected the address of the owner on the
proposed plat. The plat also indicates a dedication of right of way 45-feet from
centerline as required by the Master Street Plan.
The request is to allow the creation of a single parcel containing 0.898 acres from
a 10+ acre tract. The lot will be final platted with the remainder of the area
remaining in a metes and bounds legal description. The purpose of the lot is to
allow the construction of a fire station to serve this area of West Pulaski County.
The Commission approved a Conditional Use Permit at their August 8, 2013,
public hearing to allow the fire station on this R-2, Single-family zoned property
(Z-8877).
The lot is 180.67-feet by 218.85-feet containing 0.898 acres with access on
Pinnacle Valley Road. The property is located outside the City limits of Little
Rock and will use a septic tank for wastewater disposal. The applicant has
indicated approval from the Arkansas Department of Health will be secured prior
to construction of the new fire station.
Staff is supportive of the request to allow the creation of the lot as proposed. To
staffs knowledge there are no outstanding technical issues associated with the
request. Staff feels the creation of this 0.898 acre lot will not significantly impact
the area.
STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
PLANNING COMMISSION ACTION: (AUGUST 22, 2013)
The applicant was present. There were no registered objectors present. Staff
presented the item with a recommendation of approval of the request subject to
compliance with the comments and conditions as outlined in paragraphs D, E and F of
the agenda staff report.
There was no further discussion of the item. The Chair entertained a motion of approval
of the item as presented by staff. The motion carried by a vote of 8 ayes,
0 noes and 3 absent.
5