HomeMy WebLinkAboutS-1691 Staff AnalysisITEM NO.: 3. S-1691
NAME: Redbridge Development Addition Lots 1 & 2
LOCATION: located on the East side of Edswood Road approximately 1,200 feet South
of Kanis Road
Planning Staff Comments:
1. Provide notification of the abutting property owners of the site including the certified
abstract list, notice form with affidavit executed and proof of mailing. The notice
must be mailed no later than August 28, 2012. The Office of Planning and
Development must receive the proof of notice no later than September 7, 2012.
2. Provide the septic certification for the proposed lots.
3. Provide the document for the access easement indicating access to the property.
Variance/Waivers: Development of lots utilizing private streets.
Public Works Conditions:
Edswood Road is classified on the Master Street Plan as a principal arterial.
Dedication of right-of-way to 55 feet from centerline will be required within the width
of the access easement.
Utilities and Fire Department/County Planning:
Wastewater: Outside the service boundary. Provide septic certification from the
Arkansas Department of Health.
Entergy: Approved as submitted.
Center -Point Energy: No comment received.
AT & T: No comment received
Central Arkansas Water: No objection. All Central Arkansas Water requirements in
effect at the time of request for water service must be met. Contact Central Arkansas
Water regarding the size and location of the water meter. A Capital Investment Charge
based on the size of the meter connection(s) will apply to this project in addition to
normal charges. This fee will apply to all connections including metered connections off
the private fire system.
Fire Department: Place fire hydrants per code. Maintain a minimum access of at
least 20-feet. Contact the Little Rock Fire Department for additional information.
County Planning: Provide proof of septic approval on both lots and approval from the
volunteer fire department for the proposed plat.
Item # 3.
CATA: The site is not located on a dedicated CATA Bus Route.
Parks and Recreation: No comment received.
Planning Division: No comment.
Landscape: No comment.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, August 29, 2012.
Item # 3.
September 13, 2012
ITEM NO.: 3 FiLE NO.: S-1691
NAME: Redbridge Development Addition Lots 1 & 2
LOCATION: Located on the East side of Edswood Road approximately 1,200 feet
South of Kanis Road
DEVELOPER:
Redbridge Development LTD
Robert Schmitt
45 Ranch Ridge Road
Little Rock, AR 72223
SURVEYOR:
Donald Brooks Surveying
20820 Arch Street Pike
Hensley, AR 72065-9256
AREA: 5.17 acres
CURRENT ZONING:
PLANNING DISTRICT:
CENSUS TRACT:
NUMBER OF LOTS: 2
R-2, Single-family
18 — Ellis Mountain
42.07
FT. NEW STREET: 0 LF
VARIANCESNVAIVERS REQUESTED: None requested.
A. PROPOSAVREQUESTIAPPLICANT'S STATEMENT:
The applicant is requesting to split an existing 5.17 acre parcel located east of
Edswood Road approximately 1,200 feet south of Kanis Road. There is an
existing 30-foot ingress -egress easement extending from Edswood Road serving
this parcel as well as two parcels to the west and one parcel to the east. The
access easement splits the property into a 3.80 acre tract (Lot 1) and a 1.27 acre
tract (Lot 2). The proposed plat indicates the placement of a 20-foot platted
building line for each of the lots adjacent to the access easements. All other
setbacks will comply with the typical standards of the R-2, Single-family Zoning
District. The lots will be developed utilizing private streets.
September 13, 2012
SUBDIVfSION
NO.; 3 {Con
B. EXISTING CONDITIONS:
FILE NO.:
1691
The property is located outside the City limits but within the City's Extraterritorial
Planning Jurisdiction. The area is developed primarily with single-family homes
located on acreage with the majority of the homes located on five (5) plus acres.
East of the proposed plat area there are three (3) single-family homes near
completion located within the Hagan's Addition, which is a plat approved by the
Planning Commission in January 2011. A total of five (5) residential lots were
approved. There was an existing home located on one (1) of the lots and
construction has not begun on the fifth lot. The Commission approved a
preliminary plat to allow an additional five (5) lots to the north of the homes under
construction at their June 21, 2012, public hearing. These lots have not been
final platted,
The site proposed for platting is located east of Edswood Road along a narrow
Private access easement. There appear to be three (3) to four (4) homes
serviced by the access easement. Two (2) to three (3) homes located west of
the proposed plat area and one (1) to the east of the plat area. The property
proposed for platting is wooded with the access drive splitting the acreage and
serving a home to the east.
C- NEIGHBORHOOD COMMENTS;
As of this writing, staff has not received any comment from area residents. All
abutting property owners were notified of the public hearing. There is not a
registered neighborhood association located in the area.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Edswood Road is classified on the Master Street Plan as a principal arterial.
Dedication of right-of-way to 55 feet from centerline will be required within the
Width of the access easement. (It has been determined that the proposed
plat area does not abut Edswood Road and no right of way dedication is
required.)
E. UTlL1TIES AND I'1RE ❑EPARTIVlENT1COUNTY PLANNING;
Wastewater: Outside the service boundary. Provide septic certification from the
Arkansas Qepartment of Health,
End_: Approved as submitted.
i+:
September 13, 2012
SUBDIVISION
ITEM NO.: 3 (Cont.) FILE NO.: S-1691
Center -Point Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water: No objection. All Central Arkansas Water requirements
in effect at the time of request for water service must be met. Contact Central
Arkansas Water regarding the size and location of the water meter. A Capital
Investment Charge based on the size of the meter connection(s) will apply to this
project in addition to normal charges. This fee will apply to all connections
including metered connections off the private fire system.
Fire Department: Place fire hydrants per code. Maintain a minimum access of at
least 20-feet. Contact the Little Rock Fire Department for additional information.
County Planning: Provide proof of septic approval on both lots and approval
from the volunteer fire department for the proposed plat.
CATA: The site is not located on a dedicated CATA Bus Route.
Parks and Recreation: No comment received.
F. ISSU ES/TECHN ICAUDESIGN:
Planning Division: No comment.
Landscape: No comment.
G. SUBDIVISION COMMITTEE COMMENT: (August 22, 2012)
Mr. Bob Schmitt, Redbridge LLC, was present representing the request. Staff
presented an overview of the development stating there were few outstanding
technical issues associated with the request. Staff requested Mr. Schmitt provide
them with a copy of the access easement agreement. Staff also requested
Mr. Schmitt provide approval for the proposed septic system placement.
Public Works comment was noted. Commissioner Rector questioned how the
developer could dedicate right of way on Edswood Road when he did not own
the property. Staff stated if he was not the owner and the owner of the property
was not involved in the plat area then right of way was not required.
Staff noted comments from the other reporting departments and agencies
suggesting the applicant contact them individually for additional clarification.
There was no further discussion of the item. The Committee then forwarded the
item to the full Commission for final action.
3
September 13, 2012
SUBDIVISION
ITEM Na.: 3 Cont.
H. ANALYSIS:
ILE NO.: S-1691
The applicant has provided staff with a copy of the access easement agreement
and is continuing to work to secure septic approval for the two (2) proposed lots.
The applicant has indicated the property owner abutting Edswood Road does not
desire to grant right of way as requested by Public Works staff. That property is
not part'of this plat. The lots will be developed utilizing private streets.
The site is located outside the City limits of Little Rock but within the City's
Extraterritorial Planning Jurisdiction. Section 31-232(c) states lots served by a
public water system and proposed to be served by a septic tank system must
submit at the time of request for preliminary plat filing a written certification
approved by the State Department of Health. The lot sizes allowed by this
certification shall be indicated on the plat. The Department of Health has
indicated they do not provide approval of septic certification at preliminary
platting but at the time of actual construction of the septic system. Prior to the
Commission acting on the request the applicant will have secured a report from
Meinco Septic System to determine if the soils are suitable for septic systems
and will support the lot sizes as proposed. All the proposed lots will be served by
Central Arkansas Water with an extension of a water main as needed.
The request is to divide the 5.17 acre tract into two (2) lots. The lots will be split
based on an existing access easement which crosses the property providing
access to a single-family home to the east. The lots are proposed containing
3.80 acres (Lot 1) and 1.37 acres (Lot 2). The access easement serving this lot
and lots to both the east and west is a 30-foot ingress -egress easement which
also provides for a utility easement.
Staff is supportive of the request. Although in this area the existing lots are
mostly larger than the lots as proposed by the applicant the lots do meet the
typical standards of the R-2, Single-family Zoning District. Prior to the
Commission acting on the request a septic certification indicating the lots as
proposed are sufficient to allow for proper waste disposal will be provided. To
staff's knowledge there are no remaining outstanding technical issues in need of
addressing related to the proposed preliminary plat.
STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
4
September 13, 2012
SUBDIVISION
ITEM NO.: 3 (Cont.) FILE NO.: S-1691
PLANNING COMMISSION ACTION: (SEPTEMBER 13, 2012)
The applicant was present. There were no registered objectors present. Staff
presented the item with a recommendation of approval of the request subject to
compliance with the comments and conditions as outlined in paragraphs D, E and F of
the agenda staff report.
There was no further discussion of the item. The Chair entertained a motion for
approval of the item on the Consent Agenda as presented by staff. The motion carried
by a vote of 10 ayes, 0 noes and 1 absent.
5