HomeMy WebLinkAboutS-1028-A Staff AnalysisFILE N-1028-A
NAME: HINSON LOOP OFFICE PARK -- PRELIMINARY PLAT
LOCATION: At the southwest corner of Hinson Road and Hinson Loop
Road
DEVELOPER: ENGINEER:
Robert Brown
CLARY DEVELOPMENT CORP. DEVELOPMENT CONSULTANTS, INC.
8210 Cantrell Rd., Suite 340 10411 W. Markham St., Suite 210
Little Rock, AR 72207 Little Rock, AR 72205
225-0204 221-7880
AREA: 9.05 ACRES NUMBER OF LOTS: 9 FT. NEW STREET: 1,040
ZONING: 0-3
PLANNING DISTRICT: 2
CENSUS TRACT: 22.05
VARIANCES REQUESTED:
PROPOSED USES: General Offices
1. Approval is requested of a variance for reduced street
rights -of -way widths from the requirements of the Master
Street Plan.
2. Approval is requested of a variance from the requirement to
provide sidewalks along both side of the streets, to permit
construction of a sidewalk along one side only.
STATEMENT OF PROPOSAL:
The applicant proposes a preliminary plat for the development of
an office subdivision on a 9.05 acre tract. Nine lots ranging in
size of from just under one half acre to over one and two-thirds
acres are proposed. Approximately 1,040 linear feet of new
public streets are planned, with one access point being from
Hinson Loop Rd.; the second, a "right in -right out only" access
point, being from Hinson Rd. A reduced street section is
requested (30 feet in lieu of the required] 36 foot section for a
commercial street), and a reduced right-of-way (41 foot minimum
versus the 60 required) is proposed due to the "limited service
area" of the streets; however, a minimum 10 foot utility easement
is to be provided beyond the right-of-way line. Dedication of
required right-of-way along both Hinson Rd. and Hinson Loop Rd.
is planned, as is construction of the required right turn lane
off Hinson Rd.
FILE NO.: S-1028-A (Cont.)
A. PROPOSAL/REQUEST:
Planning Commission approval is requested for a preliminary
plat, and Planning Commission review and Board of Directors
approval is requested for variances from the minimum
required street and right-of-way widths pursuant to the
Master Street Plan.
B. EXISTING CONDITIONS:
The site is undeveloped, heavily wooded, with a man-made
pond of approximately 1 acre in size located on the site.
The site is zoned 0-3. At the northwest corner of the tract
is an office development on 0-3 zoned land. West of the
tract, is an 0-2 zoned tract and a single-family PRD. The
south is an MF-12 zoned development. To the east of the
tract, on the west side of Hinson Loop Rd. is additional 0-3
zoned property, a PCD, and some R-2 zoned property. Across
Hinson Loop Rd., where the subject property abuts Hinson
Loop Rd., there is a large PCD zoned site.
C. ENGINEERING/UTILITY COMMENTS:
Public Works Comments:ll
1) Construction of a right turn lane on Hinson, per the
Master Street Plan standards for connection with a
collector is required. On Hinson Loop Road,
improvements to bring the street up to the standards of
one-half of a collector must be provided.
2) Dedication of additional right-of-way for turn lanes,
in addition to the Master Street Plan requirements for
right-of-way, for both Hinson and Hinson Loop must be
provided.
3) A sketch grading and drainage plan, meeting the
requirements of Sec. 29-186, is required. A grading
permit will be required.
4) A sidewalk will be required to be constructed along
Hinson and Hinson Loop Roads, and along both sides of
the new interior streets.
5) Stormwater detention for the development must be
completed prior to construction on individual parcels.
Storm drain discharge and downstream capacity of
existing system will be required. Boundary survey
requirements will be required.
6) Storm drain lines are shown, but no information is
provided to substantiate their design. The storm drain
E
FILE NO.: 5-1028-A Cont.
system may not terminate at the east property line and
discharge onto the abutting property. An easement must
be obtained and the storm drain system extended to
Hinson Loop Rd., or an alternate route must be
provided.
Water Works comments that a water main extension and on -site
fire protection will be required. A pro-rata front footage
charge of $15.00 per front foot applies for service
connections directly off the main in Hinson Loop Rd.
Wastewater comments that sewer main extensions, with
easements, will be required.
Arkansas Power and Light Co. approved the preliminary plat
without comment.
Arkansas Louisiana Gas Co. approved the submittal without
comment.
Southwestern Bell Telephone Co. approved the submittal
without comment.
The Fire Department comments that the entrance drive from
Hinson Rd. must be a minimum of 18 feet in width.
D. ISSUES LEGAL TECHNICAL DESIGN:
in commercial and office subdivisions, the minimum street
width is to be 36 feet; the minimum right-of-way is to be 60
feet; and sidewalks are to be provided along both sides of
the streets (See Sec. 31-282).
Sec. 31-201(h) states that new boundary streets shall be
avoided, except that the Planning Commission may authorize
such a street when the subdivider proposes to dedicate the
entire right-of-way and construct all the required
improvements. The section states that the subdivider may
not retain a parcel of land lying between the boundary
street and the property line in order to deny access by
abutting owners.
The 0-3 zoning district requires a lot area of at least
14,000 square feet, with a minimum lot width of 100 feet.
E. ANALYSIS•
The street system which is proposed does, as the applicant
asserts, serve a limited area. As is provided for in
residential areas serving a limited number of lots and where
the streets are relatively short, a "minor" street section
is permitted which allows a reduced street and right-of-way
width, and eliminates the requirement for sidewalks. The
applicant proposes a 30 foot street width in lieu of the 36
3
FILE NO.: S-1028-A (Cont.)
foot which is required. A reduced right-of-way of a minimum
of 41 feet is proposed in lieu of the 60 foot required. (A
5 foot offset, providing 46 feet of right-of-way, exists
where the street abuts property outside the subdivision
boundary.) Eliminating the sidewalk along one side of the
street is proposed. The right-of-way width will provide
sufficient width for the sidewalks to be constructed within
the right-of-way, and the proposed utility easements will
provide the needed utility access width.
The street landscaping buffer depth is established from the
right-of-way line inward onto the property. With the
reduced right-of-way width, and with utilities being
constructed outside the right-of-way and within the boundary
of the lot, the required landscaping will be placed within
the utility easement and over utility installations. Work
by utility companies/agencies will affect the landscaping.
The proposal to reduce the width of the right-of-way will
also lessen the effective "green space" along the streets.
F. STAFF RECOMMENDATIONS:
Staff recommends approval of
requested variances. Staff
required landscaping buffer
of the utility easements, in
line.
SUBDIVISION COMMITTEE COMMENT:
the preliminary plat and of the
recommends, however, that the
be measured from the inside edge
lieu of from the right-of-way
(MARCH 16, 1995)
Robert Brown, representing the project engineering firm, and
Mr. Jeff Maxwell, representing the developer were present. Staff
presented the proposal and reviewed with Mr. Brown and Mr.
Maxwell the items contained in the discussion outline. The
Committee reviewed these items and discussed these with the
applicant and design professional. The proposed internal street
system design, the stormwater issues, boundary street
improvements issues, and submittal deficiencies were discussed.
Mr. Brown responded that he would be conferring with his client
and would present a revised plan to staff. The Committee
forwarded the item to the Commission for the public hearing.
PLANNING COMMISSION ACTION: (APRIL 4, 1995)
Staff pointed out that, since the original submission, the
applicant had changed the request to provide a public street
system within the subdivision in lieu of a private street system,
and that, therefore, the requested variances were moot. Staff
pointed out, however, that there were two new variances which
were proposed: 1) to permit a narrower street right-of-way than
is provided for in the Regulations, and to permit a narrower
street width than is required in office and commercial
4
FILE NO.: S-1028-A Cont.
subdivisions. Staff explained that the Subdivision Regulations
and the Master Street Plan require rights -of -way in office and
commercial subdivisions to be 60 feet in width, and streets to be
a minimum of 36 feet in width. The subdivider, staff explained,
proposes to provide 46 foot wide rights -of -way at the two
locations where the subdivision abut other properties; 41 foot
right-of-way at all other locations; and, 30 foot wide streets
throughout the subdivision. The variances proposed would, staff
explained, require Board of Directors approval. Staff stated
that both the Public Works and Neighborhoods and Planning staffs
recommend approval of the variances, as requested, explaining
that the interior street system within the subdivision involves a
short loop street and a short cul-de-sac section. Staff also
pointed out that the developer proposes to provide utility
easements outside of and along both sides of the rights -of -way
within the subdivision, and that the comment made in the staff
recommendation regarding requiring the developer to measure the
required landscaping depth from this easement line was not
applicable after the change from a private street in an access
easement to a public street. Since no one had completed a
registration card indicating an objection to the proposed
subdivision, the Chairperson called the question, and the
preliminary plat and a recommendation for approval of the
requested variances was approved with the vote of 8 ayes, 0 nays,
0 abstentions, and 3 absent.
5