HomeMy WebLinkAboutS-0057-UU Staff AnalysisITEM NO.: 2,
NAME: Riverdale Addition Replat of Tract D-2A-R and Tract E-2-R2
S-57-UU
LOCATION: located on the east side of Riverfront Drive at Cedar Hill Road
Planning Staff Comments:
1. Provide notification of abutting property owners complete with the certified abstract
list, notice form with affidavit executed and proof of mailing. The notice must be
mailed no later than December 21, 2011. The Office of Planning and Development
must receive the proof of notice no later than December 30, 2011.
2. The property is zoned 0-2, Office and Institutional District. There is a setback
variance proposed. Within the area of the canopy a zero setback exists.
3. Provide cross access and parking on the plat as well as in the Bill of Assurance.
Variance/Waivers:
1. A variance from Section 36-280(e)(1) to allow a reduced side yard setback.
2. A variance from Section 36-502 to allow the creation of lots with parking less than
typically allowed per the zoning ordinance.
Public Works Conditions:
1. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-
of-way prior to occupancy.
2. Easements are required for all stormwater drainage areas.
Utilities and Fire Department/County Planning:
Wastewater: Sewer available to this project. 10-foot sewer easement required for the
existing sewer main located in Cedar Hill Road. Contact Little Rock Wastewater Utility
for additional information.
Entergy: No comment received.
Center -Point Enerav: No comment received.
AT & T: No comment received.
Central Arkansas Water: Central Arkansas Water retains all water line easements as
shown on the replat. All Central Arkansas Water requirements in effect at the time of
request for water service must be met. Contact Central Arkansas Water regarding the
size and location of the water meter. If there are facilities that need to be adjusted
and/or relocated, contact Central Arkansas Water. That work would be done at the
expense of the developer. Due to the nature of the facility, installation of an approved
reduced pressure zone backflow preventer assembly (RPZ) is required on the domestic
Item # 2.
water service. This assembly must bd instal -led prior to the first point of use. Central
Arkansas Water requires that upon installation of the RPZ assembly, successful tests of
the assembly must be completed by a Certified Assembly Tester licensed in the State of
Arkansas and approved by Central Arkansas Water. The test results must be sent to
Central Arkansas Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 377-1226 if you would
like to discuss backflow prevention requirements for this project. The facilities on -site
will be private.
County Planning: No comment.
CATA: The site is located on CATA Bus Route # 21 — The University Avenue route.
Parks and Recreation: No comment received.
Planning Division: No comment.
Landscape: No comment.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include
the additional 'information as noted above) to staff on Wednesday, December 14, 2011.
Item # 2.
January 5, 2012
ITEM NO.: 2
NAME: Riverdale Addition Replat of Tract D-2A-R and Tract E-2-R2
LOCATION: Located on the east side of Riverfront Drive at Cedar Hill Road
DEVELOPER:
Alltel Communications, LLC
1 Allied Drive
Little Rock, AR 72202
ENGINEER -
Development Consultants, Inc.
2200 North Rodney Parham Road, Suite 220
Little Rock, AR 72212
AREA: 24.69 acres
CURRENT ZONING
PLANNING DISTRICT
CENSUS TRACT:
.: S-57-UU
NUMBER OF LOTS: 2 FT. NEW STREET: 0 LF
0-2, Office and Institutional District & 0-3,
General Office District
4 — Heights Hillcrest
15
VARIANCES/WAIVERS REQUESTED:
1. A variance from Section 36-280(e)(1) to allow a reduced side yard setback.
2. A variance from Section 36-502 to allow the creation of lots with parking less than
typically allowed per the zoning ordinance.
A. PROPOSAL/REQUEST./APPLICANT'S STATEMENT:
The applicant is requesting a replat of 24.69 acres of property on the
Alltel/Verizon campus in the Riverdale Addition. The majority of the property has
been previously platted as several tracts in the Riverdale Addition. The proposal
is to recombine these tracts into two new tracts. The purpose of the replat is to
create new lots/tracts so that the buildings are entirely within a lot of record and
lot lines no longer run through the buildings.
January5, 2012
SUBDIVISION
ITEM NO.: 2 Cont. FILE NO.: S-57-UU
The request includes a variance to allow a zero side yard setback between
proposed Tracts E-2-R-2 and D-2A-R, adjacent to the area of the buildings
connection via the canopy/covered walkways. There is also a variance to allow
on -site parking less than that typically required. The lots will be served by a
cross access agreement being completed. Should additional parking be required
the owner will construct additional parking located to the west of the site, across
Riverfront Drive.
B. EXISTING CONDITIONS:
The site is developed as an office campus with a number of buildings; some
attached by covered walkways. The area contains a mixture of office,
office/warehouse, commercial and residential uses. To the south are mini -
storage units, office and office/warehouse uses and the Jr. Deputy Ball Field.
West of the site, across Riverfront Drive is an open field zoned C-3, General
Commercial District currently being used as soccer fields (also being considered
on this agenda for a preliminary plat approval Item #1 File No. S-57-TT). North
of the campus are condominium residential units and further north are detached
single-family homes. Northwest of the site is an office building and further north
is a school.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has not received any comment from area residents. All
abutting property owners were notified of the public hearing. There is not an
active neighborhood association located in the area.
D. ENGINEERING COMME
PUBLIC WORKS CONDITIONS:
1. Repair or replace any curb and gutter or sidewalk that is damaged in the
public right-of-way prior to occupancy.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available to this project.
for the existing sewer main located in Cedar
Wastewater Utility for additional information.
Entergy: Approved as submitted.
Center -Point Energy: No comment received.
10-foot sewer easement required
Hill Road. Contact Little Rock
2
January 5, 2012
SUBDIVISION
ITEM NO.: 2 Cont. FILE NO.: S-57-UU
AT & T: No comment received.
Central Arkansas Water: Central Arkansas Water retains all water line
easements as shown on the replat. All Central Arkansas Water requirements in
effect at the time of request for water service must be met. Contact Central
Arkansas Water regarding the size and location of the water meter. If there are
facilities that need to be adjusted and/or relocated, contact Central Arkansas
Water. That work would be done at the expense of the developer. Due to the
nature of the facility, installation of an approved reduced pressure zone backflow
preventer assembly (RPZ) is required on the domestic water service. This
assembly must be installed prior to the first point of use. Central Arkansas Water
requires that upon installation of the RPZ assembly, successful tests of the
assembly must be completed by a Certified Assembly Tester licensed in the
State of Arkansas and approved by Central Arkansas Water. The test results
must be sent to Central Arkansas Water's Cross Connection Section within ten
days of installation and annually thereafter. Contact the Cross Connection
Section at 377-1226 if you would like to discuss backflow prevention
requirements for this project. The facilities on -site will be private.
County Planning: No comment.
CATA: The site is located on CATA Bus Route # 21 — The University Avenue
route.
Parks and Recreation: No comment received.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division: No comment.
Landscape: No comment.
G. SUBDIVISION COMMITTEE COMMENT: (December 8, 2011)
Mr. Robert Brown of Development Consultants was present representing the
request. Staff presented an overview stating there were few outstanding
technical issues associated with the request. Staff stated the plat was to create
separate parcels for the existing buildings. Staff stated the request included
variances to allow reduced building setbacks and parking less than typically
allowed on the individual lots. Staff stated there would be a cross access
agreement between the lots. Mr. Brown stated there would most likely not be a
cross parking agreement.
K!
January 5, 2012
SUBDIVISION
ITEM NO.: 2 Cont. FILE NO.: S-57-UU
Public Works comments were addressed. Staff stated any broken curb, gutter or
sidewalk damaged in the public right of way would require repair. Staff stated
easements were required for all stormwater drainage areas.
There was no further discussion of the item. The Committee then forwarded the
item to the full Commission for final action.
H. ANALYSIS:
The applicant submitted a revised plat to staff addressing the issues raised at the
December 8, 2011, Subdivision Committee meeting. The applicant has indicated
any broken curb, gutter or sidewalk damaged in the public right of way will be
repaired prior to occupancy.
The site is the former Alltel Campus which was developed as a single ownership
on multiple platted lots and viewed as a single zoning lot. The applicant is
seeking the revision to the plat to allow for future sale of buildings contained on
individual lots. The plat will allow the reconfiguration of two (2) previously platted
lots to allow a reduced side yard building setback on Tracts D-2A-R and E-2-R2.
The buildings are connected by a canopy which results in a side yard building
setback of zero where the connection is made.
With the future sale of buildings the site will longer be viewed as one (1) zoning
lot. According to the applicant, cross access agreements will be implemented for
the newly created lots. There will be cross access but there will most likely not
be cross parking rights on all properties. There will be a deed restriction
document that will describe the specific rights of cross access and parking. The
document will be referenced on the plat. The lots are being created in such a
manner that portions of the lots may not have parking on the lot itself to meet the
typical parking requirements of the Zoning Ordinance. The applicant has
indicated should additional parking be required additional parking will be
constructed to the west of the site. Staff is not concerned with the creation of the
lots with parking which does not meet the typical minimum standard due to the
applicant's commitment to provide sufficient parking for these buildings by the
construction of additional parking on vacant property located to the west across
Riverfront Drive.
Staff is supportive of the replat request. To staff's knowledge there are no
outstanding issues associated with the request. The request is to allow a lot line
adjustment within the developed office campus. Staff does not feel the variance
request to allow the zero setback in the area of the canopy connection will
significantly impact the development or the area.
0
January 5, 2012
SUBDIVISION
ITEM NO.: 2 Cont. FILE NO.: S-57-UU
I. STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
Staff recommends approval of the variance request to allow a zero side yard
building setback adjacent to the area of the buildings connected via the canopy.
Staff recommends approval of a variance to allow on site parking less than that
typically required subject to a cross parking agreement being completed or
additional parking being constructed.
PLANNING COMMISSION ACTION:
(JANUARY 5, 2012)
Mr. Robert Brown of Development Consultant, Inc. was present representing the
request. Staff presented the item with a recommendation of approval of the request
subject to compliance with the comments and conditions as outlined in paragraphs D, E
and F of the agenda staff report. Staff presented a recommendation of approval of the
variance request to allow a zero side yard building setback adjacent to the area of the
buildings connected via the canopy. Staff also presented a recommendation of
approval of a variance to allow on site parking less than that typically required subject to
additional parking being constructed should parking become an issue.
There was no further discussion of the item. The Chair entertained a motion for
approval of the item as presented by staff. The motion carried by a vote of 7 ayes,
0 noes and 4 absent.
5