HomeMy WebLinkAboutS-0978 Staff AnalysisJune 1, 1993
ITEM No.: 5 FILE NO.: S- 78
NAME: GCC ADDITION - PRELIMINARY PLAT
LOCATION: North side of Highway 10, north and northwest of the
intersection of Sam Peck Road.
DEVELOPED
GRACE COMMUNITY CHURCH
8201 Cantrell Road
Little Rock, AR 72207
225-0843
ENGINEER•
JOE WHITE
WHITE-DATERS AND ASSOC., INC.
401 victory
Little Rock, AR 72201
374-1666
AREA: 21.7813 ACRES NUMBER OF LOTS: 3 FT. NEW STREET: None
ZONING: MF-12 (0-2 rezoning
to be heard by Board
of Directors on
June 1, 1993 for
front 466± of site.
PLANNING DISTRICT: 1
- CENSUS TRACT: 42.05
VARIANCES REOUESTED: None
STATEMENT OF PROPOSAL:
PROPOSED ❑SES: Offices on front
two lots; church
at rear to be heard
by B.O.D. on
June 1, 1993 for
front and 66± of
site.
The applicant proposes a preliminary plat encompassing 21.78
acres to be subdivided into three lots. The font two lots (2.6
acres and 2.98 acres, more or less) are proposed to be developed
into offices and are in the. process of being zoned 0-2. The rear
acreage is proposed to be developed as a new church facility for
the applicant.
A. PROPOSAL/REQUEST:
Approval by the Planning Commission is requested for a
preliminary plat for the development of a three lot
subdivision. The front two lots are proposed to be
developed as office uses. The rear and major portion of the
property is proposed to be developed for the Grace Community
Church facility. The rezoning request was heard by the
Commission on May 4, 1993 and recommended for approval at
June 1, 1993
SUBDIVISION
ITEM NO.: 5 (Continued) FILE NO.: 78
the June 1, 1993 Board of Directors meeting. The
conditional use for the church is being heard by the
Commission on June 1, 1993. No variances are requested.
B. EXISTING CONDITIONS:
The site is undeveloped and is wooded and overgrown. To the
north is the Arkansas River. At the southeast corner of
Highway 10 and Sam Peck Road is an 0-2 zoned tract.
Otherwise, all of the surrounding property is zoned R-2 and
is undeveloped.
C. ENGINEERING UTILITY COMMENTS:
The Engineering Division comments that`the far west drive
approach is not permitted. Only the one central drive is to
be allowed.
Little Rock Water Works reports that a pro rate front
footage charge of $15.00/foot applies. It is added that on -
site fire protection will be required. Water Works cautions
that a main extension may be required to serve outlots
unless the property has frontage on the 16 inch main on the
west. That main also has a $15.00/front pro rate front
footage charge.
D. ISSUES/LEGAL/TECHNICAL/DESIGN:
A review of the documents submitted reveals the following
deficiencies:
No source of title is given.
There is no indication given of the source of water service
nor the means of wastewater disposal.
The plat does not address the matter of the watercourse
which leaves the tract. It does not show the location nor
the direction of flow of the watercourse; it does not show
the drainage area above the lake; it does not provide a
storm drainage analysis for the watercourse entering and
leaving the plat boundaries.
The plat does not contain a preliminary storm drainage plan
with typical ditch sections.
The plat does not include the names of recorded subdivisions
abutting the proposed subdivision, with plat book and page
number or instrument numbers.
The plat does not show the names of owners of all land
contiguous to the proposed subdivision.
June 1, 1993
SUBDIVISION
ITEM NO.: 5 Continued FILE NO.: S- 78
The proposed location of PAGIS monuments is not shown.
The zoning classification(s) within the plat and of abutting
areas is not shown.
No draft Bill of Assurance is provided.
E. ANALYSIS•
The majority of the required technical documents are
complete, with no major concerns remaining. There should be
no compelling reason for the applicant not to be able to
either meet the requirements or come to an agreement with
staff/utility companies concerning the required
modifications.
F. STAFF RECOMMENDATIONS:
Staff recommends approval of the preliminary plat, subject
to making the changes and additions cited and complying with
the Engineering requirements.
SUBDTVISION COMMITTEE COMMENT: (MAY 13, 1993)
Mr. Joe White of White-Daters and Associates, engineer on the
proposed development, was present to present the item. The
Committee reviewed the site plan and the Engineering staff
offered its comment concerning the far west access point to the
west lot. Mr. White reacted to this comment by stating that the
drive as shown is over 300 feet from the center drive and,
therefore, meets all applicable standards. He concluded that it
meets published standards and ought to be allowed. After briefly
recounting the previous hearing on the rezoning and reviewing the
conditional use for the church, the Committee referred the item
to the full Commission for resolution.
PLANNING COMMISSION ACTION: (DUNE 1, 1993)
This item was included on the Consent Agenda for approval and, as
such, was approved by the Planning Commission with a vote of nine
(9) ayes and no (0) nays to approve the Consent Agenda.
3
0
June 1, 1993
ITEM NO,: 5 _ FILE NO.-:, -978
NAME: GCC ADDITION - PRELIMINARY PLAT
LOCATION: North side of Highway 10, north and northwest of the
intersection of Sam Peck Road.
DEVELOPER:
GRACE COMMUNITY CHURCH
8201 Cantrell Road
Little Rock, AR 72207
225-0843
ENGINEER:
JOE WHITE
WHITE-DATERS AND ASSOC., INC.
401 Victory
Little Rock, AR 72201
374-1666
AREA: 21.7813 ACRES NUMBER OF LOTS: 3 FT. NEW STREET: None
ZONING: MF-12 (0-2 rezoning
to be heard by Board
of Directors on
June 1, 1993 for
front 466± of site.
PLANNING DISTRICT: 1
CENSUS TRACT: 42.05
VARIANCES REQUESTED: None
TATEMENT OF PROPOSAL:
PROPOSED USES: Offices on front
two lots; church
at rear to be heard
by B.O.D. on
June 1, 1993 for
front and 66± of
site.
The applicant proposes a preliminary plat encompassing 21.78
acres to be subdivided into three lots. The font two lots (2.6
acres and 2.98 acres, more or less) are proposed to be developed
into offices and are in the process of being zoned 0-2. The rear
acreage is proposed to be developed as a new church facility for
the applicant.
A. PR_OPOSAWREQUEST:
Approval by the Planning Commission is requested for a
preliminary plat for the development of a three lot
subdivision. The front two lots are proposed to be
developed as office uses. The rear and major portion of the
property is proposed to be developed for the Grace Community
Church facility. The rezoning request was heard by the
Commission on May 4, 1993 and recommended for approval at
June 1, 1993
SUBDIVISION
ITEM n in FILE - 7
the June 1, 1993 Board of Directors meeting. The
conditional use for the church is being heard by the
Commission on June 1, 1993. No variances are requested.
B. EXISTING CONDITIONS:
The site is undeveloped and is wooded and overgrown. To the
north is the Arkansas River. At the southeast corner of
Highway 10 and Sam Peck Road is an 0-2 zoned tract.
Otherwise, all of the surrounding property is zoned R-2 and
is undeveloped.
C. ENGINEERING/UTILITY COMMENTS:
The Engineering Division comments that:the far west drive
approach is not permitted. Only the one central drive is to
be allowed.
Little Rock Water Works reports that a pro rate front
footage charge of $15.00/foot applies. It is added that on -
site fire protection will be required. Water Works cautions
that a main extension may be required to serve outlots
unless the property has frontage on the 16 inch main on the
west. That main also has a $15.00/front pro rate front
footage charge.
D. ISSUES/LEGALITECHNICAL/DESIGN:
A review of the documents submitted reveals the following
deficiencies:
No source of title is given.
There is no indication given of the source of water service
nor the means of wastewater disposal.
The plat does not address the matter of the watercourse
which leaves the tract. It does not show the location nor
the direction of flow of the watercourse; it does not show
the drainage area above the lake; it does not provide a
storm drainage analysis for the watercourse entering and
leaving the plat boundaries.
The plat does not contain a preliminary storm drainage plan
with typical ditch sections.
The plat does not include the names of recorded subdivisions
abutting the proposed subdivision, with plat book and page
number or instrument numbers.
The plat does not show the names of owners of all land
contiguous to the proposed subdivision.
2
June 1, 1993
SUBDIVISION
ITEM NO, 5 (Continued) - FILE
The proposed location of PAGIS monuments is not shown.
The zoning classification(s) within the plat and of abutting
areas is not shown.
No draft Bill of Assurance is provided.
E. ANALYSIS:
The majority of the required technical documents are
complete, with no major concerns remaining. There should be
no compelling reason for the applicant not to be able to
either meet the requirements or come to an agreement with
staff/utility companies concerning the required
modifications.
F. STAFF RECOMMENDATIONS:
Staff recommends approval of the preliminary plat, subject
to making the changes and additions cited and complying with
the Engineering requirements.
SUBDIVISION COMMITTEE QOMMENT: (MAY 13, 1993)
Mr. Joe White of White-Daters and Associates, engineer on the
proposed development, was present to present the item. The
Committee reviewed the site plan and the Engineering staff
offered its comment concerning the far west access point to the
west lot. Mr. White reacted to this comment by stating that the
drive as shown is over 300 feet from the center drive and,
therefore, meets all applicable standards. He concluded that it
meets published standards and ought to be allowed. After briefly
recounting the previous hearing on the rezoning and reviewing the
conditional use for the church, the Committee referred the item
to the full Commission for resolution.
PLANNING COMMISSION ACTION: (JUNE 1, 1993)
This item was included on the Consent Agenda for approval and, as
such, was approved by the Planning Commission with a vote of nine
(9) ayes and no (0) nays to approve the Consent Agenda.
3