HomeMy WebLinkAboutS-0960 Staff AnalysisDecember 15, 1992
ITEM 1�0.: 3 FILE NO.: S-960
NAME: Home Center Addition -- Preliminary Plat
LOCATION: The southwest corner of State Highway 10
at the west end of Taylor Loop Road
DEVELOPER:
NATIONAL HOME CENTER
Highway 67-167
North Little Rock, AR 72116
945-2800
ENGINEER:
WHITE-DATERS AND ASSOCIATES
401 Victory
Little Rock, AR 72201
374-1666
AREA: 17.74 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: R-2 Single Family/PCD PROPOSED USES: Home Center
PLANNING DISTRICT: No. 19
CENSUS TRACT: 42.06
VARIA110ES REQUESTED: None
A. PR0P0SALIREQUEST:
This applicant proposes the platting of a single commercial
lot for purposes of constructing several large buildings for
use as a home center development.
B. EXISTING CONDITIONS:
The existing site is a semi -rural tract of land with open
space to the rear area of the lot, with several homes sited on
the property. This site is abutted on the south by
residential and a church building, to the east and west by
residential properties, some of which have boarding facilities
for horses. The area to the north is occupied as residential
across State Highway 10. The site currently drains in two
directions, a portion to the east across Taylor Loop Road and
a portion of the site draining into a pond adjacent to Highway
10 and discharging beneath the state highway.
C. ENGINEERING/UTILITY COMMENTS:
The Public Works Department reports that a minor arterial
standard is required for Taylor Loop Road, both right-of-way
and improvements. Sidewalks are required on Cantrell Road
frontage and Taylor Loop. Excavation and Detention Ordinances
apply.
F1
December 15, 1992
ITEM NO.: 3 Cont. FILE NO.: S-960
Little Rock Municipal Water Works reports that an on -site fire
protection plan will be required and should be made a part of
the site plan.
Little Rock Waste Water Utility reports that a sewer main
extension will be required with the appropriate easements.
The Hinson Road interceptor tie on charges apply for this
area. Contact should be made with Waste Water Utility for
details.
D. ISSUESILEGALITECHNICALIDESIGN:
In the staffs review of this preliminary plat, a number of
areas were noted which require a follow-up by the architect
and engineer on this project. For sake of brevity, the staff
will not enumerate all the items which were developed in our
review, but will touch on the high points relative only to the
preliminary plat. They are as follows:
1. Taylor Loop improvements and dedication
2. Indicate PAGIS information.
3. Indicate state plane coordinates.
4. Complete certificates should be placed on the plat.
5. Adjacent property owners should be indicated.
6. A Bill of Assurance should be provided for staff review.
7. A commitment should be submitted in writing that this
developer will in the future participate if needed in the
installation cost of the traffic signal for Taylor Loop
Intersection up to 50% of the then established cost.
S. Sidewalks are required along Highway 10 and Taylor Loop
Road.
E. ANALYSIS:
The staff has performed the usual site visits, plan reviews
and distribution for comment. This plat as a freestanding
issue meets the expected standards. However, a plat of this
nature is entirely out of character for a suburban large lot
single family area. There are numerous single family lots
along all of the boundary streets some of which front this
project site. In the staff view of Highway 10, the plan and
overlay standards were geared to shallow development in
transition zones. This site is one quarter mile deep. The
full effect of this depth is not realized until one drives the
east boundary to the church at the south end of the
development.
2
December 15, 1992
ITEM NO.: 3 Cont. FILE NO.: S-960
F. STAFF RECOMMENDATIONS:
Denial of the plat as being inappropriate for the location.
SUBDIVISION COMMITTEE COMMENT: (NOVEMBER 25, 1992)
The developer, the architect and engineer were present. The
Planning staff offered a brief overview of the number of items
included in the staff outline of issues. Most of the items on the
list were identified by the developer as items which could be
easily remedied or had been. A lengthy discussion involving the
design of the buildings, their height and appearance involved both
staff and the applicant. The engineer for the project, Mr. White,
pointed out several points of resolution such as the residential
street along the southern boundary and how that roadway and its
improvement might be accomplished. The screening, landscaping and
site package dealing with appearance was presented by the design
staff for the developer.
A brief discussion included the manner in which traffic accesses
the State Highway No. 10. The apparent potential for traffic
backup or conflict with the manner in which the interior parking is
designed. There being no apparent problem with resolving the
several issues attendant to the plat, the Subdivision Committee
forwarded this item to the full Commission for final resolution.
jj,G t/u/A 1j /0
FQ65T LF.✓c (rvT
L iU
TRS 2N,14W•24
PD
CT
Ek
Preliminary Plat
{ten
Home Center Addition Nimt
S-960 3
12/�
December 15, 1992
ITEM NO.: 5 FILE NO.: Z-5646
NAME: Home Center - Planned Commercial District
LOCATION: SW corner of State Highway No. 10 and the west
intersection of Taylor Loop Road
DEVELOPER•
ENGINEER•
MARVIN ITZKOWITZ WHITE-DATERS AND ASSOCIATES
BY NATIONAL HOME CENTER 401 Victory Street
Little Rock, AR 72201
374-1666
AREA: 17.74 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: R-2/PCD PROPOSED USES: Home Center and Allied
Activity
PLANNING DISTRICT: No. 19
CENSUS*TRACT: 42.06
VARIANCES REQUESTED: None
STATEMENT OF PROPOSAL:
This applicant proposes the construction of a National Home Center
store. The exterior of the building front wall along Highway 10
will be of cut concrete stone with the remaining walls around the
east, west and south of texture steel. The height of all buildings
is 24 feet with the roofing of metal construction at 12/2 pitch.
All buildings will be of a light buff color with roofing in a dark
brown. There will be two main building entrances and exits located
across the front of the main building. Lawn and garden facilities
will run down the east side with a contractor's showroom
immediately behind. The design of this project is as a closed
compound with the materials courtyard completely enclosed, with
one controlled entrance.
The main building will comprise some 102,000 square feet of
customer showroom, 10,000 square feet of contractor's sales and
showroom, 57,000 square feet in warehouse and 30,000 square feet
of lawn and garden facilities of which 15,000 square feet will be
covered. The facility will include a full vehicle maintenance
shop. The enclosed compound will also house a fuel station for
delivery vehicles. All open areas are to be planted and maintained
in addition to the frontage Highway 10 which will be burmed,
planted and sprinkled. The facility will employ between 165 and
175 persons.
1
December 15, 1992
ITEM NO.: 5 Cont. FILE NO.: 2-5646
This site was located at the intersection of two arterial streets
because it will provide easy accessibility for future construction
sites in West Little Rock. This facility is proposed to serve a
market radius of approximately 50 miles involving Perry County,
Saline County and other counties within this radius.
A. PROPOSAL RE UEST:
This application was filed as a planned commercial district in
order to approach the subject of modification of the Highway
10 land use plan and to incorporate an additional commercial
node at two arterial streets. The application is for a major
home center with significant building materials sales and
delivery. The site is a large tract of land currently
residential in nature and surrounded by residential occupancy.
B. EXISTING CONDITIONS:
The property is residential in nature with several residential
structures in place. To the south along a narrow residential
street is a church and several homes. To the west are large
homes on large residential lots. To the east and north are
residential occupancies. The land is rolling terrain with a
pond and several highpoints.
C. ENGINEERING UTILITY COMENTS:
Public Works Department reports that minor arterial
right-of-way and improvements are required for Taylor Loop
Road. Sidewalks are required on Cantrell Road frontage. The
Excavation and Detention Ordinance applies.
Little Rock Water Works reports that on -site fire protection
will be required reflecting the location of fire hydrants and
main sizes.
The Waste Water Utility reports that a sewer main extension
will be required with appropriate easements. This will tie to
the Hinson Interceptor charges apply for this area. Contact
should be made with the Waste Water Utility for detail.
D. ISSUES LEGAL• TECHNICAL• DESIGN:
The staff review of this planned unit development reflects a
number of areas of design concern. Many of these have been
discussed with the applicant with resolution to be gained
prior to the public hearing of the Commission on December 15.
At this writing, these items remain for discussion until the
site plan has been updated to resolve them.
2
December 15, 1992
ITEM NO.: Cont. FILE NO.: Z-5646
The items are as follows:
I. The Highway 10 entrance drive should be redesigned to
work better with the existing front parking lot to
provide for elimination of potential conflict between
cars entering and exiting, especially with respect to the
single loaded row of parking spaces in the middle of the
parking lot.
2. The design of this project brings truck traffic down a
residential street (Taylor Loop Road). This issue should
be resolved through provision of information concerning
the hours of operation of the trucks and access to the
warehouse facility. This should be provided in writing.
3. Identify the purpose or use of the shallow depth of the
building along the east boundary of the warehouse.
4. Identify the purpose of the gap in the building lying
along the west side of the development by notation on the
drawing.
5. Information should be provided on the garden center as to
the design and finish of the exterior walls, and whether
exterior storage or display along the sidewalk area will
be provided. This should be noted on the plan.
6. The boundary buffer on all sides of the project appear to
be deficient. This should be resolved through working
with Bob Brown of the Landscape Office.
7. A treatment plan should be submitted for the buffer and
screening areas.
S. A section through the site along the north -south axis
should be provided reflecting the treatment on the site
with plantings to break up the building mass. This is
especially important due to the lack of existing mature
timber which will remain and break up the mass of a
24 foot tall structure of this length.
9. A drainage treatment plan should be provided.
10. The location of the fuel tanks to serve the fueling
station should be indicated on the drawing.
11. Reflect on the site plan a fire fighting system
indicating fixtures, hydrants and line sizes.
12. The building roofline treatment should be indicated by
use of insets or typical illustrations on the site plan.
3
December 15, 1992
S
ITEM NO.: 5(Cont.)FILE NO.: Z-5646
13. Identify the large paved apron in the front of the
building as part of the building closed floor space.
14. A treatment plan for the improvement of Forest Lane
should be indicated, if it is to be improved.
15. Remove the concrete access aprons in the curb line along
Highway 10, serving existing driveways.
16. A site lighting plan
E. ANALYSIS•
The staff has performed the usual site visits, plan reviews
and distribution for comment. We have held a meeting with the
developer and his design professionals for purposes of
developing the request to the fullest, in order to gain a base
upon which to base our judgment.
Staff concentrated its analysis in four areas. These were
land use, traffic, site design and building mass.
Land Use
The current Highway 10 Plan indicates transitional and
expansive amounts of residential. Established commercial
nodes are centered well away from this corner. The intended
commercial use is not compatible with residential. It cannot
be made compatible on this site such as Harvest Foods was
accomplished at the east end of Taylor Loop.
This change would have a major detrimental effect on the plan.
It would make the areas adjacent to the west unsuitable as
residential. The Highway 10 Plan and overlay standards were
written to make nonresidential compatible with residential
through certain use types and increased design standards. The
other commercial nodes such as Candlewood (Kroger) Center are
not this intense.
Traffic Circulation:
Even though a five lane arterial, Highway 10 is not an
interstate. A tremendous amount of truck traffic would have a
negative effect on an already heavily traveled arterial. The
existing nodes on the plan when fully developed will use the
roadway capacity.
Site Design and Building Mass
The building plan offered cannot utilize the existing
landscaping or terrain. The main building will be on
about ten feet of fill. The finished floor elevation of
4
December 15, 1992
ITEM NO.: 5 Cont. FILE NO.: 2-5646
the retail sales area (Highway 10 front of building) will
be perhaps 15 feet above the curb line of Highway 10. The
building facade will be about forty feet in height above that
point.
The building of 200,000 square feet or more will not be
screened by the planting proposed for fifteen or twenty years.
The building long axis, north to south of 1,100± feet with one
small break will be to big for this neighborhood and present a
significant visual blight.
The site design, with respect to certain elements, landscaping
and setback generally meets the overlay standards. However,
development of this magnitude and character was never
considered along Highway 10. The changing of the terrain and
denuding the site makes the overlay standards useless.
F. STAFF RECOMMENDATIONS:
Denial of request for the many reasons set forth in our
analysis.
SUBDIVISION COMMITTEE COMMENT:
(NOVEMBER 25, 1992)
The applicant was present as well as the architect and engineer for
the project. There was a lengthy discussion of this proposal in
concert with the preliminary plat proposed for the 17 acres.
Planning staff identified the number of issues that remained to be
resolved from the total list of some 31 issues. The staff read
this list and identified its concerns for those which had not been
resolved. The applicant and the design professionals present
indicated that these points could be resolved prior to the public
hearing of the Planning Commission or they had been resolved
already.
The Committee raised numerous questions concerning the landscaping,
the height of the buildings, the lighting plan for the parking
lots, especially along the eastern property boundary. The
applicant offered some graphic material which indicated the
exterior wall treatment with elevations and landscaping material
identified. This issue was identified as being more a land use
question than a site design issue, however the two are intertwined
and the specific design of this project will have significant
baring on the appropriateness of the change in zoning for this
corner. Staff identified the site plan process as a means to
develop a good end product and that how it develops does not
decide land use appropriateness.
A brief discussion followed wherein several commissioners and
staff discussed the possibility or probability of the extension of
Taylor Loop Road to the south and west tying State Highway No. 10
December 15, 1992
ITEM NO.: 5(Cont.)FILE NO.: Z-5545
into the Chenal Valley development. There were several persons
present offering comment's concerning the development potential of
the existing properties they owned or represented which indicated
that the road connection could possibly occur in a short term.
They felt extension of that arterial street to Chenal Parkway
would support the need for a traffic signal for Highway 10 at
Taylor Loop and the possibility of a land use modification of
the Highway 10 Plan.
Specific resolution was not gained on any of the
discussed; however, the applicants reported they
resolution of each. The Committee then forwarded
the full Commission for final resolution.
several subjects
would pursue
this item to
11
TR8
PD
CT
1
T.ecr A
�Z
S�
ti �J
� M,. rrri nt s
M
V
1
�
1��
�{
1
4
Planned Commercial Development (PCD)
2N,14W,24
Z-5646
Home Center
Short Form P.C.D.
ITEM No.
12/92
TRS
PD
CT
a
LU
M
m
Area Zoning
Z-5646 �, ITEM NO.
Home Center N
Short Form P.C.D. 5
12/92