HomeMy WebLinkAboutS-0916-A Staff AnalysisDecember 3, 1998
ITEM NO.: 11 FILE NO.: S-915-A
NAME: Arkansas Electric Cooperative Corp. - Subdivision
Site Plan
LOCATION: 8,000 Scott Hamilton Drive; near the southwest corner
of Scott Hamilton Dr. and Interstate 30
DEVELOPER:
ENGINEER•
AR Electric Cooperative Corp. Steve Sharp, P.E.
8000 Scott Hamilton Dr. P. O. Box 194208
Little Rock, AR 72209 Little Rock, AR 72219-4208
AREA: 125 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: I-2 ALLOWED USES: Light Industrial
PROPOSED USE: Light Industrial
VARIANCES/WAIVERS REQUESTED:
1. Waiver of right-of-way dedication and cul-de-sac construction
at the end of Community Lane.
2. Deferral of street improvements to Scott Hamilton Drive.
BACKGROUND:
Arkansas Electric Cooperative Corporation (AECC) provides
wholesale electrical energy and services to member electric
cooperatives around the state. The continued steady growth of
AECC has required additions to staff and existing facilities.
The AECC is proposing several new buildings and building
additions to its current site. Due to the fact that this is a
multiple building site plan, Planning Commission approval is
required.
A. PROPOSAL/REQUEST:
The applicant is proposing short-term and long-term
additions to the property. The short-term additions include
new building construction over the next three (3) years.
The largest short-term project will be the new office, board
room and lobby addition to the existing office building near
the northeast corner of the property. This addition will be
approximately 24,000 square feet and 3 stories in height.
December 3, 1998
SUBDIVISION
ITEM ND • 11 (Cant.) FILE NO.: S-916-A
Several other smaller buildings and building additions will
be made during the short-term phase, as noted on the site
plan. Small areas of parking will be added to serve some of
the new buildings. A new 180 space parking area will be
constructed at the west end of the existing office building
to serve the additional office space.
The long-term additions show the anticipated growth and
expansion over the next 15 to 20 years. Long-term additions
include a new two-story office building just south of the
existing office building (which fronts on I-30), a new
warehouse building, a new electrical equipment building, and
several smaller buildings. Several new parking areas will
also be added to serve the new buildings. All of the
proposed buildings will be less than 45 feet in height.
B. EXISTING CONDITIONS:
The site contains several existing buildings and parking
areas. The existing complex is concentrated on
approximately 40 acres of the 125 acre site. The
southernmost 40 acres which fronts on Baseline Road is
vacant and heavily wooded as is the majority of 14.5 acres
which fronts on Scott Hamilton Drive. A large portion along
the western perimeter (25± acres) is also undeveloped.
These undeveloped areas are not included in the 15 to 20
year development plan.
The general area contains a mixture of uses, including
single-family residential, commercial and industrial.
Single-family residences are located along the southwest and
southeast perimeters of the property.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has received no negative comments
from the neighborhood. The Upper Baseline Neighborhood
Association was notified of the public hearing.
D. ENGINEERING COMMENTS:
Public Works Conditions:
1. Provide public access easement and/or dedication of
right-of-way and construct cul-de-sac or other approved
construction to allow vehicles to turn -around prior to or
on existing property at the end of W. 81" Streets and
Community Cove.
2. Provide details of entry off I-30 frontage to Traffic
Engineer for approval.
3. Construct detention with Phase I Construction and account
2
December 3, 1998
SUBDIVISION
ITEM NO.: 11 Cont. FILE NO.: S-916-A
for previous construction where detention was deferred.
4.Dedicate right-of-way to 45' from centerline and repair
existing curb on Baseline Road.
5.Dedicate right-of-way to 45, from centerline and improve
Scott Hamilton to minor arterial standards with Phase I
Construction.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available, not adversely affected.
AP&L: No Comment received.
ARKLA: No Comment.
Southwestern Bell: No Comment.
Water: Additional fire protection will be required for
future phases.
Fire Department: No Comment.
County Planning: No Comment received.
CATA: Served by CAT Route #15 (65`h Street). No
foreseeable adverse impacts on transit.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division: No Comment.
Landscape Issues:
Areas set aside for buffers meet with ordinance
requirements.
The proposed large parking lot (at the new electrical
equipment building) does not provide for building
landscaping. If this parking lot is to be used for public
parking, then landscaping will be needed between the parking
and building flexibility is allowed with this requirement.
If the screening is not currently in place adjacent to the
mobile home park to the east, then it should be provided.
This screen may be a wooden fence with its face directed
outward or dense evergreen plantings.
The City Beautiful Commission recommends saving as many
trees as feasible. Extra credit toward fulfilling ordinance
requirements can be given when saving trees of six inch
caliper or larger.
G. ANALYSIS•
All of the new buildings and building additions shown on the
proposed site plan comply with all setback and height
requirements of the City's Zoning Ordinance. The proposed
3
December 3, 1998
SUBDIVISION
ITEM NO.: 11 (Cont.) FILE NO.: S-916-A
site plan shows no planned construction within the 50 foot
OS buffer along the southern portion of the east property
line nor within the 200 foot wide R-2 zoned buffer along the
west property line. The applicant is proposing to plant
additional evergreens within the OS buffer area just west of
Community Lane to aid in screening the adjacent residential
uses.
The total proposed office space (after long-term additions)
near the northeast corner of the property will require
approximately 219 parking spaces. The site plan shows 280
parking spaces in this area, with additional small parking
areas to serve the smaller buildings throughout the site.
There should be no parking issues associated with the site
plan.
The applicant is requesting a deferral of street
improvements to Scott Hamilton Dr. along their property
frontage and a waiver of right-of-way dedication and street
improvements to Community Lane. Public works supports a
deferral of street improvements to Scott Hamilton Dr. for 5
years or until development of adjacent property along Scott
Hamilton Dr. Public works also supports the waiver of
right-of-way dedication and street improvements to Community
Lane based on the fact that the improvements would encroach
into the OS buffer area and the applicant does not wish to
access the property from Community Lane.
Otherwise, staff can foresee no issues left to be resolved
and feels that the proposed development plan will have no
adverse effect on the general area.
H. STAFF RECOMMENDATIONS:
Staff recommends approval of the site plan subject to the
following conditions:
1. Compliance with the requirements as noted in paragraphs
D, E and F of this report.
2. Any site lighting must be low-level and directed away
from adjacent property.
3. None of the existing vegetation should be removed from
the OS strip along the east property line nor the 200
foot R-2 strip along the west property line.
4. Staff recommends approval of the deferral of street
improvements to Scott Hamilton Dr. as noted in paragraph
G.
5. Staff also recommends approval of the waiver of right-of-
way dedication and street improvements to Community Lane.
4
December 3, 1998
SUBDIVISION
ITEM NO.: 11 (Cont.
SUBDIVISION COMMITTEE COMMENT:
FILE NO.: 5-916-
(NOVEMBER 5, 1998)
Steve Sharp and Hank Kelley were present, representing the
application. Staff briefly reviewed the site plan. Hank Kelley
gave an overview of the development plan.
Bob Turner, of Public works, reviewed his departments,
requirements. Mr. Sharp indicated that a deferral of the
improvements to Scott Hamilton Drive would be requested as would
a waiver for the Community Lane right-of-way dedication and
street improvements. Mr. Sharp also stated that some of the
stormwater detention facilities would be constructed with the
short-term phase.
In response to a question from staff, Mr. Sharp noted that only
employees will have access to the portion of the development
which is south of the main office building.
Staff noted that the 50 foot undisturbed open space buffer along
the south portion of the east property line must be maintained.
Staff noted that if a cul-de-sac were' constructed at the end of
Community Lane it would intrude into this open space area.
After the brief discussion, the Committee forwarded the site plan
to the full Commission for final action.
PLANNING COMMISSION ACTION:
(DECEMBER 3, 1998)
Staff presented a positive recommendation on this application, as
there were no further issues for resolution. There were no
objectors to this matter.
The Chairman placed the item before the
within the Consent Agenda for approval
A motion to that effect was made. The
7 ayes, 0 nays and 4 absent.
Commission for inclusion
as recommended by staff.
motion passed by a vote of