HomeMy WebLinkAboutS-0818-B Staff AnalysisAugust 28, 1990
SUBDIVISION
ITEM NO.: 3 FIL_E NO.: S-818-B
NAME, Tr i g c n Add i t i on - Rep I a t
LOCATION: Baseline Road Sibley Hole Road and I-430
DEVELOPER: ENGINEER:
Trigon Properties
3520 West 69th Street
Little Rock, AR
562-6064
Samuel Davis
5301 West 8th Street
Little Rock, AR 72206
664-0324
AREA: 4.2 Acres NUMBER OF LOTS: 3 FT. NEW STREET: 0
ZONING: I-2 PROPOSED USES: Industrial
PLANNING DISTRICT: Otter Creek
CENSUS TRACT: 41.03
VAR I_AIYCES.. REQUESTED :
1. All street improvements on Baseline Road.
A. PROPOSAL/REQUEST:
This applicant proposes a four -lot replat involving
industrial lots, presently zoned 11I-211. Owner of this
tract has immediate plans for development of Lot 1-R
with the construction of a 10,000 square foot office
and warehouse building. Lot 2-R and 3-R will remain
undeveloped at the present time, but will be available
for sale and future development.
B. EXISTING CONDITIONS:
This tract of land has been cleared and prepared for
construction. The principal arterial lying along the
south boundary is a two lane road with ditches on both
sides. The Sibley Hole Road is constructed to the
county standards and will serve as an access road to
Lot 1-R and 2-R.
C. ENGINEERING COMMENTS:
No Comments.
1
August 28, 1990
SUBDIVISION
ITEM -.NO. 3 Continued
D. I S_SUES /LEGAL,/TECHN. CAL/_DES IGv :
None.
R. ANALYSIS:
The Planning Staff's review of the site reveals no
problems with the proposal as presented.
F. STAFF RRCOMMRNDATION:
Staff recommends approval of the replat with
recommendation of the waiver approval.
SUBDIVISION COMMITTEE_ REVIEW: (August 16, 1990)
_..... ................ ..
The application was represented by Mr. Davis and Mr. Jim
Rhodes. The Staff recommendation was discussed. Mr. Davis
described the plat and various elements of the proposal. He
indicated that this plat is a preliminary plat for all lots
and final plat for Lot #1. He stated that Lot #2 and #3
will be final plated when sold for development.
Mr. Gardner suggest showing phasing on the plat to allow
final platting in the future.
Mr. Davis agreed to revise his plat before the Public
Hearing. There being no further discussion, the matter was
forwarded to the full Commission for resolution.
PLANNING COMMISSION ACTION:
(August 28, 1990)
There were no objectors in attendance. The Staff
recommended placement of this item on the consent agenda for
approval of the revised preliminary plat for Lots 1, 2, and
3 and final plat for Lot 1 with Staff support to deferral of
all street improvements until future development occurs on
Lot 3. A motion was then made to that effect. The motion
was passed by a vote of 10 ayes, 0 nays, and 1 absent.
2