HomeMy WebLinkAboutS-0801-G Application3. There is a " recommend" comment by the fire department concerning the cul-de-sac
radius. Our design meets the standards given in the subdivision ordinance. WE
DO NOT AGREE TO THIS ITEM AS A RECOMMENDATION AND REQUEST THAT
THE STAFF CLARIFY AND SPECIFICALLY REQUEST AS A CONDITIONAL
REQUIREMENT ANY RECOMMENDATIONS" THAT ARE INCORPORTATED INTO
THE APPROVAL MOTIONS AND STATEMENTS, BY THE PLANNING COMMISSION,
PRIOR TO THEIR VOTE.
Thank you for your assistance in this matter.
Sincerely,
Development Consultants, Inc.
Robert . Br
Vice P esident
cc: Chester Phillips
David Jones
l Q6Veii�",
FA
wjn f-0&1
0
'6 1Av
-47` III 0l6
h/rmb/97-164d.doc
DEVELOPMENT
CONSULTANT'S
INCORPORATED
October 15, 1997
Mr. Richard Wood
Department of Planning & Development
City of Little Rock
723 West Markham Street
Little Rock, AR 72
RE: Westrock Office Addition
Revised Preliminary Plat
DCI Project # 97-164
Dear Richard:
I am providing this memo to follow up on the two issues we discussed at the subdivision hearing.
These items are outlined as follows:
1. Phasing Plan: We confirm that we are requesting to dedicate right-of-way and
develop street for Executive Center Court in two phases. The south + 457 feet to be
developed first and the northern portion at a later date. All remaining lots (4 - 15) will be
platted individually. We understand that road improvements must be in place, or duly
guaranteed, on these lots to obtain your signature for final plat approval. We also agree
to provide some form of master map or combined plat that will express the final overall
layout of the adjustments and platting of so many individual lots.
2. Lot 10 & 11: 1 have verified that the chord distance at the building line across lots 10
& 11 is greater than 100 feet, per your request.
Engineering • Planning
Land Surveying
Landscape Architecture
2200 North Rodney Parham Road
Suite 220
Little Rock, Arkansas 72212-4155
Telephone 501-221-7880
Fax # 501-221-7882
h/rmb/97-164d.doc
DEVELOPMENT
CONSULTANTS
INCOR.PORA.T'ED
January 10, 1996
Mr. Bobby Sims
Department of Neighborhoods & Planning
723 West Markham Street
Little Rock, Arkansas 72201
RE: Westrock Addition Preliminary Plat Application
DCI Project #95-190
Dear Bobby:
Pursuant to our comments at the subdivision committee and planning commission meetings, we
have made revisions to the plat drawings and provide this letter of response. Six blueline prints
are provided of the plat drawings. The following items are addressed from the subdivision
meeting agenda:
ITEMS REQUIRING ACTION:
1. Average and minimum lot sizes have been added to the information block on the plat
drawing.
2. A copy of the existing covenants and restrictions by previous owners that are assumed by
the current owners, Westrock Partnership.
3. A vicinity map has been added to the drawing.
4. Preliminary storm drainage information has been added to the topography and drainage
sheet. No permanent drainage facilities are proposed to be constructed with ditches.
5. The physical description of all existing survey monuments have been added to the plat
drawing. Proposed PAGIS monument locations have also been added. The work "PAGIS"
appears next to those lot comers.
6. Certifications have been executed.
7. Lot 8 has been removed from the plat and is now a part of the right-of-way for the western
side of Bowman Road.
Engineering ° Planning
Land Surveying
Landscape Architecture
10809 Executive Center Dr.
Suite 210
Little Rock, AR 72211-6021
Telephone 501-221-7880
Fax # 501-221-7882
Page 2
1110/96
Mr. Bobby Sims
8. A new horizontal and vertical alignment for the relocation of Bowman Road has been
negotiated with LRDPW. The new alignment is now shown and lot layout has been adjusted
accordingly.
9. Bowman Road right-of-way will be dedicated at this time as a part of the rezoning request.
Right-of-way dedication includes area for a northbound deceleration lane on the east side of
Bowman at Executive Center Drive. The owners will meet obligations for construction of
Bown Road improvements related to Lots 4, 5 & 7 as those lots are platted. The existing
alignment will remain under an access easement for the public use until the new roadway is
complete.
10. A temporary intersection improvement has been shown at the intersection of Executive
Center Drive and Bowman Road. These improvements will provide for turn lanes on
Bowman and will restrict traffic to right turn only movements onto Bowman. These
improvements will remain until the new Bowman alignment and Executive Center extension
is constructed and open to traffic.
11. A stormwater detention analysis has been added to the Topography & Drainage sheet.
Preliminary locations for detention ponds have been shown.
12. Water main extension have been relocated to the new road alignment locations.
13. The request by AP&L to dedicate an additional 15 foot easement along all street frontages
may not be truly necessary. We would prefer not to allow overhead power lines along the
street frontages of this addition. Power poles are currently located along the east and west
sides of Bowman. Other easements are proposed along the rear and side yard lines that will
allow cross connections to Bowman and services to the lots. These easements may be
increased if necessary. We wish to defer showing any additional easements at this time and
will determine service routes where easements are essential by the time of final platting.
14. A revised phasing note is provided. Executive Center Drive and Lots 1, 2, 3 & 6 will be
platted in Phase I. The Bowman right-of-way will be dedicated at this time. Lots 4, 5 & 7
will be platted individually. Again, obligations for Bowman improvements will be met as
those lots are final platted.
All other items concerning topography, existing and proposed utilities, existing features,
water source, wastewater disposal, owners, source of title, sidewalks, etc. were addressed on
the original application submittal. Please contact my office immediately if you have any
additional questions. We appreciate your assistance with this matter.
Sincerely,
De pmCsultants, Inc.
Ro
Vice President
cc: David Jones
rm b/5190si m
]DEVELOPMENT
CONSULTANTS
LNCOP.PORATED
October 15, 1997
Mr. Richard Wood
Department of Planning & Development
City of Little Rock
723 West Markham Street
Little Rock, AR 72
RE: Westrock Office Addition
Revised Preliminary Plat
DCI Project # 97-164
Dear Richard:
I am providing this memo to follow up on the two issues we discussed at the subdivision hearing.
These items are outlined as follows:
1. Phasing Plan: We confirm that we are requesting to dedicate right-of-way and
develop street for Executive Center Court in two phases. The south + 457 feet to be
developed first and the northern portion at a later date. All remaining lots (4 - 15) will be
platted individually. We understand that road improvements must be in place, or duly
guaranteed, on these lots to obtain your signature for final plat approval. We also agree
to provide some form of master map or combined plat that will express the final overall
layout of the adjustments and platting of so many individual lots.
2. Lot 10 & 11: 1 have verified that the chord distance at the building line across lots 10
& 11 is greater than 100 feet, per your request.
Engineering • Planning
Land Surveying
Landscape Architecture
2200 North Rodney Parham Road
Suite 220
Little Rock, Arkansas 72212-4155
Telephone 501-221-7880
Fax # 501-221-7882
h/rmb/97-164d.doc
3. There is a " recommend" comment by the fire department concerning the cul-de-sac
radius. Our design meets the standards given in the subdivision ordinance. WE
DO NOT AGREE TO THIS ITEM AS A RECOMMENDATION AND REQUEST THAT
THE STAFF CLARIFY AND SPECIFICALLY REQUEST AS A CONDITIONAL
REQUIREMENT ANY RECOMMENDATIONS" THAT ARE INCORPORTATED INTO
THE APPROVAL MOTIONS AND STATEMENTS, BY THE PLANNING COMMISSION,
PRIOR TO THEIR VOTE.
Thank you for your assistance in this matter.
Sincerely,
Develo ent Consu tants, Inc.
Robert . Sr
Vice P esident
cc: Chester Phillips
David Jones
h/rmb/97-164d.doc