HomeMy WebLinkAboutS-0801-A Staff AnalysisDecember 12, 1995
ITEM NO.: 2 FILE NO.: S-Sol-A
DAME: WESTROCK OFFICE ADDITION -- PRELIMINARY PLAT
LOCATION: Between Centerview Drive and S. Bowman Road, west of
the present end of Executive Center Drive, approximately 0.4 mile
south of Kanis Road
DEVELOPER:
ENGINEER:
WESTROCK PARTNERSHIP Robert Brown
C/o David Jones DEVELOPMENT CONSULTANTS, INC.
11219 Financial Center Parkway, 10809 Executive Center Dr.,
Suite 300 Suite 210
Little Rock, AR 172211 Little Rock, AR 72211
225-6018 221-7880
AREA: 56.96 ACRES NUMBER OF LQTS: 8 FT. NEW STREET: 1,595
ZONING: 0-1, 0-3, MF-12, PROPOSED USES: General Office
R-2, & OS
PLANNING DISTRICT: 11
CENSUS TRACT: 24.04
VARIANCES REQUESTED:
1. Approval of a deferral of the requirement to dedicate
right-of-way for and realign Bowman Rd. to the adopted
alignment, as provided for in the Master Street Plan.
2. Approval of a waiver of the requirement to construct
the full width of Bowman Rd. to Master Street Plan
standards, with sidewalks along both sides of the
roadway, within the realigned right-of-way.
STATEMENT OF PROPOSAL:
The applicant proposes a preliminary plat of a 56.962 acre tract,
to include 8 lots and the construction of approximately 1,595
feet of commercial streets. The lots range in size from one at
2.86 acres to one at 10.38 acres, with the average lot size being
6.51 acres. The lots will have frontages on Centerview Dr.,
Executive Center Dr., or on Bowman Rd. It is proposed that, with
the submitted preliminary plat, Bowman Rd. be left in its
existing alignment; that dedication of right-of-way to Minor
Arterial Standards (90 feet in width) and construction of a 60-
foot wide Minor Arterial Street for Bowman Rd. be provided.
December 12, 1995
ST,7BL7IVISIQN
ITEM NO,; 2 (Continued) FILE NO.: S-801-A
Executive Center Dr., as a standard commercial street, is to be
extended from its present termination west of Centerview Dr. to
intersect Bowman Rd. Sidewalks are to be provided along both
sides of Executive Center Dr. and Bowman Rd.
The Phase I construction is to involve development of Lots 1, 2,
3, and 6, with Executive Center Dr. being constructed along the
boundary of these lots. Phase II construction is to involve
development of Lots 4, 5, and 7, with construction of Bowman Rd.
to coincide with the development of these lots. Phase III
involves the development of Lot S, which lies to the west of
Bowman Rd.
A rezoning application is accompanying the preliminary plat
application through the Planning Commission hearing, with the
request being to rezone the existing Multi -Family zoned areas to
office zoning.
There is an existing OS -zoned strip which lies along the south
boundary of the tract. It is 200 feet deep for approximately the
east half of the tract, and is 130 feet deep for the remaining
western portion of the tract. No change in the status of this OS
strip is proposed.
Because Bowman Rd. is, according to the Master Street Plan,
designated to be realigned , and, presumably, the realignment
will alter the points where Bowman Rd. meet the existing
alignment at the boundaries of the plat area, the applicant
proposes to dedicate right-of-way and construct Bowman Road along
its existing alignment. The right-of-way and roadway
construction would meet width standards for a Minor Arterial
roadway. when, at some future date, Bowman Rd. is reconstructed
in its new alignment, right-of-way is proposed to be dedicated;
however, no additional improvements are proposed to be made in
conjunction with road construction project. The applicant
requests, then, that: 1) the preliminary plat be approved with
Bowman Rd. being in its present location, and that a deferral be
granted for dedication of right-of-way along its realigned path,
and 2) that, when the Bowman Rd. reconstruction project is
undertaken, further participation by the applicant in the
construction of Bowman Rd. be waived.
A. PROPOSAL/REQUEST:
Review and approval by the Planning Commission of a
preliminary plat is requested.
2
December 12, 1995
BDIVT T
ITEM 2 on in FILE No.: - 1-A
Review by the Planning Commission and a recommendation of
approval to the Board of Directors is requested for: 1)
approval of a deferral of the requirement to dedicate right-
of-way for and realign Bowman Rd. to the adopted alignment,
as provided for in the Master Street Plan; and, 2) approval
of a waiver of the requirement to construct the full width
of Bowman Rd. to Master Street Plan standards, with
sidewalks along both sides of the roadway, within the
realigned right-of-way.
B . EXI STINQ CONDITIONS:
The site is undeveloped and wooded, and the terrain is
fairly level. A temporary "dead end" of Centerview Dr.
terminates the street at its west end abutting the proposed
subdivision. There is an "Open Space" (OS) zoned strip
along the south boundary of the subdivision, abutting the
residential subdivision.
The site contains 0-1, 0-3, MF-12, R-2, and OS zoning;
however, accompanying the subdivision application to the
Planning Commission is a rezoning request to change the
rezoning of the MF-12 area to 0-1 and 0-3. The R-2 zoned
area west of the Bowman Rd. alignment is not included .in the
rezoning request, and the R-2 zoning of this tract will be
retained until the realignment of Bowman Rd. is
accomplished.
C. ENGINEERING UTILITY COMMENTS:
Public works comments:
Proper grading plans and erosion control plans are
required prior to construction.
The plan must be revised to conform to the adopted
Master Street Plan for Bowman Rd.
Sidewalks are required on both sides of Bowman Rd. and
on Executive Center Dr. A deceleration lane will be
required on Bowman Rd. for the turn onto Executive
Center Dr. All improvements will be required prior to
final plating of lots. One driveway will be allowed
for Lot 7. The minimum horizontal curve radii on
Executive Center Dr. is 450 feet.
Stormwater detention analysis is required. Open
ditches are generally not permitted by the Stormwater
Management and Drainage Manual. If ditches are
3
December 12, 1995
SUBDIVISION
ITEM NO.: 2 (Continued) FILE NO.: S-801-A
planned, they must be shown on the preliminary plat and
must be approved by the City Engineer prior to Planning
Commission approval of the plat [Ref. Sec. 311-89(9)].
Show water courses entering the plat area, and the
planned exit points for drainage.
Little Rock Water Works comments that water main extensions
and on -site fire protection will be required. The alignment
of Bowman Rd. does not agree with the plan previously
approved by the City. If a main is laid in the right-of-way
and the right-of-way is relocated in the future, the
developer will be responsible for the relocation.
Little Rock Wastewater Utility comments that a sewer main
extension, with easements, will be required.
Arkansas Power and Light Co. notes that they will require 15
foot easements along both sides of Executive Center Dr. and
along both sides of Bowman Rd. Also, the 10 foot utility
easement shown to be dedicated along the west property line
is to be a 15 foot easement instead.
Arkansas Louisiana Gas Co. approved the submittal.
Southwestern Bell Telephone Co. approved the submittal.
The Fire Department approved the submittal.
D. ISSUESILEGALITECHNICALIDESIGN:
Sec. 31-87 requires that, in addition to the information
furnished, the applicant is to provide information on any
existing and the proposed covenants and restrictions. It is
understood by staff that there is a deed restriction which
requires that, once Executive Center Dr. is extended at all,
it must be extended to an intersection with Bowman Rd. This
restriction provides rationale for having to extend
Executive Center Dr. to Bowman Rd., even though Bowman Rd.
will eventually have to be realigned.
Sec. 31-88 requires that the preliminary plat have a
vicinity map shown.
Sec. 31-89 requires that, in additio
furnished, the plat is to show: 1)
analysis showing drainage data for a
entering and leaving the tract; 2)
drainage plan incorporating proposed
ditch section; and, 3) the location
monuments. Any proposed phasing of
indicated.
n to the information
a storm drainage
11 water courses
a preliminary storm
easements and typical
of proposed PAGIS
the development is to be
ki
December 12, 1995
OUBDIVISION
ITEM NO.: 2 (Continued) FILE Ng.; 5-801 A
Sec. 31-91 requires that the certifications be executed.
The shown alignment for Bowman Rd. does not conform to the
adopted Master Street Plan alignment. When Bowman Rd. is
realigned, the lots abutting the present alignment, and the
lot shown west of the present alignment, will be affected.
The lot which is shown west of the present alignment will
not, when the roadway is realigned, be a developable site.
In light of this situation, and in light of the Public Works
comments, provision should be made for the future alignment
of Bowman Rd., and the lot lines should provide for this
alignment.
It is anticipated by the developer that the eventual
alignment of Bowman Rd. will be such that a construction of
a portion of the roadway to the new alignment will not be
possible at this time; that the entrance and exit points
from the subdivision will not align with the existing
alignment. The developer proposes, then, to construct, as
part of this subdivision, the full width of Bowman Rd. along
the existing alignment to full Minor Arterial roadway width
standards, with sidewalks, with the understanding that,
eventually, this roadway will be abandoned, and with the
understanding that the curve in Bowman Rd. is too tight to
meet the Master Street Plan standards for a Minor Arterial
roadway. Once Bowman Rd. is to be constructed within its
realigned right-of-way, the needed right-of-way would be
dedicated and the present right-of-way would be expected to
be abandoned to the developer. Since Bowman Rd. will, as
part of the subject subdivision, be constructed, a waiver of
a requirement to participate in construction of Bowman Rd.
within the new alignment is sought. A deferral of the
requirement to dedicate right-of-way for Bowman Rd.'s Master
Street Plan alignment is sought until the project is
undertaken.
E. ANALYSIS•
There are only minimal and minor deficiencies in the
submittal documents, and these deficiencies can be easily
remedied by the applicant and project engineering firm.
There are, however, real concerns expressed by Public Works
concerning the status of Bowman Rd. Public Works notes that
the alignment of Bowman Rd. should be shifted to the west
boundary of the subdivision to eliminate the sharp curves,
and anticipates requiring the developer to construct Bowman
Rd. within its Master Street Plan alignment at this time.
The developer, however, notes that realigning Bowman Rd.
will entail extensive earth moving to go straight through a
knoll, and resists having to bear the cost of constructing
5
December 12, 1995
IIBDIVr x
ITEM NO.: 2 (Continued) FILE NO.: S-$91-A
the full width of Bowman Rd. to Master Street Plan
standards. A waiver of this requirement is, therefore,
being pursued.
F. ETAFF RECOMMENDATIONS:
Staff recommends approval of the preliminary plat, subject
to complying with the Public Works requirements, and subject
to the applicant addressing the deficiencies in the
submittal information.
SUBDIVISION COMMITTEE COMMENT: (NOVEMBER 22, 1995)
Mr. David Jones, representing the applicant, and Mr. Robert
Brown, with Development Consultants, Inc., the project
engineering firm, were present. Staff outlined the nature of the
proposal and reviewed with the Committee members the comments
contained in the discussion outline. Mr. Brown noted that many
of the deficiencies noted had been previously addressed in the
submittal documents, but that others would be remedied. David
Scherer, with the Public Works staff, and Bill Henry, the Traffic
Engineer, discussed with Mr. Jones and Mr. Brown the requirements
for Bowman Rd. Mr. Jones and Mr. Brown responded that, during
the next few days, they would meet with the Public Works staff to
discuss the situation. The Committee forwarded the item to the
full Commission for the public hearing.
PLANNING COMMISSION ACTION: (DECEMBER 12, 1995)
Staff presented the item and indicated that the issues discussed
at the Subdivision Committee meeting and noted in the staff
"write-up" have, for the most part, been resolved. Staff
indicated that the issue of how to treat the alignment of and the
requirements for construction of interim improvements on Bowman
Rd. have been resolved. Staff noted that the only remaining
issue is the amount of improvements which will be required to be
provided by the developer in the future alignment, and whether
the developer will seek a waiver of these requirements.
Mr. Robert Brown, with Development Consultants, Inc., and Mr.
David Jones, with Westrock Partnership, were present.
Mr. Brown reported that an agreement had been reached with the
Public works staff concerning the alignment and dedication of
right-of-way for the Bowman Rd. realignment. He explained that
Executive Center Dr. would be extended to and an intersection
made with the existing alignment of Bowman Rd. with the first
phase of development of the subdivision, and that the developer
N
December 12, 1995
HQ1V1 r
ITEM NO.: 2 (Continued) FILE NO.: S-801-A
and the Public Works staff had reached an agreement on the design
of the intersection. The intersection will include, he added,
limitations on turning movements onto and from Bowman Rd. He
explained that the revised preliminary plat eliminates the
initially proposed lot west of the present Bowman Rd. alignment,
since the Bowman Rd. alignment will be shifted to the west, and
no usable land will be available west of the realignment along
the west property line. He said that the revised preliminary
plat proposes a configuration of lots along the east boundary of
the future alignment of Bowman Rd., with the existing alignment
of Bowman Rd. bisecting these lots. This existing alignment
will, he explained, remain in place, in an access easement which
is being provided, until Bowman Rd. in its future right-of-way is
constructed. He explained that the easement for the existing
alignment of Bowman Rd. will be abandoned when Bowman Rd. is
relocated, and, at that time, the lots through which the easement
goes will be developable. He reported that the developer and the
Public Works staff is negotiating the manner of the required
improvements for Bowman Rd. in its new alignment; that, in lieu
of building half a street, with curb and gutter on one side, a
budget for the required improvements will be developed and an
equivalent amount of funds will be expended to provide a usable
roadway, probably being a two-lane roadway section, with
shoulders.
David Scherer, with the Public Works staff, confirmed Mr. Brown's
comments, but added that, prior the rezoning of the property
being heard by the Board of Directors, the right-of-way for
Bowman Rd. will have to be dedicated by Quit Claim Deed. He also
said that the Public Works staff would reserve the right to
continue negotiations with the developer on the type and extent
of improvements to Bowman Rd. which will be required for the
existing roadway and in the proposed alignment.
Interim Chairperson Ball called the question, and the preliminary
plat, as amended, was approved with the vote of 10 ayes, 0 nays,
0 abstentions, and 1 absent.
7