HomeMy WebLinkAboutS-0591 Map 3September 10, 1985
SUBDIVISIONS
Item No. 4 - File No. 591
NAME: Ashley Square Shopping Center
Preliminary/Site Plan
LOCATION: NE Corner of Rodney Parham and
Reservoir Road
DEVELOPER: ENGINEER:
Ashley Associates Robert D. Holloway, Inc.
2649 Pike Avenue 200,Casey Drive
NLR, AR 72114 Maumelle, AR 72118
Phone: 758-7745' Phone: 851-3366
AREA: 11.93 acres NO. OF LOTS: 1 FT. NEW STREET: 0
ZONING: "C-3"
PROPOSED USE: Shopping Center
A. Site History
Several projects on this site have been previously
approved by the Commission.
B. Proposal
1. Construction of a shopping center composed of
retail and one restaurant use on 11.93 acres.
2. Development according to the following site
statistics:
Provided
Structure Sq. Ft. Parking
Clothing Store 24,050 120
Dept. Store 30,000 150
L.L. 1-5 98,300 311
Totals 152,350 581
3. Landscaping/Screening - A privacy fence will
border the residential area to the east.
September 10, 1985
SUBDIVISIONS
Item No. 4 - Continued
4. Physical Improvements
(a) Additional property to accommodate a left
turn lane on Reservoir Road is dedicated on
the plat. On the site plan, it is indicated
as a 240' transition from the north all the
way to Rodney Parham Road.
(b) The development will have a substantial fill
on the west side of the Presbyterian
residential area and a substantial cut slope
on the north end of the property, which will
require proper slope protection and erosion
control as will be recommended in the final
design by the architect.
(c) Some in -lieu contributions for future
construction of Reservoir Road will be made
by a developer.
C. Engineering Comments
1. Street, driveway, etc., dimensions shall be shown
for review.
2. Dimensions for lane width shall be shown for
Reservoir.
3. Detention required.
4. Boundary street requirements for Reservoir Road.
5. Traffic Engineer needs to be furnished Engineering
data to determine if exit onto Rodney Parham has a
safe sight distance.
6. Fire Department must sign off on access and no
fire hydrants in back of building.
D. Analysis
This application involves the platting of unplatted
acreage with dedication of additional right-of-way and
site plan review of a multiple building site. In his
proposal, the applicant has outlined how he wishes to
develop the property. Due the physical nature of the
site, he has proposed a certain amount of grading and
site work. Also, there are plans for extensive street
improvements, along with one of the structures being a
restaurant which is a high traffic generator.
September 10, 1985
SUBDIVISIONS
Item No. 4 - Continued
Staff has a few concerns. The applicant has mentioned
verbally that he would like for the additional physical
improvements to be optional. Staff prefers that the
applicant make a commitment at this stage indicating
whether or not he plans to do the improvements. Also,
he needs to pinpoint which structure is to house a
restaurant. This would enable staff to check the
parking, even though it appears to be adequate. There
are no plans for buffering the multifamily to the
north. Staff recommends the usual requirement and that
the 6' fence be placed on top of the grade. Staff
suggests that notice be sent to neighboring property
owners. The Fire Chief must approve all drives.
E. Staff Recommendation
Approval, subject to comments made.
SUBDIVISION COMMITTEE REVIEW:
The applicant and his engineer were present. He explained
that development plans were not certain at this time so he
needed flexibility in designating the restaurant uses. He
felt that one or both of the smaller buildings on Reservoir
Road would be a restaurant. Since he met the parking
requirement, the Committee had no problem. He was advised
to meet with Engineering and work out an agreement on the
additional physical improvements and to notify property
owners in the area.
Water Works - A frontage charge of $2.50 per foot adjacent
to Reservoir Road and an acreage charge of $150 per acre
will apply. On -site fire lines and hydrants will be
required:
PLANNING COMMISSION ACTION:
The applicant was present. There were no objectors.
Mr. Mike Batie of the City Engineer's Office reported that
an agreement had been reached for improvements on Reservoir
Road. A motion for approval was made and passed by a vote
of 10 ayes, 0 noes and 1 absent.