HomeMy WebLinkAboutS-0430 Staff Analysisr September 13, 1983
SUBDIVISIONS
Item No. 1 - File No. 430
NAME:
LOCATION:
DEVELOPER:
Bek Kaiser
Route 3
#9 Country Oaks Drive
Little Rock, AR
AREA: .37 acres
ZONING: "R-4"
PROPOSED f7SES s
Kaiser Replat
Off Beechwood, 3 Blocks North
of "B" Street
ENGINEER:
Brooks and Curry
P.O. Box 897
North Little Rock, AR 72115
Phone: 372-2131
NO. OF LOTS: 2 FT. OF NEW ST.: 0
Duplex
VARIANCES REQUESTED:
None.
A. History of the Site
On April 24, 1979, the Commission considered the same
applicant's request for the rezoning of this site to
multifamily. The request was denied, but the site was
ultimately rezoned for duplex use. Petitions from 57
neighborhood objectors were submitted.
B. Existin2 Conditions
This site is currently a wooded tract which slopes very
steeply east to west. It is located in an area that
generally consists of "R-4" and "R-5" zoning. Access
to the site is currently provided by a gravel access
easement off Beechwood and an alley in fair condition
running north "I" Street. Allsopp Park abuts on the
north.
C. Development Proposal
The applicant is requesting that he be allowed to
replat a parcel of .37 acres into two lots for use as
duplexes. The access proposed for the new development
will be the same as that existing currently; a 20-foot
valley on the south and a 13-foot access easement on
the west.
September 13, 1983
3 UBDI V JPSIZ. NS
Item No. 1 - Continued
D. Engineering Considerations
The 13-foot access easement does not appear to be
adequate. We request a plan with grades for proposed
access, and for access between lots, plus internal
drainage plan.
E. Analysis
This proposal has a significant problem with access.
The only dedicated access to the site is a 20-foot
alley, which is now partially in use by neighbors. The
other portion is unconstructed. The second means of
access will be through a 13-foot private access
easement that currently leads to the rear of an
apartment building. It is unimproved and consists of a
rather steep grade. At the time of this writing, staff
had not yet received comments from the Fire Department.
It is imperative that they approve of this request. A
topographic survey is definitely needed in this
instance, so as to indicate where the lot lines lie in
respect to grade and access.
F. Staff Recommendation
Comment is reserved until additional information is
received.
SUBDIVISION COMMITTEE REVIEW:
The applicant was represented by Mr. Allen Curry. Along
with the owner, they presented their case for the replatting
of the two lots in question. The Committee discussed this
issue at length receiving comments from both the Planning
and Engineering staffs. The only issues remaining to be
resolved by the applicant are specific layout and design on
the location of the 131 driveway and its connection with the
parking lots on both lots as well as the alley. The
applicant was directed to prepare design work in this
direction prior to the meeting on July 12.
PLANNING COMMISSION ACTION: (July 12, 1983)
Mr. Bek Kaiser, the owner, was present in support of the
application. Since the revised plan was not submitted, the
Commission voted to defer this item until the July 26th
public hearing. The motion passed by a vote of 9 ayes,
0 noes and 2 absent.
September 13, 1983
SUBDIVISIONS
Item No. 1 - Continued
PLANNING COMMISSION ACTION: (7-26-83)
Staff reported that a letter had been received from the
applicant requesting deferral until the September 13th
Planning Commission meeting. A motion was made and passed
to this effect. The vote was: 10 ayes, 0 noes and
1 absent.
SUBDIVISION COMMITTEE REVIEW:
Staff reported that the applicant had requested a deferral
until a revised plan could be submitted.
PLANNING COMMISSION ACTION:
( 9-13-83 )
The applicant in this matter requested a deferral. However,
the Planning Commission felt that withdrawal and a new
application at a later would be in order. The Commission
then voted unanimously to withdraw the matter from further
consideration. The vote - 11 ayes, 0 noes.