HomeMy WebLinkAboutS-0010-CC Staff AnalysisITEM NO.: 1 FILE NO.: S-10-BH
NAME: Charles Valley Office Park - Preliminary Plat
LOCATION: South side of Huron Lane, approximately 200 feet
east of Green Mountain Drive
DEVELOPER: ENGINEER:
Rees Development, Inc. McGetrick Engineering
11125 Hinson Road 319 East Markham, Suite 202
Little Rock, AR 72212 Little Rock, AR 72201
AREA: 3.93 Acres NUMBER OF LOTS: 4 FT. NEW STREET: 0
ZONING• 0-3
PLANNING DISTRICT: 2
CENSUS TRACT: 22.05
VARIANCESIWAIVERS REQUESTED: None
A. PROPOSAL•
The applicant proposes to subdivide 3.93 acres into 4 lots
for future office developments. The property is zoned 0-3,
General Office District. The applicant is proposing a 40
foot easement running north -south through the center of the
property for access and utilities to Lots 3 and 4.
B. EXISTING CONDITIONS:
The site is currently vacant and heavily wooded. A 50 foot
wide R-2 zoned buffer area is located along the south end of
this property, with single-family residences located further
south. Single-family residences are also located to the
west along Green Mountain Dr. A mixture of office and
commercial uses are located to the east and north across
Huron Lane.
July 23, 1998
SUBDIVISION
ITEM NO.: 1 Cont. FILE NO.: S-10-BB
C.
E.
F.
NEIGHBORHOOD COMMENTS:
Staff has received no neighborhood comment as of this
writing. The Walnut Valley and Rainwood Cove Neighborhood
Associations were notified of the public hearing.
ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Show 50 foot access easement with minimum 26 wide street
and sidewalks for access to lots 3 and 4 including a
cul-de-sac to conform to minor commercial standards.
2. Huron Lane is a commercial street, dedicate right-of-way
to 30 feet from centerline.
3. Sidewalks shall be shown conforming to Sec. 31-175 and
the "MSP".
4. All driveways shall be concrete aprons per City
Ordinance.
5_ Repair or replace any curb and gutter or sidewalk that
is damaged in the public right-of-way prior to
occupancy.
6. Plans of all work in right-of-way shall be submitted for
approval prior to start of work.
7. Stormwater detention Ordinance applies to this property.
8. Easements for proposed stormwater detention facilities
are required.
UTILITIES AND FIRE DEPARTMENTMOUNTY PLANNING:
Wastewater: Sewer main extension required with easements
to serve all lots.
AP&L: No Comment received.
Arkla: No Comment received.
Southwestern Bell: A 5 foot utility easement is requested
along the east, west and south property lines.
Water: A water main extension and on -site fire protection
will be required.
Fire Department: No Comment.
County Planning:
CATA• No Comment.
No Comment received.
ISSUES/TECHNICAL/DESIGN:
Planning Division: No Comment.
Landscape Issues:
No Comment.
K
7-1-7 --
July 23, 1998
SUBDIVISION
ITEM NO.: 1 (Cont.) FILE NO.: S-10-BB
G. ANALYSIS•
The applicant submitted a revised preliminary plat to staff
on July'8, 1998. The applicant has made the additional
notations on the plat as required by staff and the revision
appears to address the Subdivision Committee comments.
There should be no outstanding issues.
H. STAFF RECOMMENDATIONS:
Staff recommends approval of the preliminary plat subject to
the conditions noted in paragraphs D and E of this report.
The 50 foot wide R-2 zoned buffer along the south property
line must remain undisturbed with development of the
property. Temporary fencing must be installed to protect
this area prior to any site work.
SUBDIVISION COMMITTEE COMMENT:
Bob Lowe, of McGetrick Engineering, was present, representing the
application. Staff gave a brief description of the preliminary
plat.
Staff made note of several minor details which needed to be shown
on a revised plat. Staff also noted that the 50 foot wide.R-2
zoned buffer along the south property line must remain
undisturbed, and the access easement must stop short of that
area.
Bob Turner, of Public Works, reviewed the Public Works
requirements with the applicant and Committee.
There being no further issues for discussion, the Committee
forwarded the preliminary plat to the full Commission for final
action.
PLANNING COMMISSION ACTION:
(JULY 23, 1998)
Pat McGetrick was present, representing the application. There
were several persons present with concerns. Staff gave a brief
description of the preliminary plat and a recommendation of
approval with conditions.
Pat McGetrick addressed the Commission in support of the
application. He stated that he had no problem with any of the
conditions placed on the application by staff.
3
-July 23, 1998
SUBDIVISION
ITEM NO.: 1_ (Cont.) _ FILE NO.: 5-10-BB
Bob Price addressed the Commission with concerns. He stated that
he was not opposed to development of the site as long as the
required buffers are in place.
Terry and Marlene Mahaffey addressed the Commission. The
Mahaffeys also noted concerns relating to the required buffers.
Mrs. Mahaffey stated that the required temporary fences should be
in place to protect the trees within the buffers.
Mr. McGetrick stated that the 50 foot buffer along the south
property line would remain undisturbed and that temporary fencing
to protect this area could be made part of a grading permit.
Jim Lawson, Director of Planning and Development, asked Mr.
McGetrick if the 40 foot area along the west property line could
be designated as an undisturbed buffer area.
Mr. McGetrick agreed to a 40 foot undisturbed buffer along the
west property line.
Russell Lemond also stated that he had concerns relating to the
buffer areas. He said that he would like the areas to be
undisturbed.
Joe Pere also addressed the Commission with concerns relating
to the buffer areas. He also asked about building heights.
Staff reviewed the allowed building height in 0-3 zoning.
There was additional discussion relating to buffer issues.
A motion was made to approve the preliminary plat as recommended
by staff including a 40 foot undisturbed buffer along the west
property line and a 50 foot undisturbed buffer along the south
property line. The motion passed by a vote of 11 ayes and
0 nays.
4
November 11, 1999
ITEM NO.: C
FILE NO.: S-10-CC
NAME: Charles Valley Office Park - Revised Preliminary Plat
LOCATION: South side of Huron Lane, approximately 200 feet east
of Green Mountain Drive
DEVELOPER: ENGINEER_
Rector -Phillips -Morse McGetrick and McGetrick
1501 N. University Avenue 319 East Markham Street, Ste. 202
Little Rock, AR 72207 Little Rock, AR 72201
AREA: 3.93 acres NUMBER OF LOTS: 3 FT. NEW STREET: 0
ZONING: O-3
PLANNING DISTRICT: 2
CENSUS TRACT: 22.05
VARIANCES/WAIVERS REQUESTED: None requested.
A. PROPOSAL:
The applicant proposes to subdivide 3.93 acres into 3 lots
for future office developments. The property is zoned 0-3,
General Office District. The applicant is proposing a 50
foot easement running north -south through the center of the
property for access and utilities to Lot 3.
A four (4) lot preliminary plat was approved by the
Planning Commission for this property on July 23, 1998.
The plat, which included a 40 foot undisturbed buffer along
the west property line, has since expired.
November 11, 1999
SUBDIVISION
ITEM NO.: C (Cont.) FILE NO.: S-10-CC
B. EXISTING CONDITIONS:
The site is currently vacant and heavily wooded. A 50 foot
wide R-2 zoned buffer area is located along the south end
of this property, with single-family residences located
further south. Single-family residences are also located
to the west along Green Mountain Dr. A mixture of office
and commercial uses are located to the east and north
across Huron Lane.
C. NEIGHBORHOOD COMMENTS:
The Walnut Valley and Rainwood Cove Neighborhood
Associations were notified of the public hearing. Staff
has received one (1) letter and two (2) phone calls from
neighbors expressing concerns with the proposed plat.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Huron Lane is a commercial street. Dedicate right-of-
way to 30 feet from centerline.
2. Provide design of street conforming to " MSP" (Master
Street Plan). Construct one-half street improvements to
these streets including 5-foot sidewalks with planned
development.
3. Internal streets must have public cul-de-sac and
sidewalk (26' wide).
4. Plans of all work in right-of-way shall be submitted for
approval prior to start work.
5. Stormwater detention ordinance applies to this property.
6. Easements for proposed stormwater detention facilities
are required.
7. Easements shown for proposed storm drainage are
required.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer main extension required with easements
to serve Lot 3.
AP&L: No Comment.
Arkla: No Comment.
Southwestern Bell: No Comment received.
Water: An acreage charge of $300 per acre will apply in
addition to normal charges. A water main extension will
F%
November 11, 1999
SUBDIVISION
ITEM NO.: C (Cont.)
FILE NO.: S-10-CC
be required along with on -site fire protection.
Fire Department: No Comment.
County Planning: No Comment received.
CATA: No Comment received.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division:
No Comment.
Landscape Issues:
No Comment.
G. ANALYSIS:
The applicant submitted a letter to staff on September 17,
1999, requesting that this item be deferred to November 11,
1999. The applicant is working to revise the preliminary
plat and needs additional time.
H. STAFF RECOMMENDATIONS:
Staff recommends approval of the deferral as requested.
SUBDIVISION COMMITTEE COMMENT:
(SEPTEMBER 9, 1999)
Bob Lowe was present, representing the application. Staff gave
a brief description of the preliminary plat.
Staff noted that the preliminary plat for this property which
was approved on July 23, 1998 had a 40 foot undisturbed buffer
along the west property line. The buffer was agreed to at that
time by the applicant in response to concerns voiced by abutting
property owners at the public hearing. Mr. Lowe noted that he
would inform the current property owners of this buffer.
Staff also noted that temporary construction fencing must be
installed to protect the buffer areas prior to any site work.
This was also a condition of the previous approval.
3
November 11, 1999
SUBDIVISION
ITEM NO.: C (Cont.) FILE NO.: S-10-CC
The Public Works requirements were briefly discussed. Tad
Borkowski noted that the internal street must have a turnaround
device and a sidewalk.
After the brief discussion, the Committee forwarded the plat to
the full Commission for final action.
PLANNING COMMISSION ACTION: (SEPTEMBER 30, 1999)
Staff informed the Commission that the applicant submitted a
letter on September 17, 1999 requesting that this item be
deferred to the November 11, 1999 agenda. Staff supported the
deferral request.
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for deferral to the November 11, 1999
agenda. A motion to that effect was made. The motion passed by
a vote of 11 ayes and 0 nays.
STAFF UPDATE:
The applicant submitted a revised preliminary plat to staff on
October 19, 1999. The revised plat increases the number of lots
from three (3) to four (4) and shows the 50 foot access as a
private drive with a cul-de-sac, as required by Public Works, tc
serve the four lots.
As noted in paragraph A. of this report, the previously
approved plat for this property included a 40 foot undisturbed
buffer along the west property line. This was a result of an
agreement between the previous developer of the property and the
adjacent property owners. This buffer was not an ordinance
requirement at that time, nor is it now. The current developer
of the property does not wish to provide the buffer. The
proposed plat does recognize the 50 foot, R-2 zoned, undisturbed
buffer along the south property line.
Otherwise, there should be no outstanding issues associated with
the proposed preliminary plat. The plat as proposed conforms to
ordinance standards.
4
November 11, 1999
SUBDIVISION
ITEM NO.: C (Cont.) FILE NO.: 5-10-CC
SUBDIVISION COMMITTEE COMMENT: (OCTOBER 21, 1999)
Pat McGetrick was present, representing the application. Staff
briefly described the revised preliminary plat.
The revisions made to the plat were briefly discussed, as was
the buffer that was shown on the previously approved plat along
the west property. Staff explained that land use buffers are
not Subdivision Ordinance requirements and could not be required
with preliminary plats.
There being no further issues for discussion, the Committee
forwarded the plat to the full Commission for final action.
STAFF RECOMMENDATIONS:
Staff recommends approval of the preliminary plat subject to the
following conditions:
1. Compliance with the requirements as noted in paragraphs D and
E of this report.
2.The 50 foot wide R-2 zoned buffer along the south property
line must remain undisturbed with development of the property.
Temporary fencing must be installed to protect this area prior
to any site work.
PLANNING COMMISSION ACTION: (NOVEMBER 11, 1999)
Pat McGetrick and Bill Hastings were present, representing the
application. Staff briefly described the proposed preliminary
plat with a recommendation of approval.
Pat McGetrick addressed the Commission in support of the
application. He noted that the R-2 zoned buffer area along the
south property line will be fenced prior to any site work.
Marlene Mahaffey addressed the Commission with concerns. She
asked when the plat would be final platted. Staff indicated
that the applicant had one (1) year to complete the final plat.
Bill Hastings noted that he had one of the proposed lots -sold.
Mrs. Mahaffey asked about building height.
W
November 11, 1999
SUBDIVISION
ITEM NO.: C (Cont.
FILE NO.: S-10-CC
Mr. Hastings noted that the buildings constructed on this
property will comply with city ordinance standards. He stated
that if his real estate company develops the first lot within
the subdivision, the building will be one-story in height.
Jim Lawson, Director of Planning and Development, noted that the
Commission only had the authority to.review the proposed plat.
He stated that building height was not an issue that could be
associated with a plat.
The ordinance standards regarding building height were briefly
discussed.
Russell Lemond addressed the Commission. He stated that he was
concerned that there was no buffer shown along the west property
line as was approved with the previous plat.
There was a general discussion regarding the buffer issue and
ordinance required setbacks. Staff noted that the ordinance
required land use buffer along the west property line would be
approximately 9.5 to 10 feet in width.
Commissioner Hawn offered comment on the buffer issue and asked
why the developer would not provide a 40 foot buffer along the
west property line.
Mr. McGetrick stated that the buffer would restrict the
buildable area of the lots.
Commissioner Adcock also asked about the 40 foot buffer.
Mr. McGetrick stated that the additional area was needed to
develop the property.
Commissioner Rahman asked if the 40 foot buffer along the west
property line was part of the previously approved plat.
Mr. Lawson responded that the buffer was part of the previously
approved plat, but was not an ordinance requirement.
Stephen Giles, City Attorney, noted that the 40 foot buffer
shown on the previous plat was not a requirement, but was
offered by the previous developer.
November 11, 1999
SUBDIVISION
ITEM NO.: C (Cont.) FILE NO.: 5-10-CC
There was a general discussion regarding the previously approved
plat, with additional comment by Russell Lemond.
Commissioner Nunnley asked Mr. Lemond if a buffer less than 40
feet in width would be acceptable.
Mr. Lemond stated that it would not.
Mr. McGetrick noted that the developer feels that he has met all
of the ordinance requirements.
There was a motion to approve the preliminary plat as
recommended by staff.
There was additional discussion concerning the buffer issue,
including the ordinance buffer standards.
Mr. Giles reviewed the Planning Commission authority in dealing
with preliminary plat applications. He noted that a buffer
issue was not a viable reason to deny a preliminary plat.
There was additional discussion pertaining to the previous plat
approval.
Chairman Earnest called the vote. The previous motion to
approve the preliminary plat passed by a vote of 6 ayes, 3 nays,
1 absent and 1 open position.
7