HomeMy WebLinkAboutZ-9392 Staff AnalysisAPRIL 29, 2019
ITEM NO.: A
File No.: Z-9392
Owner: The Student Loan Guarantee Foundation of Arkansas
Applicant Mark Rose, KATV
Address: 10 Turtle Creek Lane
Description: Tract M-2A, Riverdale Addition
Zoned: O-3
Variance Requested: A variance is requested from the height provisions of Section
36-201 to allow a broadcast tower with increased height.
Justification: The applicant's justification is presented in an attached letter.
Present Use of Property: Office Building
Proposed Use of Property: Office Building with broadcast studio
STAFF REPORT
A. Public Works Issues:
1. Public Works staff has no comment on the variance to Section 36-201.
2. Public Works staff has not reviewed any other part of this project at this time, and
additional comments may be provided prior to approval of the building permit.
B. Staff Analysis:
The 0-3 zoned property at 10 Turtle Creek Lane is occupied by a two-story office
building located within the south half of the overall 3.98 acre property. The property
is located on the north side of Turtle Creek Lane, between Brookwood Drive and
Riverfront Drive. A driveway from Turtle Creek Lane and a driveway from
Brookwood Drive serve as access to the property. Paved parking is located on the
south and west sides of the building. The north half of the overall property is
undeveloped and grass covered.
Sinclair Broadcast Group/KATV is in the process of purchasing this property at
10 Turtle Creek Lane, with the intent of relocating their broadcast studio from its
current location at 410 Main Street. As part of the relocation, the applicant proposes
to construct a 100 foot tall broadcast tower within the undeveloped, north portion of
the property, as noted on the attached site plan. The proposed tower will be a
APRIL 29, 2019
ITEM NO.: A (CON'T.) Z-9392
self-supporting metal truss frame tower. The proposed tower will be located well
over 100 feet back from the building and all property lines. The tower structure finish
will be galvanized steel. A small antenna or dish will be attached to the tower
structure near the top, but will not extend past the top of the 100 foot tall tower.
Section 36-201(e)(1)a. of the City's Zoning Ordinance allows a maximum tower
height of 75 feet for metal ground -mounted towers. Therefore, the applicant is
requesting a variance to allow the proposed tower with increased height.
Staff is supportive of the requested tower height variance. Staff views the request
as reasonable. The proposed tower height of 100 feet will not be out of character
with the heights of other buildings and tower structures in this general area.
Signal Media Radio at 2400 Cottondale Lane has a 154 foot tall broadcast tower.
There are also several multi -story buildings in this area along Riverfront Drive. The
applicant notes that studies were conducted and it was determined that the absolute
minimum tower height that will work for this location is 100 feet. Staff believes the
proposed 100 foot tall tower at this location will have no adverse impact on the
adjacent properties or the general area.
C. Staff Recommendation:
Staff recommends approval of the requested tower height variance, as filed.
Board of Adjustment (February 25, 2019)
Mark Rose and Joe White were present, representing the application. There were several
objectors present. Staff presented the application with a recommendation of approval.
Marks Rose addressed the Board in support of the application. He explained that the
proposed height of the tower was planned for long term use of the tower structure. He
noted that there would be no lights on the tower. He explained that the width of the tower
narrowed as the height of the tower increased.
Joe White also spoke in support of the application. He explained that the elevation of the
proposed tower site was 252 feet and that the elevation of the Treetops condo
development was approximately 356 to 360 feet. He further explained that the Treetops
condos owners would look down on and over the proposed tower and not into the tower.
He noted that the proposed tower should not adversely impact the view of the river from
the condos.
Bob McKuin addressed the Board in opposition. He noted that he was opposed to the
tower's close proximity to nearby multi -family developments. He stated that the variance
should be denied.
2
APRIL 29, 2019
ITEM NO.: A CON'T. Z-9392
Bob Ratchford also spoke in opposition. He explained that the tower would impact the
views from his condo. He noted that the tower would devalue his property. He asked that
the application be deferred.
James Corner also spoke in opposition. He also stated that views from his condo would
be impacted. He noted that towers were not allowed in office zoning and quoted from the
zoning ordinance.
Jack Cherry also spoke in opposition. He asked for a deferral to allow more time for
questions about the tower to be answered.
Dana Carney, of the Planning Staff, explained that towers were accessory uses to
broadcast studios and that towers were permitted in office zoning.
Joe White further explained that the elevation of the top of the tower was less than the
elevation of the Treetops property.
Chairman Allison offered a deferral to the applicant based on the fact that only three (3)
members of the Board were present. Mr. White requested to move forward.
Chairman Allison noted that he had issues that needed to be addressed. Sherri Latimer,
City Attorney, noted that the Board could defer an application on its own motion.
A motion was made to defer the application to the March 25, 2019 agenda. The vote was
3 ayes, 0 noes, 1 absent and 1 open position. The application was deferred.
Staff Update:
The applicant submitted a revised site plan to staff on May 6, 2019. The revised site
plan moves the tower location slightly to the west, within the west portion of the north
yard area. The proposed tower will be located 170 feet from the north property line, 100
feet from the west property line, and over 200 feet from the east and south property
lines. The applicant notes that the location of the proposed tower was moved to provide
a better signal than would be accomplished at the original location.
The applicant also notes that additional information on health/safety issues and sight
distance/visibility issues will be presented at the March 25, 2019 public hearing. The
information will include photos with a simulation of the tower depicted. Staff continues
to be supportive of the requested tower height variance.
Board of Adjustment (March 25, 2019)
Staff informed the Board that on March 18, 2019 the applicant submitted a letter to staff
requesting this application be deferred to the April 29, 2019 agenda. Staff supported
the deferral request. The item was placed on the consent agenda and deferred to the
April 29, 2019 agenda. The vote was 4 ayes, 0 noes, 0 absent and 1 open position.
3
APRIL 29, 2019
ITEM NO.: A (CON'T.
Board of Adjustment
(April 29, 2019)
Staff informed the Board that on April 23, 2019 the applicant submitted a letter to staff
requesting this application be withdrawn. Staff supported the withdrawal request.
The item was placed on the consent agenda and withdrawn. The vote was 4 ayes, 0
noes and 1 absent.
El