HomeMy WebLinkAboutZ-8890-B Staff AnalysisFILE NO.: Z-3875-A
NAME: Green - Short -Form PCD
LOCATION: 12825 Interstate 30
DEVELOPER:
Alvin Green
9910 Chicot Road
Little Rock, AR
AREA: 3.77 acres
SURVEYOR:
Donald W. Brooks
20820 Arch Street
72209 Hensley, AR 72065
NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: C-3/R-2 ALLOWED USES: Commercial
PROPOSED USE:
Boat sales and display;
C-3 permitted uses
VARIANCES/WAIVERS REQUESTED: None requested.
A. PROPOSAL/REQUEST:
The applicant proposes to rezone the property at 12825 I-30
from C-3/R-2 to PCD in order to allow boat sales and
display as a permitted use, which the property's current
zoning does not allow. The boat sales and display business
is currently being operated at this site, within a portion
of the existing commercial building. The applicant has
also recently constructed a 40 foot by 70 foot building
(for boat storage) at the east end of the existing
building. A gravel area for the display of boats has been
shown on the proposed site plan. There is currently a
church which occupies the west one-half of the existing
building.
B. EXISTING CONDITIONS:
The site contains an existing commercial building and
asphalt parking between the building and I-30. There is a
second building (east end of the existing building) which
has recently been constructed.
FILE NO.: Z-3875-A (Cont.
There is a mixture of commercial uses along I-30 to the
east and west and across I-30 to the north. There is a
creek within the southern portion of the property, with the
Optimist Club Park (race track) and a truck service
business further south.
C. NEIGHBORHOOD COMMENTS:
The Alexander Road and SWLR UP Neighborhood Associations
were notified of the public hearing. As of this writing,
staff has received no comment from the neighborhood.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
All properties are located in floodway. City does not
allow any structures in floodway.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available, not adversely affected.
AP&L: No Comment.
ARKLA: No Comment received.
Southwestern Bell: No Comment.
Water: No objection. A water main extension installed at
the expense of the developer will be required to provide water
service to this property.
Fire Department: No Comment.
County Planning: No Comment received.
CATA: Site is not located on a dedicated bus route and
has no effect on bus radius, turnout and route.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division:
This request is located in the Otter Creek Planning
District. The Land Use Plan shows Mixed Commercial and
Industrial. The applicant has applied for a Planned
Commercial Development for a boat sales dealership. The
property is currently zoned C-3 General Commercial. A land
use plan amendment is not required.
2
FILE NO.: Z-3875-A (Cont.
City Recognized Neighborhood Action Plan:
The Chicot West/I-30 South Neighborhood Action Plan
contains the economic development goal of providing a mixed
commercial/residential environment that will promote the
safety, attractiveness, and value of the area while
creating a competitive and adaptable economic climate that
encourages investment and diversity of employment
opportunities.
The Chicot West/I-30 South Neighborhood Action Plan also
states the recommendation of concentrating "...development
efforts in the more urbanized northern portion of the study
area..." This property is located on the northern boundary
of the study area.
Landscape Issues:
The proposed parking area encroaches into the 30 foot wide
street buffer required when abutting an expressway unless
located within a "mature area" designation.
G. SUBDIVISION COMMITTEE REVIEW:
Alvin Green and Bill Wiedower were present, representing
the application. Staff briefly described the proposed PCD.
Staff noted that this property is in the floodway, and that
no new structures could be constructed in the floodway.
This issue was briefly discussed. Staff suggested that the
application be deferred until the floodway issue could be
resolved. The applicant noted that a deferral would be
requested.
After the discussion, the Committee forwarded the
application to the full Commission for resolution.
H. ANALYSIS:
As noted in the Public Works Comments (paragraph D) and in
the Subdivision Committee Comments (paragraph G), the
property at 12825 I-30 is located in the floodway and the
City does not allow any new construction in the floodway.
Staff and the Subdivision Committee feel that this
application should be deferred to allow the applicant time
to resolve the floodway issue.
3
FILE NO.: Z-3875-A (Cont.)
The applicant submitted a letter to staff on October 11,
2000 requesting that this application be deferred to the
December 7, 2000 agenda. The applicant notes that an
engineering firm has been hired to do a preliminary study
to determine if any improvements made downstream have
altered the floodway. If not, the applicant will then
determine if he wants the engineering firm to perform the
necessary work to obtain a revision of the flood maps.
Staff supports the deferral as requested.
I. STAFF RECOMMENDATIONS:
Staff recommends that this application be deferred to the
December 7, 2000 agenda.
PLANNING COMMISSION ACTION:
(OCTOBER 26, 2000)
Staff informed the Commission that the applicant submitted a
letter on October 11, 2000 requesting that this application be
deferred to the December 7, 2000 agenda. Staff supported the
deferral request.
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for deferral to the
December 7, 2000 agenda. A motion to that effect was made.
The motion passed by a vote of 10 ayes, 0 nays and 1 absent.
STAFF UPDATE:
The applicant submitted a letter to staff on November 16, 2000
requesting that this application be deferred to the January 25,
2000 meeting. The applicant has retained an engineering firm to
determine if recent improvements downstream have altered the
floodway, which might warrant changes to the FEMA flood maps.
PLANNING COMMISSION ACTION:
(DECEMBER 7, 2000)
Staff informed the Commission that the applicant submitted a
letter on November 16, 2000 requesting that this application be
deferred to the January 25, 2001 agenda. Staff supported the
deferral request.
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for deferral to the
January 25, 2001 agenda. A motion to that effect was made.
The motion passed by a vote of 8 ayes, 0 nays and 3 absent.
4
FILE NO.: Z-3875-A (Cont.
PLANNING COMMISSION ACTION: (JANUARY 25, 2001)
Staff informed the Commission that the applicant's engineering
firm had done an analysis of the floodway issues involving this
property, and that Public Works needed additional
information/calculations. Staff noted that the Public Works
Department requested that this application be deferred to the
April 19, 2001 agenda to allow time for additional floodway
analysis. Staff also noted that the applicant agreed to the
deferral.
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for deferral to the April 19, 2001
agenda. A motion to that effect was made. The motion passed by
a vote of 10 ayes, 0 nays and 1 absent.
STAFF UPDATE:
Public Works received from the applicant the required analytical
proof that the new structure, built in the floodway, does not
adversely impact flood levels. The new building is in "the
shadow," hydraulically speaking, of older buildings on the site.
Because of this fortunate situation, any potential construction,
such as dredging to restore any lost carrying capacity, does not
come into play and is not required.
Public Works does, however, require that the applicant provide
an affidavit that the owner will not ever claim any flood
damages on the new structure or its contents. The affidavit
must be in legal form and be attached to the deed on file at the
county courthouse. It shall transfer with the deed. The
structure's bottom floor is more than 2 feet below the
regulatory Base Flood Elevation. Flood insurance premiums will
not be required for the structure.
Public Works supports PCD application subject to the above
conditions.
The property at 12825 I-30 contains an existing commercial
building and asphalt parking area within the C-3 zoned portion
of the property. There is currently a church located within the
west portion of the building and a boat sales business in the
east portion of the building. The applicant is requesting that
the property be rezoned to PCD to allow boat sales and display
as a permitted use. The applicant recently constructed a 2,800
square foot storage building at the east end of the existing
5
FILE NO.: Z-3875-A (Cont.)
commercial building to serve the boat sales business. There is
a fenced area within the east one-half of the property which is
used for the display of boats.
Given the property's location along I-30, with C-4 zoned
property to the east, I-2 zoned property to the west and a
racetruck on the R-2 zoned property to the south, staff has no
problem with the sale and display of boats on this property.
With resolution of the floodway issue, staff feels that the
recently constructed building and the proposed boat
sales/display business should have no adverse impact on the
general area.
STAFF RECOMMENDATION:
Staff recommends approval of the PCD rezoning subject to the
following conditions:
1. Compliance with the Public Works conditions as noted in the
"Staff Update".
2. Compliance with the requirements as noted in paragraph E. of
this report.
3. Staff recommends boat sales/display and C-3 permitted uses as
a use mix for the property.
4. The area devoted to the display of boats will be limited to
the existing fenced area as shown on the proposed site plan.
5. Any dumpster area must be screened on three (3) sides with an
eight (8) foot tall opaque fence or wall.
PLANNING COMMISSION ACTION: (APRIL 19, 2001)
The staff presented a positive recommendation on this
application, as there were no further issues for resolution.
There were no objectors to this matter.
Staff noted the following additional condition of approval, to
be added to the "Staff Recommendation" on page 6 of this report:
6. All required building permits and inspections
for the new building must be obtained within 30 days
of the passage of the PCD ordinance by the City
Board of Directors.
Public Works added the following comment:
0
FILE NO.: Z-3875-A (Cont.)
"Public Works must delete this second paragraph of
the "Staff Update" found on page 5 of the Item A
write-up. The paragraph concerns a condition of
approval for the PCD application, which is the
courthouse filing of an affidavit removing the new
storage building from the National Flood Insurance
Program. To be in compliance with our Flood Loss
Prevention Ordinance, and the rules of our
participation in the NFIP, we must offer the
applicant the option of remaining in the program.
The option we are offering is to floodproof the new
building. In the event the applicant refuses to
floodproof per regulations, we will file official
forms to FEMA which remove the structure from the
program. The structure's bottom floor is 2 feet
below base flood elevation, which requires
floodproofing to an elevation 3 feet above the
floor.
Compliance with floodproofing requirements will be
determined by future design review and construction
inspection.
The "Staff Recommendation" on the part of Public
Works continues to be approval of the PCD rezoning,
but subject to new conditions noted above."
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for approval as recommended by staff.
A motion to that effect was made. The motion passed by a vote
of 8 ayes, 0 nays and 3 absent.
7
April 19, 2001
ITEM NO.: A
NAME: Green - Short -Form PCD
LOCATION: 12825 Interstate 30
DEVELOPER:
Alvin Green
9910 Chicot Road
Little Rock, AR
AREA: 3.77 acres
FILE NO.: Z-3875-A
SURVEYOR:
Donald W. Brooks
20820 Arch Street
72209 Hensley, AR 72065
NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: C-3/R-2 ALLOWED USES: Commercial
PROPOSED USE: Boat sales and display;
C-3 permitted uses
VARIANCES/WAIVERS REQUESTED: None requested.
A. PROPOSAL/REQUEST:
The applicant proposes to rezone the property at 12825 I-30
from C-3/R-2 to PCD in order to allow boat sales and
display as a permitted use, which the property's current
zoning does not allow. The boat sales and display business
is currently being operated at this site, within a portion
of the existing commercial building. The applicant has
also recently constructed a 40 foot by 70 foot building
(for boat storage) at the east end of the existing
building. A gravel area for the display of boats has been
shown on the proposed site plan. There is currently a`
church which occupies the west one-half of the existing
building.
B. EXISTING CONDITIONS:
The site contains an existing commercial building and
asphalt parking between the building and I-30. There is a
second building (east end of the existing building) which
has recently been constructed.
April 19, 2001
SUBDIVISION
ITEM NO.: A (Cont.) FILE NO.: Z-3875-A
There is a mixture of commercial uses along I-30 to the
east and west and across I-30 to the north. There is a
creek within the southern portion of the property, with the
Optimist Club Park (race track) and a truck service
business further south.
C. NEIGHBORHOOD COMMENTS:
The Alexander Road and SWLR UP Neighborhood Associations
were notified of the public hearing. As of this writing,
staff has received no comment from the neighborhood.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
All properties are located in floodway. City does not
allow any structures in floodway.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available, not adversely affected.
AP &L : No Comment.
ARKLA: No Comment received.
Southwestern Bell: No Comment.
Water: No objection. A water main extension installed at
the expense of the developer will be required to provide water
service to this property.
Fire Department: No Comment.
County Planning: No Comment received.
CATA: Site is not located on a dedicated bus route and
has no effect on bus radius, turnout and route.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division:
This request is located in the Otter Creek Planning
District. The Land Use Plan shows Mixed Commercial and
Industrial. The applicant has applied for a Planned
2
April 19, 2001
SUBDIVISION
ITEM NO.: A (Cont.)
FILE NO.: Z-3875-A
Commercial Development for a boat sales dealership. The
property is currently zoned C-3 General Commercial. A land
use plan amendment is not required.
City Recognized Neighborhood Action Plan:
The Chicot West/I-30 South Neighborhood Action Plan
contains the economic development goal of providing a mixed
commercial/residential environment that will promote the
safety, attractiveness, and value of the area while
creating a competitive and adaptable economic climate that
encourages investment and diversity of employment
opportunities.
The Chicot West/I-30 South Neighborhood Action Plan also
states the recommendation of concentrating "...development
efforts in the more urbanized northern portion of the study
area..." This property is located on the northern boundary
of the study area.
Landscape Issues:
The proposed parking area encroaches into the 30 foot wide
street buffer required when abutting an expressway unless
located within a "mature area" designation.
G. SUBDIVISION COMMITTEE REVIEW:
Alvin Green and Bill Wiedower were present, representing
the application. Staff briefly described the proposed PCD.
Staff noted that this property is in the floodway, and that
no new structures could be constructed in the floodway.
This issue was briefly discussed. Staff suggested that the
application be deferred until the floodway issue could be
resolved. The applicant noted that a deferral would be
requested.
After the discussion, the Committee forwarded the
application to the full Commission for resolution.
H. ANALYSIS:
As noted in the Public Works Comments (paragraph D) and in
the Subdivision Committee Comments (paragraph G) , the
property at 12825 I-30 is located in the floodway and the
3
April 19, 2001
SUBDIVISION
ITEM NO.: A (Cont.)
FILE NO.: Z-3875-A
City does not allow any new construction in the floodway.
Staff and the Subdivision Committee feel that this
application should be deferred to allow the applicant time
to resolve the floodway issue.
The applicant submitted a letter to staff on October 11,
2000 requesting that this application be deferred to the
December 7, 2000 agenda. The applicant notes that an
engineering firm has been hired to do a preliminary study
to determine if any improvements made downstream have
altered the floodway. If not, the applicant will then
determine if he wants the engineering firm to perform the
necessary work to obtain a revision of the flood maps.
Staff supports the deferral as requested.
I. STAFF RECOMMENDATIONS:
Staff recommends that this application be deferred to the
December 7, 2000 agenda.
PLANNING COMMISSION ACTION:
(OCTOBER 26, 2000)
Staff informed the Commission that the applicant submitted a
letter on October 11, 2000 requesting that this application be
deferred to the December 7, 2000 agenda. Staff supported the
deferral request.
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for deferral to the
December 7, 2000 agenda. A motion to that effect was made.
The motion passed by a vote of 10 ayes, 0 nays and 1 absent.
STAFF UPDATE:
The applicant submitted a letter to staff on November 16, 2000
requesting that this application be deferred to the January 25,
2000 meeting. The applicant has retained an engineering firm to
determine if recent improvements downstream have altered the
floodway, which might warrant changes to the FEMA flood maps.
PLANNING COMMISSION ACTION: (DECEMBER 7, 2000)
Staff informed the Commission that the applicant submitted a
letter on November 16, 2000 requesting that this application be
deferred to the January 25, 2001 agenda. Staff supported the
4
April 19, 2001
SUBDIVISION
ITEM NO.: A (Cont.)
deferral request.
FILE NO.: Z-3875-A
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for deferral to the
January 25, 2001 agenda. A motion to that effect was made.
The motion passed by a vote of 8 ayes, 0 nays and 3 absent.
PLANNING COMMISSION ACTION:
(JANUARY 25, 2001)
Staff informed the Commission that the applicant's engineering
firm had done an analysis of the floodway issues involving this
property, and that Public Works needed additional
information/calculations. Staff noted that the Public Works
Department requested that this application be deferred to the
April 19, 2001 agenda to allow time for additional floodway
analysis. Staff also noted that the applicant agreed to the
deferral.
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for deferral to the April 19, 2001
agenda. A motion to that effect was made. The motion passed by
a vote of 10 ayes, 0 nays and 1 absent.
STAFF UPDATE:
Public Works received from the applicant the required analytical
proof that the new structure, built in the floodway, does not
adversely impact flood levels. The new building is in "the
shadow," hydraulically speaking, of older buildings on the site.
Because of this fortunate situation, any potential construction,
such as dredging to restore any lost carrying capacity, does not
come into play and is not required.
Public Works does, however, require that the applicant provide
an affidavit that the owner will not ever claim any flood
damages on the new structure or its contents. The affidavit
must be in legal form and be attached to the deed on file at the
county courthouse. It shall transfer with the deed. The
structure's bottom floor is more than 2 feet below the
regulatory Base Flood Elevation. Flood insurance premiums will
not be required for the structure.
Public Works supports PCD application subject to the above
conditions.
5
April 19, 2001
SUBDIVISION
ITEM NO.: A (Cont.) FILE NO.: z-3875-A
The property at 12825 I-30 contains an existing commercial
building and asphalt parking area within the C-3 zoned portion
of the property. There is currently a church located within the
west portion of the building and a boat sales business in the
east portion of the building. The applicant is requesting that
the property be rezoned to PCD to allow boat sales and display
as a permitted use. The applicant recently constructed a 2,800
square foot storage building at the east end of the existing
commercial building to serve the boat sales business. There is
a fenced area within the east one-half of the property which is
used for the display of boats.
Given the property's location along I-30, with C-4 zoned
property to the east, I-2 zoned property to the west and a
racetruck on the R-2 zoned property to the south, staff has no
problem with the sale and display of boats on this property.
With resolution of the floodway issue, staff feels that the
recently constructed building and the proposed boat
sales/display business should have no adverse impact on the
general area.
STAFF RECOMMENDATION:
Staff recommends approval of the PCD rezoning subject to the
following conditions:
1. Compliance with the Public Works conditions as noted in the
"Staff Update".
2. Compliance with the requirements as noted in paragraph E. of
this report.
3. Staff recommends boat sales/display and C-3 permitted uses as
a use mix for the property.
4. The area devoted to the display of boats will be limited to
the existing fenced area as shown on the proposed site plan.
5.Any dumpster area must be screened on three (3) sides with an
eight (8) foot tall opaque fence or wall.
PLANNING COMMISSION ACTION: (APRIL 19, 2001)
The staff presented a positive recommendation on this
application, as there were no further issues for resolution.
There were no objectors to this matter.
6
April 19, 2001
SUBDIVISION
ITEM NO.: A (Cont.)
FILE NO.: Z-3875-A
Staff noted the following additional condition of approval, to
be added to the "Staff Recommendation" on page 6 of this report:
6. All required building permits and inspections
for the new building must be obtained within 30 days
of the passage of the PCD ordinance by the City
Board of Directors.
Public Works added the following comment:
"Public Works must delete the second paragraph of
the "Staff Update" found on page 5 of the Item A
write-up. The paragraph concerns a condition of
approval for the PCD application, which is the
courthouse filing of an affidavit removing the new
storage building from the National Flood Insurance
Program. To be in compliance with our Flood Loss
Prevention Ordinance, and the rules of our
participation in the NFIP, we must offer the
applicant the option of remaining in the program.
The option we are offering is to floodproof the new
building. In the event the applicant refuses to
floodproof per regulations, we will file official
forms to FEMA which remove the structure from the
program. The structure's bottom floor is 2 feet
below base flood elevation, which requires
floodproofing to an elevation 3 feet above the
floor.
Compliance with floodproofing requirements will be
determined by future design review and construction
inspection.
The "Staff Recommendation" on the part of Public
Works continues to be approval of the PCD rezoning,
but subject to new conditions noted above."
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for approval as recommended by staff.
A motion to that effect was made. The motion passed by a vote
of 8 ayes, 0 nays and 3 absent.
7
April 19, 2%_1
ITEM NO.: A
NAME: Green - Short -Form PCD
LOCATION: 12825 Interstate 30
DEVELOPER:
Alvin Green
9910 Chicot Road
Little Rock, AR
AREA: 3.77 acres
FILE NO.: Z-3875-A
SURVEYOR:
Donald W. Brooks
20820 Arch Street
72209 Hensley, AR 72065
NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: C-3/R-2 ALLOWED USES: Commercial
PROPOSED USE:
Boat sales and display;
C-3 permitted uses
VARIANCES/WAIVERS REQUESTED: None requested.
A. PROPOSAL/REQUEST:
The applicant proposes to rezone the property at 12825 I-30
from C-3/R-2 to PCD in order to allow boat sales and
display as a permitted use, which the property's current
zoning does not allow. The boat sales and display business
is currently being operated at this site, within a portion
of the existing commercial building. The applicant has
also recently constructed a 40 foot by 70 foot building
(for boat storage) at the east end of the existing
building. A gravel area for the display of boats has been
shown on the proposed site plan. There is currently a
church which occupies the west one-half of the existing
building.
B. EXISTING CONDITIONS:
The site contains an existing commercial building and
asphalt parking between the building and I-30. There is a
second building (east end of the existing building) which
has recently been constructed.
April 19, 2w-_1
SUBDIVISION
ITEM NO.: A (Cont.)
FILE NO.: Z-3875-A
There is a mixture of commercial uses along I-30 to the
east and west and across I-30 to the north. There is a
creek within the southern portion of the property, with the
Optimist Club Park (race track) and a truck service
business further south.
C. NEIGHBORHOOD COMMENTS:
The Alexander Road and SWLR UP Neighborhood Associations
were notified of the public hearing. As of this writing,
staff has received no comment from the neighborhood.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
All properties are located in floodway. City does not
allow any structures in floodway.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available, not adversely affected.
AP&L: No Comment.
ARKLA: No Comment received.
Southwestern Bell: No Comment.
Water: No objection. A water main extension installed at
the expense of the developer will be required to provide water
service to this property.
Fire Department: No Comment.
County Planning: No Comment received.
CATA: Site is not located on a dedicated bus route and
has no effect on bus radius, turnout and route.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division:
This request is located in the Otter Creek Planning
District. The Land Use Plan shows Mixed Commercial and
Industrial. The applicant has applied for a Planned
`a
April 19, 2t_1
SUBDIVISION
ITEM NO.: A (Cont.
FILE NO.: Z-3875-A
Commercial Development for a boat sales dealership. The
property is currently zoned C-3 General Commercial. A land
use plan amendment is not required.
City Recognized Neighborhood Action Plan:
The Chicot West/I-30 South Neighborhood Action Plan
contains the economic development goal of providing a mixed
commercial/residential environment that will promote the
safety, attractiveness, and value of the area while
creating a competitive and adaptable economic climate that
encourages investment and diversity of employment
opportunities.
The Chicot West/I-30 South Neighborhood Action Plan also
states the recommendation of concentrating "...development
efforts in the more urbanized northern portion of the study
area..." This property is located on the northern boundary
of the study area.
Landscape Issues:
The proposed parking area encroaches into the 30 foot wide
street buffer required when abutting an expressway unless
located within a "mature area" designation.
G. SUBDIVISION COMMITTEE REVIEW:
Alvin Green and Bill Wiedower were present, representing
the application. Staff briefly described the proposed PCD.
Staff noted that this property is in the floodway, and that
no new structures could be constructed in the floodway.
This issue was briefly discussed. Staff suggested that the
application be deferred until the floodway issue could be
resolved. The applicant noted that a deferral would be
requested.
After the discussion, the Committee forwarded the
application to the full Commission for resolution.
H. ANALYSIS:
As noted in the Public Works Comments (paragraph D) and in
the Subdivision Committee Comments (paragraph G), the
property at 12825 I-30 is located in the floodway and the
3
April 19, 2t--i
SUBDIVISION
ITEM NO.: A (Cont.) FILE NO.: Z-3875-A
City does not allow any new construction in the floodway.
Staff and the Subdivision Committee feel that this
application should be deferred to allow the applicant time
to resolve the floodway issue.
The applicant submitted a letter to staff on October 11,
2000 requesting that this application be deferred to the
December 7, 2000 agenda. The applicant notes that an
engineering firm has been hired to do a preliminary study
to determine if any improvements made downstream have
altered the floodway. If not, the applicant will then
determine if he wants the engineering firm to perform the
necessary work to obtain a revision of the flood maps.
Staff supports the deferral as requested.
I. STAFF RECOMMENDATIONS:
Staff recommends that this application be deferred to the
December 7, 2000 agenda.
PLANNING COMMISSION ACTION:
(OCTOBER 26, 2000)
Staff informed the Commission that the applicant submitted a
letter on October 11, 2000 requesting that this application be
deferred to the December 7, 2000 agenda. Staff supported the
deferral request.
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for deferral to the
December 7, 2000 agenda. A motion to that effect was made.
The motion passed by a vote of 10 ayes, 0 nays and 1 absent.
STAFF UPDATE:
The applicant submitted a letter to staff on November 16, 2000
requesting that this application be deferred to the January 25,
2000 meeting. The applicant has retained an engineering firm to
determine if recent improvements downstream have altered the
floodway, which might warrant changes to the FEMA flood maps.
PLANNING COMMISSION ACTION:
(DECEMBER 7, 2000)
Staff informed the Commission that the applicant submitted a
letter on November 16, 2000 requesting that this application be
deferred to the January 25, 2001 agenda. Staff supported the
4
April 19, 2t,-1
SUBDIVISION
ITEM NO.: A (Cont.)
deferral request.
FILE NO.: Z-3875-A
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for deferral to the
January 25, 2001 agenda. A motion to that effect was made.
The motion passed by a vote of 8 ayes, 0 nays and 3 absent.
PLANNING COMMISSION ACTION:
(JANUARY 25, 2001)
Staff informed the Commission that the applicant's engineering
firm had done an analysis of the floodway issues involving this
property, and that Public Works needed additional
information/calculations. Staff noted that the Public Works
Department requested that this application be deferred to the
April 19, 2001 agenda to allow time for additional floodway
analysis. Staff also noted that the applicant agreed to the
deferral.
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for deferral to the April 19, 2001
agenda. A motion to that effect was made. The motion passed by
a vote of 10 ayes, 0 nays and 1 absent.
STAFF UPDATE:
Public Works received from the applicant the required analytical
proof that the new structure, built in the floodway, does not
adversely impact flood levels. The new building is in "the
shadow," hydraulically speaking, of older buildings on the site.
Because of this fortunate situation, any potential construction,
such as dredging to restore any lost carrying capacity, does not
come into play and is not required.
Public Works does, however, require that the applicant provide
an affidavit that the owner will not ever claim any flood
damages on the new structure or its contents. The affidavit
must be in legal form and be attached to the deed on file at the
county courthouse. It shall transfer with the deed. The
structure's bottom floor is more than 2 feet below the
regulatory Base Flood Elevation. Flood insurance premiums will
not be required for the structure.
Public Works supports PCD application subject to the above
conditions.
�1
April 19, 2-,l
SUBDIVISION
ITEM NO.: A (Cont.) FILE NO.: Z-3875-A
The property at 12825 I-30 contains an existing commercial
building and asphalt parking area within the C-3 zoned portion
of the property. There is currently a church located within the
west portion of the building and a boat sales business in the
east portion of the building. The applicant is requesting that
the property be rezoned to PCD to allow boat sales and display
as a permitted use. The applicant recently constructed a 2,800
square foot storage building at the east end of the existing
commercial building to serve the boat sales business. There is
a fenced area within the east one-half of the property which is
used for the display of boats.
Given the property's location along I-30, with C-4 zoned
property to the east, I-2 zoned property to the west and a
racetruck on the R-2 zoned property to the south, staff has no
problem with the sale and display of boats on this property.
With resolution of the floodway issue, staff feels that the
recently constructed building and the proposed boat
sales/display business should have no adverse impact on the
general area.
STAFF RECOMMENDATION:
Staff recommends approval of the PCD rezoning subject to the
following conditions:
1.Compliance with the Public Works conditions as noted in the
"Staff Update".
2.Compliance with the requirements as noted in paragraph E. of
this report.
3.Staff recommends boat sales/display and C-3 permitted uses as
a use mix for the property.
4.The area devoted to the display of boats will be limited to
the existing fenced area as shown on the proposed site plan.
5.Any dumpster area must be screened on three (3) sides with an
eight (8) foot tall opaque fence or wall.
PLANNING COMMISSION ACTION: (APRIL 19, 2001)
The staff presented a positive recommendation on this
application, as there were no further issues for resolution.
There were no objectors to this matter.
Ni
April 19, 2_A
SUBDIVISION
ITEM NO.: A (Cont.
FILE NO.: Z-3875-A
Staff noted the following additional condition of approval, to
be added to the "Staff Recommendation" on page 6 of this report:
6. All required building permits and inspections
for the new building must be obtained within 30 days
of the passage of the PCD ordinance by the City
Board of Directors.
Public Works added the following comment:
"Public Works must delete the second paragraph of
the "Staff Update" found on page 5 of the Item A
write-up. The paragraph concerns a condition of
approval for the PCD application, which is the
courthouse filing of an affidavit removing the new
storage building from the National Flood Insurance
Program. To be in compliance with our Flood Loss
Prevention Ordinance, and the rules of our
participation in the NFIP, we must offer the
applicant the option of remaining in the program.
The option we are offering is to floodproof the new
building. In the event the applicant refuses to
floodproof per regulations, we will file official
forms to FEMA which remove the structure from the
program. The structure's bottom floor is 2 feet
below base flood elevation, which requires
floodproofing to an elevation 3 feet above the
floor.
Compliance with floodproofing requirements will be
determined by future design review and construction
inspection.
The "Staff Recommendation" on the part of Public
Works continues to be approval of the PCD rezoning,
but subject to new conditions noted above."
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for approval as recommended by staff.
A motion to that effect was made. The motion passed by a vote
of 8 ayes, 0 nays and 3 absent.
7