HomeMy WebLinkAboutZ-8605-B Staff AnalysisFILE NO.: Z-8605-B
NAME: SRVC on Kanis Short -form PD-C
LOCATION: Located at 11601 Kanis Road
DEVELOPER:
SRVC
304 North Shackleford Road
Little Rock, AR 72212
SURVEYOR -
Thomas Engineering
2810 Lookout Road
North Little Rock, AR 72116
AREA: 2.93 acres
CURRENT ZONING
ALLOWED USES
PROPOSED ZONING
PROPOSED USE
VARIANCE/WAIVERS
BACKGROUND,
NUMBER OF LOTS: 1
P D-C
NEW STREET: 0 LF
0-3, General Office District uses, Resale shop and Daycare
P D-C
0-3, General Office District and Vet clinic with grooming and
indoor boarding
None requested.
Ordinance No. 20,365 adopted by the Little Rock Board of Directors on December 7,
2010, established Lot 1 Edwards Addition Short -form POD. The property was originally
constructed as a single-family residence but was later converted to an office uses prior
to annexation to the City. With the conversion, the entire front yard was paved for
parking. The applicant proposed a rezoning of the site from R-2, Single-family to POD
to allow the reuse of the site as a daycare facility. The applicant requested to utilize
0-3, General Office District uses as allowable alternative uses for the site. The daycare
center did not open at this location.
FILE NO.: Z-8605-B (Cont.
Ordinance No. 20,631 adopted by the Little Rock Board of Directors on September 4,
2012, rezoned the site to Planned Development Commercial, PD-C, to allow the use of
the building as a resale shop. The hours of operation were proposed from 7:00 am to
8:00 pm seven (7) days per week. The applicant requested 0-3, General Office District
uses as allowable alternative uses for the site.
A. PROPOSAL/REQUEST/APPLICANT'S STATEMENT:
The applicant is now requesting to demolish the existing structure and construct
a new 4,500 square foot veterinary clinic. The site plan indicates future
construction of a 3,010 square foot grooming facility and a 468 square foot
storage shed. The site plan indicates 26 on -site parking spaces. The
development is proposed in two (2) phase. The first phase will be the
construction of the vet clinic which will include indoor boarding. The second
phase will include the construction of the grooming facility which will also include
space for indoor boarding.
B. EXISTING CONDITIO
The building was previously a single-family residence but was most recently
occupied by the Sparrows Nest, a resale shop. The front yard area has been
paved from what appears to be property line to property line. The back yard area
is open. Other uses in the area include an office development located to the
north at the northwest corner of Kanis and Autumn Roads. There is a property
located on the northeast corner of Kanis and Autumn Roads that is zoned POD
and was approved for an office/warehouse development. Further north on
Autumn Road is a daycare center. East of the site with frontage on Kanis Road
is an office building and a second office building is located to the south accessed
by a driveway/access easement from Kanis Road. West of the site are
three (3) office buildings and further west is a single-family home with an
upholstery shop located behind the home.
C. NEIGHBORHOOD COMMENTS. -
As of this writing, staff has received an informational phone call from an area
property owner. All property owners located within 200-feet of the site along with
the John Barrow Neighborhood Association were notified of the public hearing.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Kanis Road is classified on the Master Street Plan as a minor arterial.
A dedication of right-of-way 45 feet from centerline will be required.
2. With site development, provide the design of street conforming to the Master
Street Plan. Construct one-half street improvement to these streets including
5-foot sidewalks with the planned development. The proposed back of curb
N
FILE NO.: Z-8605-B (Cont.
should be located 29.5 feet from centerline. If a permit is pulled prior to the
bidding of the City of Little Rock Kanis Road project, the applicant will be
responsible to construct the widening to Kanis Road. If so, a payment in -lieu
of construction should be made to the City of Little Rock.
3. A grading permit in accordance with Section 29-186 (c) & (d) will be required
prior to any land clearing or grading activities at the site. Other than
residential subdivisions, site grading and drainage plans must be submitted
and approved prior to the start of construction. Is a variance requested to
advance grade the future grooming facility with construction of the proposed
vet clinic?
4. All driveways shall be concrete aprons per City Ordinance.
5. Repair or replace any curb and gutter or sidewalk that is damaged in the
public right-of-way prior to occupancy.
6. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan.
7. If disturbed area is one (1) or more acres, obtain a NPDES stormwater permit
from the Arkansas Department of Environmental Quality prior to the start of
construction.
8. Driveway locations and widths do not meet the traffic access and circulation
requirements of Sections 30-43 and 31-210. The current driveway location
will cause vehicle waiting to make left turns into the site to block the Autumn
Road/Kanis Road intersection. The subject property must share a driveway
access with the property to the east. The width of the driveway must not
exceed 36 feet. The City of Little Rock Kanis Road project will construct one
(1) driveway at the property line for both properties to share.
9. Damage to public and private property due to hauling operations or operation
of construction related equipment from a nearby construction site shall be
repaired by the responsible party prior to issuance of a certificate
of occupancy.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available to this site-
Entergy: Entergy does not object to this proposal. A single phase power line
exists along the west side of this proposed development. There do not appear to
be any conflicts with existing Entergy facilities. Contact Entergy in advance
regarding future service requirements to the development, desired line
extensions, and future facilities locations as this project proceeds.
Centerpoint Energy: No comment received.
AT & T: No comment.
3
FILE NO.: Z-8605-B (Cont.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for
water service must be met.
2. A water main extension will be needed to provide water service to the
property.
3. The Little Rock Fire Department needs to evaluate this site to determine
whether additional public and/or private fire hydrant(s) will be required.
If additional fire hydrant(s) are required, they will be installed at the
Developer's expense.
4. Please submit plans for water facilities and/or fire protection system to
Central Arkansas Water for review. Plan revisions may be required after
additional review. Contact Central Arkansas Water regarding procedures
for installation of water facilities and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering Division and the Little Rock
Fire Department is required.
5. A Capital Investment Charge based on the size of meter connection(s) will
apply to this project in addition to normal charges. This fee will apply to all
connections including metered connections off the private fire system.
6. Contact Central Arkansas Water regarding the size and location of water
meter.
7. Due to the nature of this facility, installation of an approved reduced
pressure zone backflow preventer assembly (RPZA) is required on the
domestic water service. This assembly must be installed prior to the first
point of use. Central Arkansas Water requires that upon installation of the
RPZA, successful tests of the assembly must be completed by a Certified
Assembly Tester licensed by the State of Arkansas and approved by
Central Arkansas Water. The test results must be sent to Central Arkansas
Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 501.377.1226
if you would like to discuss backflow prevention requirements for this
project.
8. The facilities on -site will be private. When meters are planned off private
lines, private facilities shall be installed to Central Arkansas Water's
materials and construction specifications and installation will be inspected
by an engineer, licensed to practice in the State of Arkansas. Execution of
a Customer Owned Line Agreement is required.
9. Fire sprinkler systems which do not contain additives such as antifreeze
shall be isolated with a double detector check valve assembly. If additives
area used, a reduced pressure zone back flow preventer shall be required.
10. This development will have minor impact on the existing water distribution
system. Proposed water facilities will be sized to provide adequate
pressure and fire protection.
M
FILE NO.: Z-8605-B (Cont.
Fire Department: No comment.
Parks and Recreation: No comment received.
County Planning: No comment.
Rock Region Metro: Location is currently served on route 5, West Markham by
Rock Region METRO. We feel the one element missing from the plan is a
pedestrian path through the parking area from the sidewalk to give access to the
bus route for shopping and jobs. We would request to consolidate curb cuts. We
have no objections to the development proposal.
F. ISSUES/TECHNICAL/DESIGN:
Building Code: Project is subject to full commercial plan review and approval
prior to issuance of a building permit. For information on submittal requirements
and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey(a)littlerock.orq or
Mark Alderfer at 501.371.4875; malderfer littlerock.or .
Planning Division: This request is located in the 1-430 Planning District. The
Land Use Plan shows Mixed Office and Commercial (MOC). The Mixed Office
and Commercial category provides for a mixture of office and commercial uses to
occur. Acceptable uses are office or mixed office and commercial. A Planned
Zoning District is required if the use is mixed office and commercial. The
applicant has applied for a revision to an existing PD-C (Planned District
Commercial) to allow for the construction of a new building for a veterinarian
clinic and associated parking.
Master Street Plan: Kanis Road is a Minor Arterial on the Master Street Plan.
A Minor Arterial provides connections to and through an urban area and their
primary function is to provide short distance travel within the urbanized area.
Entrances and exits should be limited to minimize negative effects of traffic and
pedestrians on Kanis Road since it is a Minor Arterial. This street may require
dedication of right-of-way and may require street improvements for entrances
and exits to the site.
Bicycle Plan There are no bike routes shown in the immediate vicinity.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance
requirements.
2. Street buffers will be required at six (6) percent of the average depth of the
lot. The minimum dimension shall be one-half ('/2) the full width
5
FILE NO.: Z-8605-B
requirement but in no case less than nine (9) feet. The maximum
dimension required shall be fifty (50) feet.
3. Trees and shrubs are required planted adjacent to street right-of-way.
Plant material is to be provided at 1 tree and 3 shrubs for every 30 linear
feet. Existing trees and vegetation can be used to satisfy landscape
requirements. A fifty (50) foot street buffer will be required along Kanis
Road.
4. Screening requirements will need to be met for the vehicular use areas
adjacent to street right-of-ways. Provide screening shrubs with an average
linear spacing of not less at three (3) feet within the required landscape
area. Provide trees with an average linear spacing of not less than thirty
(30) feet.
5. A perimeter planting strip is required along any side of a vehicular use
area that abuts adjoining property or the right-of-way of any street. This
strip shall be at least nine (9) feet wide. One (1) tree and three (3) shrubs
or vines shall be planted for every thirty (30) linear feet of perimeter
planting strip.
6. An automatic irrigation system to water landscaped areas shall be
required for developments of one (1) acre or larger.
7. The development of two (2) acres or more requires the landscape plan to
be stamped with the seal of a Registered Landscape Architect.
8. The City Beautiful Commission recommends preserving as many existing
trees as feasible on this site. Credit toward fulfilling Landscape Ordinance
requirements can be given when preserving trees of six (6) inch caliper or
larger.
G. SUBDIVISION COMMITTEE COMMENT -
(December 9, 2015)
Mr. Thomas Pownell of Thomas Engineering was present representing the
request. Staff stated the applicant was proposing to amend the previously
approved PD-C to allow the demolition of an existing structure and the
construction of a new vet clinic. Staff stated new parking would be added to the
site in addition to the new building. Staff stated a second structure was indicated
on the site plan for future construction of a grooming facility. Staff requested
Mr. Pownell provide the days and hours of operation, the proposed signage plan,
the number of pets to be boarded and the location of any proposed fencing.
Public Works comments were addressed. Staff stated this drive and the drive to
the east should be combined into a single driveway location. Staff stated Kanis
Road was slated to bid in May of 2016. Staff stated if this project requested a
building permit prior to the bid letting of the Kanis Road improvements this owner
would be required to make a payment in -lieu of construction for the required
improvements along this frontage. Mr. Pownell questioned the right of way
dedication required for Kanis Road. Staff stated the right of way was shifting to
the north by 20-feet along this section of the street.
0
FILE NO.: Z-8605-B (Cont.
Landscaping comments were addressed. Staff stated the street buffer along
Kanis Road should average 50-feet and in no case be less than 25-feet. Staff
stated the minimum landscape strip adjacent to the paved areas should be nine
(9) feet. Staff stated screening of the vehicular use area was required by the
planting of shrubs or vines. Staff stated an automatic irrigation system to water
landscaped areas was required for sites larger than one (1) acre.
Staff noted the comments from the various other departments and agencies.
Staff suggested the applicant contact the departments or agencies directly with
any questions or concerns. There were no more issues for discussion. The
Committee then forwarded the item to the full Commission for final action.
H. ANALYSIS.
The applicant submitted a revised site plan to staff addressing a number of the
issues raised at the December 9, 2015, Subdivision Committee meeting. The
applicant has provided the required street buffer along Kanis Road. The
applicant has also provided the days and hours of operation, the proposed
signage plan, the number of pets to be boarded and the location of any proposed
fencing.
The request is to rezone the site to allow the redeveloping of the property with a
new vet clinic. The applicant proposes to demolish the existing structure and
construct a new 4,500 square foot veterinary clinic. The site plan indicates future
construction of a 3,010 square foot grooming facility and a 468 square foot
storage shed. The development is proposed in two (2) phase. The first phase
will be the construction of the vet clinic which will include indoor boarding. The
second phase will include the construction of the grooming facility which will also
include space for indoor boarding.
The applicant has indicated boarding will be provided to clients. The applicant
states the clinic will have spaces for approximately 25 animals. The grooming
facility will accommodate 60 animals, 40 dogs and 20 cats. All animal boarding
will be inside the building. The dogs will be walked twice a day. The applicant
has stated there will not be any outdoor runs or kennels. The site plan does
include an area to be fenced to allow a safe place to walk the animals but no pets
will be left outdoors without supervision.
The maximum building height proposed is 25-feet. The materials will be a
combination of brick, stucco, metal siding and/or stone. The applicant has
indicated the building will be constructed with a peak roof.
The site plan indicates 26 on -site parking spaces. Parking for a medical office is
six (6) spaces per doctor and parking for a general and professional office is one
(1) space for every 400 gross square feet of floor area. The clinic will have
no more than two (2) doctors. This would require the placement of
7
Z-8605-B (Cont.
twelve (12) spaces. The grooming facility contains 3,010 square feet and based
on the parking requirement for an office seven (7) spaces would be required.
The site plan indicates the placement of building signage along Kanis Road. In
addition the front of the building will face east as will the grooming facility. The
applicant is requesting signage be allowed on the eastern facades of these
two (2) buildings. A single ground sign is proposed. The applicant has indicated
the sign will be a monument style sign. Staff recommends the signage be limited
to a maximum height of six (6) feet and a maximum sign area of 64 square feet.
The site plan includes the placement of a dumpster along the southern perimeter
of the site. A note indicates the dumpster will be screened per typical ordinance
requirements by the placement of a six (6) foot wood fence around the facility.
The hours of service are limited to 7 am to 6 pm Monday through Friday. The
hours of operation of the clinic are 7 am to 8 pm Monday through Saturday.
Staff is supportive of the applicant's request. The applicant is seeking approval
of a revision to the existing PD-C to allow the redevelopment of the site as a vet
clinic. The site is shown on the City's Future Land Use Plan as Mixed Office
Commercial. Staff does not feel the development as proposed will have any
adverse impact on this site or of abutting properties.
STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
PLANNING COMMISSION ACTION' (JANUARY 7, 2016)
The applicant was present. There was one registered objector present. Staff presented
the item with a recommendation of approval of the request subject to compliance with
the comments and conditions as outlined in paragraphs D, E and F of the agenda staff
report.
Mr. Thomas Pownell, representing the applicant, stated he would yield his time to the
opposition.
Mr. Pat Malmstrom addressed the Commission with concerns. He stated he was in full
support of the vet clinic and the grooming facility but was not in support of the boarding
facility. He stated the request included up to 40 dogs which with the barking could get
very loud. He stated his office was located approximately 60-feet from the proposed
building to house the boarded animals. He stated he was also concerned with the smell
that could be generated from the animal waste. He stated the area proposed for
outdoor play was 8,000 square feet which was quiet large and if not properly cleaned
could generate a significant smell. He stated the driveway location was a concern but
FILE NO.: Z-8605-B (Cont.
felt the shared drive with the property to the east would lessen any potential impacts of
conflicting movements with Autumn Road.
Mr. Pownell stated the animals would be taken out three (3) to four (4) times per day
and all waste would be cleaned from the site on a daily basis. He stated no more than
three (3) pets would be taken outside at a time due to staffing limitations. He stated the
driveway was being relocated to align with Autumn Road which would lessen any
conflicting traffic movements.
Commissioner Bubbus questioned staff of the proposed driveway location. Staff stated
the drive was being constructed as requested by staff as a part of the Kanis Road
widening project. Staff stated the new design would align with Autumn Road.
There was no further discussion. A motion was made to approve the request as
recommended by staff including all staff recommendations and comments by a vote of
10 ayes, 0 noes and 1 absent.
9
ITEM NO.: 17,
NAME: SRVC on Kanis Short -form PD-C
LOCATION: located at 11601 Kanis Road
Planning Staff Comments:
1. Provide notification of the property owners located within 200-feet of the development
including the certified abstract list, notice form with affidavit executed and proof of
mailing. The notice must be mailed no later than December 23, 2015. The Office of
Planning and Development must receive the proof of notice no later than December
31, 2015.
Thomas Engineering Company (TEC) Response: Thomas Engineering will provide
notification.
2. Indication of location of structures and structure dimensions, dimensioned distances
between buildings and distances from structures to property lines.
TEC Response: Drawing updated to include requested items.
3. Proposed treatment of the perimeter of the property, including materials and
techniques used such as screens, fences and walls as well as description of uses,
setbacks and their relationship to surrounding uses.
TEC Response: Drawing updated to include requested items. The HVAC systems will
be screened with fencing.
4. Provide the location of the proposed dumpster facilities to serve the development.
The dumpster may not be located within the front yard setback. Provide a note
concerning the required screening of the proposed dumpster facilities to comply with
typical ordinance standards.
TEC Response: Drawing updated to include requested items.
5. Will the hours of dumpster service be limited to daylight hours? If so include a note
on the site plan stating such (7 am to 6 pm Monday through Friday).
TEC Response:
6. Provide details of any proposed fencing for the development including perimeter
fencing and any proposed interior fencing.
Response: Drawing updated to include requested items.
7. Will there be a sign identifying the development? If so provide the location(s) and the
height and total sign area proposed for the signage. Provide the elevations which are
proposed with building signage.
Response: A monument sign and building sign will be included in the final plans. The
signs will be submitted for review and approval.
8. Provide the proposed construction materials for the buildings including the proposed
roofing material.
Response: The building will be brick and wood. The roof will be asphalt shingles.
9. Provide the proposed building elevations for the proposed structures.
Response: The building elevations are to be prepared with final plans submitted for
building permit. The height of the building is noted in Item 11 below.
10. Provide details of any proposed fencing located along the perimeters.
TEC Response: Drawing updated to include requested items.
11. Provide the maximum building height and the number of stories of the proposed
structures.
Response: The buildings will be one story with a peaked roof.
12. Will there be boarding with overnight stay? If so provide the number of pets proposed
to be boarded.
Response: Yes there will be boarding. The vet clinic will have spaces for
approximately 25 animals boarded The Grooming facility will have approximately 60
spaces for animals (40 dogs, 20 cats). All animals will be boarded inside. The dogs
will be walked twice a day. No outside boarding.
13. Identify any areas proposed for outdoor activities.
TEC Response. Drawing updated to include requested items.
14. What is the purpose of the drive to the adjacent eastern property?
TEC Response: The drive to the adjacent eastern property will connect the two
properties' parking lots for access.
Variance/Waivers.
Public Works Conditions:
Kanis Rd is classified on the Master Street Plan as a minor arterial. A dedication of
right-of-way 45 feet from centerline will be required.
TEC Response: The property owner will comply with the request.
2. With site development, provide design of street conforming to the Master Street Plan.
Construct one-half street improvement to these streets including 5-foot sidewalks with
planned development. The proposed back of curb should be located 29.5 ft from
centerline. If a permit is pulled prior to the bidding of the CLR Kanis Rd project, the
applicant will be responsible to construct the widening to Kanis Rd. If so, a payment
in -lieu of construction should be made to CLR.
TEC Response: The building permit is not expected to be obtained prior the the
bidding of Kanis Rd. If the building permit is pulled prior to the bidding of Kanis Rd the
property owner will comply with the request.
3. A grading permit in accordance with section 29-186 (c) & (d) will be required prior to
any land clearing or grading activities at the site. Other than residential subdivisions,
site grading and drainage plans must be submitted and approved prior to the start of
construction. Is a variance requested to advance grade the future grooming facility
with construction of the proposed vet clinic?
TEC Response: The property will be graded for the future improvements identified on
the drawing.
4. All driveways shall be concrete aprons per City Ordinance.
TEC Response: Final design plans will comply with the comment.
5. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-
of-way prior to occupancy.
TEC Response: The improvements will comply with the above comment.
6. Storm water detention ordinance applies to this property. Show the proposed location
for stormwater detention facilities on the plan.
TEC Response: Drawing updated to include requested items.
7. If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the
Arkansas Department of Environmental Quality prior to the start of construction.
TEC Response: The improvements will comply with the above comment.
8. Driveway locations and widths do not meet the traffic access and circulation
requirements of Sections 30-43 and 31-210. The current driveway location will cause
vehicle waiting to make left turns into the site to block the Autumn Rd/Kanis Rd
intersection. The subject property must share a driveway access with the property to
the east. The width of the driveway must not exceed 36 ft. The CLR Kanis Rd Project
will construct 1 driveway at the property line for both properties to share.
TEC Response: The drawing is updated to show a shared driveway with the adjacent
property to the east. Final plans will be coordinated with CLR for location of driveway.
9. Damage to public and private property due to hauling operations or operation of
construction related equipment from a nearby construction site shall be repaired by
the responsible party prior to issuance of a certificate of occupancy.
TEC Response: The improvements will comply with the above comment.
Utilities and Fire Department/County Planning:
Wastewater: Sewer available to this site.
Entergy: Entergy does not object to this proposal. A single phase power line exists along
the west side of this proposed development. There do not appear to be any conflicts with
existing Entergy facilities. Contact Entergy in advance regarding future service
requirements to the development, desired line extensions, and future facilities locations
as this project proceeds.
Centerpoint Energy: No comment received.
AT & T: No comment.
Central Arkansas Water:
TEC Response: The final plans submitted for building permit will comply with the CAW
comments below.
1. All Central Arkansas Water requirements in effect at the time of request for water
service must be met.
2. A water main extension will be needed to provide water service to the property.
3. The Little Rock Fire Department needs to evaluate this site to determine whether
additional public and/or private fire hydrant(s) will be required. If additional fire
hydrant(s) are required, they will be installed at the Developer's expense.
4. Please submit plans for water facilities and/or fire protection system to Central
Arkansas Water for review. Plan revisions may be required after additional review.
Contact Central Arkansas Water regarding procedures for installation of water
facilities and/or fire service. Approval of plans by the Arkansas Department of Health
Engineering Division and the Little Rock Fire Department is required.
5. A Capital Investment Charge based on the size of meter connection(s) will apply to
this project in addition to normal charges. This fee will apply to all connections
including metered connections off the private fire system.
6. Contact Central Arkansas Water regarding the size and location of water meter.
7. Due to the nature of this facility, installation of an approved reduced pressure zone
backflow preventer assembly (RPZA) is required on the domestic water service. This
assembly must be installed prior to the first point of use. Central Arkansas Water
requires that upon installation of the RPZA, successful tests of the assembly must be
completed by a Certified Assembly Tester licensed by the State of Arkansas and
approved by Central Arkansas Water. The test results must be sent to Central
Arkansas Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 501.377.1226 if you
would like to discuss backflow prevention requirements for this project.
8. The facilities on -site will be private. When meters are planned off private lines, private
facilities shall be installed to Central Arkansas Water's materials and construction
specifications and installation will be inspected by an engineer, licensed to practice in
the State of Arkansas. Execution of a Customer Owned Line Agreement is required.
9. Fire sprinkler systems which do not contain additives such as antifreeze shall be
isolated with a double detector check valve assembly. If additives area used, a
reduced pressure zone back flow preventer shall be required.
10.This development will have minor impact on the existing water distribution system.
Proposed water facilities will be sized to provide adequate pressure and fire
protection.
Fire Department: No comment.
Parks and Recreation: No comment received.
County Planning: No comment.
Rock Region Metro: Location is currently served on route 5, West Markham by Rock
Region METRO. We feel the one element missing from the plan is a pedestrian path
through the parking area from the sidewalk to give access to the bus route for shopping
and jobs. We would request to consolidate curb cuts. We have no objections to the
development proposal.
Building Code: Project is subject to full commercial plan review and approval prior to
issuance of a building permit. For information on submittal requirements and the review
process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey(M-littlerock.org or
Mark AlderFer at 501.371.4875; malderferglittlerock.org.
Planning Division: This request is located in the 1-430 Planning District. The Land Use
Plan shows Mixed Office and Commercial (MOC). The Mixed Office and Commercial
category provides for a mixture of office and commercial uses to occur. Acceptable uses
are office or mixed office and commercial. A Planned Zoning District is required if the use
is mixed office and commercial. The applicant has applied for a revision to an existing
PD-C (Planned District Commercial) to allow for the construction of a new building for a
veterinarian clinic and associated parking.
Master Street Plan: Kanis Road is a Minor Arterial on the Master Street Plan. A Minor
Arterial provides connections to and through an urban area and their primary function is
to provide short distance travel within the urbanized area. Entrances and exits should be
limited to minimize negative effects of traffic and pedestrians on Kanis Road since it is a
Minor Arterial. This street may require dedication of right-of-way and may require street
improvements for entrances and exits to the site.
TEC Response: The items noted in Public Works comments and the TEC responses
address this comment.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Landscape:
Site plan must comply with the City's landscape and buffer ordinance
requirements.
TEC Response: The improvements will comply with the above comment.
2. Street buffers will be required at six (6) percent of the average depth of the lot. The
minimum dimension shall be one-half (Y2) the full width requirement but in no case
less than nine (9) feet. The maximum dimension required shall be fifty (50) feet.
TEC Response: The improvements will comply with the above comment.
3. Trees and shrubs are required planed adjacent to street right-of-way. Plant
material is to be provided at 1 tree and 3 shrubs for every 30 linear feet. Existing
trees and vegetation can be used to satisfy landscape requirements. A fifty (50)
foot street buffer will be required along Kanis Road.
TEC Response: The improvements will comply with the above comment. A 50-ft
foot street buffer was added on the updated drawing.
4. Screening requirements will need to be met for the vehicular use areas adjacent
to street right-of-ways. Provide screening shrubs with an average linear spacing of
not less at three (3) feet within the required landscape area. Provide trees with an
average linear spacing of not less than thirty (30) feet.
TEC Response: The improvements will comply with the above comment.
5. A perimeter planting strip is required along any side of a vehicular use area that
abuts adjoining property or the right-of-way of any street. This strip shall be at least
nine (9) feet wide. One (1) tree and three (3) shrubs or vines shall be planted for
every thirty (30) linear feet of perimeter planting strip.
TEC Response: The improvements will comply with the above comment.
6. An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger.
TEC Response: The improvements will comply with the above comment.
7. The development of two (2) acres or more requires the landscape plan to be
stamped with the seal of a Registered Landscape Architect.
TEC Response: The improvements will comply with the above comment. A
Registered Landscape Architect will provide plans for the building permit.
8. The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements
can be given when preserving trees of six (6) inch caliper or larger.
TEC Response: Item noted.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include