HomeMy WebLinkAboutZ-8194-B Staff AnalysisITEM NO.: 6. Z-5094-C
NAME: First Christian Church of Little Rock Short -form PD-R
LOCATION: located at 14411 Taylor Loop Road
Planning Staff Comments:
Applicant Responses in Red dated Janua 18, 2017
1. Provide notification of the property owners located within 200-feet of the site
including the certified abstract list, notice form with affidavit executed and proof of
mailing. The notice must be mailed no later than January 18, 2017. The Office of
Planning and Development must receive the proof of notice no later than January
27, 2017. We will provide.
2. Provide details of any proposed fencing, walls the purpose of these elements.
Provide the construction materials, total height and location. Refer to the Site Plan.
3. Provide the location, dimensions, nature of all existing and proposed easements,
utility and streets, and public improvements, drainage, sewer, water. Refer to the
Site Plan and Site Survey.
4. Indicate the location of structures and structure dimensions, dimensioned distances
between buildings and distances from structure to property line. Refer to the Site
Plan.
5. Provide a development schedule indicating the approximately date when
construction of the planned unit development or stages of the planned unit
development can be expected to begin and be completed. Construction is expected
to begin April/May 2017 and conclude in January of 2018.
6. Provide the proposed signage plan for the site. Provide the proposed building
signage, location and the size of the sign anticipated. Provide the location and total
height and area of any ground signage. Refer to the Site Plan.
7. Parking for churches (and other places of worship), is calculated at 1.0 space for
every four (4) seats in new principal assembly areas or additions to currently existing
structures. Choir seating and areas for folding chairs shall be counted. Twenty (20)
inches on a pew shall be considered one (1) seat. Stacked parking may be
authorized by the Planning Commission at the time of site plan reviews. Provide the
seating capacity and/or the anticipated membership for the proposed new church
facility. The maximum seating capacity for the Worship Space is 250. Current
membership of the church is 100. 64 parking spaces are shown on the proposed
Site Plan, which meets the parking requirement.
8. Provide the building square footage on the site plan. Proposed building is 11,000
square feet and is noted on the Site Plan.
9. Provide any activities such as mother's day out programs which the church may
offer now and in the future. No mother's day out programs currently provided but
could develop in the future.
10. What is the proposed use of the buildings indicated as future expansion? Either a
Sanctuary/Fellowship Hall and additional education space. Are the buildings
ITEM NO.: 6. Z-5094-C
proposed for school or daycare activities? School or day care facilities are not
planned at this time. If so indicate the maximum number of children to be served.
11. Provide the location of any proposed dumpster facilities. Proposed location is
shown on the Site Plan. Provide the hours of dumpster service. Staff recommends
the hours be limited to 7 am to 6 pm Monday through Friday. Accept Staffs
recommendations for hours of dumpster service.
12. Provide the maximum building height in the general notes section of the site plan.
Maximum building height is 25 ft. 5 in.
13. Note on the site plan areas to remain as natural. Natural areas of site noted on the
Site Plan.
14. Is the access to Black Bear Drive proposed as emergency access or will the drive be
open for access full time or during church events. Access to Black Bear Drive will be
for emergency only. A gate and Knox Box will be provided for fire truck emergency
access.
15. Will there be a staff on -site daily? Yes. If so indicate the days and hours of operation
for the church office. Staff on site daily 8am-5pm. Provide the hours of worship
service for the new construction. Some Church activities occur Mon. -Sat. 5pm -
9pm. Hours of worship on Sundays 8am-6pm.
Variance/Waivers: None requested.
Public Works Conditions:
1. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-
of-way prior to occupancy. Will comply.
2. A grading permit in accordance with Section 29-186 (c) and (d) will be required prior
to any land clearing or grading activities at the site. Other than residential
subdivisions, site grading and drainage plans must be submitted and approved prior
to the start of construction. Is an advanced grading permit being requested to grade
future parking and expansion area with the construction of the new church facility?
Will comply.
3. Provide a Sketch Grading and Drainage Plan per Section 29-186 (e). Refer to
Preliminary Grading and Drainage Plan.
4. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan. Maintenance of the detention
pond and all private drainage improvements is the responsibility of the developer
and/or property owner. Preliminary provisions for stormwater detention have been
addressed on the Site Plan.
5. If disturbed area is one (1) or more acres, obtain a NPDES stormwater permit from
the Arkansas Department of Environmental Quality prior to the start of construction.
Will comply.
6. If Black Bear Drive is proposed to not be continued as a public street, a
hammerhead turnaround must be constructed. Hammerheads should be designed
to be at least 80 feet in length and the same width as the street. Additional right-of-
way is required to be provided for the street turnaround improvements. In lieu of a
hammerhead turnaround we propose a gate with a Knox Box located at the end of
ti
ITEM NO.: 6.
Z-5094-C
Black Bear Drive. Once on the property, emergency vehicles would have access to
the turnaround located near the Church building entrance, or continue on to access
Taylor Loop.
7. Street Improvement plans shall include signage and striping. Public Works must
approve completed plans prior to construction. Will comply.
8. Hauling of fill material on or off site over municipal streets and roads requires
approval prior to a grading permit being issued. Contact Public Works Traffic
Engineering, Travis Herbner, 501.379.1805 or therbner(CDlittlerock.cov for more
information. Will comply.
9. Provide a letter prepared by a registered engineer certifying the intersection sight
distance at the intersection(s) comply with 2004 AASHTO Green Book standards.
Will comply.
10. Damage to public and private property due to hauling operations or operation of
construction related equipment from a nearby construction site shall be repaired by
the responsible party prior to issuance of a certificate of occupancy. Will comply.
11. Prior to construction of retaining walls, an engineer's certification of design and plans
must be submitted to Public Works for approval. After construction, an as -built
certification is required for construction of the retaining wall. Will comply, although
construction of retaining walls may not be necessary.
Utilities and Fire Department/County Planning:
Little Rock Wastewater: Sewer main extension required, with easements, if new sewer
service is required for this project. EAD, Environmental Assessment Division, approval
required if food prep to be done on site. Contact Little Rock Wastewater Utility for
additional information. Will comply.
Entergy: Entergy does not object to this proposal. An existing three phase, overhead
power line exists along the north side of Taylor Loop Road to the north of this property.
They do not appear to be in conflict with the proposed development. Contact Entergy in
advance to discuss future service requirements, new facilities locations/extensions and
adjustments to existing facilities (if any) as this project proceeds. Will comply.
Centerooint Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for water
service must be met. Will comply.
2. The Little Rock Fire Department needs to evaluate this site to determine whether
additional public and/or private fire hydrant(s) will be required. If additional fire
hydrant(s) are required, they will be installed at the Developer's expense.
comply.
ITEM NO.: 6. Z-5094-C
3. Please submit plans for water facilities and/or fire protection system to Central
Arkansas Water for review. Plan revisions may be required after additional review.
Contact Central Arkansas Water regarding procedures for installation of water
facilities and/or fire service. Approval of plans by the Arkansas Department of
Health Engineering Division and the Little Rock Fire Department is required.
comply.
4. A Capital Investment Charge based on the size of meter connection(s) will apply to
this project in addition to normal charges. This fee will apply to all connections
including metered connections off the private fire system. Will comply.
5. Contact Central Arkansas Water regarding the size and location of the water meter.
Will comply.
6. The facilities on -site will be private. When meters are planned off private lines,
private facilities shall be installed to Central Arkansas Water's materials and
construction specifications and installation will be inspected by an engineer, licensed
to practice in the State of Arkansas. Execution of a Customer Owned Line
Agreement is required. Will comply.
7. Due to the nature of this facility, installation of an approved reduced pressure zone
backflow preventer assembly (RPZA) is required on the domestic water service.
This assembly must be installed prior to the first point of use. Central Arkansas
Water requires that upon installation of the RPZA, successful tests of the assembly
must be completed by a Certified Assembly Tester licensed by the State of Arkansas
and approved by Central Arkansas Water. The test results must be sent to Central
Arkansas Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 501.377.1226 if you
would like to discuss backflow prevention requirements for this project. Will comply.
8. Fire sprinkler systems which do not contain additives such as antifreeze shall be
isolated with a double detector check valve assembly. If additives are used, a
reduced pressure zone back flow preventer shall be required. Will comply.
Fire Department:
Fire Hydrants. Maintain fire apparatus access roads at fire hydrant locations as per
Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D103.1 Access
road width with a hydrant. Where a fire hydrant is located on a fire apparatus access
road, the minimum road width shall be 26 feet, exclusive of shoulders. Will comply.
Grade. Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.2 Grade. Fire apparatus access roads shall
not exceed 10 percent in grade except as approved by the fire chief. Will comply.
Loading. Maintain fire apparatus access road design as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D102.1 Access and loading. Facilities,
buildings or portions of buildings hereafter constructed shall be accessible to fire
department apparatus by way of an approved fire apparatus access road with an
asphalt, concrete or other approved driving surface capable of supporting the imposed
load of fire apparatus weighing at least 75,000 pounds. Will comply.
ITEM NO.: 6. Z-5094-C
30' Tall Buildings - Maintain aerial fire apparatus access roads as per Appendix D
of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D105.1 — D105.4 Building
height does not exceed 30 feet.
D105.1 Where Required. Where the vertical distance between the grade plane
and the highest roof surface exceed 30', approved aerial fire apparatus access roads
shall be provided. For the purposes of this section the highest roof surfaces shall be
determined by measurement to the eave of a pitched roof, the intersection of a roof to
the exterior wall, or the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum
unobstructed with of 26', exclusive of shoulders, in the immediate vicinity of the building
or portion thereof.
D105.3 Proximity to building. At least one of the required access routes
meeting this condition shall be located within a minimum of 15 feet and a maximum of
30 feet from the building, and shall be positioned parallel to one entire side of the
building. The side of the building on which the aerial fire apparatus access road is
positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over
the aerial fire apparatus access road or between the aerial fire apparatus road and the
building. Other obstructions shall be permitted to be places with the approval of the fire
code official.
Gates. Maintain fire apparatus access road gates as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D103.5 Fire apparatus access road
gates. Gates securing the fire apparatus access roads shall comply with all of the
following criteria:
1. Minimum gate width shall be 20 feet. Will comply.
2. Gates shall be of swinging or sliding type. Will comply.
3. Construction of gates shall be of material that allow manual operation by one
person. Will comply.
4. Gate components shall be maintained in an operable condition at all times and
replaces or repaired when defective. Will comply.
5. Electric gates shall be equipped with a means of opening the gate by fire
department personnel for emergency access. Emergency opening devices shall
be approved by the fire code official. Will comply.
6. Manual opening gates shall not be locked with a padlock or chain and padlock
unless they are capable of being opened by means of forcible entry tools or when
a key box containing the keys to the lock is installed at the gate location. Will
comply.
7. Locking device specifications shall be submitted for approval \by the fire code
official Will comply.
8. Electric gate operators, where provided, shall be listed in accordance with UL
325. Will comply.
4
ITEM NO.: 6. Z-5094-C
9. Gates, intended for automatic operation shall be designed, constructed and
installed to comply with requirements of ASTM F 2200. Will comply.
Fire Hydrants. Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire
Prevention Code. Section C101 — C105, in conjunction with Central Arkansas Water
(Jason Lowder501-377-1245) and the Little Rock Fire Marshal's Office (Capt. Tony
Rhodes 501-918-3757). Number and Distribution of Fire Hydrants as per Table C105.1.
Will comply.
Parks and Recreation: No comment received.
County Planning: No comment.
Rock Region Metro: Location is not currently served by METRO but is in our long range
plans. We recommend providing pedestrian infrastructure form the sidewalk to the
facility front entrance. If a canopy is provided for the driveway drop off area that the
height allow paratransit vehicle access.
Building Code: Project is subject to full commercial plan review and approval prior to
issuance of a building permit. For information on submittal requirements and the review
process, contact a commercial plans examiner: Curtis Richey at 501.371.4724;
crichey&Iittlerock. gov or Mark Alderfer at 501.371.4875; malderfer littlerock. ov. Will
comply.
Planning Division: This request is located in River Mountain Planning District. The Land
Use Plan shows Residential Low (RL) for this property. The Residential Low category
provides for single family homes at densities not to exceed 6-units per acre. Such
residential development is typically characterized by conventional single family homes,
but may include patio or garden homes and cluster homes, provided that the density
remain less than 6-units per acre. The applicant has applied for a revision and
reinstatement of the existing expired PDR (Planned Development Residential) to allow
development of a new church.
Master Street Plan: To the northwest of the property is Taylor Loop Road and it is a
Minor Arterial on the Master Street Plan. A Minor Arterial provides connections to and
through an urban area and their primary function is to provide short distance travel
within the urbanized area. Entrances and exits should be limited to minimize negative
effects of traffic and pedestrians on Taylor Loop Road since it is a Minor Arterial. This
street may require dedication of right-of-way and may require street improvements for
entrances and exits to the site. Will comply.
Bicycle Plan: There is a Class I Bike Path shown along Taylor Loop Road. A Bike Class I Path
is to be a paved path physically separate for the use of bicycles. Additional right-of-way or/and
ITEM NO.: 6. Z-5094-C
easements are recommended. Nine -foot (9') paths are recommended to allow for pedestrian use
as well, replacing the sidewalk.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance requirements.
Will comply refer to Site Plan.
2. A land use buffer six (6) percent of the average width/depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The
minimum dimension shall be nine (9) feet. As a component of all land use buffer
requirements, opaque screening, whether a fence or other device, a minimum of six
(6) feet in height shall be required upon the property line side of the buffer. A
minimum of seventy (70) percent of the land use buffer shall be undisturbed.
Easements cannot count toward fulfilling this requirement. In addition to the required
screening, plant materials are to be provided in the buffer areas at the rate of one (1)
tree and three (3) shrubs for every thirty (30) linear feet. The surrounding properties
are zoned R-2, Single-family buffer requirements will need to be met. Will comply refer
to Site Plan.
3. Screening requirements will need to be met for the vehicular use areas adjacent to
street right-of-ways. Provide screening shrubs with an average linear spacing of not
less at three (3) feet within the required landscape area. Provide trees with an
average linear spacing of not less than thirty (30) feet. Will comply refer to Site Plan.
4. A perimeter planting strip is required along any side of a vehicular use area that
abuts adjoining property or the right-of-way of any street. This strip shall be at least
nine (9) feet wide. One (1) tree and three (3) shrubs or vines shall be planted for
every thirty (30) linear feet of perimeter planting strip. Will comply refer to Site Plan.
5. Eight percent (8%) of the vehicular use area must be designated for green space;
this green space needs to be evenly distributed throughout the parking area(s). The
minimum size of an interior landscape area shall be one hundred fifty (150) square
feet for developments with one hundred fifty (150) or fewer parking spaces. Interior
islands must be a minimum of seven and one half (7 1/2) feet in width. Trees shall
be included in the interior landscape areas at the rate of one (1) tree for every twelve
(12) parking spaces. Will comply refer to Site Plan.
6. Building landscape areas shall be provided between the vehicular use area used for
public parking and the general vicinity of the building. These shall be provided at the
rate equivalent to planter strip three (3) feet wide along the vehicular use area. One
(1) tree and four (4) shrubs shall be planted in the building landscape areas for each
forty (40) linear feet of vehicular use area abutting the building
7. An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger. Irrigation will be provided for selected flower
beds at the building.
8. The development of two (2) acres or more requires an approved landscape plan
stamped with the seal of a registered landscape architect prior to the issuance of a
building permit. Will comply refer to Site Plan.
ITEM NO.: 6. Z-5094-C
9. The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can
be given when preserving trees of six (6) inch caliper or larger. Will comply refer to
Site Plan.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, January 18, 2017.
ITEM NO.: 6.
NAME: First Christian Church of Little Rock Short -form PD-R
LOCATION: located at 14411 Taylor Loop Road
Planning Staff Comments:
Z-5094-C
1. Provide notification of the property owners located within 200-feet of the site including the
certified abstract list, notice form with affidavit executed and proof of mailing. The notice
must be mailed no later than January 18, 2017. The Office of Planning and Development
must receive the proof of notice no later than January 27, 2017.
2. Provide details of any proposed fencing, walls the purpose of these elements. Provide
the construction materials, total height and location.
3. Provide the location, dimensions, nature of all existing and proposed easements, utility
and streets, and public improvements, drainage, sewer, water.
4. Indicate the location of structures and structure dimensions, dimensioned distances
between buildings and distances from structure to property line.
5. Provide a development schedule indicating the approximately date when construction of
the planned unit development or stages of the planned unit development can be expected
to begin and be completed.
6. Provide the proposed signage plan for the site. Provide the proposed building signage,
location and the size of the sign anticipated. Provide the location and total height and
area of any ground signage.
7. Parking for churches (and other places of worship), is calculated at 1.0 space for every
four (4) seats in new principal assembly areas or additions to currently existing structures.
Choir seating and areas for folding chairs shall be counted. Twenty (20) inches on a pew
shall be considered one (1) seat. Stacked parking may be authorized by the Planning
Commission at the time of site plan reviews. Provide the seating capacity and/or the
anticipated membership for the proposed new church facility.
8. Provide the building square footage on the site plan.
9. Provide any activities such as mother's day out programs which the church may offer now
and in the future.
10. What is the proposed use of the buildings indicated as future expansion? Are the
buildings proposed for school or daycare activities? If so indicate the maximum number
of children to be served.
11. Provide the location of any proposed dumpster facilities. Provide the hours of dumpster
service. Staff recommends the hours be limited to 7 am to 6 pm Monday through Friday.
12. Provide the maximum building height in the general notes section of the site plan.
13. Note on the site plan areas to remain as natural.
14.Is the access to Black Bear Drive proposed as emergency access or will the drive be
open for access full time or during church events.
15. Will there be a staff on -site daily? If so indicate the days and hours of operation for the
church office. Provide the hours of worship service for the new construction.
Variance/Waivers: None requested.
ITEM NO.: 6.
Z-5094-C
Public Works Conditions:
1. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-of-
way prior to occupancy.
2. A grading permit in accordance with Section 29-186 (c) and (d) will be required prior to
any land clearing or grading activities at the site. Other than residential subdivisions, site
grading and drainage plans must be submitted and approved prior to the start of
construction. Is an advanced grading permit being requested to grade future parking and
expansion area with the construction of the new church facility?
3. Provide a Sketch Grading and Drainage Plan per Section 29-186 (e).
4. Stormwater detention ordinance applies to this property. Show the proposed location for
stormwater detention facilities on the plan. Maintenance of the detention pond and all
private drainage improvements is the responsibility of the developer and/or property
owner.
5. If disturbed area is one (1) or more acres, obtain a NPDES stormwater permit from the
Arkansas Department of Environmental Quality prior to the start of construction.
6. If Black Bear Drive is proposed to not be continued as a public street, a hammerhead
turnaround must be constructed. Hammerheads should be designed to be at least 80 feet
in length and the same width as the street. Additional right-of-way is required to be
provided for the street turnaround improvements.
7. Street Improvement plans shall include signage and striping. Public Works must approve
completed plans prior to construction.
8. Hauling of fill material on or off site over municipal streets and roads requires approval
prior to a grading permit being issued. Contact Public Works Traffic Engineering, Travis
Herbner, 501.379.1805 or therbner@littlerock-gov for more information.
9. Provide a letter prepared by a registered engineer certifying the intersection sight distance
at the intersection(s) comply with 2004 AASHTO Green Book standards.
10. Damage to public and private property due to hauling operations or operation of
construction related equipment from a nearby construction site shall be repaired by the
responsible party prior to issuance of a certificate of occupancy.
11. Prior to construction of retaining walls, an engineer's certification of design and plans must
be submitted to Public Works for approval. After construction, an as -built certification is
required for construction of the retaining wall.
Utilities and Fire Department/County Planning:
Little Rock Wastewater: Sewer main extension required, with easements, if new sewer
service is required for this project. EAD, Environmental Assessment Division, approval required
if food prep to be done on site. Contact Little Rock Wastewater Utility for additional
information.
Entergy: Entergy does not object to this proposal. An existing three phase, overhead power
line exists along the north side of Taylor Loop Road to the north of this property. They do not
appear to be in conflict with the proposed development. Contact Entergy in advance to
ITEM NO.: 6. Z-5094-C
discuss future service requirements, new facilities locations/extensions and adjustments to
existing facilities (if any) as this project proceeds.
Centerpoint Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for water service
must be met.
2. The Little Rock Fire Department needs to evaluate this site to determine whether
additional public and/or private fire hydrant(s) will be required. If additional fire hydrant(s)
are required, they will be installed at the Developer's expense.
3. Please submit plans for water facilities and/or fire protection system to Central Arkansas
Water for review. Plan revisions may be required after additional review. Contact Central
Arkansas Water regarding procedures for installation of water facilities and/or fire service.
Approval of plans by the Arkansas Department of Health Engineering Division and the
Little Rock Fire Department is required.
4. A Capital Investment Charge based on the size of meter connection(s) will apply to this
project in addition to normal charges. This fee will apply to all connections including
metered connections off the private fire system.
5. Contact Central Arkansas Water regarding the size and location of the water meter.
6. The facilities on -site will be private. When meters are planned off private lines, private
facilities shall be installed to Central Arkansas Water's materials and construction
specifications and installation will be inspected by an engineer, licensed to practice in the
State of Arkansas. Execution of a Customer Owned Line Agreement is required.
7. Due to the nature of this facility, installation of an approved reduced pressure zone
backflow preventer assembly (RPZA) is required on the domestic water service. This
assembly must be installed prior to the first point of use. Central Arkansas Water requires
that upon installation of the RPZA, successful tests of the assembly must be completed by
a Certified Assembly Tester licensed by the State of Arkansas and approved by Central
Arkansas Water. The test results must be sent to Central Arkansas Water's Cross
Connection Section within ten days of installation and annually thereafter. Contact the
Cross Connection Section at 501.377.1226 if you would like to discuss backflow
prevention requirements for this project.
8. Fire sprinkler systems which do not contain additives such as antifreeze shall be isolated
with a double detector check valve assembly. If additives are used, a reduced pressure
zone back flow preventer shall be required.
Fire Department:
Fire Hydrants. Maintain fire apparatus access roads at fire hydrant locations as per
Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D103.1 Access road
width with a hydrant. Where a fire hydrant is located on a fire apparatus access road, the
minimum road width shall be 26 feet, exclusive of shoulders.
ITEM NO.: 6. Z-5094-C
Grade. Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire
Prevention Code Vol. 1 Section D103.2 Grade. Fire apparatus access roads shall not
exceed 10 percent in grade except as approved by the fire chief.
Loading. Maintain fire apparatus access road design as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D102.1 Access and loading. Facilities,
buildings or portions of buildings hereafter constructed shall be accessible to fire department
apparatus by way of an approved fire apparatus access road with an asphalt, concrete or
other approved driving surface capable of supporting the imposed load of fire apparatus
weighing at least 75,000 pounds.
30' Tall Buildings - Maintain aerial fire apparatus access roads as per Appendix D of
the 2012 Arkansas Fire Prevention Code Vol. 1 Section D105.1 — D105.4
D105.1 Where Required. Where the vertical distance between the grade plane and
the highest roof surface exceed 30', approved aerial fire apparatus access roads shall be
provided. For the purposes of this section the highest roof surfaces shall be determined by
measurement to the eave of a pitched roof, the intersection of a roof to the exterior wall, or
the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed
with of 26', exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes meeting this
condition shall be located within a minimum of 15 feet and a maximum of 30 feet from the
building, and shall be positioned parallel to one entire side of the building. The side of the
building on which the aerial fire apparatus access road is positioned shall be approved by the
fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over the
aerial fire apparatus access road or between the aerial fire apparatus road and the building.
Other obstructions shall be permitted to be places with the approval of the fire code official.
Gates. Maintain fire apparatus access road gates as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D103.5 Fire apparatus access road
gates. Gates securing the fire apparatus access roads shall comply with all of the
following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by one person.
4. Gate components shall be maintained in an operable condition at all times and
replaces or repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire department
personnel for emergency access. Emergency opening devices shall be approved by
the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and padlock unless
they are capable of being opened by means of forcible entry tools or when a key box
containing the keys to the lock is installed at the gate location.
In
ITEM NO.: 6. Z-5094-C
7. Locking device specifications shall be submitted for approval \by the fire code official
8. Electric gate operators, where provided, shall be listed in accordance with UL 325.
9. Gates, intended for automatic operation shall be designed, constructed and installed to
comply with requirements of ASTM F 2200.
Fire Hydrants. Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire
Prevention Code. Section C101 — C105, in conjunction with Central Arkansas Water (Jason
Lowder501-377-1245) and the Little Rock Fire Marshal's Office (Capt. Tony Rhodes 501-918-
3757). Number and Distribution of Fire Hydrants as per Table C105.1.
Parks and Recreation: No comment received.
County Planning No comment.
Rock Region Metro: Location is not currently served by METRO but is in our long range
plans. We recommend providing pedestrian infrastructure form the sidewalk to the facility
front entrance. If a canopy is provided for the driveway drop off area that the height allow
paratransit vehicle access.
Building Code: Project is subject to full commercial plan review and approval prior to
issuance of a building permit. For information on submittal requirements and the review
process, contact a commercial plans examiner: Curtis Richey at 501.371.4724;
cricheyCa)_littlerock. gov or Mark Alderfer at 501.371.4875; malderfer@littlero_ck.g_o_v.
Planning Division: This request is located in River Mountain Planning District. The Land Use
Plan shows Residential Low (RL) for this property. The Residential Low category provides for
single family homes at densities not to exceed 6-units per acre. Such residential development
is typically characterized by conventional single family homes, but may include patio or
garden homes and cluster homes, provided that the density remain less than 6-units per
acre. The applicant has applied for a revision and reinstatement of the existing expired PDR
(Planned Development Residential) to allow development of a new church.
Master Street Plan: To the northwest of the property is Taylor Loop Road and it is a Minor
Arterial on the Master Street Plan. A Minor Arterial provides connections to and through an
urban area and their primary function is to provide short distance travel within the urbanized
area. Entrances and exits should be limited to minimize negative effects of traffic and
pedestrians on Taylor Loop Road since it is a Minor Arterial. This street may require
dedication of right-of-way and may require street improvements for entrances and exits to the
site.
Bicvcle Plan: There is a Class I Bike Path shown along Taylor Loop Road. A Bike Class I
Path is to be a paved path physically separate for the use of bicycles. Additional right-of-way
ITEM NO.: 6.
Z-5094-C
or/and easements are recommended. Nine -foot (9') paths are recommended to allow for
pedestrian use as well, replacing the sidewalk.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance requirements.
2. A land use buffer six (6) percent of the average width/depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The minimum
dimension shall be nine (9) feet. As a component of all land use buffer requirements,
opaque screening, whether a fence or other device, a minimum of six (6) feet in height
shall be required upon the property line side of the buffer. A minimum of seventy (70)
percent of the land use buffer shall be undisturbed. Easements cannot count toward
fulfilling this requirement. In addition to the required screening, plant materials are to be
provided in the buffer areas at the rate of one (1) tree and three (3) shrubs for every thirty
(30) linear feet. The surrounding properties are zoned R-2, Single-family buffer
requirements will need to be met.
3. Screening requirements will need to be met for the vehicular use areas adjacent to street
right-of-ways. Provide screening shrubs with an average linear spacing of not less at three
(3) feet within the required landscape area. Provide trees with an average linear spacing
of not less than thirty (30) feet.
4. A perimeter planting strip is required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street. This strip shall be at least nine (9) feet
wide. One (1) tree and three (3) shrubs or vines shall be planted for every thirty (30) linear
feet of perimeter planting strip.
5. Eight percent (8%) of the vehicular use area must be designated for green space; this
green space needs to be evenly distributed throughout the parking area(s). The minimum
size of an interior landscape area shall be one hundred fifty (150) square feet for
developments with one hundred fifty (150) or fewer parking spaces. Interior islands must
be a minimum of seven and one half (7 1/2) feet in width. Trees shall be included in the
interior landscape areas at the rate of one (1) tree for every twelve (12) parking spaces.
6. Building landscape areas shall be provided between the vehicular use area used for
public parking and the general vicinity of the building. These shall be provided at the rate
equivalent to planter strip three (3) feet wide along the vehicular use area. One (1) tree
and four (4) shrubs shall be planted in the building landscape areas for each forty (40)
linear feet of vehicular use area abutting the building
7. An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger.
8. The development of two (2) acres or more requires an approved landscape plan stamped
with the seal of a registered landscape architect prior to the issuance of a building permit.
9. The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can be
given when preserving trees of six (6) inch caliper or larger.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include the
additional information as noted above) to staff on Wednesday, January 18, 2017.
ITEM NO.: 6.
NAME: First Christian Church of Little Rock Short -form PD-R
LOCATION: located at 14411 Taylor Loop Road
Planning Staff Comments:
Applicant Responses in Red dated January 18. 2017
Z-5094-C
1. Provide notification of the property owners located within 200-feet of the site
including the certified abstract list, notice form with affidavit executed and proof of
mailing. The notice must be mailed no later than January 18, 2017. The Office of
Planning and Development must receive the proof of notice no later than January
27, 2017. We will provide.
2. Provide details of any proposed fencing, walls the purpose of these elements.
Provide the construction materials, total height and location. Refer to the Site Plan.
3. Provide the location, dimensions, nature of all existing and proposed easements,
utility and streets, and public improvements, drainage, sewer, water. Refer to the
Site Plan and Site Survey.
4. Indicate the location of structures and structure dimensions, dimensioned distances
between buildings and distances from structure to property line. Refer to the Site
Plan.
5. Provide a development schedule indicating the approximately date when
construction of the planned unit development or stages of the planned unit
development can be expected to begin and be completed. Construction is expected
to begin April/May 2017 and conclude in January of 2018.
6. Provide the proposed signage plan for the site. Provide the proposed building
signage, location and the size of the sign anticipated. Provide the location and total
height and area of any ground signage. Refer to the Site Plan.
7. Parking for churches (and other places of worship), is calculated at 1.0 space for
every four (4) seats in new principal assembly areas or additions to currently existing
structures. Choir seating and areas for folding chairs shall be counted. Twenty (20)
inches on a pew shall be considered one (1) seat. Stacked parking may be
authorized by the Planning Commission at the time of site plan reviews. Provide the
seating capacity and/or the anticipated membership for the proposed new church
facility. The maximum seating capacity for the Worship Space is 250. Current
membership of the church is 100. 64 parking spaces are shown on the proposed
Site Plan, which meets the parking requirement.
8. Provide the building square footage on the site plan. Proposed building is 11,000
square feet and is noted on the Site Plan.
9. Provide any activities such as mother's day out programs which the church may
offer now and in the future. No mother's day out programs currently provided but
could develop in the future.
10. What is the proposed use of the buildings indicated as future expansion? Either a
Sanctuary/Fellowship Hall and additional education space. Are the buildings
ITEM NO.: 6. Z-5094-C
proposed for school or daycare activities? School or day care facilities are not
planned at this time. If so indicate the maximum number of children to be served.
11. Provide the location of any proposed dumpster facilities. Proposed location is
shown on the Site Plan. Provide the hours of dumpster service. Staff recommends
the hours be limited to 7 am to 6 pm Monday through Friday. Accept Staffs
recommendations for hours of dumpster service.
12. Provide the maximum building height in the general notes section of the site plan.
Maximum building height is 25 ft. 5 in.
13. Note on the site plan areas to remain as natural. Natural areas of site noted on the
Site Plan.
14. Is the access to Black Bear Drive proposed as emergency access or will the drive be
open for access full time or during church events. Access to Black Bear Drive will be
for emergency only. A gate and Knox Box will be provided for fire truck emergency
access.
15. Will there be a staff on -site daily? Yes. If so indicate the days and hours of operation
for the church office. Staff on site daily 8am-5pm. Provide the hours of worship
service for the new construction. Some Church activities occur Mon. -Sat. 5pm -
9pm. Hours of worship on Sundays 8am-6pm.
VarianceANaivers: None requested.
Public Works Conditions:
1. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-
of-way prior to occupancy.
2. A grading permit in accordance with Section 29-186 (c) and (d) will be required prior
to any land clearing or grading activities at the site. Other than residential
subdivisions, site grading and drainage plans must be submitted and approved prior
to the start of construction. Is an advanced grading permit being requested to grade
future parking and expansion area with the construction of the new church facility?
Will comply.
3. Provide a Sketch Grading and Drainage Plan per Section 29-186 (e). Refer to
Preliminary Grading and Drainage Plan.
4. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan. Maintenance of the detention
pond and all private drainage improvements is the responsibility of the developer
and/or property owner. Preliminary provisions for stormwater detention have been
addressed on the Site Plan.
5. If disturbed area is one (1) or more acres, obtain a NPDES stormwater permit from
the Arkansas Department of Environmental Quality prior to the start of construction.
Will comply.
6. If Black Bear Drive is proposed to not be continued as a public street, a
hammerhead turnaround must be constructed. Hammerheads should be designed
to be at least 80 feet in length and the same width as the street. Additional right-of-
way is required to be provided for the street turnaround improvements. In lieu of a
hammerhead turnaround we propose a gate with a Knox Box located at the end of
ITEM NO.: 6.
Z-5094-C
Black Bear Drive. Once on the property, emergency vehicles would have access to
the turnaround located near the Church building entrance, or continue on to access
Taylor Loop.
7. Street Improvement plans shall include signage and striping. Public Works must
approve completed plans prior to construction. Will comply.
8. Hauling of fill material on or off site over municipal streets and roads requires
approval prior to a grading permit being issued. Contact Public Works Traffic
Engineering, Travis Herbner, 501.379.1805 or therbner littlerock. ov for more
information. Will comply.
9. Provide a letter prepared by a registered engineer certifying the intersection sight
distance at the intersection(s) comply with 2004 AASHTO Green Book standards.
Will comply.
10. Damage to public and private property due to hauling operations or operation of
construction related equipment from a nearby construction site shall be repaired by
the responsible party prior to issuance of a certificate of occupancy. Will comply.
11. Prior to construction of retaining walls, an engineer's certification of design and plans
must be submitted to Public Works for approval. After construction, an as -built
certification is required for construction of the retaining wall. Will comply, although
construction of retaining walls may not be necessary.
Utilities and Fire Department/County Planning:
Little Rock Wastewater: Sewer main extension required, with easements, if new sewer
service is required for this project. EAD, Environmental Assessment Division, approval
required if food prep to be done on site. Contact Little Rock Wastewater Utility for
additional information. Will comply.
Enter : Entergy does not object to this proposal. An existing three phase, overhead
power line exists along the north side of Taylor Loop Road to the north of this property.
They do not appear to be in conflict with the proposed development. Contact Entergy in
advance to discuss future service requirements, new facilities locations/extensions and
adjustments to existing facilities (if any) as this project proceeds. Will comply.
Centerpoint Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for water
service must be met. Will comply.
2. The Little Rock Fire Department needs to evaluate this site to determine whether
additional public and/or private fire hydrant(s) will be required. If additional fire
hydrant(s) are required, they will be installed at the Developer's expense.
comply.
ITEM NO.: 6. Z-5094-C
3. Please submit plans for water facilities and/or fire protection system to Central
Arkansas Water for review. Plan revisions may be required after additional review.
Contact Central Arkansas Water regarding procedures for installation of water
facilities and/or fire service. Approval of plans by the Arkansas Department of
Health Engineering Division and the Little Rock Fire Department is required.
comply.
4. A Capital Investment Charge based on the size of meter connection(s) will apply to
this project in addition to normal charges. This fee will apply to all connections
including metered connections off the private fire system. Will comply.
5. Contact Central Arkansas Water regarding the size and location of the water meter.
Will comply.
6. The facilities on -site will be private. When meters are planned off private lines,
private facilities shall be installed to Central Arkansas Water's materials and
construction specifications and installation will be inspected by an engineer, licensed
to practice in the State of Arkansas. Execution of a Customer Owned Line
Agreement is required. Will comply.
7. Due to the nature of this facility, installation of an approved reduced pressure zone
backflow preventer assembly (RPZA) is required on the domestic water service.
This assembly must be installed prior to the first point of use. Central Arkansas
Water requires that upon installation of the RPZA, successful tests of the assembly
must be completed by a Certified Assembly Tester licensed by the State of Arkansas
and approved by Central Arkansas Water. The test results must be sent to Central
Arkansas Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 501.377.1226 if you
would like to discuss backflow prevention requirements for this project. Will comply.
8. Fire sprinkler systems which do not contain additives such as antifreeze shall be
isolated with a double detector check valve assembly. If additives are used, a
reduced pressure zone back flow preventer shall be required. Will comply.
Fire Department:
Fire Hydrants. Maintain fire apparatus access roads at fire hydrant locations as per
Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D103.1 Access
road width with a hydrant. Where a fire hydrant is located on a fire apparatus access
road, the minimum road width shall be 26 feet, exclusive of shoulders. Will comply.
Grade. Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas
Fire Prevention Code Vol. 1 Section D103.2 Grade. Fire apparatus access roads shall
not exceed 10 percent in grade except as approved by the fire chief. Will comply.
Loading. Maintain fire apparatus access road design as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D102.1 Access and loading. Facilities,
buildings or portions of buildings hereafter constructed shall be accessible to fire
department apparatus by way of an approved fire apparatus access road with an
asphalt, concrete or other approved driving surface capable of supporting the imposed
load of fire apparatus weighing at least 75,000 pounds. Will comply.
ITEM NO.: 6. Z-5094-C
30' Tall Buildin-gs - Maintain aerial fire apparatus access roads as per Appendix D
of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D105.1 — D105.4 Building
height does not exceed 30 feet.
D105.1 Where Required. Where the vertical distance between the grade plane
and the highest roof surface exceed 30', approved aerial fire apparatus access roads
shall be provided. For the purposes of this section the highest roof surfaces shall be
determined by measurement to the eave of a pitched roof, the intersection of a roof to
the exterior wall, or the top of the parapet walls, whichever is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum
unobstructed with of 26', exclusive of shoulders, in the immediate vicinity of the building
or portion thereof.
D105.3 Proximity to building. At least one of the required access routes
meeting this condition shall be located within a minimum of 15 feet and a maximum of
30 feet from the building, and shall be positioned parallel to one entire side of the
building. The side of the building on which the aerial fire apparatus access road is
positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over
the aerial fire apparatus access road or between the aerial fire apparatus road and the
building. Other obstructions shall be permitted to be places with the approval of the fire
code official.
Gates. Maintain fire apparatus access road gates as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D103.5 Fire apparatus access road
gates. Gates securing the fire apparatus access roads shall comply with all of the
following criteria:
1. Minimum gate width shall be 20 feet. Will comply.
2. Gates shall be of swinging or sliding type. Will comply.
3. Construction of gates shall be of material that allow manual operation by one
person. Will comply.
4. Gate components shall be maintained in an operable condition at all times and
replaces or repaired when defective. Will comply.
5. Electric gates shall be equipped with a means of opening the gate by fire
department personnel for emergency access. Emergency opening devices shall
be approved by the fire code official. Will comply.
6. Manual opening gates shall not be locked with a padlock or chain and padlock
unless they are capable of being opened by means of forcible entry tools or when
a key box containing the keys to the lock is installed at the gate location. Will
comply.
7. Locking device specifications shall be submitted for approval \by the fire code
official Will comply.
8. Electric gate operators, where provided, shall be listed in accordance with UL
325. Will comply.
ITEM NO.: 6. Z-5094-C
9. Gates, intended for automatic operation shall be designed, constructed and
installed to comply with requirements of ASTM F 2200. Will comply.
Fire Hydrants. Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire
Prevention Code. Section C101 — C105, in conjunction with Central Arkansas Water
(Jason Lowder501-377-1245) and the Little Rock Fire Marshal's Office (Capt. Tony
Rhodes 501-918-3757). Number and Distribution of Fire Hydrants as per Table C105.1.
Will comply.
Parks and Recreation: No comment received.
County Planning: No comment.
Rock Region Metro: Location is not currently served by METRO but is in our long range
plans. We recommend providing pedestrian infrastructure form the sidewalk to the
facility front entrance. If a canopy is provided for the driveway drop off area that the
height allow paratransit vehicle access.
Building Code: Project is subject to full commercial plan review and approval prior to
issuance of a building permit. For information on submittal requirements and the review
process, contact a commercial plans examiner: Curtis Richey at 501.371.4724;
crichevCa7littlerock.gov or Mark AlderFer at 501.371.4875; maiderfer(U-Nittlerock.gov. Will
comply.
Planning Division: This request is located in River Mountain Planning District. The Land
Use Plan shows Residential Low (RL) for this property. The Residential Low category
provides for single family homes at densities not to exceed 6-units per acre. Such
residential development is typically characterized by conventional single family homes,
but may include patio or garden homes and cluster homes, provided that the density
remain less than 6-units per acre. The applicant has applied for a revision and
reinstatement of the existing expired PDR (Planned Development Residential) to allow
development of a new church.
Master Street Plan: To the northwest of the property is Taylor Loop Road and it is a
Minor Arterial on the Master Street Plan. A Minor Arterial provides connections to and
through an urban area and their primary function is to provide short distance travel
within the urbanized area. Entrances and exits should be limited to minimize negative
effects of traffic and pedestrians on Taylor Loop Road since it is a Minor Arterial. This
street may require dedication of right-of-way and may require street improvements for
entrances and exits to the site. Will comply.
Bicycle Plan: There is a Class I Bike Path shown along Taylor Loop Road. A Bike Class I Path
is to be a paved path physically separate for the use of bicycles. Additional right-of-way or/and
ITEM NO.: 6.
Z-5094-C
easements are recommended. Nine -foot (9') paths are recommended to allow for pedestrian use
as well, replacing the sidewalk.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance requirements.
Will comply refer to Site Plan.
2. A land use buffer six (6) percent of the average width/depth of the lot will be required
when an adjacent property has a dissimilar use of a more restrictive nature. The
minimum dimension shall be nine (9) feet. As a component of all land use buffer
requirements, opaque screening, whether a fence or other device, a minimum of six
(6) feet in height shall be required upon the property line side of the buffer. A
minimum of seventy (70) percent of the land use buffer shall be undisturbed.
Easements cannot count toward fulfilling this requirement. In addition to the required
screening, plant materials are to be provided in the buffer areas at the rate of one (1)
tree and three (3) shrubs for every thirty (30) linear feet. The surrounding properties
are zoned R-2, Single-family buffer requirements will need to be met. Will comply refer
to Site Plan.
3. Screening requirements will need to be met for the vehicular use areas adjacent to
street right-of-ways. Provide screening shrubs with an average linear spacing of not
less at three (3) feet within the required landscape area. Provide trees with an
average linear spacing of not less than thirty (30) feet. Will comply refer to Site Plan.
4. A perimeter planting strip is required along any side of a vehicular use area that
abuts adjoining property or the right-of-way of any street. This strip shall be at least
nine (9) feet wide. One (1) tree and three (3) shrubs or vines shall be planted for
every thirty (30) linear feet of perimeter planting strip. Will comply refer to Site Plan.
5. Eight percent (8%) of the vehicular use area must be designated for green space;
this green space needs to be evenly distributed throughout the parking area(s). The
minimum size of an interior landscape area shall be one hundred fifty (150) square
feet for developments with one hundred fifty (150) or fewer parking spaces. Interior
islands must be a minimum of seven and one half (7 1/2) feet in width. Trees shall
be included in the interior landscape areas at the rate of one (1) tree for every twelve
(12) parking spaces. Will comply refer to Site Plan.
6. Building landscape areas shall be provided between the vehicular use area used for
public parking and the general vicinity of the building. These shall be provided at the
rate equivalent to planter strip three (3) feet wide along the vehicular use area. One
(1) tree and four (4) shrubs shall be planted in the building landscape areas for each
forty (40) linear feet of vehicular use area abutting the building
7. An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger. Irrigation will be provided for selected flower
beds at the building.
8. The development of two (2) acres or more requires an approved landscape plan
stamped with the seal of a registered landscape architect prior to the issuance of a
building permit. Will comply refer to Site Plan.
ITEM NO.: 6.
Z-5094-C
9. The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can
be given when preserving trees of six (6) inch caliper or larger. Will comply refer to
Site Plan.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, January 18, 2017.
1914: a►to] WAF-15Lez,a:
NAME: First Christian Church of Little Rock Short -form PD-R
LOCATION: Located at 14411 Taylor Loop Road
DEVELOPER:
First Christian Church — Little Rock
1500 North Mississippi
Little Rock, AR 72207
C` 1 1 M% /C\/!l M
Global Surveying Consultants, Inc.
6511 Heilman Court
North Little Rock, AR 72118
ARCHITECT:
Fennell II Purifoy Architects
c/o Phil Purifoy, AIA
100 Morgan Keegan Drive, Suite 320
Little Rock, AR 72202
AREA: 3.47 acres NUMBER OF LOTS: 1 FT.NEW STREET: 0 LF
WARD: 5 PLANNING DISTRICT: 1 — River Mountain CENSUS TRACT: 42.12
CURRENT ZONING: PD-R - Expired
ALLOWED USES: Planned Development Residential, Single-family subdivision
PROPOSED ZONING: Revised PD-R
PROPOSED USE: Church
VARIANCEANAIVERS: None requested.
BACKGROUND:
Ordinance No. 20,823 adopted by the Little Rock Board of Directors on December 17,
2013, rezoned this site from R-2, Single-family to PD-R to allow the development of
5.74-acres with 27 single-family residential lots. The homes were proposed containing
FILE NO.: Z-8194-B (Cont.)
2,200 square feet of heated and cooled space. Each home would contain a 2-car
garage. The homes were proposed with a 5-foot side yard setback and a 10-foot front
yard setback. The rear yard setback was indicated at 10, 15 and 20-feet. The site plan
indicated the development of the subdivision utilizing private streets. The streets were
indicated with a 45-foot access easement with 25-feet of pavement, back of curb to back
or curb. The average lot size proposed was 88-feet by 58-feet for a lot area of 5,104
square feet.
A. PROPOSAL/REQUEST/APPLICANT'S STATEMENT:
The applicant now proposes to revise and reinstate the previously approved
PD-R, Planned Development Residential, to allow the development of the site with
a new church and associated parking. The church is proposed containing
11,000 gross square feet of floor area. The site plan indicates the placement of
64 parking spaces. The site plan indicates large wooded areas to remain in their
natural state. The plan indicates the placement of native plant materials, the
placement of rain gardens and bio-swales. Irrigation is only proposed within
selected flower beds at the building.
B. EXISTING CONDITIONS:
The former single-family home has been removed. There are a number of mature
trees located on the site. The site has varying degrees of slope. Taylor Loop
Road, adjacent to the site is a four (4) lane arterial street. The site abuts a single-
family subdivision to the east and north. The site abuts a church to the south.
C. NEIGHBORHOOD COMMENTS:
All property owners located within 200-feet of the site along with the Westchester
Property Owners Association and the Westbury Neighborhood Association were
notified of the public hearing.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS
1. Repair or replace any curb and gutter or sidewalk that is damaged in the
public right-of-way prior to occupancy.
2. A grading permit in accordance with Section 29-186 (c) and (d) will be
required prior to any land clearing or grading activities at the site. Other than
residential subdivisions, site grading and drainage plans must be submitted
and approved prior to the start of construction. Is an advanced grading permit
being requested to grade future parking and expansion area with the
construction of the new church facility?
3. Provide a Sketch Grading and Drainage Plan per Section 29-186 (e).
2
FILE NO.: Z-8194-B (Cont.)
4. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan. Maintenance of the
detention pond and all private drainage improvements is the responsibility of
the developer and/or property owner.
5. If disturbed area is one (1) or more acres, obtain a NPDES stormwater permit
from the Arkansas Department of Environmental Quality prior to the start of
construction.
6. If Black Bear Drive is proposed to not be continued as a public street, a
hammerhead turnaround must be constructed. Hammerheads should be
designed to be at least 80 feet in length and the same width as the street.
Additional right-of-way is required to be provided for the street turnaround
improvements. Staff has reconsidered this comment and it no longer applies.
A hammer head turn -around will not be required by this applicant.
7. Street Improvement plans shall include signage and striping. Public Works
must approve completed plans prior to construction.
8. Hauling of fill material on or off site over municipal streets and roads requires
approval prior to a grading permit being issued. Contact Public Works Traffic
Engineering, Travis Herbner, 501.379.1805 or therbnerp'littlerock.cgov for
more information.
9. Provide a letter prepared by a registered engineer certifying the intersection
sight distance at the intersection(s) comply with 2004 AASHTO Green Book
standards.
10. Damage to public and private property due to hauling operations or operation
of construction related equipment from a nearby construction site shall be
repaired by the responsible party prior to issuance of a certificate of
occupancy.
11. Prior to construction of retaining walls, an engineer's certification of design
and plans must be submitted to Public Works for approval. After construction,
an as -built certification is required for construction of the retaining wall.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Little Rock Wastewater: Sewer main extension required, with easements, if new
sewer service is required for this project. EAD, Environmental Assessment
Division, approval required if food prep to be done on site. Contact Little Rock
Wastewater Utility for additional information.
Ent@M: Entergy does not object to this proposal. An existing three phase,
overhead power line exists along the north side of Taylor Loop Road to the north
of this property. They do not appear to be in conflict with the proposed
development. Contact Entergy in advance to discuss future service requirements,
new facilities locations/extensions and adjustments to existing facilities (if any) as
this project proceeds.
Centerpoint Energy: No comment received-
3
FILE NO.: Z-8194-B
AT & T: No comment received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for
water service must be met.
2. The Little Rock Fire Department needs to evaluate this site to determine
whether additional public and/or private fire hydrant(s) will be required. If
additional fire hydrant(s) are required, they will be installed at the Developer's
expense.
3. Please submit plans for water facilities and/or fire protection system to Central
Arkansas Water for review. Plan revisions may be required after additional
review. Contact Central Arkansas Water regarding procedures for installation
of water facilities and/or fire service. Approval of plans by the Arkansas
Department of Health Engineering Division and the Little Rock Fire Department
is required.
4. A Capital Investment Charge based on the size of meter connection(s) will
apply to this project in addition to normal charges. This fee will apply to all
connections including metered connections off the private fire system.
5. Contact Central Arkansas Water regarding the size and location of the water
meter.
6. The facilities on -site will be private. When meters are planned off private lines,
private facilities shall be installed to Central Arkansas Water's materials and
construction specifications and installation will be inspected by an engineer,
licensed to practice in the State of Arkansas. Execution of a Customer Owned
Line Agreement is required.
7. Due to the nature of this facility, installation of an approved reduced pressure
zone backflow preventer assembly (RPZA) is required on the domestic water
service. This assembly must be installed prior to the first point of use. Central
Arkansas Water requires that upon installation of the RPZA, successful tests
of the assembly must be completed by a Certified Assembly Tester licensed by
the State of Arkansas and approved by Central Arkansas Water. The test
results must be sent to Central Arkansas Water's Cross Connection Section
within ten days of installation and annually thereafter. Contact the Cross
Connection Section at 501.377.1226 if you would like to discuss backflow
prevention requirements for this project.
8. Fire sprinkler systems which do not contain additives such as antifreeze shall
be isolated with a double detector check valve assembly. If additives are used,
a reduced pressure zone back flow preventer shall be required.
Fire Department:
Fire. Hydrants. Maintain fire apparatus access roads at fire hydrant locations as
per Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D103.1
.,i
191IN►191WARTiLOSE :1
Access road width with a hydrant. Where a fire hydrant is located on a fire
apparatus access road, the minimum road width shall be 26 feet, exclusive of
shoulders.
Grade. Maintain fire apparatus access roads as per Appendix D of the
2012 Arkansas Fire Prevention Code Vol. 1 Section D103.2 Grade. Fire
apparatus access roads shall not exceed 10 percent in grade except as approved
by the fire chief.
Loading. Maintain fire apparatus access road design as per Appendix D of the
2012 Arkansas Fire Prevention Code Vol. 1 Section D102.1 Access and loading.
Facilities, buildings or portions of buildings hereafter constructed shall be
accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface
apable of supporting the imposed load of fire apparatus weighing at
least 75,000 pounds.
30' Tall Buildings - Maintain aerial fire apparatus access roads as per
Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D105.1
— D105.4
D105.1 Where Required. Where the vertical distance between the grade
plane and the highest roof surface exceed 30', approved aerial fire apparatus
access roads shall be provided. For the purposes of this section the highest roof
surfaces shall be determined by measurement to the eave of a pitched roof, the
intersection of a roof to the exterior wall, or the top of the parapet walls, whichever
is greater.
D105.2 Width. Aerial fire apparatus access roads shall have a minimum
unobstructed with of 26', exclusive of shoulders, in the immediate vicinity of the
building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes
meeting this condition shall be located within a minimum of 15 feet and a maximum
of 30 feet from the building, and shall be positioned parallel to one entire side of
the building. The side of the building on which the aerial fire apparatus access road
is positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located
over the aerial fire apparatus access road or between the aerial fire apparatus road
and the building. Other obstructions shall be permitted to be places with the
approval of the fire code official.
Gates. Maintain fire apparatus access road gates as per Appendix D of the
2012 Arkansas Fire Prevention Code Vol. 1 Section D103.5 Fire apparatus
access road gates. Gates securing the fire apparatus access roads shall
comply with all of the following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by
one person.
5
4. Gate components shall be maintained in an operable condition at all times
and replaces or repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire
department personnel for emergency access. Emergency opening devices
shall be approved by the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and
padlock unless they are capable of being opened by means of forcible entry
tools or when a key box containing the keys to the lock is installed at the
gate location.
7. Locking device specifications shall be submitted for approval \by the fire
code official
8. Electric gate operators, where provided, shall be listed in accordance with
UL 325.
9. Gates, intended for automatic operation shall be designed, constructed and
installed to comply with requirements of ASTM F 2200.
Fire Hydrants. Locate Fire Hydrants as per Appendix C of the
2012 Arkansas Fire Prevention Code. Section C101 — C105, in conjunction with
Central Arkansas Water (Jason Lowder 501-377-1245) and the Little Rock Fire
Marshal's Office (Capt. Tony Rhodes 501-918-3757). Number and Distribution of
Fire Hydrants as per Table C105.1.
Parks and Recreation: No comment received.
County Planning: No comment.
Rock Region Metro: Location is not currently served by METRO but is in our long
range plans. We recommend providing pedestrian infrastructure from the sidewalk
to the facility front entrance. If a canopy is provided for the driveway drop off area
that the height allow paratransit vehicle access.
F. ISSUES/TECHNICAL/DESIG
Building Code: Project is subject to full commercial plan review and approval prior
to issuance of a building permit. For information on submittal requirements and
the review process, contact a commercial plans examiner: Curtis Richey at
501.371.4724; cdchey(cr7,Iittlerock. gou or Mark Alderfer at 501.371.4875;
malderferCcD-little rock. gov.
Planning Division: This request is located in River Mountain Planning District. The
Land Use Plan shows Residential Low (RL) for this property. The Residential Low
category provides for single family homes at densities not to exceed 6-units per
acre. Such residential development is typically characterized by conventional
single family homes, but may include patio or garden homes and cluster homes,
provided that the density remain less than 6-units per acre. The applicant has
FILE NO.: Z-8194-B
applied for a revision and reinstatement of the existing expired PDR (Planned
Development Residential) to allow development of a new church.
Master Street Plan: To the northwest of the property is Taylor Loop Road and it is
a Minor Arterial on the Master Street Plan. A Minor Arterial provides connections
to and through an urban area and their primary function is to provide short distance
travel within the urbanized area. Entrances and exits should be limited to minimize
negative effects of traffic and pedestrians on Taylor Loop Road since it is a Minor
Arterial. This street may require dedication of right-of-way and may require street
improvements for entrances and exits to the site.
Bicycle Plan: There is a Class I Bike Path shown along Taylor Loop Road.
A Bike Class I Path is to be a paved path physically separate for the use of bicycles.
Additional right-of-way or/and easements are recommended. Nine -foot (9') paths
are recommended to allow for pedestrian use as well, replacing the sidewalk.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance
requirements.
2. A land use buffer six (6) percent of the average width/depth of the lot will be
required when an adjacent property has a dissimilar use of a more restrictive
nature. The minimum dimension shall be nine (9) feet. As a component of all
land use buffer requirements, opaque screening, whether a fence or other
device, a minimum of six (6) feet in height shall be required upon the property
line side of the buffer. A minimum of seventy (70) percent of the land use buffer
shall be undisturbed. Easements cannot count toward fulfilling this
requirement. In addition to the required screening, plant materials are to be
provided in the buffer areas at the rate of one (1) tree and three (3) shrubs for
every thirty (30) linear feet. The surrounding properties are zoned R-2,
Single-family buffer requirements will need to be met.
3. Screening requirements will need to be met for the vehicular use areas
adjacent to street right-of-ways. Provide screening shrubs with an average
linear spacing of not less at three (3) feet within the required landscape area.
Provide trees with an average linear spacing of not less than thirty (30) feet.
4. A perimeter planting strip is required along any side of a vehicular use area that
abuts adjoining property or the right-of-way of any street. This strip shall be at
least nine (9) feet wide. One (1) tree and three (3) shrubs or vines shall be
planted for every thirty (30) linear feet of perimeter planting strip.
5. Eight percent (8%) of the vehicular use area must be designated for green
space; this green space needs to be evenly distributed throughout the parking
area(s). The minimum size of an interior landscape area shall be one hundred
fifty (150) square feet for developments with one hundred fifty (150) or fewer
parking spaces. Interior islands must be a minimum of seven and one half
(7 1/2) feet in width. Trees shall be included in the interior landscape areas at
the rate of one (1) tree for every twelve (12) parking spaces.
r�
FILE NO.: Z-8194-B (Cont.
6. Building landscape areas shall be provided between the vehicular use area
used for public parking and the general vicinity of the building. These shall be
provided at the rate equivalent to planter strip three (3) feet wide along the
vehicular use area. One (1) tree and four (4) shrubs shall be planted in the
building landscape areas for each forty (40) linear feet of vehicular use area
abutting the building
7. An automatic irrigation system to water landscaped areas shall be required for
developments of one (1) acre or larger.
8. The development of two (2) acres or more requires an approved landscape
plan stamped with the seal of a registered landscape architect prior to the
issuance of a building permit.
9. The City Beautiful Commission recommends preserving as many existing trees
as feasible on this site. Credit toward fulfilling Landscape Ordinance
requirements can be given when preserving trees of six (6) inch caliper
or larger.
G. SUBDIVISION COMMITTEE COMMENT.
(January 11, 2017)
The applicant was present representing the request. Staff presented an overview
of the item stating there were additional items necessary to complete the review
process. Staff requested additional information concerning the church activities
and the future plans for the areas indicated for future development. Staff
questioned the hours of worship service and the hours of church activities.
Public Works comments were addressed. Staff stated a grading and drainage plan
was required prior to any land clearing or grading activities on the site. Staff
requested the applicant provide a sketch grading and drainage plan. Staff stated
prior to construction of retaining walls an engineer's certification was required for
the design of the retaining walls. Staff stated upon completion an as -built
certification of the retaining wall was required. Staff requested the applicant
provide a sight distance certification for the driveway location along Taylor Loop
Road.
Rock Region Metro comments were addressed. Staff stated the site was not
currently served by Rock Region Metro but was a part of the long range plans.
Staff stated pedestrian infrastructure in the form of sidewalks to the facility front
entrance was important. Staff stated if a canopy was proposed for the drop off
entry the canopy should provide a height sufficient to allow paratransit vehicle
access.
Landscaping comments were addressed. Staff requested the site plan indicate
any areas proposed to remain with natural vegetation. Staff also stated
landscaping was required adjacent to the paved areas and the property lines. Staff
stated land use buffers were required where adjacent to single-family residences.
Staff stated easements could not count in computing the depth of the land use
buffer. Staff stated building landscaping was required adjacent to the proposed
0
FILE NO.: Z-8194
new building construction. Staff stated a minimum of eight (8) percent of the
parking lot areas were to be landscaped.
Staff noted the comments from the various other departments and agencies. Staff
suggested the applicant contact the departments or agencies directly with any
questions or concerns. There were no more issues for discussion. The Committee
then forwarded the item to the full Commission for final action.
H. ANALYSIS:
The applicant submitted a revised site plan to staff addressing most of the technical
issues associated with the request. The applicant has provided the activities of
the church as well as the future plans for the expansion areas. The applicant has
also provided the days and hours of activities taking place at the church. The site
plan indicates the placement of two (2) areas for future expansion. The applicant
notes the areas would be used for either a sanctuary/fellowship hall and/or
additional education space. All site lighting is to be low level, directional, and
directed down into the site.
The applicant is not proposing access to Black Bear. The applicant has indicated
this access will be limited to emergency access and will be gated with a Knox Box
located at the end of Black Bear. The applicant is not proposing the placement of
a turn -around at the end of Black Bear. Based on the level of grading which would
be required to install the turn -around staff no longer feels the turn -around is
required b this development.
The request is to revise and reinstate the previously approved PD-R, Planned
Development Residential, to allow the development of the site with a new church
and associated parking. The church is proposed containing 11,000 gross square
feet of floor area. The site plan indicates the placement of 64 parking spaces. The
maximum building height proposed is 26-feet. The zoning ordinance allows the
placement of steeples, chimneys or similar ornamental structures to exceed the
height of the zoning district provided the structure not exceed twice the height
permitted. In this case the underlying zoning is R-2, Single-family which allows a
maximum building height of 35-feet. Staff recommends if constructed the steeple
not exceed twice the building height for a maximum height of 52-feet in height.
The revised cover letter indicates the construction is anticipated to begin in
April/May of 2107 and be completed by January 2018. The plan indicates a
maximum seating capacity for the worship space of 250 seats. The current church
membership is 100. Parking for churches (and other places of worship), is
calculated at 1.0 space for every four (4) seats in new principal assembly areas or
additions to currently existing structures. Choir seating and areas for folding chairs
shall be counted. Twenty (20) inches on a pew shall be considered one (1) seat.
Stacked parking may be authorized by the Planning Commission at the time of site
plan reviews. The site plan indicates the placement of 64 parking spaces. Based
�0]
FILE NO.: Z-8194-B (Cont.)
on the typical parking required based on the seating capacity 62 parking spaces
would be required. The parking as indicated appears to be adequate.
The site plan indicates the placement of a single dumpster near the church facility.
The applicant has indicated the dumpster will be screened per typical ordinance
requirements. The applicant has indicated the hours of dumpster service will be
limited to 7 am to 6 pm Monday through Friday.
The site plan indicates the placement of a new ground mounted sign. The sign is
indicated four (4) feet high and eight (8) feet long on a two (2) inch high base. The
sign area excluding the base is proposed at 32 square feet. The applicant
proposes the placement of building signage to comply with the typical standards
of the office and institutional zoning district (Section 36-553). A maximum of ten
(10) percent of the fagade area abutting a public street.
indicates large wooded areas to remain in their natural state. This
fles and rain gardens. The plan indicates the placement of native
Irrigation is only proposed within selected flower beds at the
4 -s are required when an adjacent property has a dissimilar use of a
nature. The ordinance typically requires the land use buffer be
;ix (6) percent of the average depth of the lot. The minimum
dimensiui i a,,,dved is nine (9) feet. All land use buffers require opaque screening,
whether a fence or other device, a minimum of six (6) feet in height located on the
property line. A minimum of seventy (70) percent of the land use buffer is to remain
undisturbed. The ordinance states easements cannot count toward fulfilling the
buffer requirements. In addition to the required screening, plant materials are
required in the buffer areas at the rate of one (1) tree and three (3) shrubs for every
thirty (30) linear feet. All the surrounding properties are zoned R-2, Single-family
which will require the buffer requirements to be met.
With the exception of the northeastern portion of the site, adjacent to the entrance
drive, the land use buffer requirements are being met. The landscape strip in this
area is indicated nine (9) feet from the property line. The site plan notes the area
will be graded to the property line. A note on the site plan indicates plantings will
be installed at the new driveway bank. Staff recommends either the plant materials
installed provide the required screening or the applicant construct a wood fence or
wall along the property line in the areas which the land use buffer and screening
requirements are not being met.
The applicant has indicated the church will not offer a mother's day out program.
No school or daycare center is proposed with the current application request. The
applicant has indicated the church is staffed on a daily basis. Staff members are
on site from 8 am to 5 pm Monday through Friday. Occasionally the church has
activities occurring each night of the week. In these cases the activities begin at
5 pm and end by 9 pm. The worship services on Sunday are 8 am and 6 pm.
10
FILE NO.: Z-8194-B (Cont.
Staff is supportive of the applicant's request. The site contains approximately three
and one-half (3 Y2) acres and only a small percentage of the site is proposed for
development. Although there are a number of residential homes located in this
area there are also non-residential uses including two (2) churches and a City of
Little Rock Fire Station. The site is located on Taylor Loop Road which classified
on the Master Street Plan as a minor arterial which is the typical location desired
for non-residential uses. To staffs knowledge there are no remaining outstanding
technical issues associated with the request. Staff feels the development as
proposed is appropriate for the site.
STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
Staff recommends, if constructed, the steeple not exceed 52-feet in height.
Staff recommends the land use buffer and screening requirements along
the northeastern portion of the drive which will be disturbed be replanted with
plant material to provide the proper screening of the adjacent residentially
zoned property.
PLANNING COMMISSION ACTION: (FEBRUARY 2, 2017)
The applicant was present. There were registered objectors present. Staff presented the
item with a recommendation of approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda staff report.
Staff presented a recommendation that if constructed the steeple not exceed 52-feet in
height. Staff presented a recommendation the land use buffer and screening
requirements along the northeastern portion of the drive which would be disturbed be
replanted with plant material to provide the proper screening of the adjacent residentially
zoned property.
Mr. Tom Fennell addressed the Commission on the merits of the request. He stated his
architectural firm was designing the building for First Christian Church. He stated the
grading plan included benching the site which would then allow for the maintenance of
greens spaces and buffers around the site perimeters. He stated the Church held a
neighborhood meeting to gain comments from area residents. He stated there were a
number of residents concerned with the extension of Black Bear Drive. He stated working
with staff the site plan had been revised to remove any connection to Black Bear and
provided a turn -around on the Church site for emergence vehicles. He stated the site
was being designed to allow the predominance of the church and visibility from Taylor
Loop Road.
11
FILE NO.: Z-8194-B (Cont.
Mr. Steve Teague addressed the Commission stating based on the elimination of access
to Black Bear Drive he was no longer opposed to the request. He stated he and his
neighbors now welcomed the church as their new neighbor.
Mr. Trip Vogel addressed the Commission in opposition of the request. He stated the
Church leadership did meet with area residents and listened to their concerns. He stated
after the meeting he met with members of the church to address his primary concerns.
He stated one of his primary concerns was the safety and security of his family. He stated
when the Jehovah Witness Church was building their church adjacent to his property he
was also building his new home. He stated the church worked with him to address his
concerns. He stated when the church was first built there was not a gate on Hinson Road.
He stated this allowed persons to loiter in the parking lot. He stated persons also loitered
in the cul de sac adjacent to his home. He stated once the church put up a gate on Hinson
Road this eliminated persons loitering in the church parking lot. He stated working with
the Little Rock Police Department persons loitering in the cul de sac was being addressed.
He stated with regard to his family's safety he was requesting the church place a physical
barrier between their property and his. He stated he had signatures of all the neighbors
which abutted the church desiring the church put up a fence between the two uses. He
stated once the church was built persons walking on Taylor Loop Road would cut through
the church property and his yard as a short cut. He stated the church had addressed
garbage collection and gating the parking lot. He stated lighting was also a concern. He
requested the church turn off all site lighting at 9 PM. He stated currently when he went
outside there were stars. He stated once the church was built this would no longer be the
case. He stated also noise was a concern. He stated he had requested the church
consider sound proofing their building. He stated the site plan indicated future expansion
areas. He stated a daycare or school would not be a good fit for the area. He stated he
was also concerned with vehicles exiting the site. He stated based on speeds this was a
very dangerous area. He stated the curve in the road and as persons were leaving the
stop light at Hinson Road they were gaining speed as they passed this site. He stated it
would be a challenge to get out of the site.
Mr. Fennell addressed the Commission stating the Church had committed to no daycare
or mother's day out program. He stated the plan indicated a gate on Taylor Loop Road
which would be closed at all times except when church personnel were present. He
stated the lighting would be shielded and would not overspill the site. He stated the
lighting of the cross would be in such a manner the neighbors would not see any light spill
over based on placement as well as the elevation of the site. He stated the church did
not want to place fences on the adjacent properties. He stated the church was providing
the proper buffers and screening as required by City ordinances.
Commissioner May questioned the current location of the church. Mr. Fennell stated their
current location was on Mississippi. Mr. May stated he had been their neighbor for
40 years and they had been nothing but a good neighbor.
Commissioner Laha stated he questioned a neighbor of an undeveloped site one time
and the person stated if the lighting was not bright enough for him to go outdoors and
read the newspaper in his back yard then it was not bright enough. He stated proper
lighting reduced crime in areas.
12
FILE NO.: Z-8194-B (Cont.)
There was a motion to approve the request as presented by staff. The motion carried by
a vote of 10 ayes, 0 noes and 1 absent.