HomeMy WebLinkAboutZ-8045-A Staff AnalysisDecember 4, 2014
ITEM NO.: 4 FILE NO.: Z -8045-A
NAME: Little Rock Wastewater Utility Peak Flow Storage
Facility Expansion — Conditional Use Permit
LOCATION: 5200 Scott Hamilton
OWNER/APPLICANT: City of Little Rock/Little Rock Sanitary Sewer
Committee
PROPOSAL: A revision to a previously approved conditional use
permit is requested to allow for the addition of third
peak flow storage basin to this 1-2 zoned site.
SITE LOCATION:
The site is located behind the industrial businesses located on the west
side of Scott Hamilton, behind the businesses located on the north side of
Hoerner Road, behind the businesses located on the east side of
Patterson and south of Fourche Creek.
2. COMPATIBILITY WITH NEIGHBORHOOD:
The peak flow storage facility is located at the northern edge of the 65th
Street Industrial Park, adjacent to the Fourche Creek floodway. Uses
around the site include a variety of industrial uses and the floodway. The
basins are enclosed within a dike structure and the overall site is enclosed
by buffers and screening. The facility has existed for approximately five
years and has apparently been maintained and cleaned as LRWU
committed. To staff's knowledge, there have been no unresolvable issues
with the facility since its opening.
Notice of the public hearing was sent to all owners of properties located
within 200 feet of the site and the SWLR United for Progress, Upper
Baseline, Wakefield and Geyer Springs Neighborhood Associations.
LRWU has held a series of meetings with the associations and an open
house of the facility was scheduled to be held on November 15, 2014.
3. ON SITE DRIVES AND PARKING.
A single driveway off of Scott Hamilton provides access to the site. The
driveway is gated at Scott Hamilton. The driveway provides access to the
existing buildings and service area. No changes are proposed.
December 4, 2014
ITEM NO.: 4 (Cont.) FILE NO.: Z -8045-A
4. SCREENING AND BUFFE
A wooded buffer will be maintained around the developed portion of the
site. At its minimum, the buffer is 50 ft. in width. On the east side of the
site, the buffer ranges from 140 ft. to 400 ft. The buffers will be
undisturbed and left in a natural condition to the extent practical. Any
areas that must be disturbed will be re-established. Staff believes areas
that are to remain undisturbed should be protected throughout
construction by orange, contractor's fencing.
5. PUBLIC WORKS COMMENTS:
1. A grading permit in accordance with section 29-186 (c) & (d) will be
required prior to any land clearing or grading activities at the site.
Other than residential subdivisions, site grading and drainage plans
must be submitted and approved prior to the start of construction.
2. A special Grading Permit for Flood Hazard Areas will be required per
Sec. 8-283 prior to construction.
3. If disturbed area is 1 or more acres, obtain a NPDES storm water
permit from the Arkansas Department of Environmental Quality prior to
the start of construction.
4. The minimum Finish Floor elevation of 258 ft. is required to be shown
on plat and grading plans. All mechanized and electrical
improvements that could be damaged during a flood event should be
elevated above the base flood elevation.
5. Per Section 29-189(d), groups of trees and individual trees that are not
to be removed or are located within required undisturbed buffer areas
shall be protected during construction by protective fencing and shall
not be used for material storage or for any other purpose.
6. UTILITY FIRE DEPT. AND CATA COMMENTS:
Wastewater: No Comment.
Entergy: No objection. Contact Entergy in advance for any changes or
additions to the electrical service.
Centerpoint Energy: No comment received.
AT&T: No comment received.
Water: No objection.
2
December 4, 2014
ITEM NO.: 4 Cont. FILE NO.: Z -8045-A
Fire Department: Maintain access.
Building Codes: Project is subject to full commercial plan review approval
prior to issuance of a building permit. For information on submittal
requirements and the review process, contact a commercial plans
examiner:
Curtis Richey at 501.371.4724; crichey(a-,)Iittlerock.org or
Mark Alderfer at 501.371-4875; ma IderferCa7littlerock. orq.
County Planning: No comments.
CATA: The site is not located on a CATA bus route. A route is located
south of the site, at Hoerner and Scott Hamilton.
SUBDIVISION COMMITTEE COMMENT: (NOVEMBER 5, 2014)
The applicants were present. Staff presented the item and noted little additional
information was needed. Staff asked the applicants to describe existing and
proposed fencing, signage and any new buildings.
Public Works Comments were noted.
The applicants stated they had met with area neighborhood associations and a
tour of the facility was scheduled for November 15. The applicant stated no new
above -ground structures were planned but improvements would be made to
existing odor control system structure and grit chamber in response to a request
from the neighborhoods.
The applicants were advised to respond to staff questions by November 12,
2014. The Committee forwarded the item to the full Commission.
STAFF ANALYSIS:
On May 25, 2006 the Commission approved a conditional use permit to allow for
construction of two peak flow storage basins on this site. The development
involved approximately 20 acres of the 40 acre, three tract site. The approval
was appealed to the Board of Directors but the appellant withdrew the appeal
prior to the Board hearing the matter.
The facility consists of two large, concrete basins (10 million gallons and
20 million gallons) constructed within levee structures. The facility also includes
a grit chamber, odor control system and emergency generator. The developed
portion of the site is enclosed by a black; 6 foot tall, chain-link face with barbed
3
December 4, 2014
ITEM NO.: 4 (Cont.
FILE NO.: Z -8045-A
wire for security Access to the site is via a single, gated driveway off of Scott
Hamilton.
The project is an integral component of a Consent Administrative Order (CAO)
with the Arkansas Department of Environmental Quality (ADEQ). The CAO, in
part, requires adherence to the Sierra Club Settlement Agreement which
references the project. The overall objective is to reduce the number of sanitary
sewer overflows (SSO's) and associated spill volumes that occur during rain
events. SSO's are a violation of Little Rock Wastewater Utility's discharge permit
and can result in monetary fines levied by ADEQ. Odor is not typically a problem
with this type of facility. This is due in part to the fact that the sewage temporarily
stored in the basin is diluted by rainwater. The sewage is typically detained for
seventy-two (72) hours at a maximum. LRWU committed to clean the basins
within twenty-four (24) hours after the drainback is complete.
The facility has been used approximately twelve (12) times per year on average
to mitigate sanitary sewer overflows that occur as a result of significant rain
events. Since the existing basins were put into service in 2009, they have
prevented more than one billion gallons of wastewater from overflowing from
manholes across the city.
LRWU is now proposing to construct a third basin on the site. This proposed
new basin will hold 31 million gallons. A 51 million gallon basin was originally
recommended. LRWU met with representatives of several neighborhood
organizations, elected officials, city staff and management to discuss the details
of that recommendation. Partially, as a result of feedback received during these
meetings, the project was re-evaluated. The engineers determined that the size
of the proposed third basin could be reduced from 51 MG to 31 MG by shifting a
larger portion of the burden to the Adams Field Wastewater Treatment Plant.
The proposed new 31 MG basin will be of similar construction as the existing
basins and designed for similar use. Wastewater is stored in the basins on a
temporary basis and then drained back into the sanitary sewer system for
conveyance to one of the Utility's treatment plants. When the basins become
full, the pump station directing flow to the facility is turned off. This could result in
the reoccurrence of overflows within the collection system. The addition of the
proposed new basin will allow the facility to operate over a longer duration and
better accommodate larger rainfall events.
The existing storage facility has apparently operated incident free since it was
placed into service five (5) years ago. Although any odor complaints have been
few, the utility is planning to install enhanced odor control measures at the
facility. The existing grit chamber, where the overflow first enters the facility, will
be enclosed. The proposed new basin will be cleaned after each storage event
in accordance to the utility's established practice.
4
December 4, 2014
ITEM NO.: 4 (C
FILE NO.: Z -8045-A
A portion of the new basin is to be constructed on an easement held by
CenterPoint Energy (CPE) for their gas transmission mains that cross this
property. LRWU and CPE have entered into a joint use agreement regarding this
issue. CPE has installed new piping across the property to minimize the
likelihood of a line failure underneath the new basin. LRWU has committed to
making provisions within their design to minimize any encumbrances to CPE
potentially caused by construction of this facility.
The existing fifty (50) foot landscape buffer will be maintained. The existing
vegetation in the buffer will be undisturbed and left in its natural state to the
extent practical. Any areas that must be disturbed will be re-established. No
additional driveways or access points are proposed. The proposed
improvements will not include any new mechanical equipment that would require
noise abatement. Lighting will continue to be limited to the grit chamber area and
will be switched on manually in the event of an after-hours mechanical concern.
There is no bill of assurance for this acreage tract.
STAFF RECOMMENDATION:
Staff recommends approval of the requested CUP subject to compliance with the
comments and conditions outlined in Sections 4, 5 and 6 of the agenda staff
report.
PLANNING COMMISSION ACTION- (DECEMBER 4, 2014)
The applicants were present. There were two persons present who had
registered as objectors. Staff presented the item and a recommendation of
approval as outlined in the "staff recommendation" above.
John Holloway, of Little Rock Wastewater (LRWU), stated he would reserve his
time to respond to any issues raised by those who had concerns.
Pat Gee, Vice-president of SWLRUP and President of Upper Baseline
Neighborhood Association, stated they had a few concerns that they wanted
addressed. She stated the Wakefield Neighborhood Association had voted to
support the proposal and the Geyer Springs Neighborhood Association meeting
was not well attended and no vote was taken. She stated SWLRUP wanted
assurance that the grit chamber enclosure and automatic odor control chemical
feeder would be installed and used to prevent odors. She stated they also
wanted assurance no more basins would be requested on this site after this one
:7
December 4, 2014
ITEM NO.: 4 (Cont.) FILE NO.: Z -8045-A
and made note of the proximity of Fourche creek and Benny Craig Park. She
asked the cost of the facility.
Mr. Holloway stated the facility had been in use since September 2009 and had
been used to collect over one -billion gallons of overflow that would have gone
into Fourche Creek. He stated there had been 62 events in the 5 years and
17 where the facility reached maximum capacity and the pumps to the facility
had to be turned off. He stated this additional basin would provide that needed
extra capacity during those rare events. He stated the grit chamber enclosure
and odor abatement system would be installed in early 2015. He stated the cost
of the new facility was in the area of twenty-eight million dollars. Mr. Holloway
stated there had been meetings with officials and concerned stakeholders and
the original concept for the basin had been reduced from 51 million gallons to
31 million in response to concerns the Utility had heard.
Commissioner Berry stated the need for the basins came in response to a court
order. He asked how many basin sites there would be. Mr. Holloway responded
that there was this site, one at the Adams Field waste treatment site and two
additional sites that had been identified.
In response to questions from Commissioner May, Mr. Holloway stated the Utility
located the sites based on the confluence of problem and solution; where the
overflows occur and the proximity of major trunk lines. He also commented on
the process of potentially locating an overflow facility in the areas of Henderson
School and Presbyterian Village.
Troy Laha, of SWLRUP, stated he wanted assurance that the odor abatement
chemical operation will start when the pump starts, not when they get a complaint
about odor. Mr. Holloway responded that they will turn the system on when flow
starts occurring at the grit chamber.
A motion was made to approve the application, including all staff comments and
conditions. The motion was seconded and approved by a vote on 8 ayes, 0 noes
and 3 absent.
0
SUBDIVISION COMMITTEE COMMENTS
NOVEMBER 5, 2014
ITEM NO_ 4. LITTLE ROCK WASTEWATER UTILITY PEAK FLOW
STORAGE FACILITY EXPANSION CONDITIONAL USE PERMIT
5200 SCOTT HAMILTON Z -8045-A
Planning Staff Comments:
1. There is no bill of assurance for this acreage tract.
2. Describe existing and proposed fencing, locate gates.
3. Will there be any new above -ground buildings?
4. Describe existing and proposed signage.
Variance/Waivers.
• None requested.
Public Works:
1. A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land clearing or
grading activities at the site. Other than residential subdivisions, site grading and drainage plans must be
submitted and approved prior to the start of construction.
2. A special Grading Permit for Flood Hazard Areas will be required per Sec. 8-283 prior to construction.
3. If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas Department of
Environmental Quality prior to the start of construction.
4. The minimum Finish Floor elevation of 258 ft. is required to be shown on plat and grading plans. All
mechanized and electrical improvements that could be damaged during a flood event should be elevated
above the base flood elevation.
5. Per Section 29-189(d), groups of trees and individual trees that are not to be removed or are located within
required undisturbed buffer areas shall be protected during construction by protective fencing and shall not
be used for material storage or for any other purpose.
Utilities and Fire Department/Coun1y Planning_
Wastewater: No Comment.
Entergy: No objection. Contact Entergy in advance for any changes or additions to the electrical service.
Centerpoint Energy: No comment received.
AT&T: No comment received.
Water:
Fire Department: Maintain access.
Building Codes: Project is subject to full commercial plan review approval prior to issuance of a building permit.
For information on submittal requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; crichey_(wlittlerock.org or
Mark Alderfer at 501.371-4875; malderfer@littlerock.org.
County Planning: No comments.
ITEM NO.: 4. CON'T
(Z -8045-A)
CATA: The site is not located on a CATA bus route. A route is located south of the site, at Hoerner and
Scott Hamilton.
Planning Division: No comments.
Landscape: Buffer is to be marked and protected by Orange Contractor's fencing prior to site work commencing
and throughout construction.
Other: Submit responses to staff issues and four (4) copies of a revised site plan (if required) no later than
Wednesday November 12, 2014. Required notices are to be sent via certified mail to all owners of properties
located within two hundred (200) feet of the site no later than Wednesday November 19, 2014, The City -provided
notice form must be used. Proof of notice is to be provided to staff no later than November 28, 2014.