HomeMy WebLinkAboutZ-7783-A Staff AnalysisApril 14, 2005
ITEM NO.: 7.1
NAME: Miracle Development Short -form PD -C
LOCATION: Located at 14929 Cantrell Road
DEVELOPER:
Miracle Developments
8015 Stagecoach Road
Little Rock, AR 72210
ENGINEER:
Global Surveying Consultants Inc.
2.17 West 2"d Street, Suite 100
Little Rock, AR 72201
AREA: 2.21 acres
CURRENT ZONING:
ALLOWED USES
PROPOSED ZONING:
PROPOSED USE:
NUMBER OF LOTS: 1
R-2, Single-family
Single-family residential
PD -C
Carwash facility
FILE NO.: Z -7783-A
FT. NEW STREET: 0 LF
VARIANCESIWAIVERS REQUESTED: None requested.
BACKGROUND:
A requested rezoning of the property located at 14929 Cantrell Road from R-2, Single
Family District to 0-3, General Office District for future office development is currently
before the Little Rock Planning Commission. That applicant elected to defer the
rezoning request at the Commission's March 17, 2005, Public Hearing to allow this
applicant to pursue the current application request.
A. PROPOSAUREQUESTIAPPLICANT'S STATEMENT:
The applicant is now proposing to build a two -bay automatic carwash facility with
three vacuum stations along Cantrell Road with the addition of a future third bay.
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 Cont. FILE NO.: Z -7783-A
The applicant has indicated there will be no parking provided as there will be no
reason for any vehicle other than a service vehicle to be unattended on the
property. The applicant has indicated the facility will initially be a 24-hour facility.
The applicant has stated an agreement has been reached with the adjoining
property owners that should the 24-hour operation become a concern they will
close during the late night and early morning hours. The applicant has indicated
since they do not anticipate much business during these hours, just the
possibility of having a car come through will discourage loitering and illegal
activity.
The applicant has indicated the plan will provide a separation of approximately
98 -feet from the west property line to the building, which is more than three times
the 30 -feet building line requirement defined by ordinance. In addition to this, the
applicant has stated the planned use will leave 225 -feet of the southern portion of
the property (almost an acre) undeveloped as an additional buffer.
The applicant has indicated elevation concerns raised with the previous
application will be resolved with the current development. The applicant has
stated a great deal of fill was previously proposed thereby causing an issue with
the adjoining homeowners of choosing between a steep hillside or retaining walls
dominating their backyard views. The applicant has stated the current proposal
allows for a minimum of fill due to the limited use of the total property area. The
applicant has stated based on cross section views the homeowners in the
Westchester Subdivision will be unable to see any vehicles or little of the
building. The applicant has stated all that will be visible will be the roof and
possibly some of the building fascia.
The applicant has indicated drainage concerns will be addressed. The applicant
has stated according to preliminary calculations, they would not be required by
City regulations to install any sort of detention system to slow the flow rate of
storm water across and from the development due to the very small amount of
the total property that is being developed. Even so, the applicant is proposing to
install a double detention system to slow the flow rate of the storm water
currently crossing and coming from the property by a minimum of 25 percent
completely at the developer's expense. The applicant has stated they feel this
will assist in improving the drainage within the western portion of the adjacent
subdivision.
The applicant has indicated operational noise will be minimal. According to the
applicant's cover letter a decibel -meter test has been conducted at their existing
site located at 8015 Stagecoach Road and on the proposed site. The applicant
has stated they feel the addition of the facility will not cause any increase in the
noise levels in the adjacent properties over what currently exists due to the traffic
on Highway 10. Furthermore, according to the applicant, the new facility will be
quieter than the existing site on Stagecoach Road because a longer wash bay
2
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 Cont. FILE NO.: Z -7783-A
length is proposed for the Highway 10 site, which will allow the applicant to move
the equipment further within the building.
The applicant has indicated lighting will be building mounted wall -packs and
low-level pole lights that use only downward -directed lighting that is shielded
from the visibility of the adjacent properties. The applicant has indicated there
will not be any lighting on the west or south side of the building above the
building fascia.
The site plan includes the placement of one 6 -foot diameter lighted sign mounted
in the gable of the building facing north toward Highway 10 and one monument
sign at the entrance to Highway 10.
A land use plan amendment for a change to Mixed Use is a separate item on this
Agenda (LU05-01-02).
B. EXISTING CONDITIONS:
The site currently contains two (2) single family residential structures, with a
single access drive from Cantrell Road. Single family residences are located on
the property immediately west and south of the site. A mixture of residential,
office and commercial uses and zoning exists to the west along Cantrell Road.
Single family residential and office uses and zoning is located across Cantrell
Road to the north.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has received several informational phone calls from area
residents. The Westbury Neighborhood Association, the Westchester
Neighborhood Association, the Secluded Hills Neighborhood Association, all
property owners located within 200 -feet of the site and all residents, who could
be identified, located within 300 -feet of the site were notified of the public
hearing.
D. ENGINEERING COMMENTS:
Public Works Conditions:
1. Cantrell Road is classified on the Master Street Plan as a principal arterial. A
minimum dedication of right-of-way to 55 -feet from centerline will be required
at all locations. An additional easement for future storm water improvements
may be required.
2. Provide the direction of flow and all storm water flows (Q) entering and
leaving the property. Provide a sketch grading and drainage plan showing
the proposed drainage and grading for future site development.
3
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 Cont. FILE NO.: Z -7783-A
3. A grading permit in accordance with Section 29-186 (c) and (d) will be
required prior to any land clearing or grading activities at the site. Site
grading and drainage plans will need to be submitted and approved prior to
the start of construction.
4. Westchester Subdivision to the west has a history of flooding problems. The
Storm Water Detention Ordinance applies to this property and will be
required.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available, not adversely affected.
Entergy: No comment received.
Center -Point Energy: Approved as submitted.
SBC: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at
the time of request for water service must be met. A Capital Investment Charge
based on the size of the meter connection(s) will apply to this project in addition
to normal charges. Additional fire hydrant(s) will be required. Contact the Little
Rock Fire Department to obtain information regarding the required placement of
the hydrant(s) and contact Central Arkansas Water regarding procedures for
installation of the hydrant(s). Due to the nature of this facility, installation of an
approved reduced pressure zone backflow preventer assembly (RPZA) is
required on the domestic water service. This assembly must be installed prior to
the first point of use. Central Arkansas Water (CAW) requires that upon
installation of the RPZA, successful tests of the assembly must be completed by
a Certified Assembly Tester licensed by the State of Arkansas and approved by
CAW. The test results must be sent to CAW's Cross Connection Section within
ten days of installation and annually thereafter. Contact Carroll Keatts at
377-1226 if you would like to discuss backflow prevention requirements for this
project.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department at 918-3700 for additional information.
County Planning: No comment.
CATA: The site is located on CATA Bus Route #25, the Highway 10 Express.
4
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 Cont.) FILE NO.: Z -7783-A
F. ISSUES/TECHNICAL/DESIGN
Planning Division: This request is located in the River Mountain Planning
District. The Land Use Plan shows Transition for this property. The applicant is
requesting zoning for a PCD (Planned Commercial Development) for a 24-hour,
multiple bay, automated car wash.
A land use plan amendment for a change to Mixed Use is a separate item on this
Agenda (LU05-01-02).
Master Street Plan: Cantrell Road is shown as a Principal Arterial on the plan.
Cantrell Road is built as a five -lane road through this area. The primary function
of a Principal Arterial is to serve through traffic and connect major traffic
generators or activity centers within urbanized areas. Cantrell Road may require
dedication of right-of-way and street improvements. Since this property is
located on a Principal Arterial, access to the site should be minimized and should
not impede through traffic.
Bicy_c_l_e_Plan: Existing or proposed Class I, II, or III bikeways are not in the
immediate vicinity of the development.
City Recognized Neighborhood Action Plan: The applicant's property lies in the
area covered by the River Mountain Neighborhood Action Plan. The Sustainable
Natural Environment goal listed an objective of promoting the vigorous
enforcement of the Landscaping & Excavation Ordinance. This action could
result in the removal of trees in order to accommodate the development of uses
possible in a Commercial development.
Landscape: A portion of the proposed on-site landscape buffer width along
Cantrell Road is less than the 40 -feet required by the Highway 10 Design
Overlay District Ordinance.
A six foot high opaque screen, either a wooden fence with its face side directed
outward, a wall or dense evergreen plantings is required along the eastern,
western and southern perimeters of the site. Credit toward fulfilling this
requirement can be given for existing trees and undergrowth that satisfies this
year -around screening requirement.
An irrigation system to water landscaped areas will be required.
G. SUBDIVISION COMMITTEE COMMENT: (March 24, 2005)
The applicant was present representing the request. Staff stated the applicant
was requesting a rezoning to PCD to allow the construction of a two bay carwash
5
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 (Cont.) FILE NO.: Z -7783-A
facility with an expansion area for a third bay. Staff noted there were additional
items necessary to complete the review process. Staff stated the indicated
signage did not comply with the Highway 10 Design Overlay standard. Staff
stated the Highway 10 Design Overlay typically allowed for signage not to
exceed six feet in height and seventy-two square feet in area for a single
development. Staff also requested details of any proposed fencing including
height, location and construction material. Staff questioned the proposed
vacuum stations with regard to a canopy over the stations and if there would be a
logo on the canopy. Staff requested the applicant provide the height of the
proposed vacuum stations and details of screening from Highway 10.
Public Works comments were addressed. Staff requested the applicant provide
the direction of flow and all storm water flows (Q) entering and leaving the
property and a sketch grading and drainage plan showing the proposed drainage
and grading for future site development. Staff stated the Westchester
Subdivision to the west had a history of flooding problems. Staff noted the Storm
Water Detention Ordinance would apply to the property and would be. required.
Landscaping comments were addressed. Staff stated a portion of the proposed
on-site landscape buffer width along Cantrell Road was less than the 40 -feet
required by the Highway 10 Design Overlay District Ordinance. Staff also stated
a six foot high opaque screen, either a wooden fence with its face side directed
outward, a wall or dense evergreen plantings was required along the eastern,
western and southern perimeters of the site. Staff stated credit toward fulfilling
this requirement could be given for existing trees and undergrowth that satisfied
this year -around screening requirement. Staff stated an irrigation system to
water landscaped areas would be required
Staff noted comments from the various other reporting departments and
agencies indicating the applicant should contact them individually for further
clarification. There was no further discussion of the item. The Committee then
forwarded the item to the full Commission for final action.
H. ANALYSIS:
The applicant submitted a revised site plan to staff addressing most of the issues
raised at the March 24, 2005, Subdivision Committee meeting. The applicant
has indicated signage consistent with the Highway 10 Design Overlay District
standard or a maximum of six feet in height and seventy-two square feet in area.
The applicant has also indicated fencing will be placed along the eastern
property line and the southern property line both six feet in height. The applicant
has indicated an eight foot fence will be placed along the entrance drive, eight
feet in height. The applicant has also indicated the fence along the internal drive
and along the southern property line will be placed with the smooth face to the
building. The applicant has indicated the fencing is not located on the property
LV
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 Cont. FILE NO.: Z -7783-A
line and the placement of the smooth side out would have no benefit to the
adjoining property owners. In addition, the applicant has indicated a 25 -foot
landscape buffer will be added along the western property line to protect the
residences in this area. To the south of the site is a 0.93 acre tract of
undeveloped area. The applicant has indicated the existing buildings will be
removed along with all paved areas and the areas will be reseeded.
The applicant has indicated the vacuum stations will be a maximum of eight feet
in height and three and one-half feet at the base. The applicant has indicated the
stations will be covered with a canopy a maximum of ten feet in height. The
applicant has indicated the canopy will be under lit and there will not be any
logos located on the proposed vacuum station canopies. The site plan includes
vacuum station screening with a landscaping treatment or a berm or a
combination of both.
The applicant has indicated limiting the servicing hours of the proposed dumpster
to 7 am to noon Monday through Friday. The dumpster has been located along
the eastern side of the building away from the single-family homes located in the
Westchester Subdivision.
The applicant has provided Public Works staff with a sketch grading and
drainage plan as requested. The applicant has also indicated areas set aside for
storm water detention on the proposed site plan. The applicant has indicated
detention will be provided along the eastern property line and along the western
property line to ensure detention of the site's potential water run-off.
The site plan indicates all site development will take place behind the 40 -foot
landscape buffer typically required by the Highway 10 Design Overlay District.
The applicant has also indicated irrigation will be provided to water landscaped
areas and a RPZA backflow preventer will be installed per Central Arkansas
Water specifications.
Staff is not supportive of the applicant's request for a commercial development at
this location. The applicant has indicated the site plan allows for buffer of the
neighboring single-family homes. The site plan does allow for additional
buffering for a few of the homes but there are several homes, which do not
receive the benefit of the acre of undisturbed buffer. Staff feels there are
available sites in the area, which are currently zoned or indicated on the Future
Land Use Plan as Commercial, which would allow for a development as
proposed. Staff feels if this site is allowed to redevelop as a commercial use this
will only encourage the sites located immediately east to also redevelop as
commercial uses. This development pattern will extend the existing commercial
node located at Taylor Loop Road further west taking in this site as well. The site
is shown as Transition on the City's Future Land Use Plan and a change to
Mixed Use is a separate item on this agenda. Staff is not supportive of the plan
7
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 (Cont.) FILE NO.: Z -7783-A
change and feels the site should remain as Transitional and redevelop as a use
defined under the Transitional Land Use category or low density residential,
multi -family or an office use. Staff feels a commercial use is too intense a
development for this site and the plan should be maintained allowing a stepping
down of intensity of uses.
STAFF RECOMMENDATION:
Staff recommends denial of the request.
PLANNING COMMISSION ACTION: (APRIL 14, 2005)
Mr. Bill Keathly was present representing the request. There were registered objectors
present. Staff presented the item with a recommendation of denial.
Mr. Keathly addressed the Commission on the merits of his request. He stated he and
his partner had spent six months looking for a site on Highway 10 to develop a carwash
and the requested site was the only location they had been able to find. He stated he
had met with the neighborhood and the proposed site plan did offer them protection. He
stated he felt the requested use was a transitional use since there was approximately
one acre of land not being utilized but being offered as a buffer to the neighborhood.
He stated the site plan offered detention to help address the neighborhoods current
flooding problems. He stated the proposed carwash facility would not generate a great
deal of additional noise.
Mr. Gene Martin addressed the Commission in support of the proposed request. He
stated he supported the development with mixed emotions. He stated the developers
had worked closely with the neighborhood to develop a plan that was less intrusive to
the neighborhood. He stated he felt this development was more desirable than a
multi -story office building. Mr. Martin stated he felt the proposed development a good
transition for the neighbors most effected.
Mr. Mike Saar addressed the Commission in opposition of the proposed request. He
stated the Westchester Neighborhood Association was not in support of the proposed
development although for a few of the residents of the neighborhood the developer was
offering a great deal of protection. He stated with the change of the site from residential
to commercial he felt this would only erode the Transitional Land Use classification of
the area. He stated he felt if the site were changed to Commercial this would only
encourage the area to the east of the site to also develop with an intense commercial
use.
Mr. Renee Crater addressed the Commission in opposition of the proposed request.
She stated she was the neighborhood that would be most effected by the proposed
development. She stated she felt the developers had addressed concerns related to
0
April 14, 2005
SUBDIVISION
ITEM NO.: 7.1 Cont. FILE NO.: Z -7783-A
drainage and lighting but not the noise levels. She stated current the site was not used
as a carwash facility and the noise was not there. She stated the time most people
wanted to utilize a carwash facility and the peak usage time was the time she would
typically be at home and trying to enjoy her outdoors. She stated she was not
supportive of the proposed development.
Ms. Ruth Bell addressed the Commission in opposition of the proposed request. She
stated the Transitional Land Use category typically allowed for a stepping down of
intensities allowing the lesser intensity uses adjacent to residential development. She
stated she was supportive of allowing the increased buffer area adjacent to the
neighborhood but felt a commercial development was not appropriate for the site.
Mr. D.K. Robinson and Ms. Rosemary Robinson did not wish to address the
Commission but indicated opposition to the proposed request.
Commissioner Floyd questioned the applicant as to measure that would be undertaken
to eliminate persons from hanging around the site and playing loud music while detailing
their cars. Mr. Keathly stated the site was not designed to allow loitering. He stated the
site at Stagecoach had been designed to allow for customer to pull out of the flow of
traffic and detail their cars. The Commission questioned the number of cars served in a
day. Mr. Keathly stated typically 85 cars per day would be served. He stated a web
cam would be installed to discourage loitering and the neighbors would be given access
to view the web cam.
A motion was made to approve the Land Use Plan amendment. The motion failed by a
vote of 0 ayes, 10 noes and 1 absent.
A motion was made to approve the PD -C request. The motion failed by a vote of
0 ayes, 10 noes and 1 absent.
9
ITEM NO.: 7 FILE NO.: Z-778
NAME: Miracle Development Short -form PD -C
LOCATION: located at 14929 Cantrell Road
Planning Staff Comments:
1. Provide notification of property owners located within 200 -feet of the site, complete
with the certified abstract list, notice form with affidavit executed and proof of
mailing.
2. The indicated signage does not comply with the Highway 10 Design Overlay
standard. The Highway 10 Design Overlay typically allows for signage not to exceed
six feet in height and seventy-two square feet in area for a single development.
3. Provide the proposed hours of the dumpster service.
4. Provide details of any proposed fencing (height/location/material).
5. Provide details of the proposed vacuum stations. Will there be a canopy over the
stations, if so will there be a logo on the canopy. Provide the height of the proposed
vacuum stations. Will the vacuum stations be screened from Highway 10? If so
what screening mechanism will be utilized?
6. The request includes the operation of the facility on a 24-hour basis.
Variance/Waivers: None requested.
Public Works Conditions:
1. Cantrell Road is classified on the Master Street Plan as a principal arterial. A
minimum dedication of right-of-way to 55 -feet from centerline will be required at all
locations. An additional easement for future storm water improvements may be
required.
2. Provide the direction of flow and all storm water flows (Q) entering and leaving the
property. Provide a sketch grading and drainage plan showing the proposed
drainage and grading for future side development.
3. A grading permit in accordance with Section 29-186 (c) and (d) will be required prior
to any land clearing or grading activities at the site. Site grading and drainage plans
will need to be submitted and approved prior to the start of construction.
4. Westchester Subdivision to the west has a history of flooding problems. The Storm
Water Detention Ordinance applies to this property and will be required.
Utilities and Fire Department/County Planning:
Wastewater: Sewer available, not adversely affected.
Entergy: No comment received.
Center -Point Energy: No comment received.
SBC: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at the time
of request for water service must be met. A Capital Investment Charge based on the
size of the meter connection(s) will apply to this project in addition to normal charges.
Additional fire hydrant(s) will be required. Contact the Little Rock Fire Department to
obtain information regarding the required placement of the hydrant(s) and contact
Central Arkansas Water regarding procedures for installation of the hydrant(s). Due to
the nature of this facility, installation of an approved reduced pressure zone backflow
preventer assembly (RPZA) is required on the domestic water service. This assembly
must be installed prior to the first point of use. Central Arkansas Water (CAW) requires
that upon installation of the RPZA, successful tests of the assembly must be completed
by a Certified Assembly Tester licensed by the State of Arkansas and approved by
CAW. The test results must be sent to CAW's Cross Connection Section within ten days
of installation and annually thereafter. Contact Carroll Keatts at 377-1226 if you would
like to discuss backflow prevention requirements for this project.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department at 918-3700 for additional information.
County Planning: No comment.
CATA: The site is located on CATA Bus Route #25, the Highway 10 Express.
Planning Division:
Landscape: A portion of the proposed on-site landscape buffer width along Cantrell
Road is less than the 40 -feet required by the Highway 10 Design Overlay District
Ordinance.
A six foot high opaque screen, either a wooden fence with its face side directed
outward, a wall or dense evergreen plantings is required along the eastern, western and
southern perimeters of the site. Credit toward fulfilling this requirement can be given for
existing trees and undergrowth that satisfies this year -around screening requirement.
An irrigation system to water landscaped areas will be required.
Revised plat/plan; Submit four (4) copies of a revised preliminary plan (to include the