HomeMy WebLinkAboutZ-7665-A Staff AnalysisFILE NO.: Z -7665-A
NAME: Rock Haven Revised Short -form PD -R
LOCATION: Located at 1000 Kirby Road
DEVELOPER:
Rock Haven Properties
700 East 9th Street 10M
Little Rock, AR 72202
FNGINFFR-
Development Consultants, Inc.
2200 North Rodney Parham Road, Suite 220
Little Rock, AR 72212
AREA: 4.158 acres
CURRENT ZONING
ALLOWED USES
PROPOSED ZONING
NUMBER OF LOTS: 22
Single-family residential
Revised PD -R
FT. NEW STREET: 1590 LF
PROPOSED USE: Single-family residential—the allowance of an RV to locate on the
site to serve as a security/sales office for the proposed development.
VARIAN C ESNVAIVERS REQUESTED: None requested.
BACKGROUND:
The Little Rock Planning Commission reviewed this request at their July 15, 2004,
Public Hearing and forwarded a recommendation of approval to the Board of Directors.
Ordinance No. 19,164 adopted by the Little Rock Board of Directors on August 17,
2004, established the Rock Haven Short -form PD -R. The proposed development was
designed based on a concept blended between a zero lot line subdivision and a
horizontal property regime. The lots were to be minimally sized to accommodate
buildable surface areas between 1500 and 2450 square feet on each lot. Homes were
proposed with a two-story height maximum. The bill of assurance was indicated to
FILE NO.: Z-7665-A(Cont.)
prescribe minimum and maximum home sizes, as well as controls for architectural
quality that would be administered by an architectural review committee. Each
buildable area was set within one foot of one lot line, and fourteen to fifteen feet from
the other to allow for a small side yard area. All homes would have enclosed garages
located at the rear of the structure and entered from the looped drive. Homes would
front on the interior common park area. The proposed access to lots was accomplished
with a private drive that encircled the property and was within a common access and
utility easement area. This easement was proposed as a part of the large Lot 1 area,
which comprised all of the land not contained within the residential lots. All
improvements and land within Lot 1 would be held in common ownership by the
property owners association and would also be maintained by the property owners
association. The property owners association would also maintain individual lot area
landscaping.
The applicant indicated Tract A as a separate parcel containing 1.91 acres. The
applicant indicated Tract A would be reserved for future development. The applicant
requested a deferral of required street improvements to Kirby Road until development
occurred for proposed Tract A.
The applicant indicated phasing would be utilized for the development. Phase I was to
consist of the development of Lots 1-11 including all required street improvements and
infrastructure. Phase II would consist of the completion of the access easement located
within Lot 1 and Lots 12-22.
A. PROPOSAUREQUEST:
The applicant is now requesting an amendment to the previously approved PRD
for the new subdivision to allow the use of an RV as a temporary sales,
construction management and security office on the construction site. The
applicants cover letter states soon after purchasing the land, there were multiple
cases of trash and limb debris dumping on the land, along with thefts on the site
and an adjacent residence. The applicant states they explored various security
solutions and ultimately determined to locate temporarily on the site. The
applicant states this would allow them to monitor and manage the construction
progress most effectively. The applicant states the sooner they complete their
objective—unique, quaint neighborhood and park—the better for the area. The
applicant also states they foresee the need to conduct sales of lots in the
temporary office. The applicant states interest in the future neighborhood has
already proven to be great. He states the feedback they have received on all the
plans and the temporary office has been positive.
The applicants cover letter states no sewage service is available (either on the
site or the surrounding area); most types of temporary buildings were not an
option. He states given the needs, they located a Newmar Northern Star Luxury
Coach RV featuring substantial water and sewer capacity. He states the RV
enables them to stay on site with visits to an area park or travel center with water
and sewage servicing every three or four weeks.
2
FILE NO.: Z -7665-A (Cont.
The applicant states they anticipate utilizing the temporary facility in two
locations. The applicant has indicated location 131 will be utilized for four to
seven months, and then an additional four to seven months in location B2 while
completing initial development and construction of their new home in the
neighborhood.
A portion of the site is located outside the City limits but within the City's
Extraterritorial Planning Jurisdiction. The applicant has indicated there is not a
Bill of Assurance in effect for the property, which would prohibit the use of the
site as proposed.
B. EXISTING CONDITIONS:
The site is vacant and clearing of underbrush was previously completed. There
are residential uses located to the east of the site both site built and
manufactured homes. To the south of the site is a vacant C-1 zoned property.
To the west of the site is vacant R-2, Single-family zoned property.
Kirby Road is a narrow unimproved road with open ditches for drainage. Only a
portion of the site lies within the City limits. Annexation will be required prior to
development.
C. NEIGHBORHOOD COMMENTS:
As of this writing, Staff has received one phone call from an area resident. The
Parkway Place Property Owners Association, Spring Valley Manor Neighborhood
Association, all property owners within 200 feet of the site and all residents, who
could be identified, within 300 feet of the site were notified of the Public Hearing.
D. ENGINEERING COMMENTS:
1. No comments on temporary use of site for RV hook-up. All previous
comments on the PRD apply.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Outside service boundary. If annexed into the City of Little Rock,
no pump station will be allowed. A sewer main extension will be required, with
easements. Contact Little Rock Wastewater Utility at 688-1414 for additional
information.
Entergy: A 10 -foot under ground utility easement is required or a 30 -foot
overhead facility easement is required. Contact Entergy at 954-5158 for
additional information.
Center -Point Energy: Approved as submitted.
SBC: No comment received.
K
FILE NO.: Z -7665-A Cont.)
Central Arkansas Water: All Central Arkansas Water requirements in effect at
the time of request for water service must be met. A water main extension will be
required in order to provide service to this property. Water service is not available
to this property without approval of the City of Little Rock. The Little Rock Fire
Department will need to approve the fire hydrant locations and vehicular access
to all parcels. A Capital Investment Charge based on the size of connection(s)
will apply to this project in addition to normal charges. This development will have
minor impact on the existing water distribution system. Proposed water facilities
will be sized to provide adequate pressure and fire protection. Contact Central
Arkansas Water at 377-1225 for additional information.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department at 918-3700 for additional information.
County Planning: No comment.
CATA: The site is not located near a dedicated CATA Bus Route.
F. ISSUES/TECHNICAL/DESIGN:
Planning_ Division: This request is located in the Ellis Mountain Planning District.
The Land Use Plan shows Single Family for this property. The applicant has
applied for a revision to a PRD (Planned Residential Development) to allow a
recreational vehicle to be placed on the lot at two different locations during
development, for security and to house a sales office. Since the addition of the
security and office use is only temporary, the request does not require a change
to the Land Use Plan.
Master Street Plan: Kirby Road is shown as a Collector on the Master Street and
may require dedication of right-of-way and street improvements.
Bicycle Plan: A Class III bikeway is shown on Kirby Road adjacent to the
property. A Class III Bikeway is a signed route on a street shared with traffic.
No additional paving or right-of-way is required. Class III bicycle route signage
may be required.
City Recognized Neighborhood Action Plan: The applicants property lies in the
area covered by the Rock Creek Neighborhood Action Plan. The change in this
zoning case is relatively small and scale and no objectives directly relate to this
case.
Landscape: No comment.
G. SUBDIVISION COMMITTEE COMMENT:
(February 10, 2005)
The applicant was present representing the request. Staff noted the proposal
was approved by the Commission in July 2004, for the development of a single -
4
FILE NO.: Z -7665-A Cont.
family subdivision. Staff stated the applicant was now requesting the placement
of a RV on the site to serve as his residence, a sales office and a security office.
Staff stated the site plan included two locations for the proposed RV to be
located, one for the short term and the second when the subdivision began
developing.
Staff questioned the applicant concerning the previously approved development
and when the applicant anticipated the development beginning construction. The
applicant stated the annexation request had been approved by the County and
would soon be filed with the City. The applicant stated the engineering firm was
90 percent complete with the plans for development and anticipated construction
would begin within 90 to 120 days of completion of the plans. The applicant
stated sewer was the primary obstacle. He stated the estimated cost of
extending the sewer line to serve the site was $100,000.00. He stated the
engineer was working with the sewer department for alternatives.
Staff noted comments from the various other reporting departments and
agencies indicating the applicant should contact them individually for further
clarification. There was no further discussion of the item. The Committee then
forwarded the item to the full Commission for final action.
H. ANALYSIS:
The applicant is requesting to place an RV on the site to act as a sales/security
office and residence while the proposed Rock Haven Subdivision is being
constructed. The applicant has indicated two locations for the proposed parking
of the RV unit. The applicant has indicated the RV unit will be located near the
southern property line until actual construction of the subdivision begins and then
moved to the northern boundary. The applicant has indicated his home will be
the first to begin construction and once drives are placed to begin the
development, the RV unit will be relocated nearer the applicants new home.
Per the zoning ordinance, temporary buildings are allowable when incidental to
construction on a site or development of a residential subdivision. The units
allowed are temporary buildings, mobile homes or manufactured homes and may
be allowed for a period of one year by action of the Director of Planning. There is
not a provision in the ordinance for the placement of an RV to serve the same
purpose.
Staff is supportive of the applicants request to place the RV unit on the site to
serve as a sales/security office but would recommend the RV unit not be allowed
until construction of the subdivision begins. There are several issues that need
to be resolved prior to beginning construction of the proposed subdivision.
Wastewater is one issue that needs resolving. The applicant must apply for and
be annexed into the corporate limits of the City to received sewer service. The
applicant has indicated the annexation has been approved by the County but has
not yet been filed with the City. The earliest possible Board of Directors approval
date would be May 17, 2005. In addition, sewer lines must be extended to the
5
FILE NO.: Z -7665-A (Cont.
site prior to the start of construction on the new homes. Staff feels a more
defined construction schedule should be established and construction should be
imminent prior to the RV unit being allowed on the site so the use can be as
intended in the ordinance or a sales, security office.
STAFF RECOMMENDATION:
Staff recommends denial of the request as filed.
PLANNING COMMISSION ACTION: (MARCH 3, 2005)
Mr. Roy Stephens was present representing the request. There was one registered
objector present. Staff presented the item with a recommendation of denial of the
current request. Staff stated they were supportive of the applicant being able to place
the RV unit on the site to serve as a security/sales office but staff felt a more definite
construction schedule should be established.
Mr. Stephens addressed the Commission on the merits of his request. He stated the
County had approved the annexation request and the engineer was 90 percent
complete with construction plans. He stated he felt construction would begin in 60 to
90 days.
Ms. Lenice Garrison addressed the Commission with concerns. She stated her
concerns were with a more definite construction schedule. She stated the
neighborhood was not necessarily opposed to the placement of the RV on the site to be
used as a sales/security office but the question was how long would the RV unit be
located on the site.
There was a general discussion concerning the applicanfs request and staffs concerns.
Staff stated the earliest the annexation request could be before the Board of Directors
was late May. Staff stated their concern was there were no firm dates tied to a
proposed development schedule. There was a general discussion concerning the
proposed development and if the construction could begin on the portion of the site
within the City limits. Staff stated the current approvals would not allow them to begin
construction prior to annexation.
The Commission made a motion to approved the applicants request provided the
applicant request annexation by the March 21, 2005, filing deadline to be heard by the
Commission at their April 28, 2005, public hearing. The Commission also requested the
current zoning application be held until after the annexation request was heard by the
Commission to allow both item to be forwarded to the Board of Directors at the same
time. The motion carried by a vote of 10 ayes, 0 noes and 1 absent.
C
March 3, 2005
ITEM NO.: 17 FILE NO.: Z -7665-A
NAME: Rock Haven Revised Short -form PD -R
LOCATION: Located at 1000 Kirby Road
DEVELOPER:
Rock Haven Properties
700 East 9th Street 10M
Little Rock, AR 72202
ENGINEER:
Development Consultants, Inc.
2200 North Rodney Parham Road, Suite 220
Little Rock, AR 72212
AREA: 4.158 acres
CURRENT ZONING:
ALLOWED USES:
PROPOSED ZONING:
NUMBER OF LOTS: 22
-M -
Single-family residential
Revised PD -R
FT. NEW STREET: 1590 LF
PROPOSED USE: Single-family residential — the allowance of an RV to locate on the
site to serve as a security/sales office for the proposed development.
VARIANCESMAIVERS REQUESTED: None requested.
BACKGROUND:
The Little Rock Planning Commission reviewed this request at their July 15, 2004,
Public Hearing and forwarded a recommendation of approval to the Board of Directors.
Ordinance No. 19,164 adopted by the Little Rock Board of Directors on August 17,
2004, established the Rock Haven Short -form PD -R. The proposed development was
designed based on a concept blended between a zero lot line subdivision and a
horizontal property regime. The lots were to be minimally sized to accommodate
buiidable -s ell500� 2450 - -Ir' curt Nurnes� — -
March 3, 2005
SUBDIVISION
ITEM NO.: 17 (Cont.
FILE NO.: Z -
proposed with a two-story height maximum. The bill of assurance was indicated to
prescribe minimum and maximum home sizes, as well as controls for architectural
quality that would be administered by an architectural review committee. Each
buildable area was set within one foot of one lot line, and fourteen to fifteen feet from
the other to allow for a small side yard area. All homes would have enclosed garages
located at the rear of the structure and entered from the looped drive. Homes would
front on the interior common park area. The proposed access to lots was accomplished
with a private drive that encircled the property and was within a common access and
utility easement area. This easement was proposed as a part of the large Lot 1 area,
which comprised all of the land not contained within the residential lots. All
improvements and land within Lot 1 would be held in common ownership by the
property owners association and would also be maintained by the property owners
association. The property owners association would also maintain individual lot area
landscaping.
The applicant indicated Tract A as a separate parcel containing 1.91 acres. The
applicant indicated Tract A would be reserved for future development. The applicant
requested a deferral of required street improvements to Kirby Road until development
occurred for proposed Tract A.
The applicant indicated phasing would be utilized for the development. Phase I was to
consist of the development of Lots 1 -11 including all required street improvements and
infrastructure. Phase II would consist of the completion of the access easement located
within Lot 1 and Lots 12 - 22.
A. PROPOSAUREQUEST:
The applicant is now requesting an amendment to the previously approved PRD
for the new subdivision to allow the use of an RV as a temporary sales,
construction management and security office on the construction site. The
applicant's cover letter states soon after purchasing the land, there were multiple
cases of trash and limb debris dumping on the land, along with thefts on the site
and an adjacent residence. The applicant states they explored various security
solutions and ultimately determined to locate temporarily on the site. The
applicant states this would allow them to monitor and manage the construction
progress most effectively. The applicant states the sooner they complete their
objective - unique, quaint neighborhood and park - the better for the area. The
applicant also states they foresee the need to conduct sales of lots in the
temporary office. The applicant states interest in the future neighborhood has
already proven to be great. He states the feedback they have received on all the
plans and the temporary office has been positive.
The applicant's cover letter states no sewage service is available (either on the
site or the surrounding area); most types of temporary buildings were not an
-—optio""tatL--�iver-i- the-need.��ey.=Iocated a--Newmar-Nodbe-r-n star_ -Luxury
2
March 3, 2005
SUBDIVISION
ITEM NO.: 17 (Cont.
E NO.: Z -7665-A
Coach RV featuring substantial water and sewer capacity. He states the RV
enables them to stay on site with visits to an area park or travel center with water
and sewage servicing every three or four weeks.
The applicant states they anticipate utilizing the temporary facility in two
locations. The applicant has indicated location B1 will be utilized for four to
seven months, and then an additional four to seven months in location B2 while
completing initial development and construction of their new home in the
neighborhood.
A portion of the site is located outside the City limits but within the City's
Extraterritorial Planning Jurisdiction. The applicant has indicated there is not a
Bill of Assurance in effect for the property, which would prohibit the use of the
site as proposed.
B. EXISTING CONDITIONS:
The site is vacant and clearing of underbrush was previously completed. There
are residential uses located to the east of the site both site built and
manufactured homes. To the south of the site is a vacant C-1 zoned property.
To the west of the site is vacant R-2, Single-family zoned property.
Kirby Road is a narrow unimproved road with open ditches for drainage. Only a
portion of the site lies within the City limits. Annexation will be required prior to
development.
C. NEIGHBORHOOD COMMENTS:
As of this writing, Staff has received one phone call from an area resident. The
Parkway Place Property Owners Association, Spring Valley Manor Neighborhood
Association, all property owners within 200 feet of the site and all residents, who
could be identified, within 300 feet of the site were notified of the Public Hearing.
D. ENGINEERING COMMENTS:
1. No comments on temporary use of site for RV hook-up. All previous
comments on the PRD apply.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Outside service boundary. If annexed into the City of Little Rock,
no pump station will be allowed. A sewer main extension will be required, with
easements. Contact Little Rock Wastewater Utility at 688-1414 for additional
Jn armation.
3
March 3, 2005
SUBDIVISION
ITEM NO.: 17 Cont. FILE NO.: Z -7665-A
Entergy: A 10 -foot under ground utility easement is required or a 30 -foot
overhead facility easement is required. Contact Entergy at 954-5158 for
additional information.
Center -Point Energy: Approved as submitted.
SBC: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at
the time of request for water service must be met. A water main extension will be
required in order to provide service to this property. Water service is not available
to this property without approval of the City of Little Rock. The Little Rock Fire
Department will need to approve the fire hydrant locations and vehicular access
to all parcels. A Capital Investment Charge based on the size of connection(s)
will apply to this project in addition to normal charges. This development will have
minor impact on the existing water distribution system. Proposed water facilities
will be sized to provide adequate pressure and fire protection. Contact Central
Arkansas Water at 377-1225 for additional information.
Fire Department: Place fire hydrants per code. Contact the Little Rock Fire
Department at 918-3700 for additional information.
County Planning: No comment.
CATA: The site is not located near a dedicated CATA Bus Route.
F. ISSUES[TECHNICAL/DESIGN:
Planning Division: This request is located in the Ellis Mountain Planning District.
The Land Use Plan shows Single Family for this property. The applicant has
applied for a revision to a PRD (Planned Residential Development) to allow a
recreational vehicle to be placed on the lot at two different locations during
development, for security and to house a sales office. Since the addition of the
security and office use is only temporary, the request does not require a change
to the Land Use Plan.
Master Street Plan: Kirby Road is shown as a Collector on the Master Street and
may require dedication of right-of-way and street improvements.
Bicycle Plan: A Class III bikeway is shown on Kirby Road adjacent to the
property. A Class III Bikeway is a signed route on a street shared with traffic.
No additional paving or right-of-way is required. Class III bicycle route signage
may be required.
4
March 3, 2005
SUBDIVISION
ITEM NO.: 17 Cont.) FILE NO.: Z -7665-A
Cily Recognized Neighborhood Action Plan: The applicant's property lies in the
area covered by the Rock Creek Neighborhood Action Plan. The change in this
zoning case is relatively small and scale and no objectives directly relate to this
case.
Landscape: No comment.
G. SUBDIVISION COMMITTEE COMMENT: (February 10, 2005)
The applicant was present representing the request. Staff noted the proposal
was approved by the Commission in July 2004, for the development of a single-
family subdivision. Staff stated the applicant was now requesting the placement
of a RV on the site to serve as his residence, a sales office and a security office.
Staff stated the site plan included two locations for the proposed RV to be
located, one for the short term and the second when the subdivision began
developing.
Staff questioned the applicant concerning the previously approved development
and when the applicant anticipated the development beginning construction. The
applicant stated the annexation request had been approved by the County and
would soon be filed with the City. The applicant stated the engineering firm was
90 percent complete with the plans for development and anticipated construction
would begin within 90 to 120 days of completion of the plans. The applicant
stated sewer was the primary obstacle. He stated the estimated cost of
extending the sewer line to serve the site was $100,000.00. He stated the
engineer was working with the sewer department for alternatives.
Staff noted comments from the various other reporting departments and
agencies indicating the applicant should contact them individually for further
clarification. There was no further discussion of the item. The Committee then
forwarded the item to the full Commission for final action.
H. ANALYSIS:
The applicant is requesting to place an RV on the site to act as a sales/security
office and residence while the proposed Rock Haven Subdivision is being
constructed. The applicant has indicated two locations for the proposed parking
of the RV unit. The applicant has indicated the RV unit will be located near the
southern property line until actual construction of the subdivision begins and then
moved to the northern boundary: The applicant has indicated his home will be
the first to begin construction and once drives are placed to begin the
development, the RV unit will be relocated nearer the applicant's new home.
5
March 3, 2005
SUBDIVISION
ITEM NO.: 17
FILE NO.: Z -7665-A
Per the zoning ordinance, temporary buildings are allowable when incidental to
construction on a site or development of a residential subdivision. The units
allowed are temporary buildings, mobile homes or manufactured homes and may
be allowed for a period of one year by action of the Director of Planning. There is
not a provision in the ordinance for the placement of an RV to serve the same
purpose.
Staff is supportive of the applicant's request to place the RV unit on the site to
serve as a sales/security office but would recommend the RV unit not be allowed
until construction of the subdivision begins. There are several issues that need
to be resolved prior to beginning construction of the proposed subdivision.
Wastewater is one issue that needs resolving. The applicant must apply for and
be annexed into the corporate limits of the City to received sewer service. The
applicant has indicated the annexation has been approved by the County but has
not yet been filed with the City. The earliest possible Board of Directors approval
date would be May 17, 2005. In addition, sewer lines must be extended to the
site prior to the start of construction on the new homes. Staff feels a more
defined construction schedule should be established and construction should be
imminent prior to the RV unit being allowed on the site so the use can be as
intended in the ordinance or a sales, security office.
STAFF RECOMMENDATION:
Staff recommends denial of the request as filed.
PLANNING COMMISSION ACTION: (MARCH 3, 2005)
Mr. Roy Stephens was present representing the request. There was one registered
objector present. Staff presented the item with a recommendation of denial of the
current request. Staff stated they were supportive of the applicant being able to place
the RV unit on the site to serve as a security/sales office but staff felt a more definite
construction schedule should be established.
Mr. Stephens addressed the Commission on the merits of his request. He stated the
County had approved the annexation request and the engineer was 90 percent
complete with construction plans. He stated he felt construction would begin in 60 to
90 days.
Ms. Lenice Garrison addressed the Commission with concerns. She stated her
concerns were with a more definite construction schedule. She stated the
neighborhood was not necessarily opposed to the placement of the RV on the site to be
used as a sales/security office but the question was how long would the RV unit be
located on the site.
A
March 3, 2005
SUBDIVISION
ITEM NO.: 17 (Cont.) FILE NO.: Z -7665-A
There was a general discussion concerning the applicant's request and staff's concerns.
Staff stated the earliest the annexation request could be before the Board of Directors
was late May. Staff stated their concern was there were no firm dates tied to a
proposed development schedule. There was a general discussion concerning the
proposed development and if the construction could begin on the portion of the site
within the City limits. Staff stated the current approvals would not allow them to begin
construction prior to annexation.
The Commission made a motion to approved the applicant's request provided the
applicant request annexation by the March 21, 2005, filing deadline to be heard by the
Commission at their April 28, 2005, public hearing. The Commission also requested the
current zoning application be held until after the annexation request was heard by the
Commission to allow both item to be forwarded to the Board of Directors at the same
time. The motion carried by a vote of 10 ayes, 0 noes and 1 absent.
7