HomeMy WebLinkAboutZ-6532-E Staff AnalysisJanuary 14, 2010
ITEM NO.: B FILE NO.: Z -6532-E
NAME: The Enclave at Chenal Heights Long -form PD -R
LOCATION: Located on the Northeast corner of Chenal Heights Drive and Chenal
Valley Drive
DEVELOPER:
Boomer Consumer, LLC
P.O. Box 242146
Little Rock, AR 72223
F=f\IrIr,1FFR-
Thomas Engineering Company
3810 Lookout Road
North Little Rock, AR 72116
AREA: 14.12 acres
CURRENT ZONING:
ALLOWED USES:
PROPOSED ZONING
PROPOSED USE:
NUMBER OF LOTS: 68
-m
Retirement village
Revised PD -R
FT. NEW STREET: 2,060 LF
Attached and detached single-family
VARIANCES/WAIVERS REQUESTED: A variance from the City's Land Alteration
Ordinance to allow grading of the future lots with the placement of the basic
infrastructure within the proposed subdivision.
The applicant submitted a request dated August 20, 2009, requesting a deferral of this
item to the October 15, 2009, public hearing. Staff is supportive of the deferral request.
PLANNING COMMISSION ACTION:
(SEPTEMBER 3, 2009)
The applicant was present. There were no registered objectors present. Staff
presented the item stating the applicant had submitted a request dated August 20,
2009, requesting a deferral of the Item to the October 15, 2009, public hearing. Staff
stated they were supportive of the deferral request.
January 14, 2010
SUBDIVISION
ITEM NO.: B (Contj FILE NO.: Z -8532-E
There was no further discussion of the item. The chair entertained a motion for
approval of the item as presented by staff. The motion carried by a vote of 10 ayes,
0 noes and 1 absent.
STAFF UPDATE:
The applicant submitted a request dated September 30, 2009, requesting a deferral of
this item to the December 3, 2009, public hearing. The applicant has indicated the
additional time is necessary to resolve issues related to the Bill of Assurance. Staff is
supportive of the deferral request.
PLANNING COMMISSION ACTION: (OCTOBER 15, 2009)
The applicant was not present. There were no registered objectors present. Staff
presented the item stating the applicant had submitted a request dated September 30,
2009, requesting a deferral of the item to the December 3, 2009, public hearing. Staff
stated the applicant had indicated the additional time was necessary to resolve issues
related to the Bill of Assurance. Staff stated they were supportive of the deferral
request.
There was no further discussion of the item. The chair entertained a motion for
approval of the item as presented by staff. The motion carried by a vote of 8 ayes,
0 noes and 3 absent.
STAFF UPDATE:
The applicant submitted a request dated November 18, 2009, requesting this item be
deferred to the January 14, 2010, public hearing. The deferral request will require a
waiver of the Commission's By-laws with regard to the late deferral request. Staff is
supportive of the deferral request.
PLANNING COMMISSION ACTION: (DECEMBER 3, 2009)
The applicant was present. There were no registered objectors present. Staff
presented the item stating the applicant had submitted a request dated November 18,
2009, requesting a deferral of the item to the January 14, 2010, public hearing. Staff
stated the deferral request would require a waiver of the Commission's By-laws with
regard to the number of deferral request. Staff stated they were supportive of the
deferral request.
2
January 14, 2010
SUBDIVISION
ITEM NO.: B (Cont._) FILE NO.: Z -6532-E
There was no further discussion of the item. The chair entertained a motion for
approval of the By-law waiver to allow the additional deferral request. The motion
carried by a vote of 9 ayes, 0 noes, 0 absent and 2 open positions. The chair
entertained a motion for approval of the item as presented by staff. The motion carried
by a vote of 9 ayes, 0 noes, 0 absent and 2 open positions.
STAFF UPDATE:
The applicant has not been able to resolve the issue related to the Bill of Assurance for
this site. Staff recommends withdrawal of this item, without prejudice, to allow the
applicant time to resolve all outstanding issues associated with the request.
PLANNING COMMISSION ACTION: (JANUARY 14, 2010)
The applicant was not present. There were no registered objectors present. Staff
presented the item stating the applicant had not been able to resolve the issue related
to the Bill of Assurance for the site. Staff presented a recommendation of withdrawal of
the item, without prejudice, to allow the applicant time to resolve all outstanding issues
associated with the request.
There was no further discussion of the item. The chair entertained a motion of approval
of the item as presented by staff. The motion carried by a vote of 11 ayes, 0 noes and
0 absent.
Q
VAIMI SM
NAME: The Enclave at Chenal Heights Long -form PD -R
LOCATION: located on the Northeast corner of Chenal Heights Drive and Chenal
Valley Drive
Planning Staff Comments:
1. Provide notification of all property owners located within 200 -feet of the site,
complete with the certified abstract list, notice form with affidavit executed and proof
of mailing. The notice must be mailed no later than August 19, 2009. The Office of
Planning and Development must receive the proof of notice no later than August 28,
2009.
2. The site plan indicates the development is proposed as market driven but the
advanced grading request indicates grading of the entire site with the development
of Phase I. What infrastructure will be installed within the first phase? Provide the
proposed phasing plan for the lots.
3. Provide details of the proposed existing covenants and restrictions on the property.
4. Are accessory structures allowed, including outbuildings and swimming pools as a
part of the Bill of Assurance. If these are desired include a note on the proposed site
plan to allow accessory structures per the R-2, Single-family zoning district.
5. Provide the proposed square footagEs of the homes. Provide the proposed
construction materials. Provide the maximum building height and the number of
stories of the proposed structures.
6. Include the maximum buildable area for each lot on the site plan.
7. Provide the minimum square footage proposed for the single-family detached
homes.
8. Are interior fences proposed with the new construction or by the future
homeowners? Include a note on the site plan including the total height and
construction material to allow fencing to occur.
9. A minimum of ten to fifteen percent of the gross planned residential district area shall
be designated as common usable open space and single-family, duplex, zero -lot -line
and townhouse development shall have a minimum of five hundred square feet of
usable private open space per unit. Indicate the total common usable open space
and the total usable private open space provided within the development.
Variance/Waivers:
1. A variance from the Land Alteration Ordinance to allow grading of the entire site with
the development of Phase 1.
2. Section 31-207(a) — A variance to allow the development of lots utilizing private
streets.
Item # 9.
Public Works Conditions:
1. Private access is proposed for these lots. In accordance with Section 31-207,
private streets must be designed to the same standards as public streets. A
minimum access easement width of 45 feet is required and street width of 24 feet
from back of curb to back of curb.
2. With site development, provide the design of the street conforming to the Master
Street Plan. Construct street improvements to the streets within the subdivision with
the planned development. The final plat should show the streets and drainage
improvements to be private.
3. Stormwater detention ordinance applies to this property.
4. If disturbed area is one (1) or more acres, obtain a NPDES stormwater permit from
the Arkansas Department of Environmental Quality prior to the start of construction.
5. Street Improvement plans shall include signage and striping. Traffic Engineering
must approve completed plans prior to construction.
6. Streetlights are required per Little Rock Code of Ordinances. Contact Traffic
Engineering 379-1813 (Steve Philpott) for more information.
7. Obtain permits prior to doing any street cuts or curb cuts. Obtain barricade permit
prior to doing any work in the right-of-way. Contact Traffic Engineering at (501) 379-
1805 (Travis Herbner) for more information.
8. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-
of-way prior to occupancy.
9. No residential waste collection service will be provided on private streets unless the
property owners association provides a waiver of damage claims for operations on
private property. Garbage will be picked up on only one side of the 18 foot private
drive.
10. Turn around must be provided for a SU -30 vehicle attempting to enter development.
A stacking distance of 30 feet from pavement must also be provided.
11. Plans of all work in right-of-way shall be submitted for approval prior to start of work.
Obtain barricade permit prior to doing any work in the right-of-way from Traffic
Engineering at (501) 379-1805 (Travis Herbner).
12.A grading permit in accordance with Section 29-186 (c) and (d) will be required prior
to any land clearing or grading activities at the site. Other than residential
subdivisions, site grading and drainage plans must be submitted and approved prior
to the start of construction. The applicant requesting to advance grade the site with
construction of the streets and infrastructure. Provide reason for the variance
request.
13. Vegetation must be established on disturbed area within 21 days of completion of
harvest activities.
14. Per the Master Street Plan, parking is restricted to one side of the street on a 24 foot
wide street. Show on the plan now and on the final plat and bill of assurance, the
area along the street where parking is allowed.
15. The emergency access should be constructed of a hardened surface at least 18 feet
in width.
Utilities and Fire Department/County Planning:
Wastewater: Sewer main extension required with easements for this project. Contact
the Little Rock Wastewater Utility for additional information.
Item # 9.
Entergy: Ten feet of additional easements are required along Chenal Valley Drive and
Chenal Heights Drive.
Center -Point Ener : No comment received.
AT & T: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at the
time of request for water service must be met. Please submit plans for water facilities to
Central Arkansas Water for review. Plan revisions may be required after additional
review. Contact Central Arkansas Water regarding procedures for installation of water
facilities. Approval of plans by the Arkansas Department of Health Engineering Division
and the Little Rock Fire Department is required. This development will have minor
impact on existing water distribution systems. Proposed water facilities will be sized to
provide adequate pressure and fire protection. If there are facilities that need to be
adjusted and/or relocated, contact Central Arkansas Water. That work would be done
at the expense of the developer.
Fire Department: Place fire hydrants per code. A minimum gate opening of 20 -feet is
required for the gated entry.
County Planning: No comment.
CATA: The site is not located on a dedicated CATA Bus Route.
Planning Division: This request is located in the Chenal Planning District. The Land
Use Plan shows Residential Low Density for this property. The applicant has applied
for a Planned Development Residential.
The request does not require a change to the Land Use Plan.
Master Street Plan: Chenal Valley Drive is a Collector. The primary function of a
Collector Street is to provide a connection from Local Streets to Arterials. Chenal
Heights Drive is a Local Street. The primary function of a Local Street is to provide
access to adjacent properties. Local Streets which are abutted by non-residential
zoning/use or more intensive zoning than duplexes are considered as "Commercial
Streets". These streets have a design standard the same as a Collector. These streets
may require dedication of right-of-way and may require street improvements for
entrances and exits to the site.
Bicycle Plan: A Class II bikeway is shown along Chenal Valley Drive. A Class II
bikeway is located on the street as either a five foot (6) shoulder or six foot (6') marked
bike lane. Additional paving and right of way may be required.
Neiahborhood Action Plan: This area is not covered by a Neighborhood Action Plan.
Landscape: No comment.
Item # 9.
Revised Platlpla .- Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, August 19, 2009.
Item # 9.