HomeMy WebLinkAboutZ-6318-C Staff AnalysisFILE NO.: Z -6318-C
NAME: Dairy Land Revised Long -form PCD
LOCATION: Located on the Southwest corner of Chenal Parkway and Kanis Road
DEVELOPER:
Whisenhunt Investments
c/o Kemp Whisenhunt
35 Windsor Court
Little Rock, AR 72212
ENGINEER:
Development Consultants Inc.
2200 North Rodney Parham Road
Suite 220
Little Rock, AR 72212
AREA: 25.3 acres
CURRENT ZONING
ALLOWED USES
PROPOSED ZONING
PROPOSED USE
NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF
PCD
Mixed Use Development including C-3, General
Commercial District uses
Revised PCD
C-2, Shopping Center District uses
VARIANCES/WAIVERS REQUESTED: None requested.
BACKGROUND:
On August 19, 1997, the Little Rock Board of Directors adopted Ordinance No. 17,556
establishing Dairyland Long -form PCD. The property was approved for a mixed-use
development containing three Phases. Phase I was to include a 76,560 square foot
Kroger Store, 9,000 square feet of retail/restaurant, 646 parking spaces and Lease
Parcel 1. Phase II was to contain 35,000 square feet of retail and Phase III was to
contain 90,000 square feet of retail, 306 parking spaces and Lease Parcels 2 and 3.
FILE NO.: Z -6318-C (Cont.
Phase I was to begin development upon approval and Phases II and III were to begin
construction within a three year time period. No specific proposal was submitted for
approval for the three Lease Parcels. The applicant indicated approval would be
obtained at the time of development.
Ordinance No. 18,868 adopted by the Little Rock Board of Directors on November 17,
1988, revised the previously approved site plan for Dairyland Long -form PCD. The
revision included moving the approved phase line to include Lease Parcel 2 and add
12 parking spaces. The revision also included the construction of the drive along the
south side of Lease Parcel 2. The applicant submitted a site plan for Lease Parcel 2 for
approval. The site plan included the construction of a 4,200 square foot bank building
with 29 parking spaces. Phase I has been constructed. No construction has begun on
Phases II and III.
Ordinance No. 19,332 adopted by the Little Rock Board of Directors on May 17, 2005,
revised the previously approved PCD to allow twelve of the existing parking spaces to
be used as seasonal outdoor display. From March to September the approval allowed
Kroger to display lawn furniture, bar-b-que grills and miscellaneous outdoor equipment
in their parking lot. The displayed items would be barricaded to prevent customers from
parking in the display area and creating traffic conflicts.
A. PROPOSAL/REQUEST/APPLICANT'S STATEMENT:
This site has a history of PCD approvals under the name of Dairyland Shopping
Center. At this time, the developers are requesting approval of a plan revision to
allow a new 119,240 square foot Kroger store that will fill out the western end of
the shopping center area. The existing Kroger store (64,753 square feet) will be
adapted for a new user, or multiple users, after the new store is completed and
occupied. An addition to the eastern building containing 10,150 square feet is
also proposed. The proposed shopping center building area will be
approximately 194,143 square feet (7.52%) less than the main building area
approved in previous plans. A fuel service canopy has been added at the east
side of the western Chenal entry drive; and, Kroger requests the continued right
to have a limited amount of seasonal outdoor display in shopping center parking
areas.
The other significant change to the plan is at the eastern side at Kanis Road.
The drive access has been rearranged to move the primary entry further south
and away from the Chenal/Kanis intersection. This drive will now serve as
customer access and truck service.
With the newly proposed Kroger building and other plan changes, the applicant
has proposed to eliminate the requirement of any significant office uses. The
request includes a revision to the approved uses to be those listed for C-2,
Shopping Center District uses. A request to amend the City's Future Land Use
Plan from Mixed Office Commercial to Community Shopping is a separate item
on the agenda (LU08-18-01).
2
FILE NO.: Z -6318-C (Cont.
I3
C.
FBI
The improvements shown for Kirk Road and Chenal Parkway are as shown in
the design drawings for the road and intersection improvements. Whisenhunt
Investments is implementing these improvements as required under their
approvals for the neighboring property across Kirk Road.
These improvements also include the completion of the Chenal median and
conversion of the western entry for right turn only ingress and egress, as required
in the original site plan. There will be some minor right-of-way dedications
required from this site. All other boundary street rights-of-way and street
improvements have been dedicated and completed from the original
development.
EXISTING CONDITIO
The site is developed with a Kroger Store and a bank facility. The out parcels
have not developed and remain cleared and vacant. There is a traffic signal
located at the intersection with Chenal Parkway and Kanis Road. Adjacent to the
site, Chenal Parkway is a four lane roadway. Kanis Road has been constructed
to Master Street Plan standard adjacent to the development.
There is undeveloped conceptual PCD located to the west of the site on a former
golf driving range. A convenience store, automobile dealership and church are
among the uses across Chenal Parkway to the north. A building supply store is
located across Kanis Road to the east and there is an abandoned plant nursery
located to the southeast along Kanis Road.
NEIGHBORHOOD COMMENTS:
As of this writing, staff has not received any comment from area property owners.
All property owners located within 200 feet of the site, all residents, who could be
identified, located within 300 feet of the site along with the Parkway Place
Property Owners Association were notified of the Public Hearing.
ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. With site development, provide the design of street conforming to the
Master Street Plan. Construct street improvements to Chenal Parkway and
Kirk Road including 5 -foot sidewalks with the planned development. These
improvements are being completed with the Shackleford 150 project.
2. Repair or replace any curb and gutter or sidewalk that is damaged in the
public right-of-way prior to occupancy.
3. A grading permit in accordance with Section 29-186 (c) and (d) will be
required prior to any land clearing or grading activities at the site. Other
than residential subdivisions, site grading and drainage plans must be
submitted and approved prior to the start of construction.
3
FILE NO.: Z -6318-C (Cont.
4. Storm water detention ordinance applies to this property
5. A Special Grading Permit for Flood Hazard Areas will be required per
Section 8-283 prior to construction.
6. The minimum Finish Floor elevation of at least one (1) foot above the base
flood elevation is required to be shown on plat and grading plans.
7. In accordance with Section 31-176, floodway areas must be shown as
floodway easements or be dedicated to the public. In addition, a 25 -foot
wide access easement is required adjacent to the floodway boundary.
8. Plans of all work in right-of-way shall be submitted for approval prior to start
of work. Obtain barricade permit prior to doing any work in the right-of-way
from Traffic Engineering at (501) 379-1805 (Travis Herbner).
9. Driveway locations and widths do not meet the traffic access and circulation
requirements of Sections 30-43 and 31-210. Driveway spacing from an
intersection on a minor arterial street is at least 300 feet. The north
driveway on Kanis Road is to close to the intersection. With the south
driveway on Kanis Road becoming the main entrance into the development,
the northern driveway should be closed. Contact Bill Henry, Traffic
Engineering with any questions or for additional information.
10. If disturbed area is one (1) or more acres, obtain a NPDES storm water
permit from the Arkansas Department of Environmental Quality prior to the
start of construction.
11. The intersection on the southeast corner of Lot 1 should be designed as a
4 -way stop intersection.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available to this property
Entergy: No comment received.
Center -Point Ener : No comment received.
AT & T: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at
the time of request for water service must be met. Please submit plans for water
facilities and/or fire protection system to Central Arkansas Water for review. Plan
revisions may be required after additional review. Contact Central Arkansas
Water regarding procedures for installation of water facilities and/or fire service.
Approval of plans by the Arkansas Department of Health Engineering Division
and Little Rock Fire Department is required. Fire sprinkler systems which do not
contain additives such as antifreeze shall be isolated with a double detector
check valve assembly. If additives are used, a reduced pressure zone backflow
preventer shall be required. A Capital Investment Charge based on the size of
10
FILE NO:: Z -6318-C
connection(s) will apply to this project in addition to normal charges. This fee will
apply to all connections including metered connections off the private fire system.
The facilities on-site will be private. When meters are planned off private lines,
private facilities shall be installed to Central Arkansas Water's material and
construction specifications and installation will be inspected by an engineer,
licensed to practice in the State of Arkansas. Execution of Customer Owned Line
Agreement is required. This development will have minor impact on the existing
water distribution system. Proposed water facilities will be sized to provide
adequate pressure and fire protection.
Fire Department: Install and place fire hydrants per code. Contact the Little
Rock Fire Department for additional information.
County Planning: No comment.
CATA: The site is not located on a dedicated CATA Bus Route.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division: This request is located in the Ellis Mountain Planning District.
The Land Use Plan shows Mixed Office Commercial for this property. The
applicant has applied for a Revised Long Form Planned Commercial
Development for a development that includes C-2, Shopping Center District uses
as allowable uses.
A Land Use Plan amendment for a change from Mixed Office Commercial to
Community Shopping is a separate item on this agenda (LU08-18-01).
Master Street Plan: Chenal Parkway is a Principal Arterial. The primary function
of a Principal Arterial is to serve through traffic and to connect major traffic
generators or activity centers within urbanized areas. Entrances and exits should
be limited to minimize negative effects of traffic and pedestrians on Chenal since
it is a Principal Arterial. Kanis Road is shown as a Minor Arterial. A Minor
Arterial provides connections to and through an urban area and their primary
function is to provide short distance travel within the urbanized area. Entrances
and exits should be limited to minimize negative effects of traffic and pedestrians
on Kanis since it is a Minor Arterial. Kirk Road is shown as a proposed Collector
along the western property line of this development. The primary function of a
Collector Street is to provide a connection from Local Streets to Arterials. These
streets may require dedication of right-of-way and may require street
improvements for entrances and exits to the site.
Bicycle Plan: A Class I route is shown
bikeway is built separate from or alongside
way may be required.
5
along Chenal Parkway. A Class I
a road. Additional paving and right of
FILE NO.: Z -6318-C (Cont.
Neighborhood Action Plan: This area is not covered by a Neighborhood Action
Plan.
Landscape:
1. The site plan must comply with the City's landscape ordinance
requirements.
2. The zoning buffer ordinance requires an average fifty -foot wide (50') street
buffer along Kirk Road and in no case less than half.
3. The existing on site Bradford Pear trees appear to be in distress. All
existing vegetation shall be in good condition and replaced if missing, dead,
or diseased.
4. All fencing, dumpster enclosures, striping, and handicap signs also must be
in good repair or replaced.
5. The zoning buffer ordinance requires a minimum fifty -foot wide (50') land
use buffer along the southern property line. Seventy percent (70%) of
which is to be left undisturbed. Easements cannot count towards meeting
this minimal requirement.
6. A six (6) foot high opaque screen, either a wooden fence with its face side
directed outward, a wall, or dense evergreen plantings, is required along the
southern perimeter of the site. Credit towards fulfilling this requirement can
be given for existing trees and undergrowth that satisfies this year -around
requirement.
7. A small amount of building landscaping is required between the new
building and the parking lot.
8. This sites combined parking numbers exceed one hundred and fifty spaces.
Interior islands are to be a minimum of three hundred square feet (300) in
area to receive credit towards the landscape ordinance requirements.
9. An automatic irrigation system to water landscaped areas will be required.
10. Prior to the issuance of a building permit, it will be necessary to provide an
approved landscape plan stamped with the seal of a Registered Landscape
Architect.
11. The City Beautiful Commission recommends preserving as many existing
trees as feasible on tree covered sites. Credit toward fulfilling Landscape
Ordinance requirements can be given when preserving trees of six (6) inch
caliper or larger.
G. SUBDIVISION COMMITTEE COMMENT: (July 17, 2008)
Mr. Robert Brown was present representing the request. Staff presented an
overview of the development stating there were additional items necessary to
complete the review process. Staff stated the location of the proposed outdoor
and seasonal activities should be noted on the plan. Staff also questioned the
n
FILE NO.: Z -6318-C (Cont.
proposed signage plan on the gas canopy. Staff stated a minimum of ten to
fifteen percent of the site should be denoted to landscaping. Mr. Brown stated he
felt the site would meet or exceed the minimum requirement.
Public Works comments were addressed. Staff questioned the timing of street
improvements on Chenal Parkway and Kirk Road. Mr. Brown stated the
improvements would have to be in place prior to the Kroger opening. Staff
questioned the base flood elevation. Mr. Brown stated the minimum base flood
elevation would be placed on the plan. He stated the floor would be raised above
the 100 -year flood elevation as required by City ordinances. Staff stated the
northern most eastern drive should be removed. Mr. Brown stated he would
work with traffic engineering to resolve their concerns. He stated the drive was
desired as a right in right out drive to allow access to the two proposed lease
parcels.
Landscaping comments were addressed. Staff stated all fencing and dumpster
screening was to be in good repair. Staff also stated any dead, diseased or
missing landscaping was to be replaced. Staff stated building landscaping was
required or a variance from the City Beautiful Commission was to be approved
prior to the issuance of a building permit. Mr. Brown noted the land use buffer to
the south would not serve a purpose since the southern perimeter was a 100 -foot
plus floodway. He stated the developers would seek a variation from this typical
ordinance standard.
Staff noted comments from the various other reporting departments and
agencies. There was no further discussion of the item. The Committee then
forwarded the item to the full Commission for final action.
H. ANALYSIS:
Mr. Brown submitted a revised site plan to staff on July 23, 2008, addressing the
issues raised at the July 17, 2008, Subdivision Committee meeting. The revised
plan indicates locations for outdoor storage, the signage plan and the percentage
of the site denoted for landscaping and open space. The revised plan also
indicates the land use buffer along the southern perimeter will not remain
undisturbed as typically required by the ordinance. The revised plan includes the
base flood elevation and the finished floor height of the new building.
The fuel center will have outdoor display/sales and vending. The fuel center will
also house an air and water dispensary service along the eastern portion of the
fuel center site. Seasonal outdoor display will be located in the front of the
Kroger building and a small area within the parking lot.
The development signage is proposed as was previously approved. Signage for
the fuel center is proposed on the canopy of the fuel center on all four sides. The
signage will occupy less than ten percent of the facade area in which the sign is
located.
7
FILE NO.: Z -6318-C (Cont.
The site plan indicates buffers per the typical ordinance standards with the
exception of two locations. An area located along Kirk Road does not meet the
50 -foot minimum street buffer average. The buffer is indicated nearer a 30 -foot
average. The buffer proposed is similar to the previously approved site plan.
The second variation is the rear yard land use buffer. According to the applicant
grading will take place in this area not allowing the area to remain undisturbed.
The site plan indicates an existing floodway to the south of the site ranging from
350 to 400 feet.
The proposal will allow the creation of four lots, Tract 1 and 2 along with Lots 1
and 2. Tract 1 will contain 5.8 acres. Within the tract two lease parcels are
proposed. Tract 2 will contain 17.66 acres. Development plans for Tract 2
include the construction of a new 119,365 square foot Kroger store. Upon
completion of the new store the existing Kroger store will be leased to a single or
multiple users. The proposed uses for the 64,753 square foot retail space are
those listed in the C-2, Shopping Center District uses. In addition a new
10,150 square foot retail space is proposed along the eastern portion of the
existing Kroger store. The uses proposed for this area is also C-2, Shopping
Center District uses.
Street improvements for Kirk Road and Chenal Parkway will be completed prior
to the new Kroger store opening. The improvements include the completion of
the Chenal median and conversion of the western entry for right turn only ingress
and egress, as required in the original site plan. The northern drive located on
Kanis Road has been eliminated as recommended in the Public Works
comments. The site plan indicates the placement of walkways within the parking
lot area to facilitate foot traffic from the lease parcels and Chenal Parkway to the
retail uses.
The total land area of the site is 23.467 acres. The new Kroger store is proposed
with a total building area of 194,266 square feet or 19 percent. The total
landscape area is 200,301 square feet or 19.6 percent and the total paved area
is 61.4 percent of the total site area. Interior landscaping and planting areas is
proposed at 8.21 percent. A total of 2,442 square feet of building landscaping is
proposed. The new retail shop area is proposed with 14.19 percent of interior
planting area and 689 building landscaping.
The site plan indicates a total of 897 parking spaces. Based on parking
standards for a shopping center development 863 parking spaces would typically
be required.
Dumpster locations have been identified. The dumpster facilities are located in
the rear of the structures. All dumpster facilities will be screen per the typical
ordinance requirements or on three sides a minimum of two feet above the
finished height of the container.
EQ
FILE NO.: Z -6318-C (Cont.
Building signage is proposed as typically allowed per the ordinance for
commercial developments or a maximum of ten percent of the facade area.
Ground mounted signage is as was approved in the original PCD. Each of the
lots and lease parcels is allowed a single ground mounted sign. The signage
varies in size based on the parcel size. Two of the signs located along Chenal
Parkway exceed the typical Design Overlay District standard of eight feet in
height and 100 square feet in area. The signs are proposed ten feet in height
and 140 square feet in area.
Staff is supportive of the site plan as proposed. Staff is supportive of the street
buffer along Kirk Road and the land use buffer along the southern perimeter less
than the typical ordinance standards. Staff feels the revision to allow the
placement of an 119,365 square foot Kroger store and the addition of a fuel
center within the parking lot area will significantly impact the development. A
land use plan amendment to change the site to Community Shopping is a
separate item on this agenda. Staff feels this is an appropriate location for a
shopping center development.
I. STAFF RECOMMENDATIONS:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
Staff recommends approval of the variances to allow the reduced street buffer
and the reduced land use buffer as proposed.
PLANNING COMMISSION ACTION:
(AUGUST 7, 2008)
The applicant was present. There were no registered objectors present. Staff stated
the applicant had agreed to conduct a traffic study of the increase in traffic volumes
generated from the proposed development and submit the study to Public Works for
review and approval. Staff stated based on the results of that traffic study, street
improvements would be made to the southern portion of the Kirk Road and Chenal
Parkway intersection sufficient to safely handle the proposed traffic resulting from the
proposed development and any future uses as approved by Public Works. Staff stated
a certificate of occupancy would not be issued for the proposed development until the
street improvements were installed and inspected by staff.
Staff presented the item with a recommendation of approval of the request subject to
compliance with the comments and conditions as outlined in paragraphs D, E and F of
the agenda staff report. Staff also presented a recommendation of approval of the
variances to allow the reduced street buffer and the reduced land use buffer as
proposed.
There was no further discussion of the item. The Chair entertained a motion for
placement of the item on the Consent Agenda for Approval as recommended by staff.
The motion carried by a vote of 9 ayes, 0 noes and 2 absent.
August 7, 2008
ITEM NO.: 8.1 FILE NO.: Z -6318-C
NAME: Dairy Land Revised Long -form PCD
LOCATION: Located on the Southwest corner of Chenal Parkway and Kanis Road
DEVELOPER:
Whisenhunt Investments
c/o Kemp Whisenhunt
35 Windsor Court
Little Rock, AR 72212
ENGINEER:
Development Consultants Inc.
2200 North Rodney Parham Road
Suite 220
Little Rock, AR 72212
AREA: 25.3 acres
CURRENT ZONING
ALLOWED USES:
PROPOSED ZONING
NUMBER OF LOTS: 1
PCD
FT. NEW STREET: 0 LF
Mixed Use Development including C-3, General
Commercial District uses
Revised PCD
PROPOSED USE: C-2, Shopping Center District uses
VARIANCESMAIVERS REQUESTED: None requested.
BACKGROUND:
On August 19, 1997, the Little Rock Board of Directors adopted Ordinance No. 17,556
establishing Dairyland Long -form PCD. The property was approved for a mixed-use
development containing three Phases. Phase I was to include a 76,560 square foot
Kroger Store, 9,000 square feet of retail/restaurant, 646 parking spaces and Lease
Parcel 1. Phase II was to contain 35,000 square feet of retail and Phase III was to
contain 90,000 square feet of retail, 306 parking spaces and Lease Parcels 2 and 3.
Phase I was to begin development upon approval and Phases II and III were to begin
construction within a three year time period. No specific proposal was submitted for
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1
FILE NO.: Z -6318-C
approval for the three Lease Parcels. The applicant indicated approval would be
obtained at the time of development.
Ordinance No. 18,868 adopted by the Little Rock Board of Directors on November 17,
1988, revised the previously approved site plan for Dairyland Long -form PCD. The
revision included moving the approved phase line to include Lease Parcel 2 and add 12
parking spaces. The revision also included the construction of the drive along the south
side of Lease Parcel 2. The applicant submitted a site plan for Lease Parcel 2 for
approval. The site plan included the construction of a 4,200 square foot bank building
with 29 parking spaces. Phase I has been constructed. No construction has begun on
Phases II and III.
Ordinance No. 19,332 adopted by the Little Rock Board of Directors on May 17, 2005,
revised the previously approved PCD to allow twelve of the existing parking spaces to
be used as seasonal outdoor display. From March to September the approval allowed
Kroger to display lawn furniture, bar-b-que grills and miscellaneous outdoor equipment
in their parking lot. The displayed items would be barricaded to prevent customers from
parking in the display area and creating traffic conflicts.
A. PROPOSAL/REQUEST/APPLICANT'S STATEMENT:
This site has a history of PCD approvals under the name of Dairyland Shopping
Center. At this time, the developers are requesting approval of a plan revision to
allow a new 119,240 square foot Kroger store that will fill out the western end of
the shopping center area. The existing Kroger store (64,753 square feet) wili be
adapted for a new user, or multiple users, after the new store is completed and
occupied. An addition to the eastern building containing 10,150 square feet is
also proposed. The proposed shopping center building area will be
approximately 194,143 square feet (7.52%) less than the main building area
approved in previous plans. A fuel service canopy has been added at the east
side of the western Chenal entry drive; and, Kroger requests the continued right
to have a limited amount of seasonal outdoor display in shopping center parking
areas.
The other significant change to the plan is at the eastern side at Kanis Road.
The drive access has been rearranged to move the primary entry further south
and away from the Chenal/Kanis intersection. This drive will now serve as
customer access and truck service.
With the newly proposed Kroger building and other plan changes, the applicant
has proposed to eliminate the requirement of any significant office uses. The
request includes a revision to the approved uses to be those listed for C-2,
Shopping Center District uses. A request to amend the City's Future Land Use
Plan from Mixed Office Commercial to Community Shopping is a separate item
on the agenda (LU08-18-01).
2
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1 (Cont.
FILE NO.: Z -6318-C
The improvements shown for Kirk Road and Chenal Parkway are as shown in
the design drawings for the road and intersection improvements. Whisenhunt
Investments is implementing these improvements as required under their
approvals for the neighboring property across Kirk Road.
These improvements also include the completion of the Chenal median and
conversion of the western entry for right turn only ingress and egress, as required
in the original site plan. There will be some minor right-of-way dedications
required from this site. All other boundary street rights-of-way and street
improvements have been dedicated and completed from the original
development.
B. EXISTING CONDITIONS:
The site is developed with a Kroger Store and a bank facility. The out parcels
have not developed and remain cleared and vacant. There is a traffic signal
located at the intersection with Chenal Parkway and Kanis Road. Adjacent to the
site, Chenal Parkway is a four lane roadway. Kanis Road has been constructed
to Master Street Plan standard adjacent to the development.
There is undeveloped conceptual PCD located to the west of the site on a former
golf driving range. A convenience store, automobile dealership and church are
among the uses across Chenal Parkway to the north. A building supply store is
located across Kanis Road to the east and there is an abandoned plant nursery
located to the southeast along Kanis Road.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has not received any comment from area property owners.
All property owners located within 200 feet of the site, all residents, who could be
identified, located within 300 feet of the site along with the Parkway Place
Property Owners Association were notified of the Public Hearing.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
With site development, provide the design of street conforming to the
Master Street Plan. Construct street improvements to Chenal Parkway and
Kirk Road including 5 -foot sidewalks with the planned development. These
improvements are being completed with the Shackleford 150 project.
2. Repair or replace any curb and gutter or sidewalk that is damaged in the
public right-of-way prior to occupancy.
3
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1 (Cont.
E
FILE NO.: Z -6318-C
3. A grading permit in accordance with Section 29-186 (c) and (d) will be
required prior to any land clearing or grading activities at the site. Other
than residential subdivisions, site grading and drainage plans must be
submitted and approved prior to the start of construction.
4. Storm water detention ordinance applies to this property
5. A Special Grading Permit for Flood Hazard Areas will be required per
Section 8-283 prior to construction.
6. The minimum Finish Floor elevation of at least one (1) foot above the base
flood elevation is required to be shown on plat and grading plans.
7. In accordance with Section 31-176, floodway areas must be shown as
floodway easements or be dedicated to the public. In addition, a 25 -foot
wide access easement is required adjacent to the floodway boundary.
8. Plans of all work in right-of-way shall be submitted for approval prior to start
of work. Obtain barricade permit prior to doing any work in the right-of-way
from Traffic Engineering at (501) 379-1805 (Travis Herbner).
9. Driveway locations and widths do not meet the traffic access and circulation
requirements of Sections 30-43 and 31-210. Driveway spacing from an
intersection on a minor arterial street is at least 300 feet. The north
driveway on Kanis Road is to close to the intersection. With the south
driveway on Kanis Road- becoming the main entrance into the development,
the northern driveway should be closed. Contact Bill Henry, Traffic
Engineering with any questions or for additional information.
10. If disturbed area is one (1) or more acres, obtain a NPDES storm water
permit from the Arkansas Department of Environmental Quality prior to the
start of construction.
11. The intersection on the southeast corner of Lot 1 should be designed as a
4 -way stop intersection.
UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available to this property.
Entergy: No comment received.
Center -Point Encrciv: No comment received.
AT & T: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at
the time of request for water service must be met. Please submit plans for water
10
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1 (Cont.
FILE NO.: Z -6318-C
facilities and/or fire protection system to Central Arkansas Water for review. Plan
revisions may be required after additional review. Contact Central Arkansas
Water regarding procedures for installation of water facilities and/or fire service.
Approval of plans by the Arkansas Department of Health Engineering Division
and Little Rock Fire Department is required. Fire sprinkler systems which do not
contain additives such as antifreeze shall be isolated with a double detector
check valve assembly. If additives are used, a reduced pressure zone backflow
preventer shall be required. A Capital Investment Charge based on the size of
connection(s) will apply to this project in addition to normal charges. This fee will
apply to all connections including metered connections off the private fire system.
The facilities on-site will be private. When meters are planned off private lines,
private facilities shall be installed to Central Arkansas Water's material and
construction specifications and installation will be inspected by an engineer,
licensed to practice in the State of Arkansas. Execution of Customer Owned Line
Agreement is required. This development will have minor impact on the existing
water distribution system. Proposed water facilities will be sized to provide
adequate pressure and fire protection.
Fire Department: Install and place fire hydrants per code. Contact the Little
Rock Fire Department for additional information.
Countv Plannina: No comment.
CATA: The site is not located on a dedicated CATA Bus Route.
F. ISSUES/TECHNICAL/DESIGN.,
Planning Division: This request is located in the Ellis Mountain Planning District.
The Land Use Plan shows Mixed Office Commercial for this property. The
applicant has applied for a Revised Long Form Planned Commercial
Development for a development that includes C-2, Shopping Center District uses
as allowable uses.
A Land Use Plan amendment for a change from Mixed Office Commercial to
Community Shopping is a separate item on this agenda (LU08-18-01).
Master Street Plan: Chenal Parkway is a Principal Arterial. The primary function
of a Principal Arterial is to serve through traffic and to connect major traffic
generators or activity centers within urbanized areas. Entrances and exits should
be limited to minimize negative effects of traffic and pedestrians on Chenal since
it is a Principal Arterial. Kanis Road is shown as a Minor Arterial. A Minor
Arterial provides connections to and through an urban area and their primary
function is to provide short distance travel within the urbanized area. Entrances
and exits should be limited to minimize negative effects of traffic and pedestrians
5
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1 (Cont.
FILE NO.: Z -6318-C
on Kanis since it is a Minor Arterial. Kirk Road is shown as a proposed Collector
along the western property line of this development. The primary function of a
Collector Street is to provide a connection from Local Streets to Arterials. These
streets may require dedication of right-of-way and may require street
improvements for entrances and exits to the site.
Bicvcle Plan: A Class I route is shown along Chenal Parkway. A Class I
bikeway is built separate from or alongside a road. Additional paving and right of
way may be required.
Neighborhood Action Plan: This area is not covered by a Neighborhood Action
Plan.
Landscape:
1. The site plan must comply with the City's landscape ordinance
requirements.
2. The zoning buffer ordinance requires an average fifty -foot wide (50) street
buffer along Kirk Road and in no case less than half.
3. The existing on site Bradford Pear trees appear to be in distress. All
existing vegetation shall be in good condition and replaced if missing, dead,
or diseased.
4. All fencing, dumpster enclosures, striping, and handicap signs also must be
in good repair or replaced.
5. The zoning buffer ordinance requires a minimum fifty -foot wide (50') land
use buffer along the southern property line. Seventy percent (70%) of
which is to be left undisturbed. Easements cannot count towards meeting
this minimal requirement.
6. A six (6) foot high opaque screen, either a wooden fence with its face side
directed outward, a wall, or dense evergreen plantings, is required along the
southern perimeter of the site. Credit towards fulfilling this requirement can
be given for existing trees and undergrowth that satisfies this year -around
requirement.
7. A small amount of building landscaping is required between the new
building and the parking lot.
8. This sites combined parking numbers exceed one hundred and fifty spaces.
Interior islands are to be a minimum of three hundred square feet (300) in
area to receive credit towards the landscape ordinance requirements.
9. An automatic irrigation system to water landscaped areas will be required.
[el
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1
FILE NO.: Z -6318-C
10. Prior to the issuance of a building permit, it will be necessary to provide an
approved landscape plan stamped with the seal of a Registered Landscape
Architect.
11. The City Beautiful Commission recommends preserving as many existing
trees as feasible on tree covered sites. Credit toward fulfilling Landscape
Ordinance requirements can be given when preserving trees of six (6) inch
caliper or larger.
G. SUBDIVISION COMMITTEE COMMENT: (July 17, 2008)
Mr. Robert Brown was present representing the request. Staff presented an
overview of the development stating there were additional items necessary to
complete the review process. Staff stated the location of the proposed outdoor
and seasonal activities should be noted on the plan. Staff also questioned the
proposed signage plan on the gas canopy. Staff stated a minimum of ten to
fifteen percent of the site should be denoted to landscaping. Mr. Brown stated he
felt the site would meet or exceed the minimum requirement.
Public Works comments were addressed. Staff questioned the timing of street
improvements on Chenal Parkway and Kirk Road. Mr. Brown stated the
improvements would have to be in place prior to the Kroger opening. Staff
questioned the base flood elevation. Mr. Brown stated the minimum base flood
elevation would be placed on the plan. He stated the floor would be raised above
the 100 -year flood elevation as required by City ordinances. Staff stated the
northern most eastern drive should be removed. Mr. Brown stated he would
work with traffic engineering to resolve their concerns. He stated the drive was
desired as a right in right out drive to allow access to the two proposed lease
parcels.
Landscaping comments were addressed. Staff stated all fencing and dumpster
screening was to be in good repair. Staff also stated any dead, diseased or
missing landscaping was to be replaced. Staff stated building landscaping was
required or a variance from the City Beautiful Commission was to be approved
prior to the issuance of a building permit. Mr. Brown noted the land use buffer to
the south would not serve a purpose since the southern perimeter was a 100 -foot
plus floodway. He stated the developers would seek a variation from this typical
ordinance standard.
Staff noted comments from the various other reporting departments and
agencies. There was no further discussion of the item. The Committee then
forwarded the item to the full Commission for final action.
7
August 7, 2008
SUBDIVISION
[TEM NO.: 8. 1 Cont. FILE NO.: Z -6318-C
H. ANALYSIS:
Mr. Brown submitted a revised site plan to staff on July 23, 2008, addressing the
issues raised at the July 17, 2008, Subdivision Committee meeting. The revised
plan indicates locations for outdoor storage, the signage plan and the percentage
of the site denoted for landscaping and open space. The revised plan also
indicates the land use buffer along the southern perimeter will not remain
undisturbed as typically required by the ordinance. The revised plan includes the
base flood elevation and the finished floor height of the new building.
The fuel center will have outdoor display/sales and vending. The fuel center will
also house an air and water dispensary service along the eastern portion of the
fuel center site. Seasonal outdoor display will be located in the front of the
Kroger building and a small area within the parking lot.
The development signage is proposed as was previously approved. Signage for
the fuel center is proposed on the canopy of the fuel center on all four sides. The
signage will occupy less than ten percent of the facade area in which the sign is
located.
The site plan indicates buffers per the typical ordinance standards with the
exception of two locations. An area located along Kirk Road does not meet the
50 -foot minimum street buffer average. The buffer is indicated nearer a 30 -foot
average. The buffer proposed is similar to the previously approved site plan.
The second variation is the rear yard land use buffer. According to the applicant
grading will take place in this area not allowing the area to remain undisturbed.
The site plan indicates an existing floodway to the south of the site ranging from
350 to 400 feet.
The proposal will allow the creation of four lots, Tract 1 and 2 along with Lots 1
and 2. Tract 1 will contain 5.8 acres. Within the tract two lease parcels are
proposed. Tract 2 will contain 17.66 acres. Development plans for Tract 2
include the construction of a new 119,365 square foot Kroger store. Upon
completion of the new store the existing Kroger store will be leased to a single or
multiple users. The proposed uses for the 64,753 square foot retail space are
those listed in the C-2, Shopping Center District uses. In addition a new
10,150 square foot retail space is proposed along the eastern portion of the
existing Kroger store. The uses proposed for this area is also C-2, Shopping
Center District uses.
Street improvements for Kirk Road and Chenal Parkway will be completed prior
to the new Kroger store opening. The improvements include the completion of
the Chenal median and conversion of the western entry for right turn only ingress
A
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1 (Cont.
FILE NO.: Z -6318-C
and egress, as required in the original site plan. The northern drive located on
Kanis Road has been eliminated as recommended in the Public Works
comments. The site plan indicates the placement of walkways within the parking
lot area to facilitate foot traffic from the lease parcels and Chenal Parkway to the
retail uses.
The total land area of the site is 23.467 acres. The new Kroger store is proposed
with a total building area of 194,266 square feet or 19 percent. The total
landscape area is 200,301 square feet or 19.6 percent and the total paved area
is 61.4 percent of the total site area. Interior landscaping and planting areas is
proposed at 8.21 percent. A total of 2,442 square feet of building landscaping is
proposed. The new retail shop area is proposed with 14.19 percent of interior
planting area and 689 building landscaping.
The site plan indicates a total of 897 parking spaces. Based on parking
standards for a shopping center development 863 parking spaces would typically
be required.
Dumpster locations have been identified. The dumpster facilities are located in
the rear of the structures. All dumpster facilities will be screen per the typical
ordinance requirements or on three sides a minimum of two feet above the
finished height of the container.
Building signage is proposed as typically allowed per the ordinance for
commercial developments or a maximum of ten percent of the fagade area.
Ground mounted signage is as was approved in the original PCD. Each of the
lots and lease parcels is allowed a single ground mounted sign. The signage
varies in size based on the parcel size. Two of the signs located along Chenal
Parkway exceed the typical Design Overlay District standard of eight feet in
height and 100 square feet in area. The signs are proposed ten feet in height
and 140 square feet in area.
Staff is supportive of the site plan as proposed. Staff is supportive of the street
buffer along Kirk Road and the land use buffer along the southern perimeter less
than the typical ordinance standards. Staff feels the revision to allow the
placement of an 119,365 square foot Kroger store and the addition of a fuel
center within the parking lot area will significantly impact the development. A
land use plan amendment to change the site to Community Shopping is a
separate item on this agenda. Staff feels this is an appropriate location for a
shopping center development.
9
August 7, 2008
SUBDIVISION
ITEM NO.: 8. 1 (Cont.
STAFF RECOMMENDATIONS:
FILE NO.: Z -6318-C
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
Staff recommends approval of the variances to allow the reduced street buffer
and the reduced land use buffer as proposed.
PLANNING COMMISSION ACTION: (AUGUST 7, 2008)
The applicant was present. There were no registered objectors present. Staff stated
the applicant had agreed to conduct a traffic study of the increase in traffic volumes
generated from the proposed development and submit the study to Public Works for
review and approval. Staff stated based on the results of that traffic study, street
improvements would be made to the southern portion of the Kirk Road and Chenal
Parkway intersection sufficient to safely handle the proposed traffic resulting from the
proposed development and any future uses as approved by Public Works. Staff stated
a certificate of occupancy would not be issued for the proposed development until the
street improvements were installed and inspected by staff.
Staff presented the item with a recommendation of approval of the request subject to
compliance with the comments and conditions as outlined in paragraphs D, E and F of
the agenda staff report. Staff also presented a recommendation of approval of the
variances to allow the reduced street buffer and the reduced land use buffer as
proposed.
There was no further discussion of the item. The Chair entertained a motion for
placement of the item on the Consent Agenda for Approval as recommended by staff.
The motion carried by a vote of 9 ayes, 0 noes and 2 absent.
10
ITEM NO.: 8.1.
NAME: Dairy Land Revised Long -form PCD
Z -6318-C
LOCATION: located on the Southwest corner of Chenal Parkway and Kanis Road
Planning Staff Comments_
1. Provide notification of property owners located within 200 feet of the site, complete
with the certified abstract list, notice form with affidavit executed and proof of
mailing. The notices must be mailed no later than July 23, 2008. The Office of
Planning and Development must receive the proof of notice no later than August 1,
2008.
2. A minimum of 10 to 15 percent of the site is to be designated to landscape. Provide
the percentage provide.
3. Provide the percentage of building coverage, the percentage of landscaping and the
percentage of paved area.
4. Will the fuel center contain outdoor display of products such as oil, wiper blades, etc
and/or vending machines, ice machines'? If so include a note in the site plan stating
so.
5. Provide details of any other proposed outdoor activities including lawn furniture,
landscaping materials.
6. Provide the location of the proposed air and water service for the fuel center.
7. Provide the location of fuel center signage including the total height and area of the
proposed signage. Will signage be located on the south and western facades of the
fuel canopy? Is any additional ground mounted signage proposed with the new
construction.
8. Provide details of any proposed fencing to be located on the site including the
location, total height and construction material.
9. All site lighting must be low level and directional, directed downward and into the site
not over -spilling on to the adjacent residentially zoned property.
10. Will cross access and parking agreements be offered to adjoining proposed and
platted lots? If so indicate the location of the proposed access easements and
location of cross parking.
Variance/Waivers:
Public Works Conditions:
1. What is the timing of the improvements on Chenal Parkway and Kirk Road in relation
to construction of the proposed Kroger?
2. With site development, provide the design of street conforming to the Master Street
Plan. Construct street improvements to Chenal Parkway and Kirk Road including 5 -
foot sidewalks with the planned development. These improvements are being
completed with the Shackleford 150 project.
Item # 8.1.
3. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-
of-way prior to occupancy.
4. A grading permit in accordance with Section 29-186 (c) and (d) will be required prior
to any land clearing or grading activities at the site. Other than residential
subdivisions, site grading and drainage plans must be submitted and approved prior
to the start of construction.
5. Storm water detention ordinance applies to this property
6. A Special Grading Permit for Flood Hazard Areas will be required per Section 8-283
prior to construction.
7. The minimum Finish Floor elevation of at least one (1) foot above the base flood
elevation is required to be shown on plat and grading plans.
8. In accordance with Section 31-176, floodway areas must be shown as floodway
easements or be dedicated to the public. In addition, a 25 foot wide access
easement is required adjacent to the floodway boundary.
9. Plans of all work in right-of-way shall be submitted for approval prior to start of work.
Obtain barricade permit prior to doing any work in the right-of-way from Traffic
Engineering at (501) 379-1805 (Travis Herbner).
10. Driveway locations and widths do not meet the traffic access and circulation
requirements of Sections 30-43 and 31-210. Driveway spacing from an intersection
on a minor arterial street is at least 300 feet. The north driveway on Kanis Road is
to close to the intersection. With the south driveway on Kanis Road becoming the
main entrance into the development, the northern driveway should be closed.
Contact Bill Henry, Traffic Engineering with any questions or for additional
information.
11. If disturbed area is one (1) or more acres, obtain a NPDES storm water permit from
the Arkansas Department of Environmental Quality prior to the start of construction.
12. The intersection on the southeast corner of Lot 1 should be designed as a 4 way
stop intersection.
Utilities and Fire Department/County Planning:
Wastewater: Sewer available to this property.
Enter : No comment received.
Center -Point Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water: All Central Arkansas Water requirements in effect at the
time of request for water service must be met. Please submit plans for water facilities
and/or fire protection system to Central Arkansas Water for review. Plan revisions may
be required after additional review. Contact Central Arkansas Water regarding
procedures for installation of water facilities and/or fire service. Approval of plans by the
Arkansas Department of Health Engineering Division and Little Rock Fire Department is
required. Fire sprinkler systems which do not contain additives such as antifreeze shall
be isolated with a double detector check valve assembly. If additives are used, a
reduced pressure zone backflow preventer shall be required. A Capital Investment
Charge based on the size of connection(s) will apply to this project in addition to normal
Item # 8.1.
charges. This fee will apply to all connections including metered connections off the
private fire system. The facilities on-site will be private. When meters are planned off
private lines, private facilities shall be installed to Central Arkansas Water's material and
construction specifications and installation will be inspected by an engineer, licensed to
practice in the State of Arkansas. Execution of Customer Owned Line Agreement is
required. This development will have minor impact on the existing water distribution
system. Proposed water facilities will be sized to provide adequate pressure and fire
protection.
Fire Department: Install and place fire hydrants per code. Contact the Little Rock
Fire Department for additional information.
County Planning: No comment.
CATA: The site is not located on a dedicated CATA Bus Route.
Planning Division: This request is located in the Ellis Mountain Planning District. The
Land Use Plan shows Mixed Office Commercial for this property. The applicant has
applied for a Revised Long Form Planned Commercial Development for a development
that includes both office and commercial uses.
The request does not require a change to the Land Use Plan.
Master Street Plan: Chenal Parkway is a Principal Arterial. The primary function of a
Principal Arterial is to serve through traffic and to connect major traffic generators or
activity centers within urbanized areas. Entrances and exits should be limited to
minimize negative effects of traffic and pedestrians on Chenal since it is a Principal
Arterial. Kanis Road is shown as a Minor Arterial. A Minor Arterial provides
connections to and through an urban area and their primary function is to provide short
distance travel within the urbanized area. Entrances and exits should be limited to
minimize negative effects of traffic and pedestrians on Kanis since it is a Minor Arterial.
Kirk Road is shown as a proposed Collector along the western property line of this
development. The primary function of a Collector Street is to provide a connection from
Local Streets to Arterials. These streets may require dedication of right-of-way and may
require street improvements for entrances and exits to the site.
Bicycle Plan: A Class I route is shown along Chenal Parkway. A Class I bikeway is
built separate from or alongside a road. Additional paving and right of way may be
required.
Neighborhood Action Plan: This area is not covered by a Neighborhood Action Plan
Landscape:
1. The site plan must comply with the City's landscape and buffer ordinance
requirements.
2. The zoning buffer ordinance requires an average fifty foot wide (50') street buffer
along Kirk Road and in no case less than half. Currently, this minimal amount is not
being met.
Item # 8.1.
3. The existing on site Bradford Pear trees appear to be in distress; therefore, consider
replacing these existing trees with this application. All existing vegetation will need
to be in good condition, replaced if missing, dead, or diseased.
4. All fencing, dumpster enclosures, striping, and handicap signs also must be in good
repair or replaced.
5. The zoning buffer ordinance requires a minimum fifty foot wide (50') land use buffer
along the southern property line. Seventy percent (70%) of which is to be left
undisturbed. Currently, it is unclear whether or not this site is meeting this minimal
requirement due to the easements which cannot count towards meeting this minimal
requirement.
6. A six (6) foot high opaque screen, either a wooden fence with its face side directed
outward, a wall, or dense evergreen plantings, is required along the southern
perimeter of the site. Credit towards fulfilling this requirement can be given for
existing trees and undergrowth that satisfies this year -around requirement.
7. A small amount of building landscaping is required to be located between the new
building and the parking lot.
8. This sites combined parking numbers exceed one hundred and fifty spaces;
therefore, the interior islands need to be a minimum of three hundred square feet
(300) in area to receive credit towards the landscape ordinance requirements. Also,
there will need to be additional interior islands on the site to meet the evenly
distributed section of the ordinance.
9. An automatic irrigation system to water landscaped areas will be required.
10. Prior to the issuance of a building permit, it will be necessary to provide an approved
landscape plan stamped with the seal of a Registered Landscape Architect.
11. The City Beautiful Commission recommends preserving as many existing trees as
feasible on tree covered sites. Credit toward fulfilling Landscape Ordinance
requirements can be given when preserving trees of six (6) inch caliper or larger.
Revised plat/plan.- Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, July 23, 2008.
Item # 8.1.