HomeMy WebLinkAboutZ-6277 Staff AnalysisMay 15, 1997
SUBDIVISION
ITEM NO.: A Cont. FILE NO.: Z-6277
C. NEIGHBORHOOD COMMENTS:
The Garland School Neighborhood Association was noticed ------
about this site plan review. To date staff has received no
comments from the public about this case.
D. PUBLIC WORKS CONDITIONS:
1. Grading permit will be required for new development, if
it disturbs more than one acre.
2. Provide information concerning driveways proposed and
parking proposed.
3. A dedication of right-of-way will be required to 35 feet
from centerline for this 4 lane minor arterial.
4. Stormwater detention ordinance applies to this property.
5. Sidewalks shall be shown conforming to Sec. 31-175 and
.the "MSP".
6. Proposed design of streets conforming to "MSP" (Master
Street Plan).
7. Plans of all work in right-of-way shall be submitted for
approval prior to start of work.
E. UTILITIES AND FIRE DEPARTMENT:
Wastewater: Sewer main located on property.
AP&L: No response.
Arkla: No response.
Southwestern Bell: No response.
Water: On-site fire protection is needed.
Fire Department: Gates need to be a minimum of 15 feet.
CATA: Not transmitted.
F. ISSUES/TECHNICAL_/DESIGN:
Landscape: No additional required.
Issues:
• Single sign at frontage for auto sales not to exceed 4
feet by 8 feet.
• Building sign on auto sales office not to exceed 2 feet
by 2 feet.
• Move auto sales office to conform to 15 feet side yard
setback.
Planning Division: N/A
2
May 15, 1997
SUBDIVISION
ITEM NO.: A (Cont.) FILE NO.: Z -
G. ANALYSIS•
The zoning on the parcel is I-2 Light Industrial District.----
The existing buildings do not conform to the minimum side
yard setbacks. However, these are nonconforming structures.
The portable auto sales office is to be placed to conform
with the I-2 district standards. This proposal conforms to
the Site Plan Review criteria outlined in Sec. 31-13
subdivision/multiple building site plan review in the
Subdivision and Zoning Ordinance.
H. STAFF RECOMMENDATIONS:
APPROVAL based on the conditions listed is Sections D, E and
F of this staff report.
SUBDIVISION COMMITTEE COMMENT:
(MARCH 13, 1997)
Staff requested that the item be rescheduled for the Subdivision
Committee meeting of April 24, 1997. This will allow the
applicant to provide an exhibit drawn to scale.
The Committee deferred the item as requested by planning staff.
PLANNING COMMISSION ACTION:
(APRIL 3, 1997)
This item was included on the Consent Deferral agenda. The site
plan review is to be deferred to May 15, 1997 Planning Commission
meeting.
Motion to approve the Consent Agenda passed with 10 ayes, 0 nays
and 1 absent.
SUBDIVISION COMMITTEE COMMENT: (APRIL 24, 1997)
The applicant asked why he was being required to install
sidewalks since there are none in the area. There was no
representative of Public Work Department present. He was
referred to David Scherer at 371-4650.
The item was forwarded to the Planning Commission meeting of
May 15, 1997 for determination.
3
May 15, 1997
SUBDIVISION
ITEM NO.• A Cont. FILE NO.• Z-6277
PLANNING COMMISSION ACTION: (MAY 15, 1997)
The item was included in the Consent Approval agenda. Motion to
approve passed with 10 ayes, 0 nays and 1 absent.
4