HomeMy WebLinkAboutPC Minutes for Z-6323-BBMarch 9, 2023
ITEM NO.: 10 FILE NO.: Z-6323-BB
NAME: Lot 5, The Village at Rahling Road – Revised PCD
LOCATION: West side of Rahling Circle, 225 feet south of Rahling Road
DEVELOPER:
PotlatchDeltic Real Estate, LLC (Owner)
7 Chenal Club Boulevard
Little Rock, AR 72223
OWNER/AUTHORIZED AGENT:
Tim Daters (Agent)
White – Daters & Associates
24 Rahling Circle
Little Rock, AR 72223
SURVEYOR/ENGINEER:
Roark – Perkins – Perry - Yelvington
713 W Second Street
Little Rock, AR 72201
AREA: 3.31 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF
WARD: 5 PLANNING DISTRICT: 19 CENSUS TRACT: 42.16
CURRENT ZONING: PCD
VARIANCE/WAIVERS: None requested.
A. PROPOSAL/REQUEST/APPLICANT’S STATEMENT:
The applicant proposes to revise an existing approved PCD to develop a 3.31 acre
site to allow for the construction a one-story Micro Hospital that will contain nine
(9) emergency rooms and four (4) patient rooms. The hospital will operate
24 hours a day, seven days a week. The property is located on the West side of
Rahling Circle, 225 feet south of Rahling Road. The property is located in the
Chenal Overlay Design District.
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
2
B. EXISTING CONDITIONS:
The site is undeveloped and mostly wooded. The property represents a
continuation of development of an existing approved PCD. The overall site
contains a mixture of office and commercial uses in all directions.
C. NEIGHBORHOOD COMMENTS:
All owners of property located within 200 feet of the site and all neighborhood
associations registered with the City of Little Rock were notified of the public
hearing.
D. ENGINEERING COMMENTS:
1. Provide finished floor elevations (FFE) for all buildings on site plan and
grading and drainage plans.
2. A grading permit might be required prior to initiation of work. Grading permits
are issued by the Planning and Development Dept. at 723 West Markham
Street after approval of sediment and erosion control plans, grading and
drainage plans, land survey, drainage study, and soil loss calculations per
City’s stormwater management and drainage manual. Contact Planning and
Development Dept., Civil Engineering Private Development at 501-371-4817
or at 501-918-5348 or Permits@littlerock.gov to schedule an appointment for
issuance or to answer any questions. Permit cost is based on total project
area at $100.00 for the less than ½ acre, $200.00 for ½ to 1 acre, and $200.00
for the first acre and $100.00 for each additional acre for project greater than
1 acre.
3. Any work involving one (1) or more acres of disturbed area requires a
State of Arkansas NPDES permit. Contact the Arkansas Department of
Environmental Quality, NPDES branch at 501-682-0744 for applications and
information about General Stormwater Discharge Construction Permit
#ARR150000.
4. Damage to public and private property due to hauling operations or
operations of construction related equipment from a construction site shall be
repaired by the responsible party prior to the issuance of a certificate of
occupancy.
5. Provide as-built plans and data entry template of newly installed or modified
public and private stormwater drainage system prior to issuance of the
certificate of occupancy. The as-built plans should contain information as
found on the City of Little Rock website at https://www.littlerock.gov/city-
administration/city-departments/public-works/applications-details-and-
manuals/. Provide the as-built plans and data entry template to Planning and
Development Dept., Civil Engineering Private Development by email to
csmith@littlerock.gov and cc dwarner@littlerock.gov. If you have any
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
3
questions or desire additional information, please do not hesitate to contact
Planning and Development Dept., Civil Engineering Private Development at
501-371-4817 or at 501-918-5348 or email Permits@littlerock.gov.
6. A drainage study showing all hydrologic and hydraulic calculations for the
proposed storm sewer pipe system, detention ponds and structures, and
inlets is required. For final drainage report, sign, date, and seal the report per
AR State Board of Professional Engineers and Professional Surveyors rules
Article 12, Section B (1) (a). Provide engineer's certification statement saying
this drainage report was conducted by yourself or directly under your
supervision and attesting to the accuracy of the information within this report.
7. Per City Rev. Code 29-99, stormwater detention for developments is
required. Provide stormwater detention infrastructure to satisfy this
requirement. If this parcel is part of the Chenal Valley regional detention area,
provide evidence within submitted drainage report for Department
engineering staff’s review.
8. The Department requires three (3) phase sediment and erosion control (SEC)
plans to be submitted for all construction projects showing best management
practices (BMPs) for mitigating sediment runoff and erosion along with
vegetation specifications for temporary and permanent soil stabilization.
Phase 1 SEC plans shall show SEC BMPs during the stripping, clearing,
grubbing, and rough grading of the site. Phase 2 SEC plans shall show SEC
BMPs during construction of utilities, buildings, roadway infrastructure and
drainage infrastructure. Phase 3 SEC Plans shall show SEC BMPs for final
grading, seeding, and landscaping of the site.
9. Sediment and Erosion Control plans shall also show the pertinent information
as outlined in ADEQ ARR150000 Permit Part II section A-4-H (1-14) and Part
II section A-4-I-2 (A-B).
10. Pedestrian crossing signs per MUTCD are recommended for the midblock
pedestrian crossing located on the private driveway east of the project site.
11. If proposed retaining walls shown on plans are equal to or above four feet tall
measured from the bottom of the footing or leveling layer or if there is
surcharge loading for a retaining wall less than four feet tall measured from
the bottom of the footing or leveling layer, the Department requires retaining
wall design plans by an Arkansas licensed professional engineer showing
plan, profile, and cross sectional views of the wall with special details, design
loading calculations clearly showing all required factors of safety are met or
exceed per state building codes. A separate building permit-accessory
structure will be required for the retaining walls along with inspections by
Department engineering staff during their construction.
E. UTILITIES/FIRE DEPARTMENT/PARKS/COUNTY PLANNING:
Little Rock Water Reclamation Authority: No comments received.
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
4
Entergy: No comments received.
Summit Utilities: No comments.
AT & T: No comments received.
Central Arkansas Water:
1. All Central Arkansas Water requirements in effect at the time of request for
water service must be met.
2. The Little Rock Fire Department needs to evaluate this site to determine
whether additional public and/or private fire hydrant(s) will be required. If
additional fire hydrant(s) are required, they will be installed at the Developer's
expense.
3. Please submit plans for water facilities and/or fire protection system to Central
Arkansas Water for review. Plan revisions may be required after additional
review. Contact Central Arkansas Water regarding procedures for installation
of water facilities and/or fire service. Approval of plans by the Arkansas
Department of Health Engineering Division and Little Rock Fire Department
is required.
4. If there are facilities that need to be adjusted and/or relocated, contact Central
Arkansas Water. That work would be done at the expense of the developer.
5. The facilities on-site will be private. When meters are planned off private
lines, private facilities shall be installed to Central Arkansas Water's material
and construction specifications and installation will be inspected by an
engineer, licensed to practice in the State of Arkansas. Execution of
Customer Owned Line Agreement is required.
Fire Department:
Maintain Access:
Fire Hydrants.
Maintain fire apparatus access roads at fire hydrant locations as per Appendix D
of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D103.1 Access road
width with a hydrant. Where a fire hydrant is located on a fire apparatus access
road, the minimum road width shall be 26 feet, exclusive of shoulders.
Grade
Maintain fire apparatus access roads as per Appendix D of the 2012 Arkansas Fire
Prevention Code Vol. 1 Section D103.2 Grade. Fire apparatus access roads
shall not exceed 10 percent in grade except as approved by the fire chief. If
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
5
the grade exceeds 10 percent, approval will be denied and the applicant must
submit request to be reviewed by Fire Chief for Approval.
Loading
Maintain fire apparatus access road design as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D102.1 Access and loading.
Facilities, buildings or portions of buildings hereafter constructed shall be
accessible to fire department apparatus by way of an approved fire apparatus
access road with an asphalt, concrete or other approved driving surface capable
of supporting the imposed load of fire apparatus weighing at least 75,000 pounds.
Commercial and Industrial Developments – 2 means of access. - Maintain fire
apparatus access roads as per Appendix D of the 2012 Arkansas Fire Prevention
Code Vol. 1.
Section D104.1 Buildings exceeding three stories or 30 feet in height.
Building or facilities exceeding 30 feet or three stories in height shall have at least
two means of fire apparatus access for each structure.
Section D104.2 Building exceeding 62,000 square feet in area. Buildings or
facilities having a gross building area of more than 62,000 square feet shall be
provide with two separate and approved fire apparatus access roads.
Exception: Projects having a gross building area of up to 124,000 square
feet that have a single approved fire apparatus access road when all
building are equipped throughout with approved automatic sprinkler
systems.
D104.3 Remoteness. Where two fire apparatus access roads are required, they
shall be placed a distance apart equal to not less than one half of the length of the
maximum overall diagonal dimension of the lot or area to be served, measured in
a straight line between accesses.
30’ Tall Buildings - Maintain aerial fire apparatus access roads as per
Appendix D of the 2012 Arkansas Fire Prevention Code Vol. 1 Section D105.1
– D105.4
D105.1 Where Required. Where the vertical distance between the grade
plane and the highest roof surface exceed 30’, approved aerial fire apparatus
access roads shall be provided. For the purposes of this section the highest roof
surfaces shall be determined by measurement to the eave of a pitched roof, the
intersection of a roof to the exterior wall, or the top of the parapet walls, whichever
is greater.
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
6
D105.2 Width. Aerial fire apparatus access roads shall have a minimum
unobstructed with of 26’, exclusive of shoulders, in the immediate vicinity of the
building or portion thereof.
D105.3 Proximity to building. At least one of the required access routes
meeting this condition shall be located within a minimum of 15 feet and a maximum
of 30 feet from the building, and shall be positioned parallel to one entire side of
the building. The side of the building on which the aerial fire apparatus access
road is positioned shall be approved by the fire code official.
D105.4 Obstructions. Overhead utility and power lines shall not be located over
the aerial fire apparatus access road or between the aerial fire apparatus road and
the building. Other obstructions shall be permitted to be places with the approval.
Gates
Maintain fire apparatus access road gates as per Appendix D of the 2012
Arkansas Fire Prevention Code Vol. 1 Section D103.5 Fire apparatus access
road gates. Gates securing the fire apparatus access roads shall comply with
all of the following criteria:
1. Minimum gate width shall be 20 feet.
2. Gates shall be of swinging or sliding type.
3. Construction of gates shall be of material that allow manual operation by one
person.
4. Gate components shall be maintained in an operable condition at all times
and replaces or repaired when defective.
5. Electric gates shall be equipped with a means of opening the gate by fire
department personnel for emergency access. Emergency opening devices
shall be approved by the fire code official.
6. Manual opening gates shall not be locked with a padlock or chain and padlock
unless they are capable of being opened by means of forcible entry tools or
when a key box containing the keys to the lock is installed at the gate location.
7. Locking device specifications shall be submitted for approval by the fire code
official.
8. Electric gate operators, where provided, shall be listed in accordance with
UL 325.
9. Gates, intended for automatic operation shall be designed, constructed and
installed to comply with requirements of ASTM F 2200.
Fire Hydrants
Locate Fire Hydrants as per Appendix C of the 2012 Arkansas Fire
Prevention Code. Section C101 – C105, in conjunction with Central
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
7
Arkansas Water (Daniel Tull 501-377-1245) and the Little Rock Fire Marshal’s
Office (Capt. Tony Rhodes 501-918-3757, or Fire Marshal Derek N. Ingram
501-918-3756 Number and Distribution of Fire Hydrants as per Table C105.1.
Parks and Recreation: No comments received.
County Planning: No comments.
F. BUILDING CODES/LANDSCAPE:
Building Code: No comments received.
Landscape:
1. Any new site development must comply with the City’s minimal landscape
and buffer ordinance requirements. Refer to the Code of Ordinances, Chapter
15 - Landscape and Tree Protection.
2. Street buffers will be required at six (6) percent of the average depth of the
lot. The minimum dimension shall be one-half (½) the full width requirement
but in no case be less than nine (9) feet.
3. A perimeter planting strip is required along any side of a vehicular use area
that abuts adjoining property, or the right-of-way of any street. This strip shall
be at least nine (9) feet wide. One (1) tree and three (3) shrubs or vines shall
be planted for every thirty (30) linear feet of perimeter planting strip.
4. Building landscape areas shall be provided at the rate equivalent to planter
strip three (3) feet wide along the vehicular use area. One (1) tree and four
(4) shrubs shall be planted in the building landscape areas for each forty (40)
linear feet of vehicular use area abutting the building.
5. The interior landscape area of the vehicular use area shall, at a minimum,
equal eight percent (8%) of the vehicular use area and must be designated
for green space; this green space needs to be evenly distributed throughout
the parking area(s). The minimum size of an interior landscape area shall be
one hundred fifty (150) square feet for developments with one hundred fifty
(150) or fewer parking spaces. Interior islands must be a minimum seven and
one half (7 1/2) feet in width. Trees shall be included in the interior landscape
areas at the rate of one (1) tree for every twelve (12) parking spaces.
6. An automatic irrigation system to water landscaped areas shall be required
for developments of one (1) acre or larger.
7. The development of two (2) acres or more requires the landscape plan to be
stamped with the seal of a Registered Landscape Architect.
8. The City Beautiful Commission recommends preserving as many existing
trees as feasible on this site. Credit toward fulfilling Landscape Ordinance
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
8
requirements can be given when preserving trees of six (6) inch caliper or
larger.
9. A minimum of ten (10) percent of gross planned office district (POD) area
shall be designated as landscaped open space not to be used for streets or
parking.
G. TRANSPORTATION/PLANNING:
Rock Region Metro: No comments received.
Planning Division:
The request is in the Chenal Planning District. The Land Use Plan shows
Commercial (C) for the requested area. The Commercial category includes a
broad range of retail and wholesale sales of products, personal and professional
services, and general business activities. Commercial activities vary in type and
scale, depending on the trade area that they serve. The application is to rezone
from PCD (Planned Commercial Development) to PCD (Planned Commercial
Development). The request is to develop a hospital on the site.
Surrounding the application area, Future Land Use Map shows developed and
vacant Commercial (C). The commercial uses include banking, professional
offices, restaurants, and general retail uses. North and east of subject site are
areas shown as Office (O). The Office (O) category represents services provided
directly to consumers (e.g., legal, financial, medical) as well as general offices
which support more basic economic activities. The Office (O) area includes
banking, general offices as well as undeveloped land.
This site is within the Chenal Design Overlay District.
Master Street Plan:
Rahling Circle is a Local Street. A Local Street which abuts non-residential or
residential use which is more intense than duplex or two-unit residential is a
Commercial Street. These streets have the same design standard as a Collector.
Right-of-way is 60’. Sidewalks are required on both sides. Chenal Parkway is
shown on the Master Street Plan Map to be a Principal Arterial: Principal Arterials
are roads designed to serve through traffic and to connect major traffic generators
or activity centers within urbanized areas. Right of way of 110 feet is required.
Sidewalks are required on both sides. These streets may require dedication of
additional right-of-way and may require street improvements.
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
9
Bicycle Plan:
The Master Bike Plan Map shows proposed Class I Bike Path along Chenal
Parkway. Class I Bike Paths are routes designated for the sole use of bicycles
that is physically separated from vehicular lanes.
Historic Preservation Plan:
There are no Historic Sites or Districts in vicinity.
H. ANALYSIS:
The applicant proposes to revise an existing approved PCD to develop a 3.31 acre
site to allow for the construction a one-story Micro Hospital that will contain nine
(9) emergency rooms and four (4) patient rooms. The site is undeveloped and
mostly wooded. The property represents a continuation of development of an
existing approved PCD. The overall site contains a mixture of office and
commercial uses in all directions. The property is located in the Chenal Overlay
Design District.
All building setbacks comply with the City’s Zoning Code for structures in
commercial zones.
The proposed building will be 18,661 square foot in area and will operate 24 hours
a day, seven days a week. The building will not exceed thirty-five (35) feet in
height.
Access to the site will be from a concrete driveway which extends from Rahling
Circle. The site plan indicates an existing cross-access easement with the bank
facility to the west and a cross-access easement for the development to the east.
The applicant is proposing fifty (50) parking spaces of which twenty-four (24) will
be in the front of the building along Rahling Circle. The site plan indicates parking
spaces along the west and south sides of the building. Additional parking spaces
are provided further south behind the building along a retaining wall as required.
Staff feels the parking is sufficient to serve the proposed use.
The applicant notes a monument style sign to be located in the northwestern
portion of the property at the entrance to the site along Rahling Circle. Any signage
must conform to Section 36-349 of the City’s Zoning Ordinance.
The applicant notes all sight lighting will be low-level and directed away from
adjacent properties.
March 9, 2023
ITEM NO.: 10 (Cont.) FILE NO.: Z-6323-BB
10
A dumpster will be located on the west side if the building adjacent to the loading
zone. The dumpster shall comply with screening requirement as per Section
36-523(d) of the City’s Zoning Ordinance.
Staff is supportive of the requested revised PCD zoning. Staff views the request
as reasonable. To staff’s knowledge, there are no outstanding issues associated
with this application. Staff feels the development of the site is appropriate. The
proposed commercial use will be compatible with the surrounding developed
commercial and office uses in the area. The proposal represents a continuation
of development of a previously approved PCD. Staff feels the development will
not have an adverse impact on the surrounding area.
I. STAFF RECOMMEDATION:
Staff recommends approval of the requested PCD, subject to compliance with
the comments and conditions outlined in paragraphs D, E and F, and the staff
analysis, of the agenda staff report.
PLANNING COMMISSION ACTION: (MARCH 9, 2023)
The applicant was present. There were no persons registered in opposition. Staff
presented the item and a recommendation of approval as outlined in the “staff
recommendation” above. The item remained on the consent agenda for approval as
recommended by staff, including all staff comments and conditions. The vote was 9 ayes,
0 nays, 1 absent and 1 abstain (Brown).