HomeMy WebLinkAboutZ-6079-C Staff AnalysisMay 11, 2000
ITEM NO.: 21 FILE NO.: Z -6079-C
NAME: Walnut Valley Christian Academy - Revised
Conditional Use Permit
LOCATION: 19010 Highway Ten
OWNER/APPLICANT: Walnut Valley Christian Academy
PROPOSAL: To revise an existing conditional use
permit by changing the master plan,
rearranging the placement and phasing of
future buildings located at 19010 Highway
10 on property zoned R-2, Single Family
Residential.
ORDINANCE DESIGN STANDARDS:
1. SITE LOCATION:
This site is located on the north side of Highway 10,
0.4 miles east of the intersection of Highway 10 and
Chenal Parkway. It is just within an area that was
recently annexed into the City.
2. COMPATIBILITY WITH NEIGHBORHOOD:
This site contains 30 acres of R-2 zoned, single family
residential land, surrounded by large tracts of tree
covered R-2 zoned land on all sides including across
Highway 10 to the south.
There is a single family residence located immediately
to the east and one to the west.
With proper screening of this site from the adjacent
residential zoned properties, and compliance with the
Highway 10 Overlay District Ordinance, this proposed
use should have little adverse effect on the
surrounding properties.
The Aberdeen Court Neighborhood Association was
notified of the public hearing to consider this item.
3. ON SITE DRIVES AND PARKING:
The access consists of one main 4 -lane entrance with a
median. That would not change. The proposal includes
480 parking spaces versus a requirement for 195
May 11, 2000
SUBDIVISION
ITEM NO.: 21 (Cont.)
FILE NO.: Z -6079-C
spaces. This is a large site, so the parking would not
appear to cover all the green area.
4. SCREENING AND BUFFERS:
Areas set aside for buffers and landscaping meet with
ordinance requirements.
An irrigation system to water landscaped areas is a
requirement of the Highway 10 Overlay District.
A six foot high opaque screen, either a wooden fence
with its face side directed outward or dense evergreen
plantings, is required in areas where this property
abuts residential properties. Credit toward
fulfilling this requirement can be given when
preserving existing vegetation that provides the
required year-round screening.
5. PUBLIC WORKS COMMENTS:
a. Property frontage needs to have the sidewalks and
ramps brought up to the current ADA standards.
b. Repair or replace any curb and gutter or sidewalk
that is damaged in the public right-of-way prior to
occupancy.
c. Plans of all work in right-of-way shall be submitted
for approval prior to start of work.
d. Restripe Hwy. 10 as agreed on previous submittal.
e. A Sketch Grading and Drainage Plan per Sec. 29-
186(e) will be required with a building permit.
f. A Grading Permit per Secs. 29-186(c) and (d) will be
required with a building permit.
g. Obtain permits for improvements within State Highway
right-of-way from AHTD, District VI.
6. UTILITY AND FIRE DEPT. COMMENTS:
Water: No objection.
Wastewater: Sewer available, not adversely affected.
Southwestern Bell: No comments received.
ARKLA: No comments received.
2
May 11, 2000
SUBDIVISION
ITEM NO.: 21 (Cont.
FILE NO.: Z -6079-C
Entergy: No comments received.
Fire Department: Approved as submitted.
CATA: No affect. Site is on Route #25.
7. STAFF ANALYSIS:
The applicant, Walnut Valley Christian Academy, is
again requesting a revised conditional use permit to
revise their plan for the phased construction of a
private school on this R-2 zoned, 30 acre site. This
site is located approximately mile east of the
intersection of Highway 10 and Chenal Parkway, just
inside a newly annexed area. The proposed site is
within the Highway 10 Overlay District.
On December 12, 1995, the Planning Commission granted
Walnut Valley Christian Academy a conditional use
permit for the phased construction of a private school
on a 20 acre, R-2 zoned site. After that date, Walnut
Valley Christian Academy obtained an additional 10
acres along the north end of the original 20 acres. A
revised conditional use permit was obtained on June
26, 1997 to add the 10 acres, revise the master plan
and obtain approval for a specific Phase 1. On
September 3, 1998, the Planning Commission granted a
revision to that master plan and Phase 2.
The Academy is requesting to change their master plan
once again and obtain approval for a new Phase 4.
This Phase 4 would consist of a new gymnasium just to
the north of the elementary school, with an access
driveway.
All on site lighting must be designed and oriented
such that the lighting is focused on the property and
the lighting located in such a manner as not to
disturb the scenic appearance preserved in this
corridor. As it is constructed, the lighting and
sound system for the football and baseball fields as
well as the lighting for the parking areas should be
directed inward and away from the adjacent residential
parcels.
3
May 11, 2000
SUBDIVISION
ITEM NO.: 21 (Cont.)
FILE NO.: Z -6079-C
Proposed buildings will be a mix of one and two story
construction and exceed the setback requirements of
the Highway 10 Overlay District Ordinance. The
proposed number of parking spaces also exceeds
ordinance requirements, 480 versus 195 required. Any
signage must comply with the Highway 10 Overlay
District Ordinance. No new signage was proposed.
Due to facility planning issues and budget restraints,
the school desires to make these revisions. The
revised Master Plan changes the location and mix of
uses within most of the buildings on the north fourth
of the campus, and revises the phasing for their
construction. No new uses are proposed. The elementary
school total square footage has been reduced by about
12,500 feet. The large Gymatorium has been divided
into two smaller gym buildings with the same total
square footage. The cafeteria, library, and
administration offices have been combined into one
building without any classrooms. The Middle and High
schools are still proposed together but now in a
building of their own. The student and teacher
populations remain the same, 1100 and 110
respectively.
The remaining phases in the overall 9 phase Master
Plan consist of the following: Phase 4, a Practice
Gymnasium with an access road to it; Phase 5, a Middle
School/High School, Loop Drive and some additional
parking; Phase 6, a Cafeteria -Library -Administration
Building, relocation of the west side of the entrance
driveway, an extended deceleration lane along Highway
10, a Maintenance Building, a new Driveway along the
northeast side of the campus, finishing new parking
areas and removing the last house; Phase 7, an
Auditorium Gymnasium; Phase 8, a Baseball Field; and
finally, Phase 9, a Music Building.
There is an existing paved drive on site, which is
located too close to the west property line. This
drive is to be relocated 25 feet from the property
line, as indicated on the master plan. The school
would like to request a continuation of the deferral
on this relocation until the last remaining house on
the site is removed. The house is currently being used
4
May 11, 2000
SUBDIVISION
ITEM NO.: 21 (Cont.
FILE NO.: Z -6079-C
as the Administration Suite. Utility lines that serve
this house are located under the future road location,
and the utilities need to remain in service at this
time. The school would also like to request a
continuation of the deferral on the construction of
the sidewalks until the existing house is removed and
the existing road is relocated. There are currently
no sidewalks in close proximity to the school. Staff
believes the continued deferrals are reasonable.
There is an existing sign on site now. No changes to
it were proposed.
With proper screening of this site from the adjacent
residential properties and conformance to the Highway 10
Overlay District Ordinance, this proposed school
development should have little adverse impact on the
surrounding properties or area.
Staff believes these modifications are reasonable and
that the school would still be compatible with the
neighborhood with proper screening.
8. STAFF RECOMMENDATION:
Staff recommends approval of the conditional use
permit subject to compliance with the following
conditions:
a. Comply with the City's Landscape and Buffer
Ordinances.
b. Comply with Public Works Comments.
c. All exterior lighting must be low intensity and
directed downward and inward to the property and not
towards any residential zoned area.
d. Comply with the City's Highway 10 Overlay District
Ordinance.
e. The lighting of the football field and baseball
field must also be directed inward and away from
adjacent parcels.
f_ The sound system for the football and baseball
fields must also be directed inward and away from
adjacent parcels.
Staff recommends approval of the continued deferrals
for relocation of the west part of the entry drive and
5
May 11, 2000
SUBDIVISION
ITEM NO.: 21 (Cont.)
FILE NO.: Z -6079-C
also on the construction of the sidewalks until the
last house on this property is removed.
SUBDIVISION COMMITTEE COMMENTS:
(APRIL 20, 2000)
Jason Landrum was present representing the application.
Staff gave a brief description of the proposal.
Public Works briefly reviewed their comments. A discussion
followed regarding meetings the school had with the Highway
Department. The applicant stated that the Highway Dept. was
not in favor of center turn lanes or flashing school lights
at this location. Mr. Turner, Public Works Director, stated
that he would have his traffic engineer get with the
Highway Department and see what could be agreed to.
Screening requirements, and the continued deferrals for
moving the entrance drive and constructing sidewalks were
also briefly reviewed.
There being no further issues, the Committee accepted the
proposal and forwarded the item to the full Commission for
final action.
PLANNING COMMISSION ACTION:
(MAY 11, 2000)
Jason Landrum was present representing the application.
There were no registered objectors present. Staff presented
the item with a recommendation for approval subject to
compliance with the conditions listed under "Staff
Recommendation," paragraph 8 above. The approval
recommendation included continuing the deferrals for
relocating the west part of the entry drive, and the
construction of the sidewalks, until the last house on this
property is removed.
The item was placed on the Consent Agenda and approved as
submitted to include staff comments and recommendations,
and the deferrals. The vote was 8 ayes, 0 nays, 2 absent,
and 1 open position.