Mr. Jack Robinson
Little Rock School District
3601 South Bryant Street
Little Rock, AR 72204
Re: Portable classroom building for placement on the Geyer
Springs Elementary School campus
Dear Mr. Robinson:
The purpose of this communication is to provide a response
to your request for placement of a 24' x 64' classroom on
the subject school campus. I have visited the site and have
determined that the placement of this unit is appropriate as
indicated on your drawing. Therefore, I am approving the
proposal with several conditions. These are:
1. A ten foot minimum building separation
between all structural elements is
required, including covers over walkways.
2. Building permit review for Code compliance
is required.
3. Doors to the structure should face east
onto the sidewalk.
4. A six foot board fence, opaque in nature,
should be constructed along the north line
of this building providing a screen line
from the disposal field on the east to the
gravel driveway on the west, the
approximate length of the fence to be
120 feet.
5. Steps should be taken to prohibit vehicle
access from the apartment developed area
on the west to the gravel driveway serving
this property.
6. Upgrade to an all-weather surface the
existing walkway which will serve this
building.
7. All lighting on the site, existing and
proposed, should be directed away from the
residential area to the north.
Mr. Jack Robinson
September 27, 1989
Page 2
Mr. Roy Beard of the Building Codes office should be
contacted for purposes of the Building Code review. Mr.
Beard is familiar with the several previous submittals and
can deal with these issues. This approval provides for the
location of this structure on this site until June of 1994
at which time they will be removed.
If you require additional information or assistance from my
office, do not hesitate to call.
Sincerely,
RICHARD -WOOD
Current Planning Manager
RW: gIs
CC,. Case File Z-5240
Jim Lawson
APPLICATION FOR TEMPORARY SCHOOL BUILDING SITE PERMIT
Case Fi I No. Z- 52-+Q S 19 0 i at (3;00 pl.m.
Application is hr.;reby made to the Little Rock Planning Director pursuant
to ttic provisions of Chapter 36 of the Little Rock Code of Ordinances,
as amended, requesting a temporary School Building Site Permit on the
following property:
Address : (-,�YG2 Sz4o MA�6LVgL6 P I+«i 7 2 �061
General Location:2 6LKS. EASTOF UIJ►V6-r2S/Ty oN AtO457LV 67
__esa l D e s c r i p t ion: P-44TO c 'SW4 SE<-.�� Tr�I a►zvJ
Subject property is presently zoned: ROES, � 2
A temporary School Building Site Permit is requested to allow use of the
property for: (building occupancy)
40. ST�DE�.17S
Applicant (owner or authorized agent):Lr�►LjE P=�--K_SCNCO � ��5PeiC-T
(Name)
Address: SIO W,M6CKW4AA1 72Zo/ Telephone: SloS^55o�{
Lock', 3tool 5, JRRYAW-1 -7Z.Zo4
Planning Director approved: �'- %r�� e P,- .
Condi t Ions of Approval : .ie-,Att,, /F-Z7-Sf
Appeals:
Board of Adjustment approved:
Conditions of Approval: .
19 Denied
19
Pa fie 2
( c) DEVELOPMENT STANDARDS. In, carrying o u t the
Purpose of this section, the following use and
design standards shall be subject to the review
and approval of the Planning Director. The
appropriateness of these standards and compliance
therewith shall be determined for each sDecific
placement of a temporary school building/use.
�. The proposed use is designed, located and
r� proposed to be operated... such that the public
health, safety, welfare"and convenience will
be promoted.
2. The proposed land use is compatible with, and
will not adversely 2ffect,.'other properties
lf0( in the area where it is proposed to be
IJ`�) located.
The current zoning classification of the !and
y�( permits a public schac1 as a use c r n- or
conditional use permit.
4. The size and shape of the site anW the size,
sha:.e and arrangement of proposed structures
are in keeping with the intent of this
chapter.
�. The internal street system, ingress anc
egress, off-street parking, loading areas.
and pedestrianways are adequate.
Safeguards proposed to limit noxious or
offensive emissions, inclua-ine lighting
noise, Clare, dust ant odor, are acdressdc.
7. Proposed lancsc2oing and screening are in
accordance with the City of Little riocK
Landscape Ordinance.
61d �LA
L
6 1 --` L 6 Vt 1�(C—
kIA
It(-e
sce
��/ v r Oq
r.�sr dui�S " rs
CITY OF LITTLE ROCK
TO:
MEMORANDUM
ALL INTERESTED PARTIES
T`ils er e e,
to r rr17 s
Ve
FROM: RICHARD WOOD, CURRENT PLANNING MANAGER
OFFICE OF COMPREHENSIVE PLANNING
'SUBJECT: TEMPORARY SCHOOL BUILDING FOR PLACEMENT ON
THE GEYER SPRINGS ELEMENTARY SCHOOL SITE
DATE: SEPTEMBER 18, 1989
The Planning Director's office has received, a request from
the Little Rock School District for placement of a 24' x 64'
portable building on the campus of Geyer Springs Elementary.
The proposal includes the removal of an existing single wide
mobile home unit which will be transported to another
elementary school. The request is filed as provided in the
Little Rock Code of Ordinances and will be reviewed
administratively for placement.
Attached is a copy of the site plan illustrating the
proposed location on the school campus. The existing
classroom building to be moved is located in exactly the
same site. Please review this proposal at your earliest
convenience. The Ordinance requires that this office
respond to the School Board no later than 21 days after
filing. Therefore, I must respond by October 6, 1989. 1
have set a target date of September 29th for return of all
responses.
If you require additional information relative to this
proposal, do not hesitate to contact my office.
RW: gIs
cc: File Z-5240
Ci-ty of Little Rock Engineering Division
Department of 701 West Markham
Public Works Little Rock, Arkansas 72201
371-4800
M E M O R A N D U M
September 20, 1989
TO: Richard Wood, Current Planning Manager
Office of Comprehensive Planning
FROM: Roy Beard, Chief of Central Codes ,P.1
SUBJECT: Temporary School Building - Site Review
Geyer Springs Elementary School
9401 Mabelvale Cutoff
Your request for location of one temporary classroom building 24' x 64'
in size on the Geyer Springs Elementary School campus has been reviewed
by the Protective Codes Section and approved with regard to specific
location provided a space of ten feet is maintained between any adjacent
building.
The building to be moved in has not been inspected by the City for
code compliance. Any building so used must comply with all construction
related codes of the City of Little Rock and the State of Arkansas.
cc: Chuck Givens
David McClymont
File - 2
City of Little Rock Engineering Division
Department of 701 West Markham
Public Works Little Rock, Arkansas 72201
371-4800
M E M O R A N D U M
September 20, 1989
TO: Richard Wood, Current Planning Manager
Office of Comprehensive Planning ®"
FROM: Roy Beard, Chief of Central Codes 446
SUBJECT: Temporary School Building - Site Review
Geyer Springs Elementary School
9401 Mabelvale Cutoff
Your request for location of one temporary classroom building 24' x 64'
in size on the Geyer Springs Elementary School campus has been reviewed
by the Protective Codes Section and approved with regard to specific
location provided a space of ten feet is maintained between any adjacent
building.
The building to be moved in has not been inspected by the City for
code compliance. Any building so used must comply with all construction
related codes of the City of Little Rock and the State of Arkansas.
cc: Chuck Givens
David McClymont
File - 2
a
CITY OF LITTLE ROCK
MEMORANDUM
0.41vo-1-10
TO: ALL INTERESTED PARTIES
FROM: RICHARD WOOD, CURRENT PLANNING MANAGER
OFFICE OF COMPREHENSIVE PLANNING
SUBJECT: TEMPORARY SCHOOL BUILDING FOR PLACEMENT ON
THE GEYER SPRINGS ELEMENTARY SCHOOL SITE
DATE: SEPTEMBER 18, 1989
The Planning Director's office has received a request from
the Little Rock School District for placement of a 24' x 64,
portable building on the campus of Geyer Springs Elementary.
The proposal includes the removal of an existing single wide
mobile home unit which will be transported to another
elementary school. The request is filed as provided in the
Little Rock Code of Ordinances and will be reviewed
administratively for placement.
Attached is a copy of the site plan illustrating the
proposed location on the school campus. The existing
classroom building to be moved is located in exactly the
same site. Please review this proposal at your earliest
convenience. The Ordinance requires that this office
respond to the School Board no later than 21 days after
filing. Therefore, i must respond by October 6, 1989. 1
have set a target date of September 29th for return of all
responses.
If you require additional information relative to this
proposal, do not hesitate to contact my office.
RW: gIs
cc: File Z-5240
MEMORANDUM
CITY OF LITTLE ROCK
TO: ALL INTERESTED PARTIES
FROM:RICHARD WOOD, CURRENT PLANNING MANAGER
OFFICE OF COMPREHENSIVE PLANNING
SUBJECT: TEMPORARY SCHOOL BUILDING FOR PLACEMENT ON
I THE GEYER SPRINGS ELEMENTARY SCHOOL SITE
DATE: SEPTEMBER 18, 1989
The Planning Director's office has received, a request from
the Little Rock School District for placement of a 24' x 64'
portable building on the campus of Geyer Springs Elementary.
The proposal includes the removal of an existing single wide
mobile home unit which will be transported to another
elementary school. The request is filed as provided in the
Little Rock Code of Ordinances and will be reviewed
administratively for placement.
Attached is a copy of the site plan illustrating the
proposed location on the school campus. The existing
classroom building to be moved is located in exactly the
same site. Please review this proposal at your earliest
convenience. The Ordinance requires that this office
respond to the School Board no later than 21 days after
filing. Therefore, I must respond by October 6, 1989. 1
have set a target date of September 29th for return of all
responses.
If you require additional information relative to this
proposal, do not hesitate to contact my office.
RW: gIs
cc: File Z-5240
MEMORANDUM
CITY OF LITTLE ROCK
TO: ALL INTERESTED PARTIES
FROM: `1 RICHARD WOOD, CURRENT PLANNING MANAGER
OFFICE OF COMPREHENSIVE PLANNING
SUBJECT: TEMPORARY SCHOOL BUILDING FOR PLACEMENT ON
THE GEYER SPRINGS ELEMENTARY SCHOOL SITE
DATE: SEPTEMBER 18, 1989
The Planning Director's office has received, a request from
the Little Rock School District for placement of a 24' x 64'
portable building on the campus of Geyer Springs Elementary.
The proposal includes the removal of an existing single wide
mobile home unit which will be transported to another
elementary school. The request is filed as provided in the
Little Rock Code of Ordinances and will be reviewed
administratively for placement.
Attached is a copy of the site plan illustrating the
proposed location on the school campus. The existing
classroom building to be moved is located in exactly the
same site. Please review this proposal at your earliest
convenience. The Ordinance requires that this office
respond to the School Board no later than 21 days after
filing. Therefore, I must respond by October 6, 1989. 1
have set a target date of September 29th for return of all
responses.
If you require additional information relative to this
proposal, do not hesitate to contact my, office.
RW: gIs
cc: File Z-5240
S
01,
Gly'`
MEMORANDUM
CITY OF LITTLE ROCK
TO: ALL INTERESTED PARTIES
FROM: 1 RICHARD WOOD, CURRENT PLANNING MANAGER
OFFICE OF COMPREHENSIVE PLANNING
SUBJECT: TEMPORARY SCHOOL BUILDING FOR PLACEMENT ON
THE GEYER SPRINGS ELEMENTARY SCHOOL SITE
DATE: SEPTEMBER 18, 1989
The Planning Director's office has received a request from
the Little Rock School District for placement of a 24' x 64'
portable building on the campus of Geyer Springs Elementary.
The proposal includes the removal of an existing single wide
mobile home unit which will be transported to another
elementary school. The request is filed as provided in the
Little Rock Code of Ordinances and will be reviewed
administratively for placement.
Attached is a copy of the site plan illustrating the
proposed location on the school campus. The existing
classroom building to be moved is located in exactly the
same site. Please review this proposal at your earliest
convenience. The Ordinance requires that this office
respond to the School Board no later than 21 days after
filing. Therefore, I must respond by October 6, 1989. 1
have set a target date of September 29th for return of all
responses.
If you require additional information relative to this
proposal, do not hesitate to contact my office.
RW: gIs
cc: File Z-5240