HomeMy WebLinkAboutZ-5016-B Staff AnalysisFILE NO.: Z -5016-B
NAME: GKS Development Short -form PID
LOCATION: Located at 5510 West 65th Street
DEVELOPER:
GKS Development
c/o McGetrick and McGetrick Engineering
P.O. Box 30441
Little Rock, AR 72260
ENGINEER:
McGetrick and McGetrick Engineering
P.O. Box 30441
Little Rock, AR 72260
AREA: 4.22 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF
CURRENT ZONING: C-4, Open Display District
ALLOWED USES: Retail
PROPOSED ZONING: PID
PROPOSED USE: Add commercial laundry as an allowable use
VARIANCES/WAIVERS REQUESTED: None requested.
BACKGROUND:
Ordinance No. 15,492 adopted by the Little Rock Board of Directors on June 21, 1988,
rezoned this property from R-2, Single-family to C-4, Open Display District and OS,
Open Space District. The bulk of the property was zoned C-4, Open Display District
with a 50 -foot strip zoned OS along the northern perimeter. The OS portion was to
provide a buffer between the C-4, Open Display District zoning and the residential
zonings (R-2, R-4 and MF -6) located to the north, northeast and northwest which
existed at the time.
FILE NO.: Z -5016-B
Ordinance No. 18,792 adopted by the Little Rock Board of Directors on December 17,
2002, allowed a portion of the OS, Open Space zoning to be removed along the
northern perimeter. The property to the north was purchased by Sysco Foods and
zoned PID as part of their industrial development. A single-family home remained to the
west but was shown on the City's Future Land Use Plan as Mixed Commercial
Industrial. (This property has since been purchased by Sysco Foods. The house has
been removed.) There were homes remaining along the northeastern portion of the site
and the buffer was maintained in this area. The buffer maintained; 100 -feet running
north and south and 50 -feet running east and west.
A. PROPOSAL/REQUEST/APPLICANT'S STATEMENT:
The request is a rezoning from C-4, Open Display District to PID to add a
commercial laundry as an allowable use to the existing building located at
5510 65th Street. The applicant proposes to make interior modifications to the
building to allow the establishment of the commercial laundry. The hours of
operation are typically 5 day work weeks with intermittent Saturday and Sunday
hours. The hours of operation are from 4 AM to 12 AM weekly. There are
approximately 80 employees working over the course of two (2) shifts. The
minor modifications to the exterior of the building and site include a water storage
facility, two (2) additional loading dock areas and an increased paved area for
access to the loading dock.
B. EXISTING CONDITIONS:
Sysco Foods is located to the north and northwest of this site. There are
single-family homes located to the northeast of this site. The uses along West
65t Street in this area are primarily non-residential uses including a printing
service, an engine rebuilder, a school, and offices for AT&T and a veterinarian
clinic.
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has received a few informational phone calls from area
residents. All property owners located within 200 -feet of the site along with the
Wakefield Neighborhood Association and Southwest Little Rock United for
Progress were notified of the public hearing.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Due to the proposed use of the property, the Master Street Plan specifies that
Battle Street for the frontage of this property must meet commercial street
standards. Dedicate right-of-way to 30 feet from centerline.
2. A 20 foot radial dedication of right-of-way is required at the intersection of
West 65th Street and Battle Road.
2
FILE NO.: Z -5016-B (Cont.
E.
3. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan.
4. Due to the proposed development, no boundary street improvements are
required to be constructed. At the time of additional development beyond the
current proposal, the property will be subject to compliance with the Boundary
Street Ordinance and boundary street improvements.
5. Repair or replace any curb and gutter or sidewalk that is damaged in the
public right-of-way prior to occupancy.
UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer available to this project, but must be upgraded by Owner of
Development should capacity of the existing sewer main not be adequate for the
new use.
Entergy: No comment received.
Center -Point Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water:
1. No objection. All Central Arkansas Water requirements in effect at the time of
request for water service must be met.
2. If there are facilities that need to be adjusted and/or relocated, contact Central
Arkansas Water. That work would be done at the expense of the developer.
3. Contact Central Arkansas Water if additional fire protection or metered water
service is required.
4. Contact Central Arkansas Water regarding the size and location of the water
meter.
5. A Capital Investment Charge based on the size of meter connection(s) will
apply to this project in addition to normal charges. This fee will apply to all
connections including metered connections off the private fire system.
6. The Little Rock Fire Department needs to evaluate this site to determine
whether additional public and/or private fire hydrant(s) will be required. If
additional fire hydrant(s) are required, they will be installed at the Developer's
expense.
7. Due to the nature of this facility, installation of an approved reduced pressure
zone backflow preventer assembly (RPZA) is required on the domestic water
service. This assembly must be installed prior to the first point of use.
Central Arkansas Water requires that upon installation of the RPZA,
3
E NO.: Z -5016-B (Cont.
successful tests of the assembly must be completed by a Certified Assembly
Tester licensed by the State of Arkansas and approved by Central Arkansas
Water. The test results must be sent to Central Arkansas Water's Cross
Connection Section within ten days of installation and annually thereafter.
Contact the Cross Connection Section at 377-1226 if you would like to
discuss backflow prevention requirements for this project.
8. The facilities on-site will be private. When meters are planned off private
lines. Private facilities shall be installed to Central Arkansas Water's material
and construction specifications and installation will be inspected by an
engineer, licensed to practice in the State of Arkansas. Execution of
Customer Owned Line agreement is required.
Fire Department: Place fire hydrant(s) per code. Maintain access. Contact the
Little Rock Fire Department for additional information_
County Planning: No comment.
CATA: 1 block from #15 and #17/#22 bus routes.
Parks and Recreation: No comment received.
F. ISSUES/TECHNICAL/DESIGN:
Building Code: Project is a change in occupancy and is therefore subject to
current building code requirements. Review and approval is required by Building
Codes Division before occupancy takes place. For information on submittal
requirements and the review process, contact a commercial plans examiner:
Curtis Richey at 501.371.4724; cricheyoIittlerock. org or Mark Alderfer at
501.371.4875; malderfer@Iittlerock.org.
Planning Division: This request is located in the 65th Street East Planning
District. The Land Use Plan shows Service Trades District (STD) for this
property. This category provides for a selection of office, warehousing, and
industrial park activities that primarily serve other office service or industrial
businesses. The district is intended to allow support services to these businesses
and to provide for uses with an office component. A Planned Zoning District is
required for any development not wholly office. The applicant has applied for a
rezoning from C-4 (Open Display Commercial District) to PID (Planned Industrial
District) to allow for conversion of this structure to a Commercial Laundry.
Master Street Plan: 65th Street is a Minor Arterial on the Master Street Plan. A
Minor Arterial provides connections to and through an urban area and their
primary function is to provide short distance travel within the urbanized area.
Entrances and exits should be limited to minimize negative effects of traffic and
pedestrians on 65th Street since it is a Minor Arterial. This street may require
2
FILE NO.: Z-501
dedication of right-of-way and may require street improvements for entrances
and exits to the site.
Bicycle Pian: There are no bike routes shown in the immediate vicinity.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance
requirements.
2. A perimeter planting strip is required along any side of a vehicular use area
that abuts adjoining property. This strip shall be at least nine (9) feet wide.
Provide trees with an average linear spacing of not less than thirty (30) feet
within the perimeter planting strip. Provide three (3) shrubs or vines for every
thirty (30) linear feet of perimeter planting strip.
3. Street buffers will be required at six (6) percent of the average depth of the
lot. The minimum dimension shall be one-half (Y2) the full width requirement
but in no case less than nine (9) feet. A minimum eighteen (18) foot wide
buffer (6% of the average lot width) is required along Battle Road.
4. Screening requirements will need to be met for the vehicular use areas
adjacent to street right-of-ways. Provide screening shrubs with an average
linear spacing of not less at three (3) feet within the required landscape area.
Provide trees with an average linear spacing of not less than thirty (30) feet.
5. The development of two (2) acres or more requires an approved landscape
plan stamped with the seal of a registered landscape architect prior to the
issuance of a building permit.
6. A landscape irrigation system shall be required for developments of one (1)
acre or larger.
7. The City Beautiful Commission recommends preserving as many existing
trees as feasible on this site. Credit toward fulfilling Landscape Ordinance
requirements can be given when preserving trees of six (6) inch caliper or
larger.
G. SUBDIVISION COMMITTEE COMMENT: (April 23, 2014)
Mr. Pat McGetrick was present representing the request. Staff presented an
overview of the development stating there were few outstanding technical issues
in need of addressing related to the proposed site plan. Staff requested.
Mr. McGetrick provide the days and hours of operation for the laundry, details of
any proposed signage including ground and building signage and to provide the
previously zoned OS Buffer along the northern perimeter.
Public Works comments were addressed. Staff stated a radial dedication of right
of way was required at the intersection of Battle Road and West 65th Street. Staff
also stated due to the proposed development no boundary street improvements
5
FILE NO.: Z -5016-B (Cont.
H
were required to be constructed. Staff stated at the time of additional
development beyond the current proposal, the property would be subject to
compliance with the Boundary Street Ordinance and boundary street
improvements.
Landscaping comments were addressed. Staff stated a minimum street buffer of
18 -feet was required along Battle Road. Mr. McGetrick requested the existing
paved area remain and the area proposed with new paving to be brought into
compliance with the typical ordinance requirement.
Staff noted the comments from the various other agencies. There were no more
issues for discussion. The Committee then forwarded the item to the full
Commission for final action.
ANALYSIS:
The applicant submitted a revised site plan addressing issues raised at the April
23, 2014, Subdivision Committee meeting. The applicant has provided the days
and hours of operation for the laundry, details of any proposed signage and
provided the previously zoned OS Buffer along the northern perimeter.
The request is a rezoning from C-4, Open Display District to PID to add a
commercial laundry as an allowable use to the existing building. The developers
propose interior modifications to the building with the exterior modifications
including a water storage facility, two (2) additional loading dock areas and an
increased paved area for access to the loading dock.
The hours off operation are typically five (5) days per week with intermittent
Saturday and Sunday hours. The hours of operation are from 4:00 am to
12:00 midnight. There are approximately 80 employees working covering
two (2) shifts.
The applicant has indicated all signage will comply with signage typically allowed
in commercial zones. Building signage will be limited to a maximum of
ten (10) percent of the fagade area abutting the public street. Ground signage
will be limited to a single sign location. The maximum height allowed will be
36 -feet and the maximum sign area will be 160 square feet.
The site plan indicates the placement of a new paved area on the west side of
the building along Battle Road. The paved area will be used to access the
loading dock area and will not be used as parking. The new paved area will be
placed 18 -feet from the right of way of Battle Road to comply with the minimum
standards of the buffer ordinance. The applicant is requesting to not remove the
existing paving along Battle Road which does not include the minimum
landscape strip as typically required per the buffer and landscape ordinances.
D
FILE NO.: Z -5016-B Cont.
Staff is supportive of the request. The applicant is proposing the rezoning to add
a commercial laundry as an allowable use for the property. The area is primarily
non-residential along West 65th Street and to the west along Battle Road. There
are single-family homes located to the northeast and the applicant will maintain
the previously imposed buffer adjacent to these homes. Otherwise to staff's
knowledge there are no remaining outstanding technical issues associated with
the request.
STAFF RECOMMENDATION:
Staff recommends approval of the request subject to compliance with the
comments and conditions as outlined in paragraphs D, E and F of the agenda
staff report.
PLANNING COMMISSION ACTION: (MAY 15, 2014)
The applicant was present. There were no registered objectors present. Staff
presented the item with a recommendation of approval of the request subject to
compliance with the comments and conditions as outlined in paragraphs D, E and F of
the agenda staff report.
There was no further discussion of the item. The chair entertained a motion for
approval of the item as presented by staff. The motion carried by a vote of 9 ayes,
0 noes and 2 absent.
7
ITEM NO.: 9. Z -5016-B
NAME: GKS Development Short -form PID
LOCATION: located at 5510 West 65th Street
Planning Staff Comments:.
1. Provide notification of property owners located within 200 -feet of the site including
the certified abstract list, notice form with affidavit executed and proof of mailing.
The notice must be mailed no later than April 30, 2014. The Office of Planning and
Development must receive the proof of notice no later than May 9, 2014.
2. Provide the days and hours of operation for the proposed laundry.
3. Provide details of any proposed signage including ground and building signage.
Provide the maximum height and maximum sign area for the ground signage.
Provide the building facades proposed for wall signage and include a note stating
the percentage of facade coverage.
4. Provide the maximum building height for the existing structure and any additions.
5. The plan as presented does not provide the required street buffer and landscape
strip along the new proposed paved area.
6. Indicate the OS/Buffer along the northern perimeter adjacent to the residential
homes.
Variance/Waivers:
Public Works Conditions:
1. Due to the proposed use of the property, the Master Street Plan specifies that Battle
Street for the frontage of this property must meet commercial street standards.
Dedicate right-of-way to 30 feet from centerline.
2. A 20 foot radial dedication of right-of-way is required at the intersection of West 65th
Street and Battle Road.
3. Stormwater detention ordinance applies to this property. Show the proposed
location for stormwater detention facilities on the plan.
4. Due to the proposed development, no boundary street improvements are required to
be constructed. At the time of additional development beyond the current proposal,
the property will be subject to compliance with the Boundary Street Ordinance and
boundary street improvements.
5. Repair or replace any curb and gutter or sidewalk that is damaged in the public right-
of-way prior to occupancy.
Item # 9.
Utilities and Fire Department/County Planning:
Wastewater: Sewer available to this project, but must be upgraded by Owner of
Development should capacity of the existing sewer main is not adequate for the new
use.
Entergy: No comment received.
Center -Point Energy: No comment received.
AT & T: No comment received.
Central Arkansas Water:
1. No objection. All Central Arkansas Water requirements in effect at the time of
request for water service must be met.
2. If there are facilities that need to be adjusted and/or relocated, contact Central
Arkansas Water. That work would be done at the expense of the developer.
3. Contact Central Arkansas Water if additional fire protection or metered water service
is required..
4. Contact Central Arkansas Water regarding the size and location of the water meter.
5. A Capital Investment Charge based on the size of meter connection(s) will apply to
this project in addition to normal charges. This fee will apply to all connections
including metered connections off the private fire system.
6. The Little Rock Fire Department needs to evaluate this site to determine whether
additional public and/or private fire hydrant(s) will be required. If additional fire
hydrant(s) are required, they will be installed at the Developer's expense.
7. Due to the nature of this facility, installation of an approved reduced pressure zone
backflow preventer assembly (RPZA) is required on the domestic water service.
This assembly must be installed prior to the first point of use. Central Arkansas
Water requires that upon installation of the RPZA, successful tests of the assembly
must be completed by a Certified Assembly Tester licensed by the State of Arkansas
and approved by Central Arkansas Water. The test results must be sent to Central
Arkansas Water's Cross Connection Section within ten days of installation and
annually thereafter. Contact the Cross Connection Section at 377-1226 if you would
like to discuss backflow prevention requirements for this project.
8. The facilities on-site will be private. When meters are planned off private lines.
Private facilities shall be installed to Central Arkansas Water's material and
construction specifications and installation will be inspected by an engineer, licensed
to practice in the State of Arkansas. Execution of Customer Owned Line agreement
is required.
Item # 9.
Fire Department: Place fire hydrant(s) per code. Maintain access. Contact the Little
Rock Fire Department for additional information.
County Planning: No comment.
CATA: 1 block from #15 and #17/#22 bus routes.
Parks and Recreation: No comment received.
Building Code: Project is a change in occupancy and is therefore subject to current
building code requirements. Review and approval is required by Building Codes Division
before occupancy takes place. For information on submittal requirements and the
review process, contact a commercial plans examiner: Curtis Richey at 501.371.4724;
crich ey@ little rock or Mark Alderfer at 501.371.4875; malderfer _littlerock.arq.
Planning Division: This request is located in the 65th Street East Planning District. The
Land Use Plan shows Service Trades District (STD) for this property. This category
provides for a selection of office, warehousing, and industrial park activities that
primarily serve other office service or industrial businesses. The district is intended to
allow support services to these businesses and to provide for uses with an office
component. A Planned Zoning District is required for any development not wholly
office. The applicant has applied for a rezoning from C-4 (Open Display Commercial
District) to PID (Planned Industrial District) to allow for conversion of this structure to a
Commercial Laundry.
Master Street Plan: 65th Street is a Minor Arterial on the Master Street Plan. A Minor
Arterial provides connections to and through an urban area and their primary function is
to provide short distance travel within the urbanized area. Entrances and exits should
be limited to minimize negative effects of traffic and pedestrians on 65th Street since it is
a Minor Arterial. This street may require dedication of right-of-way and may require
street improvements for entrances and exits to the site.
Bicycle Plan: There are no bike routes shown in the immediate vicinity.
Landscape:
1. Site plan must comply with the City's landscape and buffer ordinance requirements.
2. A perimeter planting strip is required along any side of a vehicular use area that
abuts adjoining property. This strip shall be at least nine (9) feet wide. Provide trees
with an average linear spacing of not less than thirty (30) feet within the perimeter
planting strip. Provide three (3) shrubs or vines for every thirty (30) linear feet of
perimeter planting strip.
3. Street buffers will be required at six (6) percent of the average depth of the lot. The
minimum dimension shall be one-half (Y2) the full width requirement but in no case
less than nine (9) feet. A minimum eighteen (18) foot wide buffer (6% of the average
lot width) is required along Battle Road.
Item # 9.
4. Screening requirements will need to be met for the vehicular use areas adjacent to
street right-of-ways. Provide screening shrubs with an average linear spacing of not
less at three (3) feet within the required landscape area. Provide trees with an
average linear spacing of not less than thirty (30) feet
5. The development of two (2) acres or more requires an approved landscape plan
stamped with the seal of a registered landscape architect prior to the issuance of a
building permit.
6. A landscape irrigation system shall be required for developments of one (1) acre or
larger.
7. The City Beautiful Commission recommends preserving as many existing trees as
feasible on this site. Credit toward fulfilling Landscape Ordinance requirements can
be given when preserving trees of six (6) inch caliper or larger.
Revised plat/plan: Submit four (4) copies of a revised preliminary plat/plan (to include
the additional information as noted above) to staff on Wednesday, April 30, 2014.
Item # 9.