HomeMy WebLinkAboutZ-4923 Staff AnalysisJanuary 4, 1994
ITEM NO.: 22 FILE NO.: Z-4923
NAME: THE SUMMIT MALL -- LONG -FORM PCD TIME EXTENSION
LOCATION: On the west side of Shackleford Road, between
1I -430 -and West 36th. Street
DEVELOPER:
ENGINEER•
GERGINS INVESTMENT CORP. MCGETRICK ENGINEERING CO.
c/o McGetrick Engineering Co. 11225 Huron Lane, Suite 200
Little Rock, AR 72211
223-9900
AREA: 97.446 ACRES NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: PCD PROPOSED USES: Shopping Center
PLANNING DISTRICT: 11
CENSUS TRACT: 24.04
VARIANCES REQUESTED: None
STATEMENT OF PROPOSAL:
The developer, through the engineer, proposes a three year time
extension for implementing work associated with the establishment
of the PCD. The Planning Commission, on November 3, 1987,
reviewed the proposed PCD. The Board of Directors, on December 1,
1987, in Ordinance 15,385, conditionally established the PCD. On
February 12, 1991, the Planning Commission approved an initial
three year time extension. That time extension expires on
February 12, 1994. The applicant requests, then, a second three
year time extension.
A. PROPOSAL/REQUEST:
The applicant requests approval by the Planning Commission
of a second three year time extension for implementation of
the improvements associated with the establishment of the
Summit Mall PCD.
B. EXISTING CONDITIONS:
The site is undeveloped and wooded. The existing zoning
remains PCD.
C. ENGINEERING/UTILITY COMMENTS:
There were no comments.
�r,uarY ,4, 1994
5 DIVI I
—ON
ITEM NO.: 22 Continued FILE NO.:
D. ISSUES LEGAL TECHNICAL DESIGN:
There are no issues.
E. ANALYSIS•
The applicant wishes to retain the option of developing the
site as originally planned. The PCD will expire and the
land will revert to its former zoning classification unless
the time extension is approved.
F. STAFF RECOMMENDATIONS:
Staff recommends approval of the time extension.
SLBDIVISION COMMITTEE COMMENT:
(DECEMBER 9, 1993)
Mr. McGetrick, the engineer, was present to represent the
applicant- Staff presented the request. The Committee confirmed
that the requested time extension was the second such request.
The item was referred to the Commission for the hearing.
PLANNING CQMMISSION ACTION;
(JANUARY 4, 1994)
The item was included with the Consent Agenda for approval, and
was approved with the vote of 7 ayes, no nays, 4 absent, and no
abstentions.
2
`February 20, 1997
ITEM NO.: 9 FILE NO.: Z-4323
NAME: THE SUMMIT MALL -- LONG -FORM PCD TIME EXTENSION
LOCATION: On the west side of Shackleford Road, between
Interstate 430 and West 36th Street.
DEVELOPER:
ENGINEER:
Thomas J. Schneider Pat McGetrick
Senior Vice President Development McGetrick Engineering Co.
Simon DeBartolo Group 11225 Huron Lane, Ste. 200
National City Center Little Rock, AR 72211
P. O. Box 7033
Indianapolis, IN 46207
AREA: 97.446 ACRES NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: PCD PROPOSED USES: Shopping Center
PLANNING DISTRICT: #11 I-430
CENSUS TRACT: 24.04
VARIANCES REQUESTED: None
STATEMENT OF PROPOSAL:
The developer, through the engineer, proposes a three year time
extension for implementing work associated with the establishment
of the PCD. The Planning Commission, on November 3, 1987,
reviewed the proposed PCD. The Board of Directors, on December
1, 1987, in Ordinance 15,385, conditionally established the PCD.
On February 12, 1991, the Planning Commission approved an initial
three year time extension. A second extension was approved on
January 4, 1994 for three additional years. That extension
expired in January 1997. On December 16, 1996 prior to the
expiration date the developer requested a third time extension.
A. PROPOSAL/REQUEST:
The applicant requests approval by the Planning Commission
of a third three year time extension for implementation of
the improvements associated with the establishment of the
Summit Mall PCD.
B. EXISTING CONDITIONS:
The site is undeveloped and wooded. The existing zoning
remains PCD.
February 20, 1997
SUBDIVISION
ITEM NO.: 9 Cant. FILE NO .• Z-4923
C. ENGINEERING UTILITY COMMENTS:
The item was not transmitted to agencies for comment or
Subdivision Committee.
D. ISSUES/LEGAL/TECHNICAL/DESIGN:
• The applicant is reminded that under the current PCD no
clearing of vegetation or grading will take place without
prior approval of the City.
E. ANALYSIS•
The applicant wishes to retain the option of developing the
site as originally planned. The PCD will expire and the
land will revert to its former zoning classification unless
the time extension is approved.
The developer has had the PCD zoning in place since December
1, 1987. Over the last 9+ years there has been a great deal
of growth in the west Little Rock area that has impacted
roadways and public utilities. If the developer wishes to
proceed with "The Summit Mall", they should file a new
application that would be reviewed by staff and the public
in the light of current planning standards.
F. STAFF RECOMMENDATIONS:
DENIAL of the requested time extension and restore the
previous R-2 zoning.
PLANNING COMMISSION ACTION: (FEBRUARY 20, 1997)
Jim Lawson presented the staff report. He stated that he had met
this morning with representatives of the Simon DeBartolo Group to
discuss the project. Mr. Lawson said staff was now supporting a
3 year time extension. This will allow the developer to put the
many aspects of the future mall together. He stated that
approving a 3 year time extension was a holding pattern for a
future regional mall on this site. Several commissioners asked
questions of Mr. Lawson concerning the reality of this project.
Thomas J. Schneider spoke for the applicants. He indicated that
their demographic information showed a need for the mall in west
Little Rock. A two -three year predevelopment timeline has
started. This would be followed by a 2 year construction period.
The mall would open in the period 2000-2002.
Fa
s February 20, 1997
I
SUBDIVISION
ITEM NO.: 9 Cont. FILE No.: Z-4923
Sarah Spencer of Camp Aldersgate spoke about her concerns about
their operation being impacted by the traffic from a shopping
mall. Ruth Hell also spoke of her concern about future traffic
that will be generated by the project.
A motion to approve a three year time extension for the PCD
subject to the existing staff conditions. Motion passed with
10 ayes, 0 nays and 1 absent.
3
'January 4, 1994
ITEM NO.: 22 FILE
NAME: THE SUMMIT MALL -- LONG -FORM PCD TIME EXTENSION
LOCATION: On the west side of Shackleford Road, between
11-430 and West 36th. Street.
DEVELOPER:
ENGINEER:
GERGINS INVESTMENT CORP. MCGETRICK ENGINEERING CO.
C/o McGetrick Engineering Co. 11225 Huron Lane, Suite 200
Little Rock, AR 72211
223-9900
AREA: 97.446 ACRES NUMBER OF LOTS: 1 FT. NEW STREET: 0
BONING: PCD PROPOSED USES: Shopping Center
PLANNING DISTRICT: 11
CENSUS TRACT: 24.04
VARIANCES REp17ESTED: None
STATEMENT OF PROPOSAL:
The developer, through the engineer, proposes a three year time
extension for implementing work associated with the establishment
of the PCD. The Planning Commission, on November 3, 1987,
reviewed the proposed PCD. The Board of Directors, on December 1,
1987, in Ordinance 15,385, conditionally established the PCD. On
February 12, 1991, the Planning Commission approved an initial
three year time extension. That time extension expires on
February 12, 1994. The applicant requests, then, a second three
year time extension.
A.
B.
PROPOSAL RE VEST:
The applicant requests approval by the Planning Commission
Of a second three year time extension for implementation of
the improvements associated with the establishment of the
Summit Mall PCD.
EXISTING CONDITIONS:
The site is undeveloped and wooded.
remains PCD.
C. ENGINEERING UTILITY COMMENTS:
There were no comments.
The existing zoning
January 4, 1994
SUBDIVISION
ITEM NO.: 22 Continued FILE NO.: Z-4923
D. ISSUES LEGAL TECHNICAL DESIGN:
There are no issues.
E. ANALYSIS•
The applicant wishes to retain the option of developing the
site as originally planned. The PCD will expire and the
land will revert to its former zoning classification unless
the time extension is approved.
F. STAFF RECOMMENDATIONS:
Staff recommends approval of the time extension.
SUBDIVISION COMMITTEE COMMENT:
(DECEMBER 9, 1993)
Mr. McGetrick, the engineer, was present to represent the
applicant. Staff presented the request. The Committee confirmed
that the requested time extension was the second such request.
The item was referred to the Commission for the hearing.
PLANNING COMMISSION ACTION:
(JANUARY 4, 1994)
The item was included with the Consent Agenda for approval, and
was approved with the vote of 7 ayes, no nays, 4 absent, and no
abstentions.
2
November 3, 1987
SUBDIVISIONS
Item No. 12
NAME:
LOCATION:
DEVELOPER:
Austin Dev. Co.
2216 43rd
Meridian, MS 39305
Phone: 601-693-2703
AREA: 97.446 acres
The Summit "Long -Form PCD"
(Z-4923)
West Side of Shackleford Road
Between I-430 and West 36th
ENGINEER:
Lawrence Beame
Kober/Bellaschi. Assoc.
353 Alcazar Avenue
Coral Gables,. FL 33134
ZONING: "0-2" PROPOSED USE: PCD
A. Developmental Concept
FT. NEW STREET: 0
This submittal describes plans for a mixed use
development of office, hotel, and retail to be located
on 97.446 acres at the intersection of Shackleford Road
and I-430. A two-level retail galleria in the center
of the highest level will be the focal point; and glass
enclosed entrances will provide a welcome atmosphere.
The developer has listed several major design features
and plan components which will include:
(1) Internalized ring road.
(2) Two phased project with off-site improvements to
be constructed in Phase I. Site grading
accomplished during initial phase so that building
construction during the second phase will require
minimal disruption.
(3) Only four points of access to Shackleford in the
3,000 linear feet of spacing, whereas the City
regulations allow for ten.
(4 ) Cut and fill has been minimized.
November 3, 1987
SUBDIVISIONS
Item No. 12 - Continued
Bo
(5) Perimeter Open Space
Treatment of landscaped areas and natural buffer
areas ranging in width from 50' to 100'. A true
survey has been done to reflect the number and
location of large 'species • of trees to be
retained.
(6) Intense landscaping of open space and parking in
excess of City requirements.
(7) Pedestrian connections between major use ares
within the site and covered walkways and bridges
to facilitate encouraging pedestrian movement.
(8) Preservation of an approximate two acre lake as a
focal point for major, office development and will
serve as primary detention facility.
(9) Improvements include reconstruction of Shackleford
Road to a five -lane section of installation of
five traffic signals - cost in excess of
$1 million.
(10) Less traffic inpact than an office development
since it is spread out over more hours of the day.
Quantitative Data
Gross Acreage 97,446 acres
Right -of -Way Dedication 2.016 acres
Net acreage 95,430 acres
Use
Area
Levels
Parking
Office
111,667
6
111,667
6
111,667
6
335,000
sq.
ft.
6
840
Retail
975,000
sq.
ft.
6
4,625
Hotel
190,000
sq.
ft.
10 (type)
280
(250 room)
Restaurant
20,000
sq.
ft.
1
1
200
1,470,000
2
5,945
November 3, 1987
SUBDIVISIONS
Item No. 12 - Continued
C. Engineerin2 Comments
Will discuss at meeting -
D. Staff Recommendation
Reserved until further information provided. The main
issue involves land use and amendment of the I-430
plan. Other issues involve phasing of traffic and
excavation and grading.
Staff, therefore, feels that a mixed used development
is compatible with the surrounding area versus the
straight commercial development. The proposal
represents a reasonable use of property at this highway
interchange with very little long-term exposure to
residential uses. The plan also includes extensive
landscaping and buffering along the highway. The
sit-down restaurants are not as conducive to strip
commercial as the previously proposed fast food
restaurants.
The report on the traffic information submitted is
needed from Engineering. Staff does feel that the
extent of excavations and fills seems excessive. The
applicant should add terracing of the parking areas.
E. Subdivision Committee Review
The applicant was present. Staff reported that a
letter had been reviewed from Aldersgate requesting
deferral until they had further time to study the
situation. The engineer, Pat McGetrick, stated that
they were working to develop ponds to minimize runoff
to Aldersgate.
Staff felt that the plan indicated excessive grading
and that more terracing should be provided.
SUBDIVISIONS
PLANNING M SS ON ACTION:
The Applicant was present. The Planning Director called on
Jim Lawson to make the staff presentation, and reported that
City Manager Tom Dalton desired to make a statement. Mr.
Dalton addressed questions that had been previously raised,
concerning the involvement of the City Manager's Office in
this issue. He explained that his involvement was justified
on projects of this magnitude that involved multiple issues
such as land use and zoning, traffic flow, transportation,
aesthetics and public improvements that involved a number of
City departments; and commitments close to 1.5 million
dollars. His role was to coordinate the several meetings
held between the City's various departments and the
developer, and to ensure that the administration spoke with
one voice regarding the proposal; especially since there had
also been prior complaints as to the City's actual position.
Mr. Lawson stated staff's recommendation as approved,
subject to several agreements made by the Developer.
Agreements made include:
(1) Ensuring that there is no ground runoff problems
that would affect Camp Aldersgate and that the
water quality would be checked periodically.
(2) Improve Shackleford to 5 lanes and a contribution
of 1.5 million dollars to the City for the
widening and 5 traffic signals.
(3) Preservation of as many trees as possible.
(4) No grading of the site or cutting of the trees
until assurance is given that the money is
available for development. The preliminary
will be approved now but■ before any work can
be done on the site, they have to present their
final plans.
(5) Donation of $240,000 worth of fill materials.
The City is looking at the possibilty of having
an interchange built at I-430 and 36th Street.
This will save taxpayers a tremendous amount
of money due to the amount of dirt that has to
be moved to this site. They are requiring that
within 1 year or 18 months when they begin the
project, the City should have the site determined
so as not to inhibit the progress of their
development.
(6) A $10,000 cash contribution to help fund an
engineering study for the interchange. The
interchange is for the whole of West Little Rock
since it is growing very rapidly and there
is now a traffic problem on I-630, so other
options need to be explored very soon.
Several persons spoke in regard to the project. Those
representing the project included: Mr. Webb Hubbell of the
Rose Law Firm; Ron Mastriana, who represented the Developer,
Larry Beame-Architectural Firm; Merle Seaman -Landscape
Architect; Ernie Peters -Traffic Engineer; and Patrick
McGetrick, the local Engineer. Those offering favorable
comments included: Mr. Ron Hackleman, the General Manager
of Roger Properties, Mr. Patrick Herndon representing
Property Owners in in Pecan Lake, Colonel Glenn and the
South Stagecoach area.
Mr. Doug Strock represented the Sandpiper Property Owners
Association. He requested deferral. Their concerns
involved traffic, Little Rock's ability to support this
development, and the types of -stores to be put into the
mall.
Mr. Joe Davis was concerned about security and did not feel
that this was a proper location for this type of
development.
Mr. David Worley, President of NOBLE encouraged
reexamination of the traffic study; and disencouraged
speedily dismissing the City's I-430 plan.
Mr. James Stuckley expressed fears that Peachtree would
become a thoroughfare for people wanting to get to the mall,
thereby creating negative effects on Sandpiper Subdivision.
Finally, a vote for approval was made and passed by a vote
of 8 ayes, 1 noes, 1 absent, 1 abstention.
February 12, 1991
SUBDIVISION
ITEM NO.: 21 - OTHER MATTERS
NAME: Summit Mall PCD - Time Extension Request
LOCATION: Southwest corner of the I-430 & Shackleford Road
DEVELOPER: Jim Wilson and Associates
REOUUE_ST :
A three year extension for Summit Mall project.
REASON FOR REQUEST:
Difficulty in obtaining the financial commitments under the
current economic conditions to proceed with this major
development.
STAFF RECOM-KENDATIONS:
Staff recommends approval of Jim Wilson's request.
SUBDIVISION COMMITTEE MEETING (January 31, 1991)
The applicant agent was present. The subdivision committee
accepted Mr. McGetrick's request.
PLANNING COMMISSION ACTION (February 12, 1991)
There were no objectors in attendance. The application was
represented. After a brief discussion, the Commission
determined it appropriate to place this item on the consent
agenda for approval. A motion was made to that effect and
passed by a vote of 10 ayes, 0 nays, and 1 absent.
1
November 3, 1987
SUBDIVISIONS
Item No. 12
NAME:
LOCATION:
DEVELOPER:
Austin Dev. Co.
2216 43rd
Meridian, MS 39305
Phone: 601-693-2703
AREA: 97.446 acres
The Summit "Long -Form PCD"
(Z-4923)
West Side of Shackleford Road
Between I-430 and West 36th
RNGTNRRR
Lawrence Beame
Kober/Bellaschi Assoc.
353 Alcazar Avenue
Coral Gables, FL 33134
ZONING: "0-2" PROPOSED USE: PCD
A. Developmental Concept
FT. NEW STREET: 0
This submittal describes plans for a mixed use
development of office, hotel, and retail to be located
on 97.446 acres at the intersection of Shackleford Road
and I-430. A two-level retail galleria in the center
of the highest level will be the focal point; and glass
enclosed entrances will provide a welcome atmosphere.
The developer has listed several major design features
and plan components which will include:
(1) Internalized ring road.
(2) Two phased project with off-site improvements to
be constructed in Phase I. Site grading
accomplished during initial phase so that building
construction during the second phase will require
minimal disruption.
(3) Only four points of access to Shackleford in the
3,000 linear feet of spacing, whereas the City
regulations allow for ten.
(4) Cut and fill has been minimized.
November 3, 1987
SUBDIVISIONS
Item No. 12 - Continued
(5) Perimeter Open Space
Treatment of landscaped areas and natural buffer
areas ranging in width from 50' to 1001. A true
survey has been done to reflect the number and
location of large species of trees to be
retained.
(6 ) Intense landscaping of open space and parking in
excess of City requirements.
(7) Pedestrian connections between major use ares
within the site and covered walkways and bridges
to facilitate encouraging pedestrian movement.
(8) Preservation of an approximate two acre lake as a
focal point for major office development and will
serve as primary detention facility.
(9) Improvements include reconstruction of Shackleford
Road to a five -lane section of installation of
five traffic signals - cost in excess of
$1 million.
(10) Less traffic inpact than an office development
since it is spread out over more hours of the day.
B. Quantitative Data
Gross Acreage
97,446 acres
Right -of -Way
Dedication
2.016 acres
Net acreage
95,430 acres
Use
Area
Levels
Parking
Office
111,667
6
111,667
6
111,667
6
335,000
sq.
ft.
6
840
Retail
975,000
sq.
ft.
ft.
6
10 (type)
4,625
280
Hotel
190,000
sq.
(250 room)
Restaurant
20,000
sq.
ft.
1
200
1
1,470,000
2
5,945
November 3, 1987
SUBDIVISIONS
Item No. 12 - Continued
C. Enqineering Comments
D.
Will discuss at meeting -
Staff Recommendation
Reserved until further information provided. The main
issue involves land use and amendment of the I-430
plan. Other issues involve phasing of traffic and
excavation and grading.
Staff, therefore, feels that a mixed used development
is compatible with the surrounding area versus the
straight commercial development. The proposal
represents a reasonable use of property at this highway
interchange with very little long-term exposure to
residential uses. The plan also includes extensive
landscaping and buffering along the highway. The
sit-down restaurants are not as conducive to strip
commercial as the previously proposed fast food
restaurants.
The report on the traffic information submitted is
needed from Engineering. Staff does feel that the
extent of excavations and fills seems excessive. The
applicant should add terracing of the parking areas.
E. Subdivision Committee Review
The applicant was present. Staff reported that a
letter had been reviewed from Aldersgate requesting
deferral until they had further time to study the
situation. The engineer, Pat McGetrick, stated that
they were working to develop ponds to minimize runoff
to Aldersgate.
Staff felt that the plan indicated excessive grading
and that more terracing should be provided.
SUBDIVISIONS
PLAN14INQ COMMISSION ACTI0I4.
The Applicant was present. The Planning Director called on
Jim Lawson to make the staff presentation, and reported that
City Manager Tom Dalton desired to make a statement. Mr.
Dalton addressed questions that had been previously raised,
concerning the involvement of the City Manager's Office in
this issue. He explained that his involvement was justified
on projects of this magnitude that involved multiple issues
such as land use and zoning, traffic flow, transportation,
aesthetics and public improvements that involved a number of
City departments; and commitments close to 1.5 million
dollars. His role was to coordinate the several meetings
held between the City's various departments and the
developer, and to ensure that the administration spoke with
one voice regarding the proposal; especially since there had
also been prior complaints as to the City's actual position.
Mr. Lawson stated staff's recommendation as approved,
subject to several agreements made by the Developer.
Agreements made include:
(1) Ensuring that there is no ground runoff problems
that would affect Camp Aldersgate and that the
water quality would be checked periodically.
(2) Improve Shackleford to 5 lanes and a contribution
of 1.5 million dollars to the City for the
widening and 5 traffic signals.
(3) Preservation of as many trees as possible.
(4) No grading of the site or cutting of the trees
until assurance is given that the money is
available for development. The preliminary
will be approved now but, before any work can
be done on the site, they have to present their
final plans.
(5) Donation of $240,000 worth of fill materials.
The City is looking at the possibilty of having
an interchange built at I-430 and 36th Street.
This will save taxpayers a tremendous amount
of money due to the amount of dirt that has to
be moved to this site. They are requiring that
within 1 year or 18 months when they begin the
project, the City should have the site determined
so as not to inhibit the progress of their
development.
(6) A $10,000 cash contribution to help fund an
engineering study for the interchange. The
interchange is for the whole of West Little Rock
since it is growing very rapidly and there
is now a traffic problem on I-630, so other.
options need to be explored very soon.
Several persons spoke in regard to the project. Those
representing the project included: Mr. Webb Hubbell of the
Rose Law Firm; Ron Mastriana, who represented the Developer,
Larry Beame-Architectural Firm; Merle Seaman -Landscape
Architect; Ernie Peters -Traffic Engineer; and Patrick
McGetrick, the local Engineer. Those offering favorable
comments included: Mr. Ron Hackleman, the General Manager
of Roger Properties, Mr. Patrick Herndon representing
Property Owners in in Pecan Lake, Colonel Glenn and the
South Stagecoach area.
Mr. Doug Strock represented the Sandpiper Property Owners
Association. He requested deferral. Their concerns
involved traffic, Little Rock's ability to support this
development, and the types of -stores to be put into the
mall.
Mr. Joe Davis was concerned about security and did not feel
that this was a proper location for this type of
development.
Mr. David Worley, President of NOBLE encouraged
reexamination of the traffic study; and disencouraged
speedily dismissing the City's I-430 plan.
Mr. James Stuckley expressed fears that Peachtree would
become a thoroughfare for people wanting to get to the mall,
thereby creating negative effects on Sandpiper Subdivision.
Finally, a vote for approval was made and passed by a vote
of 8 ayes, 1 noes, 1 absent, 1 abstention.
ITEM NO. 12 - THE SUMMIT PCD
FINAL STAFF RECOMMENDATION:
After much review and discussion of the Summit PCD project, the staff
recommends approval of the rezoning.
The staff has had numerous meetings with the developers since the
Subdivision Committee meeting and have finalized the City staff's
requirements for the project. Their approval recommendation includes
the developer's commitments outlined in the attached letters from
Ron Mastriana dated October 23, 1987, November 2, 1987 and November 3,
1987.
November 3, 1987
SUBDIVISIONS
Item No. 12
NAME:
LOCATION -
DEVELOPER:
Austin Dev. Co.
2216 43rd
Meridian, MS 39305
Phone: 601-693-2703
AREA: 97.446 acres
The Summit "Long -Form PCD"
(Z-4923)
West Side of Shackleford Road
Between I-430 and West 36th
ENGINRRR :
Lawrence Beame
Kober/Bellaschi. Assoc.
353 Alcazar Avenue
Coral Gables,. FL 33134
ZONING: "0-2" PROPOSED USE: PCD
A. Developmental Concept
FT. NEW STREET: 0
This submittal describes plans for a mixed use
development of office, hotel, and retail to be located
on 97.446 acres at the intersection of Shackleford Road
and I-430. A two-level retail galleria in the center
of the highest level will be the focal point; and glass
enclosed entrances will provide a welcome atmosphere.
The developer has listed several major design features
and plan components which will include:
(1) Internalized ring road.
(2) Two phased project with off-site improvements to
be constructed in Phase I. Site grading
accomplished during initial phase so that building
construction during the second phase will require
minimal disruption.
(3) Only four points of access to Shackleford in the
3,000 linear feet of spacing, whereas the City
regulations allow for ten.
(4) Cut and fill has been minimized.
November 3, 1987
SUBDIVISIONS
Item No. 12 - Continued
(5) Perimeter Open Space
Treatment of landscaped areas and natural buffer
areas ranging in width from 50' to 100'. A true
survey has been done to reflect the number and
location of large •species • of trees to be
retained.
(6) Intense landscaping of open space and parking in
excess of City requirements.
(7) Pedestrian connections between major use ares
within the site and covered walkways and bridges
to facilitate encouraging pedestrian movement.
(8) Preservation of an approximate two acre lake as a
focal point for major. office development and will
serve as primary detention facility.
(9) Improvements include reconstruction of Shackleford
Road to a five -lane section of installation of
five traffic signals - cost in excess of
$1 million.
(10) Less traffic inpact than an office development
since it is spread out over more hours of the day.
B. Quantitative Data
Gross Acreage 97,446 acres
Right -of -Way Dedication 2.016 acres
Net Acreage 95,430 acres
Use Area Levels Parking
Office
111,667
6
111,667
6
111,667
6
335,000
sq.
ft.
6
840
Retail
975,000
sq.
ft.
6
4,625
Hotel
190,000
sq.
ft.
10 (type)
280
(250 room)
Restaurant
20,000
sq.
ft.
1
1
200
1,470,000
2
5,945
November 3, 1987
SUBDIVISIONS
Item No. 12 - Continued
C. Engineering Comments
Will discuss at meeting
D. Staff Recommendation
Reserved until further information provided. The main
issue involves land use and amendment of the I-430
plan. Other issues involve phasing of traffic and
excavation and grading.
Staff, therefore, feels that a mixed used development
is compatible with the surrounding area versus the
straight commercial development. The proposal
represents a reasonable use of property at this highway
interchange with very little long-term exposure to
residential uses. The plan also includes extensive
landscaping and buffering along the highway. The
sit-down restaurants are not as conducive to strip
commercial as the previously proposed fast food
restaurants.
The report on the traffic information submitted is
needed from Engineering. Staff does feel that the
extent of excavations and fills seems excessive. The
applicant should add terracing of the parking areas.
E. Subdivision Committee Review
The applicant was present. Staff reported that a
letter had been reviewed from Aldersgate requesting
deferral until they had further time to study the
situation. The engineer, PatrlcGetrick, stated that
they were working to develop ponds to minimize runoff
to Aldersgate.
Staff felt that the plan indicated excessive grading
and that more terracing should_be provided.
SUBDIVISIONS
PLANNING COMMISSION ACTIQN_
The Applicant was present. The Planning Director called on
Jim Lawson to make the staff presentation, and reported that
City Manager Tom Dalton desired to make a statement. Mr.
Dalton addressed questions that had been previously raised,
concerning the involvement of the City Manager's Office in
this issue. He explained that his involvement was justified
on projects of this magnitude that involved multiple issues
such as land use and zoning, traffic flow, transportation,
aesthetics and public improvements that involved a number of
City departments; and commitments close to 1.5 million
dollars. His role was to coordinate the several meetings
held between the City's various departments and the
developer, and to ensure that the administration spoke with
one voice regarding the proposal; especially since there had
also been prior complaints as to the City's actual position.
Mr. Lawson stated staff's recommendation as approved,
subject to several agreements made by the Developer.
Agreements made include:
(1) Ensuring that there is no ground runoff problems
that would affect Camp Aldersgate and that the
water quality would be checked periodically.
(2) Improve Shackleford to 5 lanes and a contribution
of 1.5 million dollars to the City for the
widening and 5 traffic signals.
(3) Preservation of as many trees as possible.
(4) No grading of the site or cutting of the trees
until assurance is given that the money is
available for development. The preliminary
will be approved now but, before any work can
be done on the site, they have to present their
final plans.
(5) Donation of $240,000 worth of fill materials.
The City is looking at the possibilty of having
an interchange built at I-430 and 36th Street.
This will save taxpayers a tremendous amount
of money due to the amount of dirt that has to
be moved to this site. They are requiring that
within 1 year or 18 months when they begin the
project, the City should have the site determined
so as not to inhibit the progress of their
development.
(6) A $10,000 cash contribution to help fund an
engineering study for the interchange. The
interchange is for the whole of West Little Rock
since it is growing very rapidly and there
is now a traffic problem on I-630, so other
options need to be explored very soon.
Several persons spoke in regard to the: project. Those
representing the project included: Mr. Webb Hubbell of the
Rose Law Firm; Ron Mastriana, who represented the Developer,
Larry Beame-Architectural Firm; Merle Seaman=Landscape
Architect; Ernie Peters -Traffic Engineer; and Patrick
McGetrick, the local Engineer. Those offering favorable
comments included: Mr. Ron Hackleman, the General Manager
of Koger Properties, Mr. Patrick Herndon representing
Property Owners in in Pecan Lake, Colonel Glenn and the
South Stagecoach area.
Mr., Doug Strock represented the Sandpiper Property Owners
Association. He requested deferral. Their concerns
involved traffic, Little Rock's ability to support this
development, and the types of .stores to be put into the
mall.
Mr. Joe Davis was concerned about security and did not feel
that this was a proper location for this type of
development.
Mr. David Worley, President of NOBLE encouraged
reexamination of the traffic study; and disencouraged
speedily dismissing the City's I-430 plan.
Mr. James Stuckley expressed fears that Peachtree would
become a thoroughfare for people wanting to get to the mall,
thereby creating negative effects on Sandpiper Subdivision.
Finally, a vote for approval was made and passed by a vote
of 8 ayes, 1 noes, 1 absent, 1 abstention.