From:Hood, Mike
Sent:Tuesday, November 15, 2022 12:31 PM
To:Malone, Walter
Cc:Honeywell, Jon; Floriani, Vince; Petty, Eric
Subject:Proposed Annexation Crystal Valley Road at Col Miller Road
Attachments:PRELIMINARY PLAT 6-14-21.pdf; Crystal Valley Col Miller Annexation Cost
Discussion.docx; Miles of Streets and other Stats LR 2021.jpg; Crystal Valley Col Miller
Annexation Street Cost.xlsx
Here is our proposed response to the inquiry about the cost to service the proposed annexation.
From: Malone, Walter <WMalone@littlerock.gov>
Sent: Tuesday, November 15, 2022 9:39 AM
To: Hood, Mike <Mhood@littlerock.gov>
Subject: Plat for A-342
This is the approved plat for the annexation. The Developer says they will plat the first 75 to 90 lots after about 6
months from annexation. We are assuming the first houses would come on line about 6 months later. After discussion
with Joe White we are using 30 houses per year as the added units.
Proximately 1971 linear feet of Crystal Valley Road would be included. The plat approval required 1200 linear feet to be
improved with phase 1 (eastern side of the north side of Crystal valley Road). The remained is with Phase V of the
development.
Walter Malone, AICP
Planning Manager