HomeMy WebLinkAboutZ-4391 Staff AnalysisJanuary 21, 1985
Item No. 5 - Z-4391
Owner:
Address:
Description:
Zoned:
Variance
Requested:
JUSTIFICATION:
First Commercial Bank
East 9th Street at I-30
Lots 1,, 2, 3, 11 and 12, Block 12,
Woodruff's Addition
"C-3" General Commercial
From the side yard setback
provisions of Section 7-103.3/D.2 to
permit a new building with side
yards of 9.5 feet and 18.5 feet
(ordinance requires 25 feet)
1. The proposed structure is further back from the
right-of-way lines than the existing bank.
2. The I-30 acquisition has created a narrow site, too
narrow for 25 -foot setbacks.
Present Use
of the Property: Branch bank
Proposed Use
of the Property: Same
STAFF REPORT:
A. Engineering Issues
None reported at this time.
B. Staff Analysis
The proposal is replace the existing branch bank with a
new structure. The present facility is located on the
southern one-half of the property, situated right on
the east property line. The current drive-through
tellers are located to the south of the building, and
this is not the most ideal situation for traffic
movement and circulation. The new structure will be
more centrally located on the site and be an
improvement over the existing conditions because of
increasing the setback on the east side and upgrading
the site's circulation. The drive-through tellers will
January 21, 1985
Item No. 5 - Z-4391
be located to the north of the proposed building,
will be a more desirable location than the currentwhich one.
The new site plan makes better use of the tract that
has been impacted by I-30 and having street frontage on
three sides. The ordinance requires that on a corner
lot, the side yard on the street side or exterior side
shall be equal to the front yard setback. Because of
right-of-way,it is impossible to maintain the
required
ired setbackss an the three sides. Staff supports
the variance because the applicant has provided
adequate justification, and a hardship does exist. One
additional point, the existing structure will be
removed after the new building is completed.
C. Staff Recommendation
Staff recommends approval of the requested variance.
BOARD OF ADJUSTMENT ACTION:
The applicant, Bill Ruck, was present. Thera were no
objectors in attendance. Mr. Ruck spoke briefly about the
request. A motion was made to approve the variance,
sugbject to the building location being clarified for the
wastewater utility and the Traffic Engineer's approval of
access, parking, curb cuts and circulation. The motion
passed by a vote of: 8 ayes, 0 noes and 1 absent.
January 21, 1985
Item Mn- 5 - Z-4391
Owner:
Address:
Description:
Zoned:
Variance
Requested:
JUSTIFICATION:
First Commercial Bank
East 9th Street at I-30
Lots 1, 2, 3, 11 and 12, Block 12,
Woodruff's Addition
"C-3" General Commercial
From the side yard setback
provisions of Section 7-103.3/D.2 to
permit a new building with side
yards of 9.5 feet and 18.5 feet
(ordinance requires 25 feet)
1. The proposed structure is further back from the
right-of-way lines than the existing bank.
2. The I-30 acquisition has created a narrow site, too
narrow for 25 -foot setbacks.
Present Use
of the Property: Branch bank
Proposed Use
of the Property: Same
STAFF REPORT:
A. Enqineering Issues
None reported at this time.
B. Staff Analysis
The proposal is replace the existing branch bank with a
new structure. The present facility is located on the
southern one-half of the property, situated right on
the east property line. The current drive-through
tellers are located to the south of the building, and
this is not the most ideal situation for traffic
movement and circulation. The new structure will be
more centrally located on the site and be an
improvement over the existing conditions because of
increasing the setback on the east side and upgrading
the site's circulation. The drive-through tellers will
January 21, 1985
Item No. 5 - Z-4391
be located to the north of the proposed building, which
will be a more desirable location than the current one.
The new site plan makes better use of the tract that
has been impacted by I-30 and having street frontage on
three sides. The ordinance requires that on a corner
lot, the side yard on the street side or exterior side
shall be equal to the front yard setback. Because of
I-30 right-of-way, it is impossible to maintain the
required setbacks on the three sides. Staff supports
the variance because the applicant has provided
adequate justification, and a hardship does exist. One
additional point, the existing structure will be
removed after the new building is completed.
C. Staff Recommendation
Staff recommends approval of the requested variance.
BOARD OF ADJUSTMENT ACTION:
The applicant, Bill Ruck, was present. There were no
objectors in attendance. Mr. Ruck spoke briefly about the
request. A motion was made to approve the variance,
sugbject to the building location being clarified for the
wastewater utility and the Traffic Engineer's approval of
access, parking, curb cuts and circulation. The motion
passed by a vote of: 8 ayes, 0 noes and 1 absent.