HomeMy WebLinkAboutZ-4305-C Staff AnalysisJuly 23, 1998
ITEM NO.: I FILE NO.: Z -43Q5 -C
NAME: Riddick - Zoning Site Plan Review
LOCATION: 2300 Cottondale Lane
DEVELOPER:
ENGINEER•
June Riddick Riddick Engineering Corp.
#7 Greenbrier Rd. First Commercial Barak Bldg.
Little Rock, AR 72202 Little Rock, AR 72201
AREA: 2.25 Acres NUMBER OF LOTS: 1 FT. NEW STREET: 0
ZONING: 0-2 ALLOWED USES: Office
PROPOSED USE: Office
VARIANCE /WAIVERS REQUESTED:
1. A variance to allow a reduced side yard setback along the
west property line.
2. A variance for reduced setback from the floodway line.
(25 foot setback required; 2 foot setback proposed.)
BACKGROUND:
The 2.25 acre tract (Tract F -2B, Riverdale Addition) contains a
sump and a portion of the levee, adjacent to the Arkansas River.
There is also a pump house on the property.
A large amount of the stormwater for the Riverdale area drains
into the sump and is pumped into the river.
A. PROPOSAL RE UEST:
The applicant proposes to construct a four-story, 34,020
square foot office building on the site, which will be built
into the levee, similar to the Edgewater Building to the
east. The first level of the building will be an indoor
parking garage for approximately 31 vehicles, with 3 levels
Of office space. An additional 57 parking spaces and access
drive will be constructed along the southern. western and
northern perimeter of the sump. The applicant will also acid
a third pump, as required by the levee improvement district,
to enhance stormwater drainage.
E.
s, 1998
VISION
. NO.: I _(Cont.) FILE NO • Z -4305-C
EXISTING CONDITIONS:
The site is undeveloped and overgrown with grass and weeds.
There is an office building located east and west of the
site, with the Arkansas River located to the north.
Undeveloped 0-2 zoned property is located to the south
across Cottondale Lane.
NEIGHBORHOOD COMMENTS:
Staff has received one (1) informational phone call as of
this writing. The Hillcrest and Capitol View Stifft Station
Neighborhood Associations were notified of the public
hearing.
ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Sidewalks shall be shown conforming to Sec. 31-175 and
the "MSP",
2. A sketch grading and drainage plan, a special flood
hazard permit, and a special grading permit for flood
hazard areas are required. Arkansas Department of
Pollution Control and Ecology (ADPCE) and NPDES permit
are also required.
3. Contact Levee District -Engineer for approval and provide
approval to Public Works.
4. Utility excavation within proposed rights-of-way shall
be per Article V of Sec. 30.
5. Driveways shall conform to Sec. 31-210 or Ordinance
16,577.
6. FEMA approval required.
7. The applicant needs to request a waiver from the
required 25 foot setback from the floodway.
UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer located on southwest side of Cottondale
Lane. Contact Little Rock Wastewater Utility prior to
construction.
AP&L: No Comment.
ARKLA : No Comment.
Southwestern Bell: No Comment.
Water: On site fire protection may be required.
KI
July 23, 1998
UBDIVISION
ITEM NO.: I Cont,
Fire Department:
Count Plannin :
F.
G.
FILE
No Comment.
No Comment received.
-4305-C
LATA: Served by Route #21 - University Avenue.
pathway connecting to Riverfront Dr.?Is A walkway would a
provide more convenient access to ##21 for pedestrians and
encourage more ridership among the many business -persons in
the area.
ISSUES/TECHNICAL DESIGN:
Plannxn Division: No Comment.
Landscape Issues:
The plan submitted does not provide for the 17 foot wide
street buffer nor the 6 foot wide landscape strip
requirements by the zoning buffer and landscape ordinances.
Nor does it Provide for the minimum 4 foot wide landscape
strip northwest of the proposed parking area. However, the
proposal far exceeds the area of interior landscaping
required.
It will be necessary to obtain a variancf: from the City
Beautiful Commission before minimum Landscape Ordinance
requirements can be reduced or deleted.. To make application
to seek this approval, contact Bob Brown, Plans Review
Specialist. He may be reached at 371-4864.
ANA_ L
The applicant submitted a revised site plan to staff on May
27. 1998. The applicant also submitted letters from the
Army Corps of Engineers and the Riverdale Levee District.
(See attached letters.) The Army Corps of Engineers
approves the proposed site Plan and the Riverdale Levee
District approves of the site plan concept. However, the
Riverdale Levee District notes that several detailed plans,
including finished contours, earthwork
sump, geotechnical information and structural of within the
building, must be reviewed and a tr ct the
approved by the District.
The 34,020 square foot office building
spaces. The revisedevised plan shows 88 g requires 85 parking
the first floor parkin Parking spaces (31 within
the sump), g garage and 57 along the perimeter of
The applicant is requesting a variance to allow a reduced
side yard building setback along the west side. The
required setback is 25 feet and the proposed setback is 19
3
H.
July 23, 1998
SUBDIVISION
V
Z-43QN-
feet. Otherwise, the building conforms to the ordinance
setback requirements. The applicant is proposing a building
height of 71 feet.
The applicant is also requesting a waiver of the sidewalk
requirement along Cottondale Lane. The applicant notes that
the adjacent property does not have a sidewalk and the
installation of a sidewalk will require removal of specimen
Bradford Pear trees which exist along Cottondale Lane.
Public Works recommends denial of the waiver request.
Public Works has indicated that a deferral of sidewalk
construction, until construction of sidewalk on adjacent
property, will be supported.
The applicant has also applied to the City Beautiful
Commission for a waiver of the required buffer and
landscaping along the western perimeter of the site and the
street side perimeter. The City Beautiful Commission has
the authority to waive landscape requirements.
Public Works has noted that a FEMA permit will be required.
Public works also notes that the applicant needs to request
a waiver from the required 25 foot setback -from the
floodway.
The applicant will also install a diesel pump which will
Provide additional capacity to overcome the loss of water
storage due to filling which will be done along the
perimeter of the sump to accommodate the proposed parking
and driveways.
It is very evident that the applicant has additional work to
do (provide detailed plans to Riverdale Levee District,
obtain FEMA permit, Board of Directors waiver of sidewalk
requirement and City Beautiful waiver of landscaping) before
a building permit can be issued for the site. Staff
recommends a conditional approval of the site plan as
submitted, granting the applicant 6 months to work out the
outstanding issues noted above. If, in resolving any of
these issues the site plan is significantly changed, the
site plan will be brought back to the Commission.
STAFF RECOMMENDATIONS:
Staff recommends a conditional approval of the site plan
subject to the following conditions:
I. Compliance with the requirements noted in paragraphs D,
E and F of this report.
4
July 23, 1998
SUBDIVISION
ITEM NO.: I (Cont.) FILE NO.: Z-4305-
2.
-4305 2. Staff recommends approval of the side yard setback
variance.
3. Staff recommends denial of the requested waiver of
sidewalk.
4. The applicant will have 6 months to complete the
necessary steps in order to qualify for a building
permit.
a. Submit all required information to the Riverdale
Levee District and receive a final letter of
approval from the District.
b. Receive a waiver (or deferral) of required sidewalk
from the Little Rock Board of Directors or submit
plans showing planned construction of the sidewalk.
c. Receive approval from the City Beautiful Commission
on the waiver of required perimeter buffers and
landscaping.
d. Obtain a FEMA permit.
5. If any of the above issues cause the site plan to
significantly change (for example, shifting the drive
and/or parking further into the sump area) the site plan
will be brought back before the Commission.
SUBDIVISION COMMITTEE COMMENT: (MAY 21, 1998)
June Riddick was present, representing the application. Staff
gave a brief description of the site plan.
Staff noted that letters from the Riverdale Levee Improvement
District #134 and the Army Corps of Engineers approving the
proposed construction would need to be submitted to staff. Staff
also noted that a section through the property would need to be
submitted.
The Public Works requirements were briefly discussed. Mrs.
Riddick noted that a waiver of the required sidewalk may be
requested, in order to save the existing trees and landscaping
along Cottondale Lane.
Bob Brown, Site Plan Review Specialist, noted that the proposed
variance from the ordinance required landscaping would have to be
approved by the City Beautiful Commission.
After the discussion, the Committee forwarded the site plan to
the full Commission for final action.
July 23, 1998
SUBDIVISION
ITEM NO.: I Cont. FILE NO.: Z -4305-C
PLANNING COMMISSION ACTION: (JUNE 11, 1998)
June Riddick was present, representing the application. There
was one person present with concerns. Staff gave a brief
description of the site plan and a recommendation of conditional
approval.
June Riddick addressed the Commission in support of the
application. She noted several changes in the site plan relating
to parking and a second drive from Cottondale Lane. She noted
that the sump area would be used as a sunken garden with a
fountain.
Bob Turner, of Public Works, noted that there is not enough
street frontage to support two entrances.
There was a brief discussion concerning changes in the site plan.
Jim Lawson, Director of Planning and Development, stated that
there were major issues involved with this development, primarily
the levee district approval.
Chairman Lichty asked how the Commission could,'make a decision on
the site plan without final approval from the levee district.
Mr. Lawson stated that there were two ways to deal with the
application:
1. Not act on the application until all approvals have been
granted, thereby deferring the application, or
2. Approving the concept of the site plan and allowing the
applicant time to resolve the remaining issues.
Commissioner Rahman asked about the setback from the floodway.
Bob Turner stated that the proposed building is out of the
floodway but it does not meet the required 25 foot setback from
the floodway. He stated that Mrs. Riddick has requested a
setback variance.
Commissioner Berry asked how people will get from the parking lot
to the building.
Mrs. Riddick stated that there will be a walkway through the sump
to the building.
There was a brief discussion concerning the Corps of Engineers
and the Levee District approvals. There was also discussion
concerning the sidewalk waiver which has been requested.
A
July 23, 1998
SUBDIVISION
ITEM No.: I Cont.
FILE No-- Z-4305
Bob East addressed the Commission with concerns. He stated that
he developed the Edgewater building to the east. He noted that
he had not seen a site plan prior to this meeting and had also
asked to see elevations. He asked the Commission to defer the
item in order to give the levee district engineer
time to
review the site plan. He also noted that hethoughtrthat Mrs.
Riddick was trying to overbuild the site.
Mr. Lawson stated that based on the comments by Mr. East and the
Possible concerns of other property owners in the area, staff
would recommend that the item be deferred.
There was a brief discussion regarding the possibility of
deferring the item.
Chairman Lichty asked Mrs. Riddick if she would agree to a
deferral.
Mrs. Riddick stated that she would agree to the deferral.
A motion was made to defer the item to the July 23, 1998 agenda.
The motion passed by a vote of 9 ayes, 0 nays and 2 absent.
STAFF UPDATE:
The applicant submitted a revised site plan to staff as a result
of the City Beautiful Commission meeting held on July 2, 1998.
The revised plan shows a 4 foot landscape buffer along the west
side property line and a 4 foot landscape buffer along the street
side property line as required by the City Beautiful Commission.
The revised site plan also shows the 10 foot by 14 foot addition
to the existing pump house which will accommodate the new pump as
originally proposed with this application.
The applicant has committed to construct the sidewalk along
Cottondale Lane as required by Public works. The sidewalk will
be constructed behind the existing landscape strip along
Cottondale Lane (within the right-of-way) and the existing
landscaping will not be disturbed.
The applicant has also requested a variance for reduced setback
from the floodway line (25 foot setback required; 2 foot setback
Proposed). Public Works supports the variance request.
As of this writing, the applicant is awaiting a final letter of
approval from the Riverdale Levee District.
7
July 23, 1998
SUBDIVISION
ITEM No.: I (Cont.
V
Z-4305
SUBDIVISION COMMITTEE COMMENT:
(JULY 2, 1998 )
June Riddick and Tim Daters were present, representing the
application. Staff noted that as a result of the City Beautiful
Commission meeting (July 2, 1998) the site plan has been slightly
revised. The revised plan shows the 4 foot landscape buffers
along the west side property line and front (street) side
property line as required by the City Beautiful Commission.
Mr. Daters noted that the revised plan also shows the addition to
the pump station that will be needed to accommodate the proposed
new pump.
Mr. Daters noted that he is continuing to work with the Levee
District. He noted that the approval letter will be forthcoming.
Mrs. Riddick stated that she would construct the sidewalk along
Cottondale Lane as required by Public Works. She also noted that
there would be no landscaping installed within the sump area.
After the brief discussion, the Committee forwarded the issue to
the full Commission for final action.
F
July 23, 1998
SUBDIVISION
ITEM NO.: I Cont. FILE NO.: z -4305-C
SUBDIVISION COMMITTEE COMMENT: (JULY 2, 1998)
June Riddick and Tim Daters were present, representing the
application. Staff noted that as a result of the City Beautiful
Commission meeting (July 2, 1998) the site plan has been slightly
revised. The revised plan shows the 4 foot landscape buffers
along the west side property line and front (street) side
property line as required by the City Beautiful Commission.
Mr. Daters noted that the revised plan also shows the addition to
the pump station that will be needed to accommodate the proposed
new pump.
Mr. Daters noted that he is continuing to work with the Levee
District. He noted that the approval letter will be forthcoming.
Mrs. Riddick stated that she would construct the sidewalk along
Cottondale Lane as required by Public Works. She also noted that
there would be no landscaping installed within the sump area.
After the brief discussion, the Committee forwarded the issue to
the full Commission for final action.
PLANNING COMMISSION ACTION: (JULY 23, 1998)
Staff presented a positive recommendation on this application, as
there were no further issues for resolution. There were no
objectors to this matter.
Staff informed the Commission that a final letter of approval had
been received by the Riverdale Levee District. Staff also
informed the Commission that a minor height variance was also
requested, with the proposed building being a height of 50 feet.
Staff recommended approval of this variance.
The Chairman placed the item before the Commission for inclusion
within the Consent Agenda for approval as recommended by staff,
with the letter from the Riverdale Levee District being included
as an additional condition of approval. A motion to that effect
was made. The motion passed by a vote of 11 ayes, and 0 nays.
July 2, 1998
ITEM NO.2 - C.B.C. 560 -NEW MATTERS
Applicant:
Address:
Description:
ORDINANCE REQUIREMENTS:
June Riddick, Owner
Riddick Office Building
2300 Cottondale Lane
Lot F -2B, Riverdale Addition
Area of Tract F -2B
1. A perimeter planting strip shall be required along any side of a vehicular use area that abuts
adjoining property or the right-of-way of any street, highway or freeway. This strip shall be at
least six (6) feet wide.
2. One (1) tree and four (4) shrubs or vines for every forty (40) linear feet shall be planted in the
perimeter planting strip.
3. Up to one-third (1/3) of the perimeter planter area and associated trees and shrubs can be shifted
from one (1) area of the site to another, for the purpose of improving visual esthetics or for other
appropriate environmental concerns.
VARIANCE REQUESTED:
To not require the minimum four (4) foot wide perimeter landscape strip and associated trees along the
southern, western and a portion of the eastern perimeter of the proposed parking areas.
FINDINGS:
This 2.25 acre tract contains a sump and a portion of the Arkansas River Levee. Much of the stormwater
of the Riverdale area drains into this sump which is then pumped into the river.
The applicant purposes to build a four level office structure with the first level to be used for parking.
The site is undeveloped and overgrown with grass and weeds. Office buildings are located to the east and
west of this site. The Arkansas River is located to the north.
The applicant purposes to plant vines on the existing six (6) foot high chain link fence around the perimeter
of the site and to plant three trees within the rip -rap area along the corners of the sump. Cat tails and
aquatic plants are planned to remain within the sump.
There are existing Bradford pear trees and photinias within the public right-of-way in front of this property
and additional landscaping immediately to the east and west of the site.
Because of the properties office and institutional zoning, Planning Commission approval is required. Final
disposition of this matter is set for July 23, 1998.
STAFF RECOMMENDATION:
Staff recognizes the difficulty with development when not over fifty (50) percent of the site is allowed to be
disturbed.
Staff recommends a reduction in perimeter landscaping width but not a deletion.
Staff will suppm a reduction.in perimeter landscape width to two (2) feet provided the applicant will (in
addition to landscaping proposed):
1. Install a total of three (3) additional trees between those proposed along the perimeter of the sump.
2. Replace fallen Bradford pear tree within the public right-of-way.
3. Provide shrubs or trees along the top of sump around proposed eastern parking lot.
July 23, 1998
STEM NO.: I
FILE Nd. Z -4305-C
NAME: Riddick - Zoning Site Plan Review
LOCATION: 2300 Cottondale Lane
DEVELOPER:
ENG.INNEER:
June Riddick Riddick Engineering Co
#7 Greenbrier Rd. First Commercial Bank Bldg,
Little Rock, AR 72202 Little Rock, AR 72201
AREA: 2.25 Acres NUMBER OF LDTS• 1
FT. NEW STREET; 0
ZONING • 0-2 ALLOWED] IISES
Office
PROPOSED USE: Office
VARIANCES WAi%rERS RE IIESTED:
1• A variance to allow a reduced side yard setback along the
west property line.
2. A variance for reduced setback from the floodway line.
(25 foot setback required; 2 foot setback proposed.)
BACKGROUND:
The 2.25 acre tract (Tract F -2B, Riverdale Addition) contains a
BUMP and a portion of the levee, adjacent to the Arkansas River.
There is also a pump house on the property.
A large amount of the stormwater for -the Riverdale area drains
into the sump and is pumped into the river.
A. PROPOSAL RE QEST:
The applicant proposes to construct a four-stO
square foot Office building on the site, which willghe2built
into the levee similar to the Edgewater Building to the
east. The first level of the building will be an indoor
parking garage for approximately 31 vehicles, with 3 levels
Of office space. An additional 57
parking
drive will be constructed along theSouthern, es and access
northern perimeter Of the sum western and
a third pump, as required by the leveepimprovementldistrict,
to enhance stormwater drainage.
July 23, 1998
SUBDIVISION
ITEM NO.: I Cont. FILE NO.: Z -4305-C
B. EXISTING CONDITIONS:
The site is undeveloped and overgrown with grass and weeds.
There is an office building located east and west of the
site, with the Arkansas River located to the north.
Undeveloped 0-2 zoned property is located to the south
across Cottondale Lane.
C. NEIGHBORHOOD COMMENTS:
Staff has received one (1) informational phone call as of
this writing. The Hillcrest and Capitol View Stifft Station
Neighborhood Associations were notified of the public
hearing.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Sidewalks shall be shown conforming to Sec. 31-175 and
the "MSP",
2. A sketch grading and drainage plan, a special flood
hazard permit, and a special grading permit for flood
hazard areas are required. Arkansas Department of
Pollution Control and Ecology (ADPCE) and NPDES permit
are also required.
3. Contact Levee District Engineer for approval and provide
approval to Public Works.
4. Utility excavation within proposed rights-of-way shall
be per Article V of Sec. 30.
5. Driveways shall conform to Sec. 31-210 or Ordinance
16,577.
6. FEMA approval required.
7. The applicant needs to request a waiver from the
required 25 foot setback from the floodway.
E. UTILITIES AND FIRE DEPARTMENT COUNTY PLANNING:
Wastewater: Sewer located on southwest side of Cottondale
Lane. Contact Little Rock Wastewater Utility prior to
construction.
AP&L: No Comment.
ARKLA: No Comment.
Southwestern Bell: No Comment.
Water: On site fire protection may be required.
K
July 23, 1998
SUBDIVISION
ITEM NO.: I Cont,
Fire Department:
Counter Planninq :
No Comment.
No Comment received.
-_ Z -430 -9 -
LATA: Served by Route #21 -- University Avenue. Is there a
pathway connecting to Riverfront Dr.? A walkway would
Provide more convenient access to ##21 for pedestrians and
encourage more ridership among the many business -persons in
the area.
F. ISSUES TECHNICAL DESIGN:
Plannin, Division: No Comment.
Landscape Issues:
The plan submitted does not provide for the 17 foot wide
street buffer nor the 6 foot wide landscape strip
requirements by the zoning buffer and landscape ordinances.
Nor does it provide for the minimum 4 fo,Dt wide landscape
strip northwest of the proposed parking ,area. However, the
Proposal far exceeds the area of interior landscaping
required.
It will be necessaryto obtain a variances from the City
Beautiful Commission before minimum Landscape Ordinance
requirements can be reduced or deleted. To make application
to seek this approval, contact Bob Brown, plans Review
Specialist. He may be reached at 371-4864.
G. ANALYSIS:
The applicant submitted a revised site plan to staff on May
27, 1998. The applicant also submitted letters from the
Army Corps of Engineers and the Riverdale Levee District.
(See attached letters.) The Army Corps of Engineers
approves the proposed site plan and the Riverdale Levee
District approves of the site plan concept. However, the
Riverdale Levee District notes that several detailed plans,
including finished contours, earthwork quantities within the
sump, geotechnical information and structural design of the
building, must be reviewed and approved by the District.
The 34,020 square foot office building requires 85 parking
spaces. The revised plan shows 88 parking spaces (31 within
the first floor parking garage and 57 along the perimeter of
the sump).
The applicant is requesting a variance to allow a reduced
side yard building setback along the west side. The
required setback is 25 feet and the proposed setback is 19
3
July 23, 1998
SUBDIVISION
00
H.
Z -4305 --
feet. Otherwise, the building conforms to the ordinance
setback requirements. The applicant is proposing a building
height of 71 feet.
The applicant is also requesting a waiver of the sidewalk
requirement along Cottondale Lane. The applicant notes that
the adjacent property does not have a sidewalk and the
installation of a sidewalk will require removal of specimen
Bradford Pear trees which exist along Cottondale Lane.
Public Works recommends denial of the waiver request.
Public Works has indicated that a deferral of sidewalk
construction, until construction of sidewalk on adjacent
Property, will be supported.
The applicant has also applied to the City Beautiful
Commission for a waiver of the required buffer and
landscaping along the western, perimeter of the site and the
street side perimeter. The City Beautiful Commission has
the authority to waive landscape requirements.
Public Works has noted that a FEMA permit will be required.
Public Works also notes that the applicant needs to request
a waiver from the required 25 foot setback from the
floodway.
The applicant will also install a diesel Pump which will
Provide additional capacity to overcome the loss of water
storage due to filling which will be done along the
Perimeter of the sump to accommodate the proposed parking
and driveways.
It is very evident that the applicant has additional work to
do (provide detailed plans to Riverdale Levee District,
obtain FEMA permit, Board of Directors waiver of sidewalk
requirement and City Beautiful waiver of landscaping) before
a building permit can be issued for the site. Staff
recommends a conditional approval of the site plan as
submitted, granting the applicant 6 months to work out the
outstanding issues noted above. If, in resolving any of
these issues the site plan is significantly changed, the
site plan will be brought back to the Commission.
STAFF RECOMMENDATIONS:
Staff recommends a conditional approval of the site plan
subject to the following conditions:
1. Compliance with the requirements noted in paragraphs D,
E and F of this report.
4
July 23, 1998
SUBDIVISION
ITEM NO.: T Cont. FILE NO.: 2-4385-C
2. Staff recommends approval of the side yard setback
variance.
3. Staff recommends denial of the requested waiver of
sidewalk.
4. The applicant will have 6 months to complete the
necessary steps in order to qualify for a building
permit.
a. Submit all required information to the Riverdale
Levee District and receive a final letter of
approval from the District.
b. Receive a waiver (or deferral) of required sidewalk
from the Little Rock Board of Directors or submit
plans showing planned construction of the sidewalk.
c. Receive approval from the City Beautiful Commission
on the waiver of required perimeter buffers and
landscaping.
d. Obtain a FEMA permit.
5. If any of the above issues cause the site plan to
significantly change (for example, shifting the drive
and/or parking further into the sump area) the site plan
will be brought back before the Commission.
SUBDIVISION COMMITTEE COMMENT: (MAY 21, 1998)
June Riddick was present, representing the application. Staff
gave a brief description of the site plan.
Staff noted that letters from the Riverdale Levee Improvement
District #134 and the Army Corps of Engineers approving the
proposed construction would need to be submitted to staff. Staff
also noted that a section through the property would need to be
submitted.
The Public Works requirements were briefly discussed. Mrs.
Riddick noted that a waiver of the required sidewalk may be
requested, in order to save the existing trees and landscaping
along Cottondale Lane.
Bob Brown, Site Plan Review Specialist, noted that the proposed
variance from the ordinance required landscaping would have to be
approved by the City Beautiful Commission.
After the discussion, the Committee forwarded the site plan to
the full Commission for final action.
61
July 23, 1998
SUBDIVISION
ITEM NO.: I Cont. FILE NO.: Z -4305-C
PLANNING COMMISSION ACTION: (JUNE 11, 1998)
June Riddick was present, representing the application. There
was one person present with concerns. Staff gave a brief
description of the site plan and a recommendation of conditional
approval.
June Riddick addressed the Commission in support of the
application. She noted several changes in the site plan relating
to parking and a second drive from Cottondale Lane. She noted
that the sump area would be used as a sunken garden with a
fountain.
Bob Turner, of Public Works, noted that there is not enough
street frontage to support two entrances.
There was a brief discussion concerning changes in the site plan.
Jim Lawson, Director of Planning and Development, stated that
there were major issues involved with this development, primarily
the levee district approval.
Chairman Lichty asked how the Commission could make a decision on
the site plan without final approval from the levee district.
Mr. Lawson stated that there were two ways to deal with the
application:
1. Not act on the application until all approvals have been
granted, thereby deferring the application, or
2. Approving the concept of the site plan and allowing the
.applicant time to resolve the remaining issues.
Commissioner Rahman asked about the setback from the floodway.
Bob Turner stated that the proposed building is out of. the
floodway but it does not meet the required 25 foot setback from
the floodway. He stated that Mrs. Riddick has requested a
setback variance.
Commissioner Berry asked how people will get from the parking lot
to the building.
Mrs. Riddick stated that there will be a walkway through the sump
to the building.
There was a brief discussion concerning the Corps of Engineers
and the Levee District approvals. There was also discussion
concerning the sidewalk waiver which has been requested.
G
July 23, 1998
SUBDIVISION
ITEM NO.: I [Cont.} FILE NC • Z -4305-C
Bob East addressed the Commission with concerns. He stated that
he developed the Edgewater building to the east. He noted that
he had not seen a site plan prior to this meeting and had also
asked to see elevations. He asked the Commission to defer the
item in order to give the levee district engineer more time to
review the site plan. He also noted that he thought that Mrs.
Riddick was trying to overbuild the site.
Mr. Lawson stated that based on the comments by Mr. East and the
possible concerns of other property owners in the area, staff
would recommend that the item be deferred.
There was a brief discussion regarding the possibility of
deferring the item.
Chairman Lichty asked Mrs. Riddick if she would agree to a
deferral.
Mrs. Riddick stated that she would agree to the deferral.
A motion was made to defer the item to the July 23, 1998 agenda.
The motion passed by a vote of 9 ayes, 0 nays and 2 absent.
STAFF UPDATE•
The applicant submitted a revised site plan to staff as a result
of the City Beautiful Commission meeting held on July 2, 1998.
The revised plan shows a 4 foot landscape buffer along the west
side property line and a 4 foot landscape buffer along the street
side property line as required by the City Beautiful Commission.
The revised site plan also shows the 10 foot by 14 foot addition
to the existing pump house which will accommodate the new pump as
originally proposed with this application.
The applicant has committed to construct the sidewalk along
Cottondale Lane as required by Public Works. The sidewalk will
be constructed behind the existing landscape strip along
Cottondale Lane (within the right-of-way) and the existing
landscaping will not be disturbed.
The applicant has also requested a variance for reduced setback
from the floodway line (25 foot setback required; 2 foot setback
proposed). Public Works supports the variance request.
As of this writing, the applicant is awaiting a final letter of
approval from the Riverdale Levee District.
rl