HomeMy WebLinkAboutZ-4283-A Staff AnalysisAugust 26, 2002
ITEM NO.: A
File No.:
Owner:
Address:
Description:
Zoned:
Z -4283-A
Albert Ross Sparks
7825 % Stagecoach Road
Northeast corner of Stagecoach and Sibley
Hole Roads
C-1
Variance Requested: A variance is requested from the area
provisions of Section 36-299 to allow a
building addition with a reduced front yard
setback.
Justification:
Present Use of Property:
Proposed Use of Property:
STAFF REPORT
A. Public Works Issues:
The applicant's justification is presented in
an attached letter.
Office and Catering Business
Office and Catering Business
Stagecoach Road is classified on the Master Street Plan as a major
arterial with a right-of-way width of 55' from centerline. Existing right-of-
way is adequate at the planned building addition, but inadequate at the
northern property boundary.
With the buildin ermit:
a. Dedicate right-of-way to 55' from centerline.
b. Construct boundary street improvements as required by the Master
Street Plan or provide in -lieu contribution for street improvements.
The hardship clause of the ordinance would apply and limit
contribution to 15% of building cost.
C. Stormwater detention ordinance will apply to this expansion.
August 26, 2002
Item No.: A Cont.
B. Landscape and Buffer Issues:
A landscaping upgrade toward compliance with the Landscape Ordinance
equal to the building expansion proposed (29%) will be required.
C. Staff Analysis:
The C-1 zoned property at 7825 Stagecoach Road is occupied by two (2)
existing one-story, brick and frame structures. There is an existing gravel
parking area between the buildings and Stagecoach Road, with an access
drive from Stagecoach Road. There is a catering business located in the
southernmost building, with a contractor's office in the north building.
The property owner proposes to construct a 32 foot by 36 foot building
addition at the north end of the northernmost building for additional office
space. The building addition will be located 9.25 feet from the front (west)
property line. Section 36-299(e)(1) of the City's Zoning Ordinance
requires a minimum front yard setback of 25 feet. Therefore, the property
owner is requesting a variance to allow a reduced front yard setback for
the building addition. All other setbacks for the proposed building addition
conform to ordinance standards.
Staff is not supportive of the requested variance. With the potential for
future widening of Stagecoach Road, staff feels that the proposed building
addition is too close to the street right-of-way. As noted in paragraph A. of
this report, Stagecoach Road is a Principal Arterial on the City's Master
Street Plan, with 55 feet of right-of-way required from centerline. At the
location of the proposed building addition (9.25 foot setback) there is
approximately 57.5 feet of right-of-way for Stagecoach Road. Therefore,
there is only approximately 2.5 feet of excess right-of-way at this point. As
a possible solution, staff suggests designing a building addition for the
south end of the building. Although this may eliminate a small area of
parking between the two buildings, there appears to be a large enough
area of gravel parking along the west side of the buildings to
accommodate the two businesses.
D. Staff Recommendation:
Staff recommends denial of the requested front yard setback variance.
2
August 26, 2002
Item No.: A (Cont.
BOARD OF ADJUSTMENT: (JUNE 24, 2002)
Brian Sparks was present, representing the application. There were no objectors
present. Staff presented the application with a recommendation of denial.
Brian Sparks spoke in support of the application. He explained the reasons for
locating the building addition on the noft end of the building. He noted that he
could make the building addition smaller (24 foot X 32 foot). He explained that
there is a parking area (9-10 spaces) between the two buildings and that he
wished not to lose that parking. There was a general discussion regarding
revising the proposed site plan. Staff indicated support for the possible 24 foot
by 32 foot building addition (revised plan) and explained.
Chairman Ruck asked if there would be windows on the north and east sides of
the proposed building addition. Mr. Sparks stated that there would be no
windows on the north side and residential style windows on the east side (one
per office).
There was a discussion about moving the proposed building addition back to be
flush with the front of the existing building.
Chairman Ruck stated that he had no problem with the application as proposed
and explained. Vice -Chairman Gray noted that he supported leaving the building
area as proposed and moving the addition back.
Dana Carney, of the Planning Staff, noted that Stagecoach Road is a principal
arterial, at the intersection with an interstate highway. He asked the Board not to
lose sight of the fact that Stagecoach Road would be redeveloped at some point
in time, and be located very close to the proposed building addition.
Vice Chairman Gray asked if widening Stagecoach Road in this area was in the
works. Mike Hood, of Public Works, noted that the widening was on the State's
agenda, but not being designed at this time. He noted that the right-of-way for
Stagecoach Road could go beyond the current front property line if a turn lane is
needed.
Chairman Ruck noted that the Board could vote on the application as proposed,
vote on an amended application (if the applicant wished to amend) or vote on a
deferral of the application. These options were discussed. Mr. Sparks stated
that he wished to defer the application in order to work on a revision that staff
could possibly support.
There was a motion to defer the application to the July 29, 2002 agenda. The
motion passed by a vote of 5 ayes and 0 nays. The application was deferred.
3
August 26, 2002
Item No.: A Cont.
STAFF UPDATE:
The applicant submitted a letter to staff on July 15, 2002 requesting that this
application be deferred to the August 26, 2002 agenda. The applicant has noted
that the will be out of town and unable to attend the July meeting. Staff supports
the deferral request.
BOARD OF ADJUSTMENT: (JULY 29, 2002)
Staff informed the Board that the applicant submitted a letter requesting that this
application be deferred to the August 26, 2002 agenda. Staff supported the
deferral request.
The item was placed on the Consent Agenda and deferred to the August 26,
2002 agenda by a vote of 4 ayes, 0 nays and 1 absent.
BOARD OF ADJUSTMENT: (AUGUST 26, 2002)
The applicant was present. There were no objectors present. Staff noted that
the applicant had revised the application reducing the size of the proposed
building addition and increasing the front yard setback. The proposed building
addition was reduced to 630 square feet, with a 20 foot front yard setback. Staff
recommended approval of the revised application subject to the following
conditions:
1. Compliance with the requirements as noted in paragraphs A and B of the
agenda report.
2. A building permit must be obtained.
The applicant offered no additional comments.
The item was placed on the Consent Agenda and approved as recommended by
staff by a vote of 4 ayes, 0 nays and 1 absent.
M