HomeMy WebLinkAboutZ-4213-D Staff Analysise June 22, 2000
ITEM NO.: 7
NAME: Bowman Plaza - Revised POD
FILE NO.: Z -4213-D
LOCATION: Northwest corner of Colonel Glenn Road and
Bowman Road
DEVELOPER:
ENGINEER:
Leonard Boen McGetrick and McGetrick
10600 Colonel Glenn Road 319 E. Markham Street, Suite 202
Little Rock, AR 72204 Little Rock, AR 72201
AREA: 16.366 acres NUMBER OF LOTS: 2 FT. NEW STREET: 0
ZONING: POD/0-3 ALLOWED USES:
PROPOSED USE:
Office, Office/Warehouse
Office, Office/Warehouse
VARIANCES/WAIVERS REQUESTED: None requested.
BACKGROUND:
On March 4, 1999 the Planning Commission approved a preliminary
plat (4 lots) and a POD (Lots 1 and 2) for this property at the
northwest corner of Colonel Glenn and Bowman Roads. On April 6,
1999 the Board of Directors passed Ordinance No. 17,974
approving the POD for Lots 1 and 2.
The approved POD included the construction of two (2) office-
showroom/warehouse buildings (one per lot) and associated
parking areas. The following site specifics were approved:
1. Lot 1 - 63,575 square foot building and 79 parking spaces.
2. Lot 2 - 111,000 square foot building and 202 parking spaces.
3. Driveway from Bowman Road to` serve Lot 1 and a shared
driveway from Colonel Glenn Road (with access easement) to
serve Lots 1 and 2.
June 22, 2000
SUBDIVISION
ITEM NO.: 7 (Cont.)
4
5
6.
A.
B.
FILE NO.: Z -4213-D
A 50 foot undisturbed buffer along the north property line.
An in -lieu contribution for the future traffic signal at the
intersection of Bowman and Colonel Glenn Roads.
Hours of operation - 8:00 a.m. to 5:00 p.m., Monday -Friday.
PROPOSAL/REQUEST:
The applicant is proposing a revised site plan for Lot 2 of
this POD development. There are no changes proposed for
Lot 11 which is currently under construction.
With the revised plan, the applicant proposes to
incorporate the proposed Lot 3 of this subdivision (1.225
acres) and a sliver of the eastern portion of the proposed
Lot 4 into Lot 2 for the development of an office-
showroom/warehouse. The applicant is proposing to
construct a 192,000 square foot building and 200 parking
spaces on Lot 2. The building is proposed to be used as
follows:
15 percent - office/showroom
85 percent - warehouse
The proposed hours of operation will be the same as
previously approved. The applicant will also maintain the
50 foot undisturbed buffer area along the property's north
boundary. The applicant has noted that the street
improvements along the entire Colonel Glenn Road frontage
will be provided with the development of Lot 2.
EXISTING CONDITIONS:
There is currently an office/warehouse building under
construction on Lot 1 of this property, with site work
being done throughout the remainder of the property.
The general area has a mixture of uses, including a mobile
home park to the north and a few residential structures on
large tracts to the west. A large office building is
located at the northeast corner of Colonel Glenn and Bowman
Roads. There are a couple of single-family structures to
the south across Colonel Glenn Road, with a convenience
food store and a telephone cable company (C-4 type use)
located at the southeast and southwest corners of Colonel
Glenn and Lawson Roads. There is also a large amount of
vacant property in the general area.
2
June 22, 2000
SUBDIVISION
ITEM NO.: 7 (Cont.) FILE NO.: Z -4213-D
C. NEIGHBORHOOD COMMENTS:
As of this writing, staff has received no comment from the
neighborhood. There was no established neighborhood
association to notify of the public hearing.
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
I. Colonel Glenn Road is listed on the Master Street Plan as
a principal arterial, dedication of right-of-way to 55
feet from centerline is required.
2. Provide design of streets conforming to "MSP" (Master
Street Plan). Construct one-half street improvements to
these streets including 5 -foot sidewalks with planned
development.
3. Plans of all work in right-of-way shall be submitted for
approval prior to start of work.
4. Stormwater detention ordinance applies to this property.
5. Colonel Glenn Road has a 1998 average daily traffic count
of 9,900.
6. Shackleford Road has a 1998 average daily traffic count
of 3,600.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer main extension required with easements
to serve property.
AP&L: No Comments.
Arkla: No Comment.
Southwestern Bell: No Comments received.
Water: An acreage charge of $150 per acre applies in
addition to normal charges.
Fire Department: Provide turnarounds at the ends of the
parking lots.
County
Planning:
No Comments
received.
CATA:
No effect;
Site is not
on a dedicated bus route.
3
f June 22, 2000
SUBDIVISION
ITEM NO.: 7 (Cont.)
F. ISSUES/TECHNICAL/DESIGN:
Planning Division:
FILE NO.: Z -4213-D
The request is located in the Ellis Mountain Planning
District. The Land Use Plan shows Mixed Office Commercial
for this location. The property is currently zoned Planned
Office Development and the request is for a revision of the
current Planned Office Development. The applicant wishes
to change the configuration of the proposed buildings on
the property. The proposed changes are consistent with the
adopted Land Use Plan.
City Recognized Neighborhood Action Plan: This property is
located in an area that is not covered by a city recognized
neighborhood action plan.
Landscape Issues:
A minimum four (4) foot wide perimeter landscaping strip is
required between separate tracks of property unless access
easements are present.
A three (3) foot wide building landscape strip is required
between the public parking areas and building. There is
considerable flexibility with this requirement.
G. SUBDIVISION COMMITTEE CONMNT:
(JUNE 1, 2000)
Pat McGetrick was present, representing the application.
Staff briefly described the proposed revised POD, noting
that some additional informa.tion�was needed.
Mr. McGetrick briefly reviewed the proposed project and
noted the following:
1. Lot 2 would be replatted to include the additional
area.
2. A 50 foot buffer along the north property line would be
maintained.
3. All of the Colonel Glenn Road improvements (entire
property frontage) would be constructed with the
development of Lot 2. These issues were briefly
discussed.
4
June 22, 2000
SUBDIVISION
ITEM NO.: 7 (Cont.) FILE NO.: Z -4213-D
After the discussion, the Committee forwarded the revised
POD to the full Commission for resolution.
H. ANALYSIS:
The applicant submitted a revised site plan to staff on
June 7, 2000. The revised plan addresses the issues as
raised by staff and the Subdivision Committee. The
appropriate lot lines have been shown for the proposed Lot
2 and the legal description for the area of the Revised POD
has been provided. The dumpster areas have also been shown
on the site plan.
The applicant provided the following information to staff
which needs to be shown on a revised site plan:
1. The access easement will be extended the length of the
parking area and drive between Lots 1 and 2 to provide
cross access and parking.
2. The required building landscaping will be provided
between the front parking area and the building on
Lot 2.
The ordinance would typically require 108 parking spaces
for a development of this size (Lot 2). The applicant is
proposing 200 parking spaces (202 spaces were approved on
the previous plan). Staff is comfortable with the parking
plan as proposed, as some of the parking could be used by
employees/customers of the Lot 1 development.
There is currently a 10 foot utility easement which runs
along the existing south and west property lines of Lot 2
and through the proposed building. There are no existing
utilities within this easement. The applicant will be
required to replat Lot 2 (staff level) and can relocate the
easement to the west property line of Lot 2 at that time.
The Fire Department has requested a turnaround at the east
end of the parking lot in front of the building on Lot 2.
The Fire Department has worked with the applicant and
agreed to a secondary access for this parking lot to allow
fire trucks that enter the lot an exit point. The
secondary access will have a base of a special type
5
June 22, 2000
SUBDIVISION
ITEM NO.: 7 (Cont.) FILE NO.: Z -4213-D
concrete block that will allow grass to grow through.
There will be no curb cut onto Colonel Glenn Road. Public
Works has noted no concerns with the secondary access
point.
Otherwise, to staff's knowledge, there are no outstanding
issues associated with this application. With compliance
with the conditions as noted in the next paragraph, the
proposed development should have no adverse impact on the
general area.
I. STAFF RECOMMENDATIONS:
Staff recommends approval of the revised POD subject to the
following conditions:
1. Compliance with the requirements as noted in paragraphs
D, E and F of this report.
2. Any site lighting should be low-level and directed away
from adjacent residential property.
3. The 50 foot undisturbed buffer along the property's
north boundary must be maintained.
4. A revised preliminary plat must be submitted to staff
Prior to a building permit being issued for Lot 2.
5. A replat of Lot 2 (to include the additional area) must
be filed prior to a building permit being issued for
Lot 2. The 10 foot utility easement will be relocated
with this replat.
6. The dumpster areas must be screened on three (3) sides
with an 8 -foot opaque fence or wall.
7. A revised site plan must be submitted to staff with the
additional items as noted in paragraph H.
PLANNING COMMISSION ACTION:
(JUNE 22, 2000)
The staff presented a positive recommendation on this
application, as there were no further issues for resolution.
There were no objectors to this matter.
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for approval as recommended
by staff. A motion to that effect was made. The motion passed
by a vote of 9 ayes, 0 nays and 2 absent.
FILE NO.: Z -4213-D
NAME: Bowman Plaza - Revised POD
LOCATION: Northwest corner of Colonel Glenn Road and
Bowman Road
DEVELOPER: ENGINEER:
Leonard Boen McGetrick and McGetrick
10600 Colonel Glenn Road 319 E. Markham Street, Suite 202
Little Rock, AR 72204 Little Rock, AR 72201
AREA: 16.366 acres
ZONING: POD/0-3
NUMBER OF LOTS: 2
ALLOWED USES
PROPOSED USE:
FT. NEW STREET: 0
Office, Office/Warehouse
Office, Office/Warehouse
VARIANCES/WAIVERS REQUESTED: None requested.
BACKGROUND:
On March 4, 1999 the Planning Commission approved a preliminary
plat,(4 lots) and a POD (Lots 1 and 2) for this property at the
northwest corner of Colonel Glenn and'Bowman Roads. On April 6,
1999 the Board of Directors passed Ordinance No. 17,974
approving the POD for Lots 1 and 2.
The approved POD included the construction of two (2) office-
showroom/warehouse buildings (one per lot) and associated
parking areas. The following site specifics were approved:
1. Lot 1 - 63,575 square foot building and 79 parking spaces.
2. Lot 2 - 111,000 square foot building and 202 parking spaces.
3. Driveway from Bowman Road to serve Lot 1 and a shared
driveway from Colonel Glenn Road (with access easement) to
serve Lots 1 and 2.
4. A 50 foot undisturbed buffer along the north property line.
FILE NO.: Z -4213-D (Cont.)
5. An in -lieu contribution for the future traffic signal at the
intersection of Bowman and Colonel Glenn Roads. -
6. Hours of operation - 8:00 a.m. to 5:00 p.m., Monday -Friday.
A.
B.
C.
PROPOSAL/REQUEST:
The applicant is proposing a revised site plan for Lot 2 of
this POD development. There are no changes proposed for
Lot 1, which is currently under construction.
With the revised plan, the applicant proposes to
incorporate the proposed Lot 3 of this subdivision (1.225
acres) and a sliver of the eastern portion of the proposed
Lot 4 into Lot 2 for the development of an office-
showroom/warehouse. The applicant is proposing to
construct a 192,000 square foot building and 200 parking
spaces on Lot 2. The building is proposed to be used as
follows:
15 percent - office/showroom
85 percent - warehouse
The proposed hours of operation will be the same as
previously approved. The applicant will also maintain the
50 foot undisturbed buffer area along the property's north
boundary. The applicant has noted that the street
improvements along the entire Colonel Glenn Road frontage
will be provided with the development of Lot 2.
EXISTING CONDITIONS:
There is currently an office/warehouse building under
construction on Lot 1 of this property, with site work
being done throughout the remainder of the property.
The general area has a mixture of uses, including a mobile
home park to the north and a few residential structures on
large tracts to the west. A large office building is
located at the northeast corner of Colonel Glenn and Bowman
Roads. There are a couple of single-family structures to
the south across Colonel Glenn Road, with a convenience
food store and a telephone cable company (C-4 type use)
located at the southeast and southwest corners of Colonel
Glenn and Lawson Roads. There is also a large amount of
vacant property in the general area.
NEIGHBORHOOD COMMENTS:
As of this writing, staff has received no comment from the
neighborhood. There was no established neighborhood
association to notify of the public hearing.
2
FILE NO.: Z -4213-D (Cont.)
D. ENGINEERING COMMENTS:
PUBLIC WORKS CONDITIONS:
1. Colonel Glenn Road is listed on the Master Street Plan as
a principal arterial, dedication of right-of-way to 55
feet from centerline is required.
2. Provide design of streets conforming to "MSP" (Master
Street Plan). Construct one-half street improvements to
these streets including 5 -foot sidewalks with planned
development.
3. Plans of all work in right-of-way shall be submitted for
approval prior to start of work.
4. Stormwater detention ordinance applies to this property.
5. Colonel Glenn Road has a 1998 average daily traffic count
of 9,900.
6. Shackleford Road has a 1998 average daily traffic count
of 3,600.
E. UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater: Sewer main extension required with easements
to serve property.
AP&L: No Comments.
Arkla : No Comment.
Southwestern Bell: No Comments received.
Water: An acreage charge of $150 per acre applies in
addition to normal charges.
Fire Department: Provide turnarounds at the ends of the
parking lots.
County Planning: No Comments received.
CATA: No effect; Site is not on a dedicated bus route.
F. ISSUES/TECHNICAL/DESIGN:
Planning Division:
The request is located in the Ellis Mountain Planning
District. The Land Use Plan shows Mixed Office Commercial
for this location. The property is currently zoned Planned
Office Development and the request is for a revision of the
current Planned Office Development. The applicant wishes
to change the configuration of the proposed buildings on
the property. The proposed changes are consistent with the
adopted Land Use Plan.
3
FILE NO.: Z -4213-D (Cont.)
City Reco nized Neighborhood Action Plan: This property is
located in an area that is not covered by a city recognized
neighborhood action plan.
Landscape Issues:
A minimum four (4) foot wide perimeter landscaping strip is
required between separate tracks of property unless access
easements are present.
A three (3) foot wide building landscape strip is required
between the public parking areas and building. There is
considerable flexibility with this requirement.
G. SUBDIVISION COMMITTEE COMMENT: (JUNE 1, 2000)
Pat McGetrick was present, representing the application.
Staff briefly described the proposed revised POD, noting
that some additional information was needed.
Mr. McGetrick briefly reviewed the proposed project and
noted the following:
1. Lot 2 would be replatted to include the additional
area.
2. A 50 foot buffer along the north property line would be
maintained.
3. All of the Colonel Glenn Road improvements (entire
property frontage) would be constructed with the
development of Lot 2. These issues were briefly
discussed.
After the discussion, the Committee forwarded the revised
POD to the full Commission for resolution.
H. ANALYSIS:
The applicant submitted a revised site plan to staff on
June 7, 2000. The revised plan addresses the issues as
raised by staff and the Subdivision Committee. The
appropriate lot lines have been shown for the proposed Lot
2 and the legal description for the area of the Revised POD
has been provided. The dumpster areas have also been shown
on the site plan.
The applicant provided the following information to staff
which needs to be shown on a revised site plan:
4
FILE NO.: Z -4213-D (Cont.
1. The access easement will be extended the length of the
parking area and drive between Lots 1 and 2 to provide
cross access and parking.
2. The required building landscaping will be provided
,between the front parking area and the building on
Lot 2.
The ordinance would typically require 108 parking spaces
for a development of this size (Lot 2). The applicant is
proposing 200 parking spaces (202 spaces were approved on
the previous plan). Staff is comfortable with the parking
plan as proposed, as some of the parking could be used by
employees/customers of the Lot 1 development.
There is currently a 10 foot utility easement which runs
along the existing south and west property lines of Lot 2
and through the proposed building. There are no existing
utilities within this easement. The applicant will be
required to replat Lot 2 (staff level) and can relocate the
easement to the west property line of Lot 2 at that time.
The Fire Department has requested a turnaround at the east
end of the parking lot in front of the building on Lot 2.
The Fire Department has worked with the applicant and
agreed to a secondary access for this parking lot to allow
fire trucks that enter the lot an exit point. The
secondary access will have a base of a special type
concrete block that will allow grass to grow through.
There will be no curb cut onto Colonel Glenn Road. Public
Works has noted no concerns with the secondary access
point.
Otherwise, to staff's knowledge, there are no outstanding
issues associated with this application. With compliance
with the conditions as noted in the next paragraph, the
proposed development should have no adverse impact on the
general area.
1. STAFF RECOMMENDATIONS:
Staff recommends approval of the revised POD subject to the
following conditions:
1. Compliance with the requirements as noted in paragraphs
D, E and F of this report.
2. Any site lighting should be low-level and directed away
from adjacent residential property.
3. The 50 foot undisturbed buffer along the property's
north boundary must be maintained.
ln�
FILE NO.: Z -4213-D (Cont.
4. A revised preliminary plat must be submitted to staff
prior to a building permit being issued for Lot 2.
5. A replat of Lot 2 (to include the additional area) must
be filed prior to a building permit being issued for
Lot 2. The 10 foot utility easement will be relocated
with this replat.
6. The dumpster areas must be screened on three (3) sides
with an 8 -foot opaque fence or wall.
7. A revised site plan must be submitted to staff with the
additional items as noted in paragraph H.
PLANNING COMMISSION ACTION: (JUNE 22, 2000)
The staff presented a positive recommendation on this
application, as there were no further issues for resolution.
There were no objectors to this matter.
The Chairperson placed the item before the Commission for
inclusion within the Consent Agenda for approval as recommended
by staff. A motion to that effect was made. The motion passed
by a vote of 9 ayes, 0 nays and 2 absent.
ri