HomeMy WebLinkAboutZ-4115-A Staff AnalysisNovember 13, 2008
ITEM NO.: 3 FILE NO.: Z-4115-A
NAME: Life Skills for Youth — Conditional Use Permit
LOCATION: 10710 1-30
OWNER/APPLICANT: Temple Baptist Church/Larry Clark
PROPOSAL: A conditional use permit is requested to allow for the
addition of an after -school, Saturday, summer day
care and mentoring program to this existing church.
The property is zoned R-2.
1. SITE LOCATION:
The church site is located on the north side of 1-30, approximately Y2 mile
east of 1-430.
2. COMPATIBILITY WITH NEIGHBORHOOD:
The church campus consists of some 24± acres located in an area of
mixed zoning and uses. The property fronts onto the 1-30 frontage road.
Undeveloped 1-1 zoned property and a PDC zoned equipment rental
company are adjacent to the west. Undeveloped C-3 zoned property and
a variety of commercial uses are located east of the site. Undeveloped
PCD zoned property and a PID zoned salvage yard are located across
Baseline Road to the north. The proposed day care will be located within
the church's existing family life center building. The use will not affect the
church's continued compatibility with the area.
All owners of properties located within 200 feet of the site, all residents
within 300 feet who could be identified and the SWLR United for Progress
Neighborhood Association were notified of this request.
3. ON SITE DRIVES AND PARKING:
Access to the site is via driveways off of the 1-30 frontage road and
Childers Drive. The property has paved parking lots containing 350±
parking spaces. The day care will operate during hours that do not conflict
with typical church activities. The existing parking lot is more than
sufficient to provide the required parking and drop off/pickup spaces.
November 13, 2008
ITEM NO.: 3 Cont. FILE NO.: Z-4115-A
4. SCREENING AND BUFFERS:
No comments on this use -only issue.
5. PUBLIC WORKS COMMENTS:
1. Baseline Road is classified on the Master Street Plan as a principal
arterial. Dedication of right-of-way to 55 feet from centerline will be
required.
2. A twenty (20) foot radial dedication of right-of-way is required at the
intersection of Baseline Road and Childers Drive.
6. UTILITY, FIRE DEPT. AND CATA COMMENTS:
Wastewater: Sewer available to this project.
Entergy: No comments received.
Centerpoint Energy: No comments received.
AT&T (SBC): No comments received.
Water: No objection.
Fire Department: No comments received.
County Planning: No Comments.
CATA: This site is not located on a CATA bus route.
SUBDIVISION COMMITTEE COMMENT: (OCTOBER 23, 2008)
Larry Clark was present, representing the application. Staff briefly described the
proposed conditional use permit, noting the hours of operation and maximum
enrollment. Staff noted that a signage plan was needed for the property.
The Public Works requirements were briefly discussed. Vince Floriani, of Public
Works, discussed the required right-of-way dedication. Mr. Clark noted that he
would take the information to the church leadership.
Mr. Clark indicated that a signage plan would be provided to staff.
E
November 13, 2008
M i1►[011�14 TiH
FILE NO.: Z-4115-A
After the discussion, the Committee forwarded the application to the full
Commission for final action.
STAFF ANALYSIS:
Temple Baptist Church occupies the R-2 zoned, 26± acre tract located at 10710
1-30. The property contains a church building, a family life center/gymnasium
building, office building, 350+ parking spaces and outside play areas and
ballfields. A conditional use permit is requested to allow the addition of an after-
school/summer day care program, utilizing the family life center/gymnasium
building.
Life Skills for Youth is a non-profit program that specializes in mentoring
disadvantaged youth between the ages of 4 and 18. The program currently has
70 children signed up with a maximum attendance of 300 expected, primarily
during the summer months. The proposed days and hours of operation are 4:00
p.m. — 7:00 p.m., Monday, Tuesday, Thursday and Friday; 9:00 a.m. — 3:00 p.m.,
Saturday and 7:00 a.m. — 7:00 p.m. in summer. The hours are designed so as
not to conflict with primary church activity times. The family life center building
contains classrooms, meeting rooms, restrooms, a gymnasium and a concession
area. An outside playground is located near the building and a ballfield is located
behind the church, near the Baseline Road perimeter of the site.
Staff is supportive of the request. The site contains an established institutional
use with ample parking, building space and outside play areas. Allowing the
addition of this after -school, Saturday and summer day care and mentoring
program to the activities of this existing church should have no impact on nearby
properties. There is no bill of assurance for this acreage tract.
STAFF RECOMMENDATION:
Staff recommends approval of the requested C.U.P. subject to compliance with
the following conditions:
1. Compliance with the comments and conditions in Section 5 of the agenda
staff report.
2. Signage is to be limited to that allowed in office and institutional zones.
3
November 13, 2008
ITEM NO.: 3 (Cont.
PLANNING COMMISSION ACTION:
FILE NO.: Z-4115-A
(NOVEMBER 13, 2008)
The applicant was present. There were no objectors present. Staff presented
the item and a recommendation of approval subject to compliance with the
conditions outlined in the "staff recommendation" above. There was no further
discussion. The item was placed on the consent agenda and approved as
recommended by staff. The vote was 7 ayes, 0 noes, 2 absent and 2 open
positions.
Ll
SUBDIVISION COMMITTEE COMMENTS
OCTOBER 23, 2008
ITEM NO.: 3. LIFE SKILLS FOR YOUTH CONDITIONAL USE PERMIT
10710 INTERSTATE 30 Z-4115-A
Planning Staff Comments:
1. Provide signage plan.
2. Information for Commissioners:
a. There is no Bill of Assurance for this acreage tract.
b. Days and hours of operation are 4:00 p.m. — 7:00 p.m., Monday, Tuesday, Thursday and Friday;
9:00 a.m. — 3:00 p.m. Saturday and 7:00 a.m. — 7:00 p.m. in summer.
c. Maximum capacity requested is up to 300 youth ages 4-18; likely less during school year than
during summer program.
d. Program will use existing Family Life Center building which contain classrooms, meeting rooms,
restrooms, gymnasium and concession area.
Variance/Waivers:
■ None requested.
Public Works:
1. Baseline Road is classified on the Master Street Plan as a principal arterial. Dedication of right-of-way to
55 feet from centerline will be required.
2. A twenty (20) foot radial dedication of right-of-way is required at the intersection of Baseline Road and
Childers Drive.
Utilities and Fire Department/County Planning:
Wastewater: Sewer available to this project.
Entergy: No comments received.
Center -point Energy: No comments received.
AT&T (SBC): No comments received.
Water: No objection.
Fire Department: No comments received.
County Planning: No Comments.
CATA: The site is not located on a CATA bus route.
Planning Division: No Comments.
Landscape: No comments on this use -only issue.
Other: Submit responses to staff issues and four (4) copies of revised site plan (if necessary) to staff no later than
Wednesday October 29, 2008.
Required notification must be completed by October 29, 2008 and proof of notice returned to staff by November 7,
2008.
ITEM #3
SUBDIVISION COMMITTEE COMMENTS: (OCTOBER 23, 2008)
Larry Clark was present, representing the application. Staff briefly described the
proposed conditional use permit, noting the hours of operation and maximum
enrollment. Staff noted that a signage plan was needed for the property.
The Public Works requirements were briefly discussed. Vince Floriani, of Public Works,
discussed the required right-of-way dedication. Mr. Clark noted that he would take the
information to the church leadership.
Mr. Clark indicated that a signage plan would be provided to staff.
After the discussion, the Committee forwarded the application to the full Commission for
final action.