HomeMy WebLinkAboutZ-3689-B Staff AnalysisJuly 9, 1985
SUBDIVISIONS
Item No. 6
NAME: Corporate Hill - Site Plan
Review (Z -3689-B)
LOCATION: South of the Intersection of
�- Corporate Hill Drive and
West Markham Street
(#18 Corporate dill Drive)
OWNER/APPLICANT: Corpex/Townley, Williams,
Blair, Architects
P RnPOSAL
To construct a two-story office building (28,000 square
feet) and 130 parking spaces on 2.03+ acres of land that is
zoned "0-2."
ANALYSIS:
The applicant has submitted a landscape plan. This site
plan is a part of an office park development and is
compatible with the surrounding area. This application
meets all City ordinance requirements.
CITY ENGINEERING REQUIREMENTS:
The applicant needs to submit drainage and detention plans.
STAFF RECOMMENDATION:
Staff recommends approval subject to the City Engineering
comments.
SUBDIVISION COMMITTEE REVIEW:
The applicant was present and agreed to comply with staff
recommendations. There were no unresolved issues.
PLANNING COMMISSION ACTION:
The applicant was present. There were no objectors. The
Commission voted 8 ayes, 0 noes and 3 absent to approve this
application as reviewed by the Subdivision Committee and
recommended by staff.
July 9, 1985
SUBDIVISIONS
Item No. 6
NAME: Corporate Hill - Site Plan
Review (Z -3689-B)
LOCATION: South of the Intersection of
Corporate Hill Drive and
West Markham Street
(#18 Corporate Hill Drive)
OWNER/APPLICANT: Corpex/Townley, Williams,
Blair, Architects
PROPOSAL:
To construct a two-story office building (28,000 square
feet) and 130 parking spaces on 2.03+ acres of land that is
zoned "0-2." —
ANALYSIS:
The applicant has submitted a landscape plan. This site
plan is a part of an office park development and is
compatible with the surrounding area. This application
meets all City ordinance requirements.
CITY ENGINEERING REQUIREMENTS:
The applicant needs to submit drainage and detention plans.
STAFF RECOMMENDATION:
Staff recommends approval subject to the City Engineering
comments.
SUBDIVISION COMMITTEE REVIEW:
The applicant was present and agreed to comply with staff
recommendations. There were no unresolved issues.
PLANNING COMMISSION ACTION:
The applicant was present. There were no objectors in
attendance. After a brief discussion, the Planning
Commission voted unanimously to approve the site plan as
recommended by staff. The vote: 8 ayes, 0 noes and
3 absent.
July 9, 1985
SUBDIVISIONS
Item No. 6
NAME: Corporate Hill - Site Plan
Review (Z -3689-B)
LOCATION: South of the Intersection of
Corporate Hill Drive and
West Markham Street
(#18 Corporate Hill Drive)
OWNER/APPLICANT: Corpex/Townley, Williams,
Blair, Architects
PROPOSAL:
To construct a two-story office building (28,000 square
feet) and 130 parking spaces on 2.03+ acres of land that is
zoned "0-2."
ANALYSIS:
The applicant has submitted a landscape plan. This site
plan is a part of an office park development and is
compatible with the surrounding area. This application
meets all City ordinance requirements.
CITY ENGINEERING REQUIREMENTS:
The applicant needs to submit drainage and detention plans.
STAFF RECOMMENDATION:
Staff recommends approval subject to the City Engineering
comments.
SUBDIVISION COMMITTEE REVIEW:
The applicant was present and agreed to comply with staff
recommendations. There were no unresolved issues.
PLANNING COMMISSION ACTION:
The applicant was present. There were no objectors in
attendance. After a brief discussion, the Planning
Commission voted unanimously to approve the site plan as
recommended by staff. The vote: 8 ayes, 0 noes and
3 absent.