HomeMy WebLinkAboutZ-3638-A Staff AnalysisApril 24, 1984
Item No. D - Z -3638-A
Owner: Various Owners
Applicant: Gary Dean
Location: Financial Centre Parkway at
Shackleford Road NW Corner
Request: Rezone from 11C-3" General
Commercial to "0-2" Office and
Institutional District
Purpose:
Size:
Existing Use:
Office
4.59 acres +
Vacant
SURROUNDING LAND USE AND ZONING:
North - Single Family, Zoned "R-2"
South - Office, Zoned "C-3"
East - Interstate, Zoned "R-2"
West - Vacant and Single Family, Zoned "R-2," O-3 "
and "C-3"
PLANNING CONSIDERATIONS:
1. The proposal is to construct a single office building
not to exceed 120' in height and one parking deck. The
120' limit is the maximum height in the "0-2" District.
There will be additional surface parking. The site is
located in an area that is rapidly developing as a
major office center for west Little Rock. There is
substantial office development directly to the south
and to the north and northeast. This area is commonly
referred to as the I-430 office corridor, and the
proposed project is compatible with that land use
pattern. The property has good access for high volumes
of traffic and needed commercial services are also
provided in the area. (The "0-2" District requires a
site plan review by the Planning Commission. The site
plan has been filed for the Commission's April 12
meeting.)
2. The site is vacant with wooded areas. The property has
some slope to it with the east side, the Shackleford
frontage, being at 380' and increases in elevation to
410' at the southwest corner. The grade is fairly
gradual and should not present any problems.
April 24, 1984
Item No. D - Continued
3. There are no right-of-way requirements or Master Street
Plan issues associated with this request.
4. There have been no adverse comments received from the
reviewing agencies at this time.
5. There are no.legal issues.
6. The site was rezoned from 110-3" to "C-3" as conversion
adjustment. That action was accomplished in
February 1981. At that time, the proposed use was a
hotel. The neighborhood's position relative to
mid -rise office buildings in the area is well
documented. (The proposed height is permitted in the
"0-2" District.) Staff has not received any comments
from the neighborhood regarding this rezoning request
at this writing.
7. The staff supports the request and views the rezoning
as being appropriate for the location, the intersection
of an arterial and an interstate. The Shackleford
frontage from Kanis to Markham is zoned for
nonresidential uses, except an "R-2" piece directly
north of this tract. The proposed use is compatible
with the area and the existing land use patterns which
includes a major office corridor to the south and a
commercial strip to the north. Because of what is
occurring along Shackleford, it appears that the
long-term viability of the residential lots on
Birchwood within 200' of Shackleford is questionable.
The continue residential use at this location will
probably have to be reevaluated.
STAFF RECOMMENDATION:
Staff recommends approval of the request as filed.
PLANNING COMMISSION ACTION: (3-27-84)
The applicant was not present but had requested a 30 -day
deferral. Staff supported the request because the applicant
also did not notify all the property owners within the
required 200'. A motion to defer the item passed by a vote
of 10 ayes, 0 noes and 1 absent.
April 24, 1984
Item No. D - Continued
PLANNING COMMISSION ACTION: (4-24-84)
The applicant, Gary Dean, was present. There were also two
persons present that addressed the Commission about some
concerns of the neighborhood. Mr. Dean spoke in support of
the request and stated that he had met with'the neighborhood
and had revised the proposed site plan based on those
discussions. The building design had changed and the height
of the building would not exceed 801. This was a reduction
of approximately 40' from the original proposal. He said
that the new plan was a good compromise and should satisfy
all parties involved. Dorothy Straton of the Birchwood
neighborhood stated that they were not opposed to office
use, but wanted quality development. She then described
some of the neighborhood's concerns which included traffic
on Shackleford Road, drainage, sewer capacity and the width
of the proposed buffer. She requested that the City look
into the traffic situation and provide some help. They were
also concerned about the zoning changes occurring in the
area and the staff's statement regarding the viability of
long-term residential use on the western end of Birchwood.
During this discussion, it was pointed out that the required
site plan review for the 110-2" district would address all of
the design issues. Ms. Straton said that the neighborhood
was pleased with the 80 -foot height. John Straton
questioned the method of measuring the height of the
}wilding. The Zoning Ordinance definition of building
height uses the central access of the building for this
purpose. Mr. Dean then discussed some of the concerns
raised by the representatives of the neighborhood. After a
lengthy discussion, a motion was made to recommend approval
of the request as filed. The motion passed by a vote of
9 ayes, 4 noes and 2 absent.
April 24, 1984
Item No. D - Z -3638-A
Owner:
Applicant:
Location:
Request:
Purpose:
Size:
Various Owners
Gary Dean
Financial Centre Parkway at
Shackleford Road NW Corner
Rezone from "C-3" General
Commercial to 110-2" Office and
Institutional District
Office
4.59 acres +
Existing Use: Vacant
SURROUNDING LAND USE AND ZONING:
North - Single Family, Zoned "R-2"
South - Office, Zoned "C-3"
East - Interstate, Zoned "R-2"
West - Vacant and Single Family, Zoned "R-2," 110-3"
and "C-3"
PLANNING CONSIDERATIONS:
1. The proposal is to construct a single office building
not to exceed 120' in height and one parking deck. The
120' limit is the maximum height in the 110-2" District.
There will be additional surface parking. The site is
located in an area that is rapidly developing as a
major office center for west Little Rock. There is
substantial office development directly to the south
and to the north and northeast. This area is commonly
referred to as the I-430 office corridor, and the
proposed project is compatible with that land use
pattern. The property has good access for high volumes
of traffic and needed commercial services are also
provided in the area. (The 110-2" District requires a
site plan review by the Planning Commission. The site
plan has been filed for the Commission's April 12
meeting.)
2. The site is vacant with wooded areas. The property has
some slope to it with the east side, the Shackleford
frontage, being at 380' and increases in elevation to
410' at the southwest corner. The grade is fairly
gradual and should not present any problems.
April 24, 1984
Item No. D - Continued
3. There are no right-of-way requirements or Master Street
Plan issues associated with this request.
4. There have been no adverse comments received from the
reviewing agencies at this time.
5. There are no legal issues.
6. The site was rezoned from "0-3" to 11C-3" as conversion
adjustment. That action was accomplished in
February 1981. At that time, the proposed use was a
hotel. The neighborhood's position relative to
mid -rise office buildings in the area is well
documented. (The proposed height is permitted in the
"0-2" District.) Staff has not received any comments
from the neighborhood regarding this rezoning request
at this writing.
7. The staff supports the request and views the rezoning
as being appropriate for the location, the intersection
of an arterial and an interstate. The Shackleford
frontage from Kanis to Markham is zoned for
nonresidential uses, except an "R-2" piece directly
north of this tract. The proposed use is compatible
with the area and the existing land use patterns which
includes a major office corridor to the south and a
commercial strip to the north. Because of what is
occurring along Shackleford, it appears that the
long-term viability of the residential lots on
Birchwood within 200' of Shackleford is questionable.
The continue residential use at this location will
probably have to be reevaluated.
STAFF RECOMMENDATION:
Staff recommends approval of the request as filed.
PLANNING COMMISSION ACTION: (3-27-84)
The applicant was not present but had requested a 30 -day
deferral. Staff supported the request because the applicant
also did not notify all the property owners within the
required 200'. A motion to defer the item passed by a vote
of 10 ayes, 0 noes and 1 absent.
April 24, 1984
Item No. D - Continued
PLANNING COMMISSION ACTION: (4-24-84)
The applicant, Gary Dean, was present. There were also two
persons present that addressed the Commission about some
concerns of the neighborhood. Mr. Dean spoke in support of
the request and stated that he had met with the neighborhood
and had revised the proposed site plan based on those
discussions. The building design had changed and the height
of the building would not exceed 80'. This was a reduction
of approximately 40' from the original proposal. He said
that the new plan was a good compromise and should satisfy
all parties involved. Dorothy Straton of the Birchwood
neighborhood stated that they were not opposed to office
use, but wanted quality development. She then described
some of the neighborhood's concerns which included traffic
on Shackleford Road, drainage, sewer capacity and the wid-th
of the proposed buffer. She requested that the City look
into the traffic situation and provide some help. They were
also concerned about the zoning changes occurring in the
area and the staff's statement regarding the viability of
long-term residential use on the western end of Birchwood.
During this discussion, it was pointed out that the required
site plan review for the "0-2" district would address all of
the design issues. Ms. Straton said that the neighborhood
was pleased with the 80 -foot height. John Straton
questioned the method of measuring the height of the
building. The Zoning Ordinance definition of building
height uses the central access of the building for this
purpose. Mr. Dean then discussed some of the concerns
raised by the representatives of the neighborhood. After a
lengthy discussion, a motion was made to recommend approval
of the request as filed. The motion passed by a vote of
9 ayes, 0 noes and 2 absent.
April 24, 1984
Item No. D - Z -3638-A
Owner: Various Owners
Applicant: Gary Dean
Location: Financial Centre Parkway at
Shackleford Road NW Corner
Request: Rezone from "C-3" General
Commercial to 110-2" Office and
Institutional District
Purpose: Office
Size: 4.59 acres +
Existing Use: Vacant
SURROUNDING LAND USE AND ZONING:
North - Single Family, Zoned "R-2"
South - Office, Zoned "C-3"
East - Interstate, Zoned "R-2"
West - Vacant and Single Family, Zoned "R-2," "O-3"
and "C-3"
PLANNING CONSIDERATIONS:
1. The proposal is to construct a single office building
not to exceed 120' in height and one parking deck. The
120' limit is the maximum height in the "0-2" District.
There will be additional surface parking. The site is
located in an area that is rapidly developing as a
major office center for west Little Rock. There is
substantial office development directly to the south
and to the north and northeast. This area is commonly
referred to as the I-430 office corridor, and the
proposed project is compatible with that land use
pattern. The property has good access for high volumes
of traffic and needed commercial services are also
provided in the area. (The 110-2" District requires a
site plan review by the Planning Commission. The site
plan has been filed for the Commission's April 12
meeting.)
2. The site is vacant with wooded areas. The property has
some slope to it with the east side, the Shackleford
frontage, being at 380' and increases in elevation to
410' at the southwest corner. The grade is fairly
gradual and should not present any problems.
April 24, 1984
Item No. D - Continued
3. There are no right-of-way requirements or Master Street
Plan issues associated with this request.
4. There have been no adverse comments received from the
reviewing agencies at this time.
5. There are no legal issues.
6. The site was rezoned from "0-3" to "C-3" as conversion
adjustment. That action was accomplished in
February 1981. At that time, the proposed use was a
hotel. The neighborhood's position relative to
mid -rise office buildings in the area is well
documented. (The proposed height is permitted in the
"0-2" District.) Staff has not received any comments
from the neighborhood regarding this rezoning request
at this writing.
7. The staff supports the request and views the rezoning
as being appropriate for the location, the intersection
of an arterial and an interstate. The Shackleford
frontage from Kanis to Markham is zoned for
nonresidential uses, except an "R-2" piece directly
north of this tract. The proposed use is compatible
with the area and the existing land use patterns which
includes a major office corridor to the south and a
commercial strip to the north. Because of what is
occurring along Shackleford, it appears that the
long-term viability of the residential lots on
Birchwood within 200' of Shackleford is questionable.
The continue residential use at this location will
probably have to be reevaluated.
STAFF RECOMMENDATION:
Staff recommends approval of the request as filed.
PLANNING COMMISSION ACTION: (3-27-84)
The applicant was not present but had requested a 30 -day
deferral. Staff supported the request because the appl.icant
also did not notify all the property owners within the
required 200'. A motion to defer the item passed by a vote
of 10 ayes, 0 noes and 1 absent.
April 24, 1984
Item No. D - Continued
PLANNING COMMISSION ACTION: (4-24-84)
The applicant, Gary Dean, was present. There were also two
persons present that addressed the Commission about some
concerns of the neighborhood. Mr. Dean spoke in support of
the request and stated that he had met with the neighborhood
and had revised the proposed site plan based on those
discussions. The building design had changed and the height
of the building would not exceed 801. This was a reduction
of approximately 40' from the original proposal. He said
that the new plan was a good compromise and should satisfy
all parties involved. Dorothy Straton of thBirchwood
neighborhood stated that they were not opposed
to ce
use, but wanted quality development. She then described
some of the neighborhood's concerns which included traffic
on Shackleford Road, drainage, sewer capacity and the width
of the proposed buffer. She requested that the City look
into the traffic situation and provide some help. They were
also concerned about the zoning changes occurring in the
area and the staff's statement regarding the viability of
long-term residential use on the western end of Birchwood.
During this discussion, it was pointed out that the required
site plan review for the "0-2" district would address all of
the design issues. Ms. Straton said that the neighborhood
was pleased with the 80 -foot height. John Straton
questioned the method of measuring the height of the
building. The Zoning Ordinance definition of building
height uses the central access of the building for this
purpose. Mr. Dean then discussed some of the concerns
raised by the representatives of the neighborhood. After a
lengthy discussion, a motion was made to recommend approval
of the request as filed. The motion passed by a vote of
9 ayes, 0 noes and 2 absent.
March 27, 1984
Item No. 3 - Z -3638-A
Owner:
Applicant:
Location:
Request:
Purpose:
Size:
Various Owners
Gary Dean
Financial Centre Parkway at
Shackleford Road NW Corner
Rezone from "C-3" General
Commercial to "0-2" Office and
Institutional District
Office
4.59 acres +
Existing Use: Vacant
SURROUNDING LAND USE AND ZONING:
North- - Single Family, Zoned "R-2"
South - Office, Zoned "C-3"
East - Interstate, Zoned "R-2"
West - Vacant and Single Family, Zoned "R-2," 110-3"
and "C-3"
PLANNING CONSIDERATIONS:
1. The proposal is to construct a single office building
not to exceed 120' in height and one parking deck. The
120' limit is the maximum height in the "0-2" District.
There will be additional surface parking. The site is
located in an area that is rapidly developing as a
major office center for west Little Rock. There is
substantial office development directly to the south
and to the north and northeast. This area is commonly
referred to as the I-430 office corridor, and the
proposed project is compatible with that land use
pattern. The property has good access for high volumes
of traffic and needed commercial services are also
provided in the area. (The "0-2" District requires a
site plan review by the Planning Commission. The site
plan has been filed for the Commission's April 12
meeting.)
2. The site is vacant with wooded areas. The property has
some slope to it with the east side, the Shackleford
frontage, being at 380' and increases in elevation to
410' at the southwest corner. The grade is fairly
gradual and should not present any problems.
March 27, 1984
Item No. 3 - Continued
3. There are no right-of-way requirements or Master Street
Plan issues associated with this request.
4. There have been no adverse comments received from the
reviewing agencies at this time.
5. There are no legal issues.
6. The site was rezoned from "0-3" to "C-3" as conversion
adjustment. That action was accomplished in
February 1981. At that time, the proposed use was a
hotel. The neighborhood's position relative to
mid -rise office buildings in the area is well
documented. (The proposed height is permitted in the
"0-2" District.) Staff has not received any comments
from the neighborhood regarding this rezoning request
at this writing.
7. The staff support's the request and views the rezoning
as being appropriate for the location, the intersection
of an arterial and an interstate. The Shackleford
frontage from Kanis to Markham is zoned for
nonresidential uses, except an "R-2" piece directly
north of this tract. The proposed use is compatible
with the area and the existing land use patterns which
includes a major office corridor to the south and a
commercial strip to the north. Because of what is
occurring along Shackleford, it appears that the
long-term viability of the residential lots on
Birchwood within 200' of Shackleford is questionable.
The continue residential use at this location will
probably have to be reevaluated.
STAFF RECOMMENDATION:
Staff recommends approval of the request as filed.