HomeMy WebLinkAboutZ-3484-D Staff AnalysisOctober 9, 1984
SUBDIVISIONS
Item No. A
NAME:
LOCATION:
OWNER/APPLICANT:
PROPOSAL:
Rodney Parham
Conditional Use Permit
(Z -3484-D)
Northeast Corner of Rodney
Parham Road and Reservoir Road
Wengroup, Inc./Chris Barrier
To rezone the property from "R-6" to "C-3" and to obtain a
conditional use which would allow the construction of seven
buildings (removal of two buildings), six office warehouses
(125,000 square feet of warehouse and 14,000 square feet of
office), one retail building (34,200 square feet up to
60,200 square feet, and 650 parking spaces on 11.943+
acres.
ORDINANCE DESIGN STANDARDS:
1. Site Location
This site is located at the intersection of two
arterial streets (Rodney Parham and Reservoir).
2. Compatibility with Neighborhood
The site plan as submitted is not compatible. There is
potential for a commercial use on this site if properly
developed. An institutional use (retirement center)
lies to the east, office and multifamily to the south,
vacant to the north and commercial to the west.
3. On -Site Drives and Parki
This proposal contains three access drives (two on
Reservoir and one on Rodney Parham) and 650 paved
parking spaces.
4. Screening and Buffers
The applicant has not proposed any screening or buffers
or shown any landscaping.
October 9, 1984
SUBDIVISIONS
Item No. A - Continued
5. Analysis
The staff supports the proposed "C-3" rezoning as this
site was formerly zoned "C-3" and a portion (north) is
currently zoned "C-3." There are however major
deficiencies in the site plan. The buildings appear to
have little relationship to the steep slope of the
land. This proposal contains no provision for a buffer
or open space on the east property line. This site
plan does not appear to take into consideration the
potential major drainage problems. The City Engineer
has requested an internal drainage plan and has
recommended that a detention facility be considered.
Finally, the applicant will be required to dedicate
additional right-of-way on Reservoir Road (to five
lanes) and construct it.*
*The applicant has indicated that a revised site plan
will be submitted.
6. Staff Recommendation
The staff withholds recommendation subject to the note
cited above.
SUBDIVISION COMMITTEE REVIEW:
The applicant was not present. The staff stated that the
applicant had written a letter asking that this item be
deferred until the October 9, 1984, Planning Commission
meeting.
PLANNING COMMISSION ACTION:
The Commission voted 11 ayes, 0 noes to defer this item to
the October 91 1984, Planning Commission meeting.
SUBDIVISION COMMITTEE REVIEW:
The applicant was not present. The staff stated that the
applicant had submitted a letter requesting withdrawal of
this item.
October 9, 1984
SUBDIVISIONS
Item No. A - Continued
PLANNING COMMISSION ACTION:
The applicant was not present but had submitted a letter
requesting withdrawal of this item. The Commission voted
8 ayes, 0 noes, 3 absent to withdraw this item.
September 11, 1984
SUBDIVISIONS
Item No. 12
NAME:
LOCATION:
OWNER/APPLICANT:
PROPOSAL:
Rodney Parham
Conditional Use Permit
(Z -3484-D)
Northeast Corner of Rodney
Parham Road and Reservoir Road
Wengroup, Inc./Chris Barrier
To rezone the property from "R-6" to "C-3" and to obtain a
conditional use which would allow the construction of seven
buildings (removal of two buildings), six office warehouses
(125,000 square feet of warehouse and 14,000 square feet of
office), one retail building (34,200 square feet up to
60,200 square feet, and 650 parking spaces on 11.943+
acres.
ORDINANCE DESIGN STANDARDS:
1. Site Location
This site is located at the intersection of two
arterial streets (Rodney Parham and Reservoir).
2. Compatibility with Neighborhood
The site plan as submitted is not compatible. There is
potential for a commercial use on -this -site if properly
developed. An institutional use (retirement center)
lies to the east, office and multifamily to the south,
vacant to the north and commercial to the west.
3. On -Site Drives and Parking
This proposal contains three access drives (two on
Reservoir and one on Rodney Parham) and 650 paved
parking spaces.
4. Screening and Buffers
The applicant has not proposed any screening or buffers
or shown any landscaping.
September 11, 1984
SUBDIVISIONS
Item No. 12 - Continued
5. Analysis
The staff supports the proposed "C-3" rezoning as this
site was formerly zoned "C-3" and a portion (north) is
currently zoned "C-3." There are however major
deficiencies in the site plan. The buildings appear to
have little relationship to the steep slope of the
land. This proposal contains no provision for a buffer
or open space on the east property line. This site
plan does not appear to take into consideration the
potential major drainage problems. The City Engineer
has requested an internal drainage plan and has
recommended that a detention facility be considered.
Finally, the applicant will be required to dedicate
additional right-of-way on Reservoir Road (to five
lanes) and construct it.*
*The applicant has indicated that a revised site plan
will be submitted.
6. Staff Recommendation
The staff withholds recommendation subject to the note
cited above.
SUBDIVISION COMMITTEE REVIEW:
The applicant was not present. The staff stated that the
applicant had written a letter asking that this item be
deferred until the October 9, 1984, Planning Commission
meeting.
PLANNING COMMISSION ACTION:
The Commission voted 11 ayes, 0 noes to defer this item to
the October 9, 1984, Planning Commission meeting.
October 9, 1984
SUBDIVISIONS
Item No. A
NAME:
LOCATION:
OWNER/APPLICANT:
PROPOSAL:
Rodney Parham
Conditional Use Permit
(Z -3484-D)
Northeast Corner of Rodney
Parham Road and Reservoir Road
Wengroup, Inc./Chris Barrier
To rezone the property from "R-6" to "C-3" and to obtain a
conditional use which would allow the construction of seven
buildings (removal of two buildings), six office warehouses
(125,000 square feet of warehouse and 14,000 square feet of
office), one retail building (34,200 square feet up to
60,200 square feet, and 650 parking spaces on 11.943+
acres.
ORDINANCE DESIGN STANDARDS:
1. Site Location
This site is located at the intersection of two
arterial streets (Rodney Parham and Reservoir).
2. Compatibility with Neighborhood
The site plan as submitted is not compatible. There is
potential for a commercial use on this site if properly
developed. An institutional use (retirement center)
lies to the east, office and multifamily to the south,
vacant to the north and commercial to the west.
3. On -Site Drives and Parki
This proposal contains three access drives (two on
Reservoir and one on Rodney Parham) and 650 paved
parking spaces.
4. Screeninq and Buffers
The applicant has not proposed any screening or buffers
or shown any landscaping.
October 9, 1984
SUBDIVISIONS
Item No. A - Continued
5. Analysis
The staff supports the proposed "C-3" rezoning as this
site was formerly zoned "C-3" and a portion (north) is
currently zoned "C-3." There are however major
deficiencies in the site plan. The buildings appear to
have little relationship to the steep slope of the
land. This proposal contains no provision for a buffer
or open space on the east property line. This site
plan does not appear to take into consideration the
potential major drainage problems. The City Engineer
has requested an internal drainage plan and has
recommended that a detention facility be considered.
Finally, the applicant will be required to dedicate
additional right-of-way on Reservoir Road (to five
lanes) and construct it.*
*The applicant has indicated that a revised site plan
will be submitted.
6. Staff Recommendation
The staff withholds recommendation subject to the note
cited above.
SUBDIVISION COMMITTEE REVIEW:
The applicant was not present. The staff stated that the
applicant had written a letter asking that this item be
deferred until the October 9, 1984, Planning Commission
meeting.
PLANNING COMMISSION ACTION:
The Commission voted 11 ayes, 0 noes to defer this item to
the October 9, 1984, Planning Commission meeting.
SUBDIVISION COMMITTEE REVIEW:
The applicant was not present. The staff stated that the
applicant had submitted a letter requesting withdrawal of
this item.
October 9, 1984
SUBDIVISIONS
Item No. A - Continued
PLANNING COMMISSION ACTION:
The applicant was not present but had submitted a letter
requesting withdrawal of this item. The Commission voted
8 ayes, 0 noes, 3 absent to withdraw this item.