HomeMy WebLinkAboutZ-3459-F Staff AnalysisApril 3, 2003
ITEM NO.: 6
FILE NO.: Z -3459-F
NAME: Home Depot — Conditional Use Permit
LOCATION: Mabelvale Pike and 1-30
OWNER/APPLICANT: Conservative Development Company/
Greenberg Farrow Architecture
PROPOSAL: A conditional use permit is requested to allow
development of a home center with lawn and garden
center on this C-3 zoned 12f acre tract.
ORDINANCE DESIGN STANDARDS:
1. SITE LOCATION:
The property is located on the south side of 1-30 at the Mabelvale
Pike/Baseline Road overpass.
2. COMPATIBILITY WITH NEIGHBORHOOD:
The proposed Home Depot site lies within a large commercially zoned
and developed area. New commercial development is occurring on the C-
3 zoned tracts to the east and north. A large area of undeveloped, C-3
zoned property extends to the south. A narrow strip of R-2 zoned
properties lies to the west, adjacent to Mabelvale Pike. These R-2
properties are shown as commercial on the Land Use Plan. Some of the
homes have been removed. Home Depot has shown a 46 foot buffer on
the west perimeter; 70% of which will remain wooded and undisturbed.
The proposed store should be compatible with the neighborhood.
All owners of property within 200 feet of the site, all residents within 300
feet who could be identified and the SWLR United for Progress, West
Baseline, Pinedale and Mavis Circle Neighborhood Associations were
notified of this request.
3. ON SITE DRIVES AND PARKING:
The proposed building will be 102,513 square feet in size and will have an
additional garden center area of 34,643 square feet. This 137,156 square
feet of retail use requires 387 spaces. Home Depot is proposing to
provide 426 parking spaces. Access to the site is via 3 driveways off of a
private road that serves the overall commercial development.
April 3, 2003
ITEM NO.: 6 Cont.) FILE NO.: Z -3459-F
4. SCREENING AND BUFFERS:
The proposed street buffer drops five feet below the twenty (20) foot
minimum width allowed at any given point. The average width
requirement is forty (40) feet.
The proposed areas designated for landscaping within the interior of the
vehicular use areas needs to be more evenly distributed. Also, a small
amount of landscaping between the public parking area and building is
required. Considerable flexibility is allowed with the building landscaping
requirement.
An irrigation system to water landscaped areas will be required.
At least seventy (70) percent of the land use buffer is required to remain
undisturbed.
Prior to a building permit being issued, it will be necessary to present
landscape plans stamped with the seal of a Registered Landscape
Architect.
5. PUBLIC WORKS COMMENTS:
1. The "Proposed Roadway" as shown in a previous preliminary plat must
be constructed to Master Street Plan standards and be accepted prior
to occupancy.
2. Sidewalks with appropriate handicap ramps are required in
accordance with Sec. 31-175 of the Little Rock Code and the Master
Street Plan.
3. A Sketch Grading and Drainage Plan will be required per Sec. 29-
186(e). Show all stormwater flows entering and leaving the property,
and the location of stormwater detention facilities.
4. Driveway locations and widths do not meet the traffic access and
circulation requirements of Sections 30-43 and 31-210. The first
driveway centerline must be located at least 250 feet back from the
right-of-way line of Mabelvale Pike, spacing between driveways must
not be closer than 250'. Driveway must also be located 125' from
property boundaries unless the drive is centered on the property line
and platted as a shared access drive.
5. Provide traffic impact and warrant analysis for proposed signal in
Mabelvale Pike. Both initial, and full development conditions should
be considered.
6. A right turn lane from the proposed development onto Mabelvale Pike
should be provided.
2
April 3, 2003
ITEM NO.: 6 (Cont.) FILE NO.: Z -3459-F
7. Obtain permits and approval for all improvements within State Highway
right-of-way from AHTD, District VI.
8. Contact the ADEQ for approval prior to start of work.
6. UTILITY, FIRE DEPT. AND CATA COMMENTS:
Wastewater: Sewer main extension required with easements if service is
required for project.
Entergy: Easements required along rear (south) perimeter as follows:
5' either side of UG primary, either 1 or 3 phase; and 30' easement
along rear property line for 3 phase overhead, 15' either side of poles.
Reliant: No Comments received.
Southwestern Bell: 10' easement needed on north and east perimeters.
Water: According to our records water service will be available to this
property after the proposed 12 -inch water main is installed. Service is
not available at this time. A Capital Investment Charge based on the
size of the meter connection(s) will apply to this project in addition to
normal charges. This fee will apply to all meter connections including
any metered connections off the private fire system. This development
will have minor impact on existing water distribution system. Proposed
water facilities will be sized to provide adequate pressure and fire
protection.
Fire Department: Approved as submitted.
County Planning: No Comments.
CATA: Site is on bus route #17 but has no effect on bus radius, turnout
and route.
SUBDIVISION COMMITTEE COMMENT
(MARCH 13, 2003)
The applicant was present. Staff presented the item and noted additional
information was needed on building design, signage, days and hours of
operation and site lighting. The applicant was asked to provide details on the
treatment of the perimeter of the garden center and to describe the nature of the
screening fence along the south perimeter. It was noted that no area had been
shown for seasonal -parking lot sales. The applicant was advised to show such
areas and to request approval if any seasonal display is anticipated. Staff
3
April 3, 2003
ITEM NO.: 6 Cont.) FILE NO.: Z -3459-F
commented that the easternmost north -south driveway needed to be shown in a
cross -access easement because of its tie-in to the property to the east.
Public Works Comments were presented. Discussion centered primarily on two
issues; the need to relocate the driveways to comply with Ordinance standards
and the need to submit a sketch grading and drainage plan showing all
stormwater flow entering and leaving the property and the location of stormwater
detention areas. It was noted that a traffic impact and warrant analysis would be
required for any proposed traffic signal.
Landscape Comments were presented. It was noted that the street buffer fell
below ordinance minimums, no building landscaping was shown and the interior
landscaping needed to be more evenly distributed. It was also noted that 70% of
the land use buffer on the west needed to remain undisturbed. The applicant
was urged to preserve as many trees on the site as possible.
The Committee ended its discussion and forwarded the item to the full
Commission.
STAFF ANALYSIS:
Home Depot proposes to construct a new home center with garden center on the
vacant, C-3 zoned, 11.89± acre tract located south of the Mabelvale Pike/1-30
interchange. The project consists of a 102,513 square foot home center, an
attached 34,643 square foot garden center and a 426 -space parking lot.
Outdoor sales will be located on the sidewalk area directly in front of the store
and along the east perimeter of the garden center. Access to the site is from 3
driveways off of a private road that will be built to serve this site and adjacent
commercial development. The one story building will be constructed of tilt -up
wall panels with a smooth concrete finish. The garden center will be covered by
a roof extension and a plexiglass material. The garden center will be enclosed
by a chain-link wall. A small, fenced area at the southwest corner of the building
will be used primarily as a staging area to off-load lumber before it is brought into
the store. Pallet storage will be located behind the building. That area will be
screened by an 8 foot tall wood fence. A 46 foot wide buffer will be left along the
west perimeter of the site. At least 70% of that buffer will remain undisturbed.
Signage will consist of a single ground -mounted sign not to exceed commercial
standards (36 feet in height and 160 square feet in area) and wall signs on the
front fagade of the building. The store's operating hours are proposed to be 6:00
a.m. — 10:00 p.m. Monday — Saturday and 8:00 a.m. — 8:00 p.m. on Sundays. A
trash compactor is located at the rear of the store, near the truck loading bays.
The applicant has submitted a site -lighting plan. Lighting should be low-level
and directional, so as to reduce light spillage onto adjacent properties.
4
April 3, 2003
ITEM NO.: 6
FILE NO.: Z -3459-F
Staff is supportive of the requested conditional use permit. The proposed
location is within a substantial, commercially zoned area. Commercially zoned
and developed properties are located north, south and east of the site. The row
of residential properties adjacent to the west are shown as commercial on the
land use plan. Some of the residential structures have recently been removed.
On March 19, 2003, the applicant submitted a revised plan and responses to
issues raised at Subdivision Committee and noted in the analysis above. The
access easement has been shown along the eastern driveway. Seasonal -
outdoor display will be limited to the sidewalk and the area directly east of the
garden center. The applicant is requesting approval of a variance to allow year-
round outdoor display in the indicated areas. To staff's knowledge, there are no
outstanding issues.
STAFF RECOMMENDATION:
Staff recommends approval of the requested conditional use permit subject to
compliance with the following conditions:
Compliance with the staff comments and conditions outlined in sections 4, 5
and 6 of this report.
2. Site lighting is to be low-level and directional, aimed inward to the site.
3. Outdoor sales and display is to be limited to those areas shown on the
sidewalk directly in front of the store and along the eastern perimeter of the
garden center.
4. Signage is to be limited to a single ground -mounted sign conforming to
commercial standards and wall signs on the building's front facade.
Staff recommends approval of a variance to allow year-round outdoor sales and
display in the areas specifically noted.
PLANNING COMMISSION ACTION: (APRIL 3, 2003)
The applicant was present. There were two interested parties present. A letter
of support had been submitted by the West Baseline Neighborhood Association.
A letter had also been submitted by SWLR United for Progress. In its letter,
SWLR United for Progress voiced support for the project and asked that two
conditions be added; that the developer agree to pay for or participate in the cost
of a traffic signal at Mabelvale Pike when it is warranted and that the site lighting
be high intensity, not low-level as recommended by staff. Staff presented the
item and a recommendation of approval subject to compliance with the following
conditions:
5
April 3, 2003
ITEM NO.: 6 (Cont.) FILE NO.: Z -3459-F
Compliance with the conditions outlined in the "Staff Recommendation"
above.
2. A right -turn lane is to be installed on the roadway at its intersection with
Mabelvale Pike.
3. The developer is to pay for or participate in the cost of a traffic signal at
Mabelvale Pike (as recommended by SWLR United for Progress).
4. Site lighting is to comply with proposed State of Arkansas House Bill 1282,
"The Night Sky Protection Act" as follows:
a. The outdoor lighting fixtures are to be shielded in such a manner that
light rays emitted by the fixture, either directly from the lamp or
indirectly from the fixture, are projected below a horizontal plane
running through the lowest point on the fixture where light is emitted.
b. No mercury vapor outdoor lighting fixtures are to be used.
Janet Berry, president of SWLR United for Progress, stated she agreed with the
conditions.
Staff recommended approval of a variance to allow year-round outdoor sales
and display in the areas specifically noted on the site plan. There was no further
discussion.
The item was placed on the Consent Agenda and approved, including all
recommended conditions and variances. The vote was 8 ayes, 0 noes and
3 absent.
0
April 3,'2003
ITEM NO.: 6 FILE NO.: Z -
NAME: Home Depot — Conditional Use Permit
LOCATION: Mabelvale Pike and 1-30
OWNER/APPLICANT: Conservative Development Company/
Greenberg Farrow Architecture
PROPOSAL: A conditional use permit is requested to allow
development of a home center with lawn and garden
center on this C-3 zoned 12t acre tract.
ORDINANCE DESIGN STANDARDS:
SITE LOCATION:
The property is located on the south side of 1-30 at the Mabelvale
Pike/Baseline Road overpass.
2. COMPATIBILITY WITH NEIGHBORHOOD:
The proposed Home Depot site lies within a large commercially zoned
and developed area. New commercial development is occurring on the C-
3 zoned tracts to the east and north. A large area of undeveloped, C-3
zoned property extends to the south. A narrow strip of R-2 zoned
properties lies to the west, adjacent to Mabelvale Pike. These R-2
properties are shown as commercial on the Land Use Plan. Some of the
homes have been removed. Home Depot has shown a 46 foot buffer on
the west perimeter; 70% of which will remain wooded and undisturbed.
The proposed store should be compatible with the neighborhood.
All owners of property within 200 feet of the site, all residents within 300
feet who could be identified and the SWLR United for Progress, West
Baseline, Pinedale and Mavis Circle Neighborhood Associations were
notified of this request.
3. ON SITE DRIVES AND PARKING:
The proposed building will be 102,513 square feet in size and will have an
additional garden center area of 34,643 square feet. This 137,156 square
feet of retail use requires 387 spaces. Home Depot is proposing to
provide 426 parking spaces. Access to the site is via 3 driveways off of a
private road that serves the overall commercial development.
April 3; 2003
ITEM NO.: 6 Cont. FILE NO.: Z -3459-F
4. SCREENING AND BUFFERS:
The proposed street buffer drops five feet below the twenty (20) foot
minimum width allowed at any given point. The average width
requirement is forty (40) feet.
The proposed areas designated for landscaping within the interior of the
vehicular use areas needs to be more evenly distributed. Also, a small
amount of landscaping between the public parking area and building is
required. Considerable flexibility is allowed with the building landscaping
requirement.
An irrigation system to water landscaped areas will be required.
At least seventy (70) percent of the land use buffer is required to remain
undisturbed.
Prior to a building permit being issued, it will be necessary to present
landscape plans stamped with the seal of a Registered Landscape
Architect.
5. PUBLIC WORKS COMMENTS:
1. The "Proposed Roadway" as shown in a previous preliminary plat must
be constructed to Master Street Plan standards and be accepted prior
to occupancy.
2. Sidewalks with appropriate handicap ramps are required in
accordance with Sec. 31-175 of the Little Rock Code and the Master
Street Plan.
3. A Sketch Grading and Drainage Plan will be required per Sec. 29-
186(e). Show all stormwater flows entering and leaving the property,
and the location of stormwater detention facilities.
4. Driveway locations and widths do not meet the traffic access and
circulation requirements of Sections 30-43 and 31-210. The first
driveway centerline must be located at least 250 feet back from the
right-of-way line of Mabelvale Pike, spacing between driveways must
not be closer than 250'. Driveway must also be located 125' from
property boundaries unless the drive is centered on the property line
and platted as a shared access drive.
5. Provide traffic impact and warrant analysis for proposed signal in
Mabelvale Pike. Both initial, and full development conditions should
be considered.
6. A right turn lane from the proposed development onto Mabelvale Pike
should be provided.
2
April 3; 2003
ITEM NO.: 6 (Cont.
FILE NO.: Z -3459-F
7. Obtain permits and approval for all improvements within State Highway
right-of-way from AHTD, District VI.
8. Contact the ADEQ for approval prior to start of work.
6. UTILITY, FIRE DEPT. AND CATA COMMENTS:
Wastewater: Sewer main extension required with easements if service is
required for project.
Entergy: Easements required along rear (south) perimeter as follows:
5' either side of UG primary, either 1 or 3 phase; and 30' easement
along rear property line for 3 phase overhead, 15' either side of poles.
Reliant: No Comments received.
Southwestern Bell: 10' easement needed on north and east perimeters.
Water: According to our records water service will be available to this
property after the proposed 12 -inch water main is installed. Service is
not available at this time. A Capital Investment Charge based on the
size of the meter connection(s) will apply to this project in addition to
normal charges. This fee will apply to all meter connections including
any metered connections off the private fire system. This development
will have minor impact on existing water distribution system. Proposed
water facilities will be sized to provide adequate pressure and fire
protection.
Fire Department: Approved as submitted.
County Planning: No Comments.
CATA: Site is on bus route #17 but has no effect on bus radius, turnout
and route.
SUBDIVISION COMMITTEE COMMENT: (MARCH 13, 2003)
The applicant was present. Staff presented the item and noted additional
information was needed on building design, signage, days and hours of
operation and site lighting. The applicant was asked to provide details on the
treatment of the perimeter of the garden center and to describe the nature of the
screening fence along the south perimeter. It was noted that no area had been
shown for seasonal -parking lot sales. The applicant was advised to show such
areas and to request approval if any seasonal display is anticipated. Staff
3
April 3; 2003
ITEM NO.: 6 (Cont.
FILE NO.: Z
commented that the easternmost north -south driveway needed to be shown in a
cross -access easement because of its tie-in to the property to the east.
Public Works Comments were presented. Discussion centered primarily on two
issues; the need to relocate the driveways to comply with Ordinance standards
and the need to submit a sketch grading and drainage plan showing all
stormwater flow entering and leaving the property and the location of stormwater
detention areas. It was noted that a traffic impact and warrant analysis would be
required for any proposed traffic signal.
Landscape Comments were presented. It was noted that the street buffer fell
below ordinance minimums, no building landscaping was shown and the interior
landscaping needed to be more evenly distributed. It was also noted that 70% of
the land use buffer on the west needed to remain undisturbed. The applicant
was urged to preserve as many trees on the site as possible.
The Committee ended its discussion and forwarded the item to the full
Commission.
STAFF ANALYSIS:
Home Depot proposes to construct a new home center with garden center on the
vacant, C-3 zoned, 11.89± acre tract located south of the Mabelvale Pike/1-30
interchange. The project consists of a 102,513 square foot home center, an
attached 34,643 square foot garden center and a 426 -space parking lot.
Outdoor sales will be located on the sidewalk area directly in front of the store
and along the east perimeter of the garden center. Access to the site is from 3
driveways off of a private road that will be built to serve this site and adjacent
commercial development. The one story building will be constructed of tilt -up
wall panels with a smooth concrete finish. The garden center will be covered by
a roof extension and a plexiglass material. The garden center will be enclosed
by a chain-link wall. A small, fenced area at the southwest corner of the building
will be used primarily as a staging area to off-load lumber before it is brought into
the store. Pallet storage will be located behind the building. That area will be
screened by an 8 foot tall wood fence. A 46 foot wide buffer will be left along the
west perimeter of the site. At least 70% of that buffer will remain undisturbed.
Signage will consist of a single ground -mounted sign not to exceed commercial
standards (36 feet in height and 160 square feet in area) and wall signs on the
front fagade of the building. The store's operating hours are proposed to be 6:00
a.m. — 10:00 p.m. Monday — Saturday and 8:00 a.m. — 8:00 p.m. on Sundays. A
trash compactor is located at the rear of the store, near the truck loading bays.
The applicant has submitted a site -lighting plan. Lighting should be low-level
and directional, so as to reduce light spillage onto adjacent properties.
El
April 3,. 2003
ITEM NO.: 6 (Cont.
FILE NO.: Z -3459-F
Staff is supportive of the requested conditional use permit. The proposed
location is within a substantial, commercially zoned area. Commercially zoned
and developed properties are located north, south and east of the site. The row
of residential properties adjacent to the west are shown as commercial on the
land use plan. Some of the residential structures have recently been removed.
On March 19, 2003, the applicant submitted a revised plan and responses to
issues raised at Subdivision Committee and noted in the analysis above. The
access easement has been shown along the eastern driveway. Seasonal -
outdoor display will be limited to the sidewalk and the area directly east of the
garden center. The applicant is requesting approval of a variance to allow year-
round outdoor display in the indicated areas. To staff's knowledge, there are no
outstanding issues.
STAFF RECOMMENDATION:
Staff recommends approval of the requested conditional use permit subject to
compliance with the following conditions:
1. Compliance with the staff comments and conditions outlined in sections 4, 5
and 6 of this report.
2. Site lighting is to be low-level and directional, aimed inward to the site.
3. Outdoor sales and display is to be limited to those areas shown on the
sidewalk directly in front of the store and along the eastern perimeter of the
garden center.
4. Signage is to be limited to a single ground -mounted sign conforming to
commercial standards and wall signs on the building's front fagade.
Staff recommends approval of a variance to allow year-round outdoor sales and
display in the areas specifically noted.
PLANNING COMMISSION ACTION:
(APRIL 3, 2003)
The applicant was present. There were two interested parties present. A letter
of support had been submitted by the West Baseline Neighborhood Association.
A letter had also been submitted by SWLR United for Progress. In its letter,
SWLR United for Progress voiced support for the project and asked that two
conditions be added; that the developer agree to pay for or participate in the cost
of a traffic signal at Mabelvale Pike when it is warranted and that the site lighting
be high intensity, not low-level as recommended by staff. Staff presented the
item and a recommendation of approval subject to compliance with the following
conditions:
5
April 3, 2003
ITEM NO.: 6 (Cont.) FILE NO.: Z -3459-F
1. Compliance with the conditions outlined in the "Staff Recommendation"
above.
2. A right -turn lane is to be installed on the roadway at its intersection with
Mabelvale Pike.
3. The developer is to pay for or participate in the cost of a traffic signal at
Mabelvale Pike (as recommended by SWLR United for Progress).
4. Site lighting is to comply with proposed State of Arkansas House Bill 1282,
"The Night Sky Protection Act" as follows:
a. The outdoor lighting fixtures are to be shielded in such a manner that
light rays emitted by the fixture, either directly from the lamp or
indirectly from the fixture, are projected below a horizontal plane
running through the lowest point on the fixture where light is emitted.
b. No mercury vapor outdoor lighting fixtures are to be used.
Janet Berry, president of SWLR United for Progress, stated she agreed with the
conditions.
Staff recommended approval of a variance to allow year-round outdoor sales
and display in the areas specifically noted on the site plan. There was no further
discussion.
The item was placed on the Consent Agenda and approved, including all
recommended conditions and variances. The vote was 8 ayes, 0 noes and
3 absent.